Section 210 of the Public Utility Regulatory Policies Act of
1978 (PURPA) was designed to encourage the development of
cogeneration facilities and small power production facilities and
to reduce the demand for fossil fuels. Section 210(a) directs the
Federal Energy Regulatory Commission (FERC) to prescribe rules
requiring electric utilities to deal with qualifying cogeneration
and small power facilities. With respect to utilities' purchases of
electricity from such facilities, § 210(b) provides that rates
set by FERC "shall be just and reasonable to the electric consumers
of the electric utility and in the public interest," shall not
discriminate against qualified cogeneration and small power
facilities, and shall not exceed "the incremental cost to the
electric utility of alternative electric energy." Following
rulemaking proceedings, FERC promulgated a rule requiring utilities
to purchase electric energy from a qualifying facility at a rate
equal to the utility's "full avoided cost,"
i.e., the cost
to the utility which, but for the purchase from the qualifying
facility, would be incurred by the utility in generating the
electricity itself or purchasing the electricity from another
source. FERC also promulgated a rule requiring utilities to make
such physical interconnections with cogenerators and small power
producers as are necessary to effect purchases or sales of
electricity authorized by PURPA. Upon review, the Court of Appeals
vacated both rules, holding that FERC had not adequately explained
its adoption of the full-avoided-cost rule, and that it exceeded
its statutory authority in promulgating the interconnection rule,
in view of § 210(e)(3) of PURPA, which provides that "[n]o
qualifying small power production facility or qualifying
cogeneration facility may be exempted under this subsection from"
specified provisions of the Federal Power Act (FPA) which require
FERC to afford an opportunity for a hearing before ordering an
interconnection.
Held:
1. FERC did not act arbitrarily or capriciously in promulgating
the full-avoided-cost rule, which is the maximum rate permissible
under
Page 461 U. S. 403
§ 210(b). Such rule plainly satisfies the requirement of
§ 210(b) that the rate not discriminate against qualifying
cogeneration and small power production facilities. FERC also
adequately explained why the rate is "just and reasonable to the
electric consumers of the electric utility and in the public
interest." Both the statutory language and the legislative history
confirm that Congress did not intend to impose traditional
ratemaking concepts on sales by qualifying facilities to utilities.
And although FERC recognized that the rule would not directly
provide any rate savings to consumers, it reasonably deemed it more
important at this time that the rule would provide a significant
incentive for the development of cogeneration and small power
production, and that ratepayers and the Nation as a whole will
benefit from the decreased reliance on scarce fossil fuels and the
more efficient use of energy. Pp.
461 U. S.
412-418.
2. Nor did FERC exceed its authority in promulgating the
interconnection rule. The authority granted by § 210(a) to
promulgate such rules as are necessary to require utilities to deal
with qualifying facilities plainly encompasses the power to
promulgate rules requiring utilities to make physical connections
with such facilities, and FERC reasonably interpreted §
210(e)(3) as forbidding it to exempt qualifying facilities from
being the "target" of interconnection applications by other
facilities under the FPA, but not as forbidding it to grant
qualifying facilities the right to obtain interconnections under
PURPA without applying for an order under the FPA. Such
interpretation is supported by the purposes of PURPA and the
statutory scheme created by both Acts. Pp.
461 U. S.
418-423.
219 U.S.App.D.C. 1, 675 F.2d 1226, reversed and remanded.
MARSHALL, J., delivered the opinion of the Court, in which all
other Members joined, except POWELL, J., who took no part in the
consideration or decision of the cases.
Page 461 U. S. 404
JUSTICE MARSHALL delivered the opinion of the Court.
This case concerns two rules promulgated by the Federal Energy
Regulatory Commission (FERC) pursuant to § 210 of the Public
Utility Regulatory Policies Act of 1978 (PURPA), 92 Stat. 3144, as
amended, 16 U.S.C. § 824a-3 (1976 ed., Supp. V). The first
rule requires electric utilities to purchase electric energy from
cogenerators and small power producers at a rate equal to the
purchasing utility's full avoided cost,
i.e., the cost the
utility would have incurred had it generated the electricity itself
or purchased the electricity from another source. The second rule
requires utilities to make such interconnections with cogenerators
and small power producers as are necessary to effect purchases or
sales of electricity authorized by PURPA. The Court of Appeals held
that FERC had not adequately explained its adoption of the
full-avoided-cost rule, and that it exceeded its statutory
authority in promulgating the interconnection rule. 219
U.S.App.D.C. 1, 675 F.2d 1226 (1982). We reverse.
I
A
Section 210 of PURPA was designed to encourage the development
of cogeneration and small power production facilities. [
Footnote 1]
Page 461 U. S. 405
As we noted in
FERC v. Mississippi, 456 U.
S. 742,
456 U. S. 750
(1982) (footnote omitted), "Congress believed that increased use of
these sources of energy would reduce the demand for traditional
fossil fuels," and it recognized that electric utilities had
traditionally been "reluctant to purchase power from, and to sell
power to, the nontraditional facilities." Accordingly, Congress
directed FERC to prescribe, within one year of the statute's
enactment, rules requiring electric utilities to deal with
qualifying cogeneration and small power production facilities.
PURPA § 210(a), 16 U.S.C. § 824a-3(a) (1976 ed., Supp.
V). With respect to the purchase of electricity from cogeneration
and small power production facilities, Congress provided that the
rate to be set by the Commission
"(1) shall be just and reasonable to the electric consumers of
the electric utility and in the public interest, and"
"(2) shall not discriminate against qualifying cogenerators or
qualifying small power producers."
"No such rule prescribed under subsection (a) of this section
shall provide for a rate which exceeds the incremental cost to the
electric utility of alternative electric energy."
PURPA § 210(b), 16 U.S.C. § 824a-3(b) (1976 ed., Supp.
V). Following rulemaking proceedings, FERC promulgated regulations
governing transactions between utilities and those cogeneration and
small power production facilities, designated as "qualifying
facilities," 18 CFR §§ 292.201-292.207
Page 461 U. S. 406
(1982), that may invoke the provisions of PURPA to sell
electricity to and purchase electricity from utilities.
The first regulation at issue in this case, 18 CFR §
292.304(b)(2) (1982), requires a utility to purchase electricity
from a qualifying facility at a rate equal to the utility's full
avoided cost. The utility's full avoided cost is
"the cost to the electric utility of the electric energy which,
but for the purchase from such cogenerator or small power producer,
such utility would generate or purchase from another source."
PURPA § 210(d), 16 U.S.C. § 824a-3(d)(1976 ed., Supp.
V).
See 18 CFR § 292.101(b)(6) (1982) (the term full
"avoided costs" used in the regulations is the equivalent of the
term "incremental cost of alternative electric energy" used in
§ 210(d) of PURPA). In its order accompanying the promulgation
of this rule, FERC explained its decision to set the rate at full
avoided cost, rather than at a level that would result in direct
rate savings for utility customers by permitting a utility to
obtain energy at a cost less than the cost to the utility of
producing the energy itself or purchasing it from an alternative
source. 45 Fed.Reg. 12214 (1980). The Commission emphasized the
need to provide incentives for the development of cogeneration and
small power production:
"[I]n most instances, if part of the savings from cogeneration
and small power production were allocated among the utilities'
ratepayers, any rate reductions will be insignificant for any
individual customer. On the other hand, if these savings are
allocated to the relatively small class of qualifying cogenerators
and small power producers, they may provide a significant incentive
for a higher growth rate of these technologies."
Id. at 12222. The Commission noted that
"ratepayers and the nation as a whole will benefit from the
decreased reliance on scarce fossil fuels, such as oil and gas, and
the more efficient use of energy."
Ibid.
Page 461 U. S. 407
FERC rejected proposals that it set the rate for the purchase of
electricity from qualifying facilities at a fixed percentage of the
purchasing utility's full avoided cost:
"[I]n most situations, a qualifying cogenerator or small power
producer will only produce energy if its marginal cost of
production is less than the price he receives for its output. If
some fixed percentage is used, a qualifying facility may cease to
produce additional units of energy when its costs exceed the price
to be paid by the utility. If this occurs, the utility will be
forced to operate generating units which either are less efficient
than those which would have been used by the qualifying facility or
which consume fossil fuel, rather than the alternative fuel which
would have been consumed by the qualifying facility had the price
been set at full avoided costs."
Id. at 12222-12223.
The second regulation at issue here, 18 CFR § 292.303
(1982), provides that electric utilities shall purchase electricity
made available by qualifying facilities, sell electricity to
qualifying facilities upon request, and, most important for present
purposes, "make such interconnections with any qualifying facility
as may be necessary to accomplish purchases or sales under this
subpart." § 292.303(c)(1). An interconnection is a physical
connection that allows electricity to flow from one entity to
another. [
Footnote 2]
In its order, the Commission rejected the contention that §
210(e)(3) of PURPA requires it to afford an opportunity for an
evidentiary hearing to any utility that is unwilling to make an
interconnection with a qualifying facility that has invoked the
provisions of PURPA to enter into a purchase or sale with the
utility. Section 210(e)(3), 92 Stat. 3145, provides in relevant
part:
Page 461 U. S. 408
"No qualifying small power production facility or qualifying
cogeneration facility may be exempted under this subsection from
--"
* * * *
"(B) the provisions of section 210 . . . or 212 of the Federal
Power Act . . . or the necessary authorities for enforcement of any
such provision under the Federal Power Act. . . ."
16 U.S.C. § 824a-3(e)(3) (1976 ed., Supp. V). Sections 210
and 212 of the Federal Power Act (FPA), 16 U.S.C. §§ 824i
and 824k (1976 ed., Supp. V), describe the procedure to be followed
by FERC when an electric utility, federal power marketing agency,
cogenerator, or small power producer applies for an order requiring
another such facility to make an interconnection. Section 210
provides that, upon receipt of an application for an order
requiring an interconnection, the Commission shall issue notice to
each affected state regulatory authority, utility, federal power
marketing agency, and owner or operator of a cogeneration facility
or small power production facility, and to the public, §
210(b)(1), 16 U.S.C. § 824i(b)(1) (1976 ed., Supp. V), afford
an opportunity for an evidentiary hearing, § 210(b)(2), 16
U.S.C. § 824i(b)(2) (1976 ed., Supp. V), and issue an order
approving the application only if it determines that approval
"(1) is in the public interest,"
"(2) would -- "
"(A) encourage overall conservation of energy or capital,"
"(B) optimize the efficiency of use of facilities and resources,
or"
"(C) improve the reliability of any electric utility system or
Federal power marketing agency to which the order applies, and"
"(3) meets the requirements of [§ 212 of the FPA]."
16 U.S.C. § 824i(c) (1976 ed., Supp. V).
Page 461 U. S. 409
Section 212 of the FPA, 16 U.S.C. § 824k (1976 ed., Supp.
V), provides that an order approving an interconnection under
§ 210 may be issued only if the Commission determines that the
interconnection is not likely to result in a reasonably
ascertainable uncompensated loss for any electric utility,
cogenerator, or small power producer, impose an undue burden on any
such facility, unreasonably impair the reliability of any electric
utility, or impair the ability of any electric utility to supply
adequate service to its customers. [
Footnote 3]
Page 461 U. S. 410
In concluding that an evidentiary hearing under the FPA is not
required prior to an interconnection necessary to complete a
purchase or sale authorized by PURPA, the Commission reasoned that
§ 210(a) of PURPA "provides a general mandate for the
Commission to prescribe rules necessary to encourage cogeneration
and small power production." 45 Fed.Reg. 12221 (1980). The
Commission also emphasized that "a basic purpose of section 210 of
PURPA is to provide a market for the electricity generated by small
power producers and cogenerators," and that
"to require qualifying facilities to go through the complex
procedures set forth in section 210 of the Federal Power Act to
gain interconnection would, in most circumstances, significantly
frustrate"
the achievement of that purpose.
Ibid.
Following the filing of several petitions for rehearing, the
Commission issued an order adhering to both the full-avoided-cost
rule and the interconnection rule.
Id. at 33958.
B
Respondents American Electric Power Service Corp., Consolidated
Edison Co. of New York, Inc., and Colorado-Ute Electric
Association, Inc., sought review of the Commission's rules in the
United States Court of Appeals for the District of Columbia
Circuit. The Court of Appeals vacated both rules. 219 U.S.App.D.C.
1, 675 F.2d 1226 (1982).
The Court of Appeals concluded that FERC had not adequately
demonstrated that the full-avoided-cost rule was consistent with
the mandate of § 210(b) of PURPA that the Commission prescribe
rates for purchases of electric energy from qualifying facilities
that are "
just and reasonable to the electric consumers of the
electric utility'" and "`in the public interest.'" Id. at
7, 675 F.2d at 1232.
"By ordering that the purchase rate be equal to the full avoided
cost in every case, FERC has, without convincing explanation,
simply adopted as a uniform rule the maximum purchase rate
Page 461 U. S. 411
specified in the statute."
Id. at 8, 675 F.2d at 1233. [
Footnote 4] The court stressed that
"FERC should allocate the benefits more evenly between the
cogenerators and the utilities if the utilities can demonstrate
that, under a percentage of avoided cost approach, an allocation
less heavily favoring the cogenerators is in the public interest
and the interest of the utilities' electric consumers, and will not
disproportionately discourage cogeneration."
Id. at 9, 675 F.2d at 1234. While acknowledging that an
approach requiring calculation of each cogenerator's costs on a
case-by-case basis "would indeed veer toward the public
utilities-style rate setting that Congress wanted to avoid," the
Court of Appeals emphasized that FERC should have given additional
consideration to a percentage-of-avoided-cost approach, whereby
FERC would either set a percentage itself or establish a range
within which each state regulatory commission could fix a precise
percentage.
Ibid. [
Footnote 5]
The Court of Appeals held that FERC had exceeded its authority
in promulgating the interconnection rule. The court reasoned that
the
"relatively
specific limitation on authority in PURPA
section 210(e)(3) . . . must control over the relatively general
grant of authority in FPA section 212(e)."
Id. at 15, 675 F.2d at 1240 (emphasis in original). The
court concluded that the Commission must provide notice to
interested parties and afford an opportunity for an evidentiary
Page 461 U. S. 412
hearing with respect to each interconnection requested by a
qualifying facility.
Following the denial of petitions for rehearing and rehearing en
banc, [
Footnote 6] petitions
for certiorari were filed by both FERC and American Paper
Institute, Inc., the national trade association of the pulp, paper,
and paperboard industry, which accounts for a large share of the
cogeneration of electric power in the United States today. We
granted both petitions. 459 U.S. 904 (1982).
II
The first question before us is whether FERC's action in
promulgating the full-avoided-cost rule was "arbitrary, capricious,
[or] an abuse of discretion." 5 U.S.C. § 706(2)(A). [
Footnote 7]
Page 461 U. S. 413
We cannot answer this question simply by noting that the
full-avoided-cost rule is within the range of permissible rates
that Congress established in § 210(b) of PURPA. The Commission
plainly has the authority to adopt a full-avoided-cost rule, for
PURPA sets full avoided cost as the maximum rate that the
Commission may prescribe. Whether the Commission properly exercised
that authority is a separate issue. To decide whether the
Commission's action was "arbitrary, capricious, [or] an abuse of
discretion," we must determine whether the agency adequately
considered the factors relevant to choosing a rate that will best
serve the purposes of the statute, and whether the agency committed
"a clear error of judgment."
Citizens to Preserve Overton Park
v. Volpe, 401 U. S. 402,
401 U. S. 416
(1971).
FERC's explanation of its reasons for promulgating the
full-avoided-cost rule must be examined in light of the criteria
set forth in § 210(b) of PURPA, 16 U.S.C. § 824a-3(b)
(1976 ed., Supp. V), which provides that the purchase rate
established by the Commission must be "just and reasonable to the
electric consumers of the electric utility and in the public
interest," and must not discriminate against qualifying facilities.
[
Footnote 8] Since the
full-avoided-cost rule plainly satisfies the nondiscrimination
requirement, we need only consider whether FERC adequately
explained why the rule is "just and reasonable to the electric
consumers of the electric utility and in the public interest."
We cannot accept respondents' suggestion, Brief for Respondent
Electric Utilities 9, and n. 4, that the "just and reasonable"
language in § 210(b) was intended to require that the purchase
rate be set "
at the lowest possible reasonable rate
Page 461 U. S.
414
consistent with the maintenance of adequate service in the
public interest.'" Atlantic Refining Co. v. Public Service
Comm'n of New York, 360 U. S. 378,
360 U. S. 388
(1959), quoting the original version of the Natural Gas Act. Simply
on the basis of the statutory language, we would be reluctant to
infer that Congress intended the terms "`just and reasonable,'"
which are frequently associated with cost-of-service utility
ratemaking, see, e.g., NAACP v. FPC, 425 U.
S. 662, 425 U. S. 666
(1976), to adopt a cost-of-service approach in the very different
context of cogeneration and small power production by
nontraditional facilities. The legislative history confirms,
moreover, that Congress did not intend to impose traditional
ratemaking concepts on sales by qualifying facilities to utilities.
The Conference Report states in pertinent part:
"It is not the intention of the conferees that cogenerators and
small power producers become subject . . . to the type of
examination that is traditionally given to electric utility rate
applications to determine what is the just and reasonable rate that
they should receive for their electric power. The conferees
recognize that cogenerators and small power producers are different
from electric utilities, not being guaranteed a rate of return on
their activities generally or on the activities
vis a vis
the sale of power to the utility and whose risk in proceeding
forward in the cogeneration or small power production enterprise is
not guaranteed to be recoverable."
"[C]ogeneration is to be encouraged under this section, and
therefore the examination of the level of rates which should apply
to the purchase by the utility of the cogenerator's or small power
producer's power should not be burdened by the same examination as
are utility rate applications, but rather in a less burdensome
manner. The establishment of utility type regulation over them
would act as a significant disincentive to firms interested in
cogeneration and small power production."
H.R.Conf.Rep. No. 95-1750, pp. 97-98 (1978).
Page 461 U. S. 415
In contrast, a subsequent passage in the Conference Report
explicitly states that the "just and reasonable" language of §
210(c), 16 U.S.C. § 824a-3(c) (1976 ed., Supp. V), which
concerns sales by utilities to qualifying facilities, "is intended
to refer to traditional utility ratemaking concepts." H.R. Conf
Rep. No. 95-1750,
supra, at 98 (emphasis added).
The Commission did not ignore the interest of electric utility
consumers "in receiving electric energy at equitable rates."
H.R.Conf.Rep. No. 95-1750,
supra, at 97. [
Footnote 9] The Commission recognized that
the full-avoided-cost rule would not directly provide any rate
savings to electric utility consumers, but deemed it more important
that the rule could "provide a significant incentive for a higher
growth rate" of cogeneration and small power production, and
that
"these ratepayers and the nation as a whole will benefit from
the decreased reliance on scarce fossil fuels, such as oil and gas,
and the more efficient use of energy. [
Footnote 10]"
45 Fed.Reg. 12222 (1980). As the Commission explained, a
purchase rate established
Page 461 U. S. 416
at a fixed percentage of avoided cost would discourage
production of electric energy by qualifying facilities whose
marginal costs exceeded the rate that a purchasing utility would be
required to pay under this approach, whereas those same facilities
would retain an incentive to produce energy under the
full-avoided-cost rule so long as their marginal costs did not
exceed the full avoided cost of the purchasing utility.
Id. at 12222-12223.
The Commission would have encountered considerable difficulty
had it attempted to determine an appropriate rate less than full
avoided cost. A wide variety of technologies are used in
cogeneration and small power production, including internal
combustion engines, steam turbines, combustion turbines, windmills,
solar cells, and hydro turbines. Facilities may vary greatly in
capacity. It would have been extremely difficult, if not
impossible, for the Commission to make any useful estimate of the
amount of cogeneration and small power production that would be
discouraged by setting the rate at a level lower than full avoided
cost.
It bears emphasizing that the full-avoided-cost rule is not as
inflexible as might appear at first glance. First, any state
regulatory authority and any nonregulated utility may apply to the
Commission for a waiver of the rule. A waiver may be granted if the
applicant demonstrates that a full-avoided-cost rate is unnecessary
to encourage cogeneration and small power production. 18 CFR §
292.403 (1982). Second, a qualifying facility and a utility may
negotiate a contract setting a price that is lower than a
full-avoided-cost rate. § 292.301(b)(1). Because the
full-avoided-cost rule is subject to revision by the Commission as
it obtains experience with the effects of the rule, it may often be
in the interest of a qualifying facility to negotiate a long-term
contract at a lower rate. The Commission's rule simply establishes
the rate that applies in the absence of a waiver or a specific
contractual agreement.
Page 461 U. S. 417
Under these circumstances, it was not unreasonable for the
Commission to prescribe the maximum rate authorized by PURPA.
[
Footnote 11] The
Commission's order makes clear that the Commission considered the
relevant factors and deemed it most important at this time to
provide the maximum incentive for the development of cogeneration
and small power production, in light of the Commission's judgment
that the entire country will ultimately benefit from the increased
development of these technologies and the resulting decrease in the
Nation's dependence on fossil fuels. The Commission has a statutory
mandate to set a rate that is "in the public interest," and as this
Court stated in
NAACP v. FPC, 425 U.S. at
425 U. S. 669,
"the words
public interest' in a regulatory statute . . . take
meaning from the purposes of the regulatory legislation." The basic
purpose of § 210 of PURPA was to increase the utilization of
cogeneration and small power production facilities and to reduce
reliance on fossil fuels. See FERC v. Mississippi, 456
U.S. at 750. At this early stage
Page 461 U. S. 418
in the implementation of PURPA, it was reasonable for the
Commission to prescribe the maximum rate authorized by Congress,
and thereby provide the maximum incentive for the development of
cogeneration and small power production.
III
Absent § 210(e)(3) of PURPA, there would be no doubt as to
the validity of the Commission's interconnection rule. Section
210(a) of PURPA, 16 U.S.C. § 824a-3(a) (1976 ed., Supp. V),
provides the Commission with general authority to promulgate
"such rules as it determines necessary to encourage cogeneration
and small power production . . . which rules require electric
utilities to offer to -- "
"(1) sell electric energy to qualifying cogeneration facilities
and qualifying small power production facilities and"
"(2) purchase electric energy from such facilities."
The authority to promulgate such rules as are necessary to
require purchases and sales plainly encompasses the power to
promulgate rules requiring utilities to make physical connections
with qualifying facilities in order to consummate purchases and
sales authorized by PURPA. No purchase or sale can be completed
without an interconnection between the buyer and seller.
In the absence of a specific provision to the contrary, the
Commission's power to promulgate rules under PURPA requiring
interconnections would not be negated by the provisions of the FPA
that give the Commission the authority to conduct adjudicatory
proceedings and issue orders requiring interconnections. As a
general matter, the existence of power to proceed by adjudication
under one statute is in no way inconsistent with the existence of
power to proceed by rulemaking under another statute. Moreover,
there is nothing in the FPA to suggest that the Commission must
proceed by adjudication in determining the obligations of
facilities
Page 461 U. S. 419
within its jurisdiction to make interconnections. On the
contrary, Congress expressly provided in § 212(e) of the FPA,
16 U.S.C. § 824k(e) (1976 ed., Supp. V), that § 210 of
the FPA shall not be construed "as requiring any person to utilize
the authority of [§ 210] . . . in lieu of any other authority
of law," or "as limiting, impairing, or otherwise affecting any
authority of the Commission under any other provision of law."
The critical question, therefore, is whether § 210(e)(3) of
PURPA deprives FERC of the power it would otherwise have under
§ 210(a) of PURPA to promulgate rules requiring utilities to
make such interconnections with qualifying facilities as are
necessary to effect purchases or sales authorized by the Act. In
holding the interconnection rule invalid, the Court of Appeals
relied upon what it took to be "the literal meaning" of §
210(e)(3), 219 U.S.App.D.C. at 15, 675 F.2d at 1240, which states
in pertinent part:
"No qualifying small power production facility or qualifying
cogeneration facility may be exempted under this subsection from
--"
* * * *
"(B) the provisions of section 210 . . . or 212 of the Federal
Power Act . . . or the necessary authorities for enforcement of any
such provision under the Federal Power Act. . . ."
The Court of Appeals interpreted § 210(e)(3) of PURPA to
mean that FERC may not promulgate a rule requiring utilities to
interconnect with qualifying facilities in order to complete
purchases and sales the utilities are required to enter into under
PURPA, but must instead afford an opportunity for an evidentiary
hearing under §§ 210 and 212 of the FPA in the case of
each purchase and sale.
While the language of § 210(e)(3) of PURPA can be so
interpreted, the purposes of PURPA strongly support the
Commission's contrary reading of that provision. The purposes of
the statute make it most unlikely that Congress could have intended
that an evidentiary hearing be held for
Page 461 U. S. 420
every interconnection necessary to consummate a purchase or sale
of electricity authorized by the Act. Evidentiary hearings under
§ 210 of the FPA entail a determination of whether a proposed
interconnection (1) is in the public interest, and (2) would
encourage overall conservation of energy or capital, optimize the
efficiency of use of facilities and resources, or improve the
reliability of the affected utility systems. 16 U.S.C. §
824i(c)(1) (1976 ed., Supp. V). It is highly doubtful that Congress
could have intended that the Commission make such a determination
every time a qualifying facility seeks to hook up with a utility to
complete a purchase or sale under PURPA, for Congress itself
determined in enacting PURPA that these purchases and sales are in
the public interest, and that the development of cogeneration and
small power production will help to conserve energy and capital and
ensure the more efficient use of the Nation's resources.
Providing an opportunity for evidentiary hearings before the
Commission for every interconnection necessary to complete a
purchase or sale under PURPA would seriously impede the very
development of cogeneration and small power production that
Congress sought to facilitate. Many of the facilities in question
are small operations. By definition, a small power production
facility has a production capacity of no more than 80 megawatts, 16
U.S.C. § 796(17)(A)(ii) (1976 ed., Supp. V), and cogeneration
facilities may also be of modest size. Many owners of qualifying
facilities would have little incentive to purchase or sell electric
energy if they had to go through an evidentiary hearing before FERC
in Washington, D.C. every time they needed to hook up with a
utility to consummate a purchase or sale. The average cost to FERC
of a contested interconnection proceeding is currently more than
$57,000,
see FERC Notice of Proposed Rulemaking, Docket RM
82-38-000, Fees Applicable to Electric Utilities, Cogenerators, and
Small Power Producers 29-30 (Sept. 1, 1982), and the costs to
private parties are doubtless
Page 461 U. S. 421
also substantial. If we were to hold that utilities must be
provided an opportunity for a hearing whenever a qualifying
facility seeks an interconnection in order to effectuate a purchase
or sale under PURPA, we would be "imput[ing] to Congress a purpose
to paralyze with one hand what it sought to promote with the
other."
Clark v. Uebersee Finanz-Korporation, A.G.,
332 U. S. 480,
332 U. S. 489
(1947).
Cf. E. I. du Pont de Nemours & Co. v. Train,
430 U. S. 112,
430 U. S.
132-133 (1977);
Permian Basin Area Rate Cases,
390 U. S. 747,
390 U. S. 777
(1968).
We agree with the Commission that, in light of the entire
statutory scheme, § 210(e)(3) of PURPA may reasonably be
interpreted to forbid the Commission to exempt qualifying
facilities from being the target of applications under the FPA for
orders "requiring . . . [a] physical connection," FPA, §
210(a)(1), but not to forbid the Commission to grant qualifying
facilities the right to obtain interconnections without applying
for an order under the FPA. The use of the word "exempted" in
§ 210(e)(3) is consistent with an intent to ensure only that
qualifying facilities not be immunized from the requirements that
the Commission may impose under §§ 210 and 212 of the
FPA. The term "exemption" is ordinarily used to denote relief from
a duty or service.
See, e.g., Black's Law Dictionary 513
(5th ed.1979) (to "exempt" is "to relieve, excuse or set free from
a duty or service imposed upon the general class to which the
individual exempted belongs"). The only duty that §§ 210
and 212 of the FPA directly impose upon any facility is the duty to
obey an order "requiring . . . [a] physical connection." Section
212(e) of the FPA expressly states that § 210 of the FPA shall
not be construed "as requiring any person to utilize the authority
of [§ 210] . . . in lieu of any other authority of law."
Significantly, the Commission's interconnection rule does not
immunize qualifying facilities from the only requirement that
§§ 210 and 212 of the FPA do directly impose on them --
the requirement that they obey an interconnection order issued
Page 461 U. S. 422
under those provisions. Qualifying facilities remain subject to
applications by other facilities for orders requiring them to make
interconnections. The Commission's rule simply permits qualifying
facilities to take certain steps to require other parties, namely,
electric utilities, to make interconnections. [
Footnote 12] The Commission's interconnection
rule represents
"'a contemporaneous construction of a statute by the men charged
with the responsibility of setting its machinery in motion, of
making the parts work efficiently and smoothly while they are yet
untried and new.'"
Udall v. Tallman, 380 U. S. 1,
380 U. S. 16
(1965), quoting
Power Reactor Development Co. v. Electrical
Workers, 367 U. S. 396,
367 U. S. 408
(1961). To uphold it,
"we need not find that [FERC's] construction is the only
reasonable one, or even that it is the result we would have reached
had the question arisen in the first instance in judicial
proceedings. "
Page 461 U. S. 423
Unemployment Compensation Comm'n v. Aragon,
329 U. S. 143,
329 U. S. 153
(1946).
See Mourning v. Family Publications Service, Inc.,
411 U. S. 356,
411 U. S.
371-372 (1973). We need only conclude that it is a
reasonable interpretation of the relevant provisions. For the
reasons stated above, we do conclude that the Commission's
interpretation is reasonable, and that the Court of Appeals erred
in rejecting that interpretation.
IV
We hold that the Commission did not act arbitrarily or
capriciously in promulgating the full-avoided-cost rule or exceed
its authority in promulgating the interconnection rule.
Accordingly, the judgment of the Court of Appeals is reversed, and
the case is remanded for further proceedings consistent with this
opinion.
It is so ordered.
JUSTICE POWELL took no part in the consideration or decision of
these cases.
* Together with No. 82-226,
Federal Energy Regulatory
Commission v. American Electric Power Service Corp. et al.,
also on certiorari to the same court.
[
Footnote 1]
The statute defines a "cogeneration facility" as a facility that
produces both electric energy and steam or some other form of
useful energy, such as heat. 16 U.S.C. § 796(18)(A) (1976 ed.,
Supp. V). A "small power production" facility is a facility that
has a production capacity of not more than 80 megawatts and
produces electric power from biomass, waste, or renewable resources
such as wind, water, or solar energy. 16 U.S.C. § 796(17)(A)
(1976 ed., Supp. V).
[
Footnote 2]
In an accompanying regulation, FERC directed that each
qualifying facility
"pay any interconnection costs which the State regulatory
authority . . . or nonregulated electric utility may assess against
the qualifying facility on a nondiscriminatory basis."
18 CFR § 292.306(a) (1982).
[
Footnote 3]
Section 212 of the FPA, as set forth in 16 U.S.C. § 824k
(1976 ed., Supp. V), provides in pertinent part:
"(a) No order may be issued by the Commission under section 824i
[FPA § 210] . . . of this title unless the Commission
determines that such order -- "
"(1) is not likely to result in a reasonably ascertainable
uncompensated economic loss for any electric utility, qualifying
cogenerator, or qualifying small power producer, as the case may
be, affected by the order;"
"(2) will not place an undue burden on an electric utility,
qualifying cogenerator, or qualifying small power producer, as the
case may be, affected by the order;"
"(3) will not unreasonably impair the reliability of any
electric utility affected by the order; and"
"(4) will not impair the ability of any electric utility
affected by the order to render adequate service to its
customers."
"The determination under paragraph (1) shall be based upon a
showing of the parties. The Commission shall have no authority
under section 824i . . . of this title to compel the enlargement of
generating facilities."
"(b) No order may be issued under section 824i . . . of this
title unless the applicant for such order demonstrates that he is
ready, willing, and able to reimburse the party subject to such
order for -- "
"(1) in the case of an order under section 824i of this title,
such party's share of the reasonably anticipated costs incurred
under such order . . ."
* * * *
"(d) If the Commission does not issue any order applied for
under section 824i . . . of this title, the Commission shall, by
order, deny such application and state the reasons for such
denial."
"(e) No provision of section 824i . . . of this title shall be
treated -- "
"(1) as requiring any person to utilize the authority of such
section 824i . . . of this title in lieu of any other authority of
law, or"
"(2) as limiting, impairing, or otherwise affecting any
authority of the Commission under any other provision of law."
[
Footnote 4]
With respect to the Commission's statement that any savings to
consumers that a lower rate might produce would be insignificant in
comparison to the benefit to qualifying facilities provided by the
full-avoided-cost rate, the court suggested that the Commission had
failed to "bear in mind, as Congress surely knew, that inevitably
the impact of FERC's rules per consumer will be less than their
impact per cogenerator." 219 U.S.App.D.C. at 9, 675 F.2d at
1234.
[
Footnote 5]
The court proceeded to "outline some additional concerns raised
by the full avoided cost rule, which the Commission should address
in its subsequent rulemaking."
Ibid. See id. at
9-11, 675 F.2d at 1234-1236.
[
Footnote 6]
In denying a petition for rehearing, the Court of Appeals
emphasized that it had not declared the full-avoided-cost rule
inconsistent with PURPA, but had "simply remanded the matter
because the Commission had failed to explain
its rationale and
process of consideration.'" 219 U.S.App.D.C. at 21, 675 F.2d at
1246, quoting id. at 8, 675 F.2d at 1233. A suggestion for
rehearing en banc was denied by a vote of 3 to 2, with 6 of the 11
active Circuit Judges not participating. Id. at 21, 675
F.2d at 1246.
[
Footnote 7]
It is not entirely clear.from the Court of Appeals' opinion what
standard of review the court applied, but it appears that the court
may have erroneously employed the substantial evidence standard.
The court criticized FERC for failing "to demonstrate the factual
basis,"
id. at 9, 675 F.2d at 1234, for its finding that
sharing the savings from cogeneration with consumers would afford
consumers only insubstantial savings, and it cited in a footnote an
earlier decision that had employed the substantial evidence test in
a case involving informal rulemaking by the Commission under the
FPA.
Id. at 9, n. 36, 675 F.2d at 1234, n. 36, citing
Public System v. FERC, 196 U.S.App.D.C. 66, 606 F.2d 973
(1979).
In any event, the Court of Appeals should have applied only the
arbitrary-and-capricious standard. Unlike the FPA,
see 16
U.S.C. § 8251(b), PURPA does not direct reviewing courts to
determine whether orders entered thereunder are supported by
substantial evidence. In the absence of a specific command in PURPA
to employ a particular standard of review, the full-avoided-cost
rule must be reviewed solely under the more lenient
arbitrary-and-capricious standard prescribed by the Administrative
Procedure Act for judicial review of informal rulemaking.
See,
e.g., FCC v. National Citizens Committee for Broadcasting,
436 U. S. 775,
436 U. S. 803
(1978).
[
Footnote 8]
See also H.R.Conf.Rep. No. 95-1750, p. 98 (1978) (the
purchase rate prescribed by the Commission is to be "the lower of .
. . a rate which is just and reasonable to consumers of the
utility, in the public interest, and nondiscriminatory, or the
incremental cost of alternate electric energy").
[
Footnote 9]
We interpret the "just and reasonable" language of § 210(b)
to require consideration of potential rate savings for electric
utility consumers. Of course, even when utilities purchase electric
energy from qualifying facilities at full avoided cost, rather than
at some lower rate, the rates the utilities charge their customers
will not be increased, for, by hypothesis, the utilities would have
incurred the same costs had they generated the energy themselves or
purchased it from other sources. Moreover, a utility's existing
rates will ordinarily have been determined to be "just and
reasonable" by the appropriate state regulatory authority. But it
does not follow that the full-avoided-cost rule is necessarily
"just and reasonable to the electric consumers of the electric
utilities" within the meaning of § 210(b) of PURPA. Unless the
"just and reasonable" language is to be regarded as mere
surplusage, it must be interpreted to mandate consideration of rate
savings for consumers that could be produced by setting the rate at
a level lower than the statutory ceiling.
[
Footnote 10]
A decrease in the utilities' reliance on fossil fuels may result
in a reduction of the prices of those fuels to levels lower than
would have been the case with higher demand. Since the rates the
utilities are permitted to charge their customers are based on
their costs, electric utility customers can expect to share in the
savings to the utilities resulting from reduced fuel prices.
[
Footnote 11]
We reach this conclusion even though we agree with the Court of
Appeals,
see n 4,
supra, that the rule was not adequately explained by the
Commission's observation that,
"in most instances, if part of the savings from cogeneration and
small power production were allocated among the utilities'
ratepayers, any rate reductions will be insignificant for any
individual customer,"
whereas the rule would provide significant incentives for
cogenerators and small power producers. 45 Fed.Reg. 12222 (1980).
In the context of ratemaking, it is typically the case that any
increment in the rate will "make a small dent in the consumer's
pocket,"
FPC v. Texaco Inc., 417 U.
S. 380,
417 U. S. 399
(1974), while that same increment will have substantial
consequences for the parties to whom the rate is paid. FERC's
statutory mandate to prescribe a rate that "shall be just and
reasonable to the electric consumers of the electric utility," 16
U.S.C. § 824a-3(b)(1) (1976 ed., Supp. V), obviously reflects
a congressional determination that potential savings for consumers
as a class are important even though rate changes will generally
not have great economic significance for any individual consumer.
Cf. FPC v. Texaco Inc., supra, at
417 U. S. 399
("Even if the effect of increased small-producer prices would make
a small dent in the consumer's pocket, . . . the [Natural Gas] Act
makes unlawful all rates which are not just and reasonable, and
does not say a little unlawfulness is permitted").
[
Footnote 12]
The Commission's interpretation also finds support in the
indications in the legislative history of §§ 210 and 212
of the FPA that those provisions were intended to address a
different situation. Prior to their enactment the Commission's
authority to order interconnections was limited, under §
202(b) of the FPA, 16 U.S.C. § 824a(b), to utilities over
which it had regulatory jurisdiction and, except in emergencies, to
situations in which a "person engaged in the . . . sale of electric
energy" applied for an order directing such a utility to
interconnect. Congress was concerned with the refusal of some
intrastate utilities to make interconnections with other systems
because, had they done so, they would have become part of the
interstate system, and thereby become subject to the full range of
regulation under the FPA.
See 124 Cong.Rec. 34763-34764
(1978) (Sen. Metzenbaum);
id. at 34770 (Sen. Bartlett);
123 Cong.Rec. 31194 (1977) (Sen. Johnston);
id. at
32397-32398 (colloquy between Sen. Johnston and Sen. Domenici).
Sections 210, 211, and 212 of the FPA were enacted to give the
Commission authority to order interconnections where they will
enhance the reliability of the Nation's electric power systems and
optimize the use of its generating capacity. At the same time,
Congress provided, in § 201(b)(2) of the FPA, 16 U.S.C. §
824(b)(2) (1976 ed., Supp. V), that compliance with orders to
interconnect issued under § 210 or § 211 would not
subject an entity to regulation by the Commission under any other
provision of the Act. There is nothing in the legislative history
of §§ 210-212 to suggest that they were intended to
provide the exclusive means of obtaining an interconnection.