Section 8(f) of the National Labor Relations Act (NLRA)
authorizes construction industry employers and unions to enter into
so-called "prehire" agreements setting the terms and conditions of
employment for workers hired by the signatory employer without the
union's majority status first having been established under §
9 of the Act. Section 8(f) also provides that such an agreement
shall not bar a petition for a representative election under §
9. A local union and a contractors association entered into a
Master Labor Agreement which provided that work at jobsites was to
be performed only by subcontractors who had signed a labor
agreement with the union and that covered employees, including
those of subcontractors, must become union members. The agreement
also required employers to make monthly contributions to fringe
benefit trust funds on behalf of covered employees. When petitioner
subcontractor began work on a jobsite, it was not a signatory to a
labor agreement with the union, and none of its employees on the
jobsite were union members. Upon being notified by representatives
of the union and the general contractor that it was required to do
so, petitioner became a signatory to the Master Labor Agreement,
and its employees signed union cards. After petitioner submitted
monthly reports to the union trust funds, falsely stating that "no
members of this craft were employed during this month," petitioner
on several occasions postponed audits requested by respondents, the
trustees of the funds, to verify the monthly reports. Respondents
then filed suit in Federal District Court under § 301 of the
Labor Management Relations Act to compel an accounting and to
recover payment of any trust fund contributions found to be due.
The District Court entered summary judgment for respondents and
ordered payment of unpaid contributions. The Court of Appeals
affirmed.
Held: Monetary obligations assumed by an employer under
a prehire contract authorized by § 8(f) may be recovered in a
§ 301 action brought by a union prior to repudiation of the
contract by the employer, even though the union has not obtained
majority support in the relevant unit. Pp.
461 U. S.
265-272.
(a) In authorizing § 8(f) prehire contracts even though the
union's majority status was not first established, Congress
recognized that, because of the uniquely temporary, transitory, and
sometimes seasonal nature of
Page 461 U. S. 261
construction industry employment, unions often would not be able
to establish majority support with respect to many bargaining
units. Congress also recognized that an employer must know labor
costs in preparing contract bids, and must have available a supply
of skilled craftsmen for quick referral. Pp.
461 U. S.
265-267.
(b) The question presented was not decided by
NLRB v. Iron
Workers, 434 U. S. 335,
which held that § 8(b)(7)(C) of the NLRA, prohibiting
picketing to force an employer to recognize a union that is not the
certified representative of the employees in the relevant unit, was
violated by a union's picketing to enforce a § 8(f) contract
with the employer where the union had failed to request a timely
representative election. That decision was based on Congress'
intent, when it enacted § 8(f), to protect employees' rights
to select their own bargaining representatives, and to ensure that
prehire agreements are arrived at voluntarily and are voidable
until the union attains majority support in the relevant unit.
However, union enforcement, by way of a § 301 suit, of
monetary obligations incurred by an employer under a prehire
contract prior to its repudiation does not impair the right of
employees to select their own bargaining agent, or trench on the
voluntary and voidable characteristics of a 8(f) prehire agreement.
Allowing an action such as respondents' vindicates Congress'
policies in authorizing prehire contracts to meet problems unique
to the construction industry. When a § 8(f) agreement is
voluntarily executed, as here, both parties must abide by its terms
until it is repudiated. Pp.
461 U. S.
267-271.
667 F.2d 800, affirmed.
BURGER, C.J., delivered the opinion for a unanimous Court.
Page 461 U. S. 262
CHIEF JUSTICE BURGER delivered the opinion of the Court.
We granted certiorari to resolve conflicts in the Circuits as to
whether monetary obligations that have accrued under a prehire
contract authorized by § 8(f) of the National Labor Relations
Act, 73 Stat. 545, 29 U.S.C. § 158(f), can be enforced, prior
to the repudiation of such a contract, in a suit brought by a union
against an employer under § 301 of the Labor Management
Relations Act, 61 Stat. 156, 29 U.S.C. § 185, absent proof
that the union represented a majority of the employees.
I
Petitioner is engaged in the construction industry and, in
September 1978, was a subcontractor on a jobsite in southern
California. The general contractor was contractually bound to the
Master Labor Agreement negotiated between the International Union
of Operating Engineers, Local No. 12, and the Southern California
General Contractors Associations. The Master Labor Agreement
provided that work at the jobsite was to be performed only by
subcontractors who had signed a labor agreement with the Union.
[
Footnote 1] The Master Labor
Agreement also contained a union security clause requiring covered
employees, including those of subcontractors,
Page 461 U. S. 263
to become members of the Union. [
Footnote 2] At the time petitioner began work on the
jobsite as a subcontractor, it was not a signatory to a labor
agreement with the Union and none of its employees on the jobsite
were members of the Union.
On September 13, 1978, petitioner's president, McNeff, was
approached on the jobsite by a representative of the Union who
informed him that, in order to remain on the project, he was
required to sign the Master Labor Agreement. McNeff refused. Later
that day, the Union representative returned with a representative
of the general contractor, who also informed McNeff that he was
required to sign the agreement in order to remain on the project.
McNeff then signed the agreement on behalf of petitioner. [
Footnote 3] Petitioner's employees
signed union cards that same day.
The Master Labor Agreement required petitioner to make monthly
contributions to fringe benefit trust funds on behalf of each
covered employee. [
Footnote 4]
From October, 1978, through
Page 461 U. S. 264
March, 1979, petitioner submitted required monthly reports to
the trust funds, but made no contributions. Each form was submitted
by petitioner with the false notation that "no members of this
craft were employed during this month." In November, 1978, after
petitioner had filed the first of such reports, respondents, the
trustees of the funds, requested permission from petitioner to
audit its records to verify the statements made in its monthly
report. Petitioner purported to agree, but postponed the audit
several times. On April 4, 1979, respondents brought this suit
under § 301 of the Labor Management Relations Act, 29 U.S.C.
§ 185, [
Footnote 5] to
compel an accounting and payment of any contributions found to be
due the trust funds. An audit performed in pretrial discovery
proceedings revealed that petitioner had five employees covered by
the agreement during the period October, 1978, through March, 1979,
and therefore owed a total of $5,316.79 in trust fund contributions
for that period.
The District Court for the Central District of California
granted respondents' motion for summary judgment and ordered
payment of the unpaid trust fund contributions. The Court of
Appeals for the Ninth Circuit affirmed. 667 F.2d 800 (1982).
Page 461 U. S. 265
We granted certiorari, 458 U.S. 1120 (1982), in part to resolve
Circuit conflicts on this issue, [
Footnote 6] and we affirm.
II
By authorizing so-called "prehire" agreements like that at issue
in this case, § 8(f) of the National Labor Relations Act, 29
U.S.C. § 158(f), exempts construction industry employers and
unions from the general rule precluding a union and an employer
from signing
"a collective bargaining agreement recognizing the union as the
exclusive bargaining representative when in fact only a minority of
the employees have authorized the union to represent their
interests."
NLRB v. Iron Workers, 434 U. S. 335,
434 U. S.
344-345 (1978) (
Higdon).
See Garment
Workers v. NLRB, 366 U. S. 731,
366 U. S.
737-738 (1961). Section 8(f) provides in pertinent
part:
"It shall not be an unfair labor practice under subsections (a)
and (b) of this section for an employer engaged primarily in the
building and construction industry to make an agreement covering
employees engaged (or who, upon their employment, will be engaged)
in the building and construction industry with a labor organization
of which building and construction employees are members . . .
because (1) the majority status of such labor organization has not
been established under the provisions of section 9 of this Act
prior to the making of such agreement . . . :
Provided . .
. That any agreement
Page 461 U. S. 266
which would be invalid, but for clause (1) of this subsection,
shall not be a bar to a petition filed pursuant to section 9(c) or
9(e)."
73 Stat. 545.
Thus, § 8(f) allows construction industry employers and
unions to enter into agreements setting the terms and conditions of
employment for the workers hired by the signatory employer without
the union's majority status first having been established in the
manner provided for under § 9 of the Act. One factor prompting
Congress to enact § 8(f) was the uniquely temporary,
transitory, and sometimes seasonal nature of much of the employment
in the construction industry. Congress recognized that construction
industry unions often would not be able to establish majority
support with respect to many bargaining units.
See S.Rep.
No. 187, 86th Cong., 1st Sess., 55-56 (1959), 1 NLRB, Legislative
History of the Labor-Management Reporting and Disclosure Act of
1959, pp. 451-452 (Leg.Hist.). Congress was also cognizant of the
construction industry employer's need to "know his labor costs
before making the estimate upon which his bid will be based," and
that "the employer must be able to have available a supply of
skilled craftsmen for quick referral." H.R.Rep. No. 741, 86th
Cong., 1st Sess., 19 (1959), 1 Leg.Hist. 777.
See generally,
Higdon, supra, at
434 U. S.
348-349.
We first addressed the enforceability of a § 8(f) prehire
agreement in
Higdon. In response to the employer's
violation of a prehire agreement, the minority union in that case
picketed the employer for more than 30 days without filing an
election petition. The National Labor Relations Board concluded
that such picketing violated § 8(b)(7)(C). Section 8(b)(7)(C)
was intended to ensure voluntary, uncoerced selection of a
bargaining representative by employees; unless a union is the
certified representative of the employees in the relevant unit, it
prohibits picketing to force an employer "to recognize or bargain
with a labor organization as the representative of his employees."
In
Higdon, we affirmed the Board's view that a prehire
agreement does not make a union
Page 461 U. S. 267
the "representative of [an employer's] employees" as that
language is used in § 8(b)(7)(C):
"[Absent] majority credentials . . the collective bargaining
relationship and the union's entitlement to act as the exclusive
bargaining agent had never matured. Picketing to enforce the §
8(f) contract was the legal equivalent of picketing to require
recognition as the exclusive agent, and § 8(b)(7)(C) was
infringed when the union failed to request an election within 30
days."
434 U.S. at
434 U. S.
346.
III
We did not decide in
Higdon whether prehire agreements
are enforceable in a § 301 action. There is a critical
distinction between an employer's obligation under the Act to
bargain with the representative of the majority of its employees
and its duty to satisfy lawful contractual obligations that accrued
after it enters a prehire contract. Only the former obligation was
treated in
Higdon. [
Footnote 7]
In upholding the Board's view that a union commits an unfair
labor practice by picketing to enforce a prehire agreement before
it has attained majority status, we noted in
Page 461 U. S. 268
Higdon that this view protects two interests that
Congress intended to uphold when it enacted § 8(f). First, our
holding in
Higdon protects the § 7 rights of
employees to select their own bargaining representative. [
Footnote 8] To be sure, § 8(f)
affects the § 7 rights of employees by allowing a minority
union to reach an agreement with the employer setting the terms and
conditions of employment. This is the direct and intended
consequence of § 8(f) and, in any event, is limited by the
final proviso in § 8(f) that permits employees -- and other
parties mentioned in §§ 9(c) and (e) of the Act -- to
challenge a prehire agreement at any time by petitioning the Board
for a representative election. If, however, an employer could be
compelled by picketing to treat a minority union as the exclusive
bargaining agent of employees, the § 7 rights of those
employees would be undermined to an extent not contemplated by
Congress. As we noted in
Higdon, 434 U.S. at
434 U. S. 338,
a union that is the certified representative of the employees in
the relevant unit does not commit an unfair labor practice under
§ 8(b)(7)(C) by picketing to compel compliance with a
collective bargaining agreement. Consequently, freeing a minority
union from the confines of § 8(b)(7)(C) would grant that union
power otherwise accorded only to certified bargaining
representatives chosen by a majority of the affected employees. It
is up to those employees to decide what organization, if any, will
enter into a collective bargaining agreement on their behalf and
have the consequent right to engage in picketing, if necessary, to
enforce it; the union signatory to a
Page 461 U. S. 269
prehire agreement cannot arrogate such power to itself until it
"successfully seeks majority support."
Higdon, supra, at
434 U. S.
350.
Second, our decision in
Higdon promotes
Congress"'intention . . . that prehire agreements were to be
arrived at voluntarily. . . ."
Higdon, 434 U.S. at
434 U. S. 348,
n. 10. In accord with this intention, we approved the Board's
conclusion that a "prehire agreement is voidable" "until and unless
[the union] attains majority support in the relevant unit."
Id. at
434 U. S. 341.
Allowing the union to picket to enforce a prehire agreement before
it attains majority status is plainly inconsistent with the
voidable nature of a prehire agreement.
The concerns with the § 7 rights of employees to select
their own bargaining representative and our fidelity to Congress'
intent that prehire agreements be voluntary -- and voidable -- that
led to our decision in
Higdon are not present in this
case. Union enforcement, by way of a § 301 suit, of monetary
obligations incurred by an employer under a prehire contract prior
to its repudiation does not impair the right of employees to select
their own bargaining agent. Unlike the situation in
Higdon, enforcement of accrued obligations in a § 301
suit does not mean that the union represents a majority of the
employer's employees. In a § 301 suit, the District Court
merely enforces a contract entered into by the employer -- a
contract that Congress has legitimated to meet a special situation
even though employees themselves have no part in its negotiation or
execution. Such enforcement does not grant the plaintiff union a
right otherwise enjoyed only by a majority union except in the very
narrow sense, expressly intended by Congress, that employers and
minority unions in the construction industry do not violate the Act
by entering into prehire agreements. There is no sense in which
respondents' contract action has a recognitional purpose like that
forbidden in
Higdon.
Neither does respondents' § 301 action trench on the
voluntary and voidable characteristics of a § 8(f) prehire
agreement.
Page 461 U. S. 270
It is clear in this case that petitioner entered into the
prehire agreement voluntarily. [
Footnote 9] Moreover, although the voidable nature of
prehire agreements clearly gave petitioner the right to repudiate
the contract, it is equally clear that petitioner never manifested
an intention to void or repudiate the contract. For the relevant
period of time, [
Footnote
10] the record shows conclusively that petitioner accepted the
benefits of the prehire agreement and misled the union of its true
intention never to fulfill its contractual obligations. Whatever
may be required of a party wishing to exercise its undoubted right
to repudiate a prehire agreement before the union attains majority
support in the relevant unit, no appropriate action was taken by
petitioner to do so in this case. [
Footnote 11] Consequently, respondents' suit does not
enervate the voluntary and voidable characteristics of the prehire
agreement.
Page 461 U. S. 271
Apart from not offending the concerns noted in
Higdon,
allowing a minority union to enforce overdue obligations accrued
under a prehire agreement prior to its repudiation vindicates the
policies Congress intended to implement in § 8(f). Congress
clearly determined that prehire contracts should be lawful to meet
problems unique to the construction industry. However limited the
binding effect of a prehire agreement may be, it strains both logic
and equity to argue that a party to such an agreement can reap its
benefits and then avoid paying the bargained-for consideration.
Nothing in the legislative history of § 8(f) indicates
Congress intended employers to obtain free the benefits of stable
labor costs, labor peace, and the use of the union hiring hall.
[
Footnote 12] Having had the
music, he must pay the piper.
By the same token, the union cannot simply accept the employer's
performance under a prehire contract without upholding its end of
the bargain. Neither party is compelled to enter into a § 8(f)
agreement. But when such an agreement is voluntarily executed, both
parties must abide by its terms until it is repudiated. [
Footnote 13]
IV
A § 8(f) prehire agreement is subject to repudiation until
the union establishes majority status. However, the monetary
obligations assumed by an employer under a prehire
Page 461 U. S. 272
contract may be recovered in a § 301 action brought by a
union prior to the repudiation of the contract, even though the
union has not attained majority support in the relevant unit. There
having been no repudiation in this case, the judgment of the Court
of Appeals is
Affirmed.
[
Footnote 1]
Article IV, § D, of the agreement provides:
"The Contractor agrees that neither he nor any of his
subcontractors on the jobsite will subcontract any work to be done
at the site of construction, alteration, painting or repair of a
building, structure or other work (including quarries, rock, sand
and gravel plants, asphalt plants, ready-mix concrete plants,
established on or adjacent to the jobsite to process or supply
materials for the convenience of the Contractor for jobsite use),
except to a person, firm or corporation, party to an appropriate,
current labor agreement with the appropriate Union, or subordinate
body signatory to this Agreement."
App. 39.
[
Footnote 2]
Article II, §§ D and E, of the agreement provide:
"D. Employees employed by one or more of the Contractors for a
period of eight (8) days continuously or accumulatively under the
work jurisdiction of a particular Union as that term is defined
herein shall be or become on the eighth (8th) day or eight (8) days
after the effective date of this Agreement, whichever is later,
members of such Union and shall remain members of such Union as a
condition of continued employment. Membership in such Union shall
be available upon terms and qualifications not more burdensome than
those applicable at such times to other applicants for membership
to such Union."
"E. The Contractor shall discharge any employee pursuant to the
foregoing section upon written notice from the Union of such
employee's nonpayment of initiation fees or dues."
App. 38.
[
Footnote 3]
Specifically, petitioner entered into an agreement that adopted
the Master Labor Agreement "in its entirety," with certain
exceptions that are not relevant to this case.
Id. at
9-13.
[
Footnote 4]
The agreement provides:
"The undersigned employer by his signature acknowledges receipt
of a true and correct copy of the Agreement establishing the
Operating Engineers Trusts:"
"AND, further by his signature, accepts all of the terms and
conditions of said Trust Agreements and agrees to be bound thereto
in every way, including the obligation to make periodic
contributions and payments pursuant to the requirement of the Board
of Trustees consistent with said Trust Agreements and the
Collective Bargaining Agreement between said employer and Local 12,
International Union of Operating Engineers."
Id. at 12-13.
The record shows that McNeff initialed petitioner's acceptance
of the following trust fund obligations: (1) pension trust; (2)
health and welfare trust; (3) vacation-holiday trust; (4)
apprentice trust; (5) journeyman training trust; and (6) industry
fund trust.
Id. at 13.
[
Footnote 5]
Section 301(a) provides:
"Suits for violation of contracts between an employer and a
labor organization representing employees in an industry affecting
commerce as defined in this Act, or between any such labor
organizations, may be brought in any district court of the United
States having jurisdiction of the parties, without respect to the
amount in controversy or without regard to the citizenship of the
parties."
61 Stat. 156.
[
Footnote 6]
Compare Washington Area Carpenters' Welfare Fund v. Overhead
Door Co. of Metropolitan Washington, 220 U.S.App.D.C. 273, 681
F.2d 1 (1982); 667 F.2d 800 (CA9 1982) (case below);
W. C.
James, Inc. v. Oil, Chemical & Atomic Workers International
Union, 646 F.2d 1292 (CA8 1981);
New Mexico District
Council of Carpenters v. Mayhew Co., 664 F.2d 215 (CA10 1981);
and Contractors, Laborers, Teamsters & Engineers Health
& Welfare Plan v. Associated Wrecking Co., 638 F.2d 1128
(CA8 1981),
with Laborers District Council of Alabama v.
McDowell Contractors, Inc., 680 F.2d 94 (CA11 1982),
and
Baton Rouge Building & Construction Trades Council v. E. C.
Schafer Construction Co., 657 F.2d 806 (CA5 1981).
[
Footnote 7]
In
Higdon, we addressed the question whether holding a
prehire contract to be unenforceable in a § 301 suit would be
contrary to
Retail Clerks v. Lion Dry Goods, Inc.,
369 U. S. 17
(1962). In
Lion Dry Goods, the Court stated that §
301(a) confers jurisdiction on the federal courts to entertain
suits on contracts between an employer and a minority union, as
well as suits on contracts between an employer and actual
collective bargaining agents. Section 8(f) contracts were noted as
being within a federal court's § 301(a) jurisdiction.
Id. at
369 U. S. 29. In
Higdon, we merely noted that
"[i]t would not be inconsistent with
Lion Dry Goods for
a court to hold that the union's majority standing is subject to
litigation in a § 301 suit to enforce a § 8(f) contract .
. . and that, absent a showing that the union is the majority's
chosen instrument, the contract is unenforceable."
434 U.S. at
434 U. S.
351-352. This statement was intended to show that the
question of jurisdiction under § 301 is different from the
question of enforceability of a prehire agreement in a § 301
action. We did not decide the latter question.
[
Footnote 8]
Section 7 of the Act, 29 U.S.C. § 157, guarantees employees
the right to bargain collectively through representatives of their
own choosing. Section 9(a) of the Act, 29 U.S.C. § 159(a),
provides that the bargaining agent for all employees in the
appropriate unit must be the representative "designated or selected
for the purposes of collective bargaining by the majority of the
employees. . . ." It is an unfair labor practice for an employer
under §§ 8(a)(1) and (2) and for a union under §
8(b)(1)(A) to interfere with, restrain, or coerce employees in the
exercise of their right to select their representative.
See
generally Garment Workers v. NLRB, 366 U.
S. 731 (1961).
[
Footnote 9]
There is no merit to petitioner's claim that it was coerced into
entering the agreement. Petitioner was simply informed that the
general contractor on the jobsite was bound by a union signatory
subcontracting clause in its collective bargaining agreement with
the Union. That clause required petitioner to enter into a similar
agreement with the Union if it wanted to stay on the jobsite. Such
clauses are lawful under the construction industry proviso of
§ 8(e) of the Act, 29 U.S.C. § 158(e). As we said in
Woelke & Romero Framing, Inc. v. NLRB, 456 U.
S. 645 (1982), whatever pressures petitioner complains
of as a result of the union signatory subcontracting clause are
"implicit in the construction industry proviso."
Id. at
456 U. S. 663.
Petitioner cannot rely on such "pressure," made lawful by the
construction industry proviso, to support its contention that it
entered the prehire agreement at issue in this case
involuntarily.
[
Footnote 10]
The only time period relevant to this case is that between
September 13, 1978 (the date the prehire agreement was entered
into), and April 26, 1979 (the date respondents' § 301 suit
was filed). The District Court entered judgment for respondents for
the trust fund obligations incurred by petitioner for this period
of time only. App. to Pet. for Cert. 10-11. Respondents did not
appeal the amount of their recovery.
[
Footnote 11]
It is not necessary to decide in this case what specific acts
would effect the repudiation of a prehire agreement -- sending
notice to the union, engaging in activity overtly and completely
inconsistent with contractual obligations, or, as respondents
suggest, precipitating a representation election pursuant to the
final proviso in § 8(f) that shows the union does not enjoy
majority support.
[
Footnote 12]
Petitioner received another benefit not expressly contemplated
by Congress. Here, the Union had a collective bargaining agreement
with the general contractor requiring that work at the jobsite was
to be performed only by subcontractors who had signed an agreement
with the Union.
See n
l,
supra. Thus, the direct consequence of petitioner's
entering into the prehire agreement was to enable petitioner to
remain on the job.
[
Footnote 13]
We need not consider in this case whether considerations
properly cognizable by a court under § 301 might prevent
either party, in particular circumstances, from exercising its
option under § 8(f) to repudiate a prehire agreement before
the union demonstrates majority status.