Where a
scire facias was issued to enforce a lien upon
a house under the lien law of the District of Columbia, there was
no necessity to file a declaration.
Where the contract between the owner and the builder, who was
also the carpenter stipulated for a forfeiture
per diem in
case the carpenter should delay the work, the court below ought to
have allowed evidence of such delay to be given to the jury by the
defendant under a notice of setoff, and also evidence that the work
and materials found and provided upon and for the building were
defective in quality and character and far inferior in value to
what the contract and specification called for.
A master builder, undertaker, or contractor who undertakes by
contract with the owner to erect a building or some part or portion
thereof on certain terms does not come within the letter or spirit
of the Act of Congress passed March 2, 1833, 4 Stat. 659, entitled
"An act to secure to mechanics and others, payment for labor done
and materials furnished in the erection of buildings in the
District of Columbia."
This was an action of
scire facias brought by Caldwell
against Winder upon a claim filed under the Act of Congress
passed
Page 55 U. S. 435
March 2, 1833, entitled "An act to secure to mechanics and
others, payment for labor done and materials furnished in the
erection of buildings of the District of Columbia." 4 Stat.
659.
Caldwell, in March, 1849, filed his claim in the clerk's office
consisting of the gross sum of $10,500, claimed as due under a
special agreement, and the further sum of $4,086 for extra work --
the items of the extra work being particularly mentioned in the
claim.
Upon this claim the writ of
scire facias issued March
20, 1849. No declaration was filed. The defendant appeared and
pleaded
nonassumpsit, upon which issue was joined.
Upon the trial, the jury found a verdict for the plaintiff in
the sum of $4,746, with interest from 9 March, 1849.
Upon the trial, the plaintiff took three bills of exceptions and
the defendant ten. The substance of them all is stated in the
opinion of the Court.
Page 55 U. S. 442
MR. JUSTICE GRIER delivered the opinion of the Court.
Caldwell, who was plaintiff below, entered into a contract with
Winder "to furnish all the materials and do all the carpenter work
required to a certain house to be erected in the City of
Washington" for the sum of ten thousand dollars. After the house
was finished, the contractor filed a lien against the building
claiming this sum, together with sundry charges for extra work. A
scire facias was issued to enforce this claim, and
Page 55 U. S. 443
a trial had in the course of which numerous bills of exception
were sealed by the court at the defendant's instance, which form
the subjects for our consideration in this case.
1. The want of a declaration, though not the subject of
exception below, has been urged here as an error. But we think this
objection is without foundation.
A
scire facias is a judicial writ used to enforce the
execution of some matter of record on which it is usually founded,
but, though a judicial writ or writ of execution, it is so far an
original that the defendant may plead to it. As it discloses the
facts on which it is founded and requires an answer from the
defendant, it is in the nature of a declaration, and the plea is
properly to the writ. In the present case, the bill of particulars
of the plaintiff's claim is filed of record under the statute which
gives this remedy, and it is recited in the writ, and thereby made
part of it, so that any further pleading on his part to set forth
the nature of his demand would be wholly superfluous.
2. In the written contract between the parties given in evidence
on the trial, it is stipulated that "the work is to be promptly
executed, so that no delay shall be occasioned to the builder by
having to wait for the carpenter's work," and also
"that in any and every case in which the carpenter shall
occasion delay to the building, the sum of twenty-five dollars per
day shall be deducted for each and every day so delayed from the
amount to be paid by this contract."
The defendant, under a notice of setoff, offered to prove
"that in consequence of the plaintiff's not being ready to put
up his work according to said contract, delay was occasioned by him
in the construction of the building of not less than three
weeks,"
and also
"that the work and materials found and provided upon and for the
said building, were defective in quality and character, and far
inferior in value to what said contract and specification called
for."
The refusal of the court to permit such evidence to go to the
jury is the subject of the first two bills of exception.
The statute which authorizes this proceeding, gives the
defendant liberty "to plead and make such defense as in personal
actions for the recovery of debts." Had the plaintiff below brought
his action of assumpsit on the contract, the right to make this
defense cannot now be doubted. For although it is true as a general
rule that unliquidated damages cannot be the subject of setoff, yet
it is well settled that a total or partial failure of
consideration, acts of nonfeasance or misfeasance, immediately
connected with the cause of action, or any equitable defense
arising out of the same transaction, may be given in evidence in
mitigation of damages, or recouped, not strictly
Page 55 U. S. 444
by way of defalcation or setoff, but for the purpose of
defeating the plaintiff's action in whole or in part, and to avoid
circuity of action. Without noticing the numerous cases on this
subject, it is sufficient to say that the cases of
Withers v.
Green, 9 How. 214, and
Van Buren
v. Digges, 11 How. 461, decided in this Court, are
conclusive of the question. The court below therefore erred in the
rejection of the testimony offered.
3. The remaining bills of exception involve in fact but one
prominent and important question, and the decision of it will
dispose of this case.
The right to file a "mechanic's lien," as it is usually
denominated, is claimed by the plaintiff, under the Act of Congress
of March 2, 1833, entitled "An act to secure to mechanics and
others, payment for labor done and materials furnished, in the
erection of buildings in the District of Columbia." The first
section of this act defines the persons who shall be entitled to
this peculiar security and remedy as follows:
"All and every dwelling house, or other building, hereafter
constructed and erected within the City of Washington, in the town
of Alexandria, or in Georgetown, in the District of Columbia, shall
be subject to the payment of the debts contracted for or by reason
of any work done or materials found and provided by any brickmaker,
bricklayer, stonecutter, mason, lime-merchant, carpenter, painter
and glazier, ironmonger, blacksmith, plasterer and lumber-merchant,
or any other person or persons employed in furnishing materials
for, or in erecting and constructing such house or other building,
before any other lien which originated subsequent to the
commencement of such house, or other building. But if such dwelling
house or other building, or any portion thereof, shall have been
constructed under contract, or contracts, entered into by the owner
thereof or his or her agent, with any person or persons, no person
who may have done work for such contractor or contractors or
furnished materials to him or on his order or authority, shall have
or possess any lien on said house or other building for work done
or materials so furnished unless the person or persons employed by
such contractor to do work on or furnish materials for such
building, shall, within thirty days after being so employed, give
notice in writing to the owner or owners of such building, or to
his or to their agent, that he or they are so employed to work or
to furnish materials, and that they claim the benefit of the lien
granted by this act."
Does a master builder, undertaker, or contractor who undertakes
by contract with the owner to erect a building or some part or
portion thereof on certain terms come within the letter or spirit
of this act or within any of the classes enumerated as
Page 55 U. S. 445
entitled to this special remedy? Such persons have an
opportunity, and are capable of obtaining their own securities.
They do not labor as mechanics, but superintend work done by
others. They are not tradesmen in lumber or other materials for
building, but employ others to furnish materials. If such
contractor should by accident be a carpenter or an owner or vendor
of lumber, yet he deals not with the owner in this capacity, but as
an undertaker, who has covenanted for his own securities.
The title to this act shows its policy and intention. It is to
secure, to "mechanics and others, payment for labor done and
materials found," and the persons enumerated in the first section
are plainly those mechanics and tradesmen whose personal labor or
property have been incorporated into the building, and not the
agents, supervisors, undertakers, or contractors who employed them.
The act contemplates two conditions, under which such labor and
materials may have been furnished: first, on the order of the
owner, who may act without the intervention of any middleman, and
thus become indebted directly to his mechanics and tradesmen. Or
secondly, when they have been furnished on the order of a
contractor or undertaker. In such cases, the mechanic, or
materialman, if he intends to look to the credit of the building,
and not to that of the contractor with whom he deals, must give
notice to the owner of the building, within thirty days, of his
intention to claim this security. The contractor, though mentioned
in the act, is not enumerated among those entitled to its benefit.
The aim and policy of this act is also obvious. Experience has
shown that mechanics and tradesmen, who furnish labor and materials
for the construction of buildings, are often defrauded by insolvent
owners and dishonest contractors. Many build houses on speculation,
and after the labor of the mechanic and the materials are
incorporated into them, the owner becomes insolvent, and sells the
buildings, or encumbers them with liens; and thus, one portion of
his creditors are paid at the expense of the labor and property of
others. Or, the solvent owner, who builds by the agency of a
contractor or middleman, pays his price and receives his building,
without troubling himself to inquire what has been the fate of
those whose labor or means have constructed it. These evils
required a remedy, and such a one as is given by this act. Its
object is, not to secure contractors, who can take care of
themselves, but those who may suffer loss by confiding in them. It
is not the merit of the contractor, that gave rise to the system,
but the protection of those who might be wronged by him, if the
owner were not compelled thus to take care of their interests
before he pays away the price stipulated.
Page 55 U. S. 446
But the contractor is neither within the letter nor the spirit
of the act.
A question has been made in the argument, whether the Act of
Maryland, of 19 December, 1791, formerly in force in this district,
is supplied or repealed by the act of Congress now under
consideration. But as the proceedings in this case are not within
or under the act of Maryland, the question is not before us for
decision. The plaintiff claims his right to support this
proceeding, under the act of Congress alone, and if that fails him,
his only resource is to his action on his contract. That he has
mistaken his remedy, the court entertain no doubt.
If precedent were needed to justify this construction of the act
of Congress, it may be found in the reports of the Supreme Court of
Pennsylvania, where similar legislation has always received the
same construction.
See Jones v. Shawhan, 4 Watts &
Serg. 257;
Hoatz v. Patterson, 5 W. & S. 537,
&c.
4. It is unnecessary to notice particularly the exception to the
form of the judgment. It is certainly not in the form required by
the act, and although the act may be construed to prescribe the
effect rather than the form of the judgment, there is no reason why
the form should differ from the effect, or that, in words, it
should give the plaintiff anything more than the law gives him,
viz., execution of the property described in the
scire
facias.
The judgment of the circuit court is therefore
Reversed and venire de novo awarded.
Order
This cause came on to be heard on the transcript of the record
from the Circuit Court of the United States for the District of
Columbia holden in and for the County of Washington, and was argued
by counsel. On consideration whereof, it is now here ordered and
adjudged, by this Court, that the judgment of the said circuit
court in this cause be and the same is hereby reversed with costs,
and that this cause be and the same is hereby remanded to the said
circuit court with directions to award a venire facias
de
novo.