Petitioner brought a diversity action in Federal District Court
against respondent, seeking damages and reformation with regard to
a certain series of contracts between the parties. Various claims
were asserted, including a $19 million claim for amounts due on the
contracts already performed. Respondent filed counterclaims. The
facts as to most of the claims and counterclaims are in dispute,
but the sole dispute as to petitioner's claim for the $19 million
balance due concerns the application of a release clause in each of
the contracts. The District Court granted summary judgment for
petitioner for $19 million, plus prejudgment interest at the
statutory rate of 6%, notwithstanding the release clause.
Petitioner then moved for a certification of this judgment as a
final judgment under Federal Rule of Civil Procedure 54(b), which
provides that, when more than one claim is presented in an action,
whether as a claim or counterclaim, a district court may direct the
entry of a final judgment as to one or more but fewer than all of
the claims upon an express determination that there is no just
reason for delay. The court granted the motion and directed entry
of final judgment for petitioner after determining that there was
"no just reason for delay" and finding,
inter alia, that
certification would not result in unnecessary appellate review;
that the claims finally adjudicated were separate from
Page 446 U. S. 2
any of the other claims or counterclaims; that the nature of the
claims was such that no appellate court would have to decide the
same issues more than once even if there were subsequent appeals;
that petitioner would suffer severe financial loss from nonpayment
of the $19 million judgment because current interest rates were
higher than the statutory prejudgment rates; and that the solvency
of the parties was not a significant factor, since each appeared to
be financially sound. Dismissing the case for want of an appealable
order, the Court of Appeals held that the District Court had abused
its discretion by granting the Rule 54(b) certification, since the
possibility of a setoff required that the
status quo be
maintained unless petitioner could show harsh or unusual
circumstances and since no such showing had been made.
Held: The District Court did not abuse its discretion
in granting petitioner's motion for certification under Rule 54(b).
Pp.
446 U. S.
7-13.
(a) In deciding whether there are just reasons to delay an
appeal of individual final judgments in a setting such as this, a
district court must take into account the interests of sound
judicial administration, as well as the equities involved. Hence,
it was proper for the District Court here to consider such factors
as whether the claims under review were separable from the others
remaining to be adjudicated and whether the nature of the claims
already determined was such that no appellate court would have to
decide the same issues more than once even if there were subsequent
appeals. The mere presence of nonfrivolous counterclaims does not
render a Rule 54(b) certification inappropriate. Pp.
446 U. S. 8-9.
(b) The Court of Appeals' holding that the
status quo
had to be maintained absent a showing by petitioner of harsh or
unusual circumstances reflects a misinterpretation of the standard
of review for Rule 54(b) certifications and a misperception of the
appellate function in such cases. Pp.
446 U. S.
9-10.
(c) The proper standard against which a district court's
exercise of discretion in granting a Rule 54(b) certification is to
be judged is the interest of sound judicial administration. Under
this standard, although the court of appeals must scrutinize the
district court's evaluation of such factors as the
interrelationship of the claims so as to prevent piecemeal appeals,
once such juridical concerns have been met, the district court's
discretionary judgment should be given substantial deference, and
the court of appeals should disturb the district court's assessment
of the equities only if it can say that the district judge's
conclusion was clearly unreasonable. Pp.
446 U. S.
10-11.
(d) The question before the District Court here came down to
which of the parties should get the benefit of the difference
between the prejudgment
Page 446 U. S. 3
and market rates of interest on the debts admittedly owing and
adjudged to be due while unrelated claims were litigated. While the
possibility of a setoff against the amount respondent owed
petitioner was not an insignificant factor, the District Court took
this into account when it determined that both litigants appeared
to be financially sound, and that petitioner would be able to
satisfy a judgment on the counterclaims if any were entered. Pp.
446 U. S.
11-12.
597 F.2d 35, vacated and remanded. BURGER, C.J., delivered the
opinion for a unanimous Court.
MR. CHIEF JUSTICE BURGER delivered the opinion of the Court.
Federal Rule of Civil Procedure 54(b) allows a district court
dealing with multiple claims or multiple parties to direct the
entry of final judgment as to fewer than all of the claims or
parties; to do so, the court must make an express determination
that there is no just reason for delay. We granted certiorari in
order to examine the use of this procedural device. 444 U.S. 823
(1979).
I
From 1968 to 1972, respondent General Electric Co. entered into
a series of 21 contracts with petitioner Curtiss-Wright Corp. for
the manufacture of components designed for use in nuclear powered
naval vessels. These contracts had a total value of $215
million.
In 1976, Curtiss-Wright brought a diversity action in the United
States District Court for the District of New Jersey, seeking
damages and reformation with regard to the 21 contracts. The
complaint asserted claims based on alleged fraud,
Page 446 U. S. 4
misrepresentation, and breach of contract by General Electric.
It also sought $19 million from General Electric on the outstanding
balance due on the contracts already performed.
General Electric counterclaimed for $1.9 million in costs
allegedly incurred as the result of "extraordinary efforts"
provided to Curtiss-Wright during performance of the contracts
which enabled Curtiss-Wright to avoid a contract default. General
Electric also sought, by way of counterclaim, to recover $52
million by which Curtiss-Wright was allegedly unjustly enriched as
a result of these "extraordinary efforts."
The facts underlying most of these claims and counterclaims are
in dispute. As to Curtiss-Wright's claims for the $19 million
balance due, however, the sole dispute concerns the application of
a release clause contained in each of the 21 agreements, which
states that
"Seller . . . agree[s] as a condition precedent to final
payment, that the Buyer and the Government . . . are released from
all liabilities, obligations and claims arising under or by virtue
of this order."
App. 103a. When Curtiss-Wright moved for summary judgment on the
balance due, General Electric contended that, so long as
Curtiss-Wright's other claims remained pending, this provision
constituted a bar to recovery of the undisputed balance.
The District Court rejected this contention and granted summary
judgment for Curtiss-Wright on this otherwise undisputed claim.
Applying New York law by which the parties had agreed to be bound,
the District Court held that Curtiss-Wright was entitled to payment
of the balance due notwithstanding the release clause. The court
also ruled that Curtiss-Wright was entitled to prejudgment interest
at the New York statutory rate of 6 per annum.
Curtiss-Wright then moved for a certification of the District
Court's orders as final judgments under Federal Rule of Civil
Procedure 54(b), [
Footnote 1]
which provides:
"When more than one claim for relief is presented in an
Page 446 U. S. 5
action, whether as a claim, counterclaim, cross-claim, or
third-party claim, or when multiple parties are involved, the court
may direct the entry of a final judgment as to one or more but
fewer than all of the claims or parties only upon an express
determination that there is no just reason for delay and upon an
express direction for the entry of judgment. In the absence of such
determination and direction, any order or other form of decision,
however designated, which adjudicates fewer than all the claims or
the rights and liabilities of fewer than all the parties shall not
terminate the action as to any of the claims or parties, and the
order or other form of decision is subject to revision at any time
before the entry of judgment adjudicating all the claims and the
rights and liabilities of all the parties."
The court expressly directed entry of final judgment for
Curtiss-Wright, and made the determination that there was "no just
reason for delay" pursuant to Rule 54(b).
The District Court also provided a written statement of reasons
supporting its decision to certify the judgment as final. It
acknowledged that Rule 54(b) certification was not to be granted as
a matter of course, and that this remedy should be reserved for the
infrequent harsh case because of the overload in appellate courts
which would otherwise result from appeals of an interlocutory
nature. The essential inquiry was stated to be
"whether, after balancing the competing factors, finality of
judgment should be ordered to advance the interests of sound
judicial administration and justice to the litigants."
The District Court then went on to identify the relevant factors
in the case before it. It found that certification would not result
in unnecessary appellate review; that the claims
Page 446 U. S. 6
finally adjudicated were separate, distinct, and independent of
any of the other claims or counterclaims involved; that review of
these adjudicated claims would not be mooted by any future
developments in the case; and that the nature of the claims was
such that no appellate court would have to decide the same issues
more than once, even if there were subsequent appeals.
Turning to considerations of justice to the litigants, the
District Court found that Curtiss-Wright would suffer severe daily
financial loss from nonpayment of the $19 million judgment, because
current interest rates were higher than the statutory prejudgment
rate, a situation compounded by the large amount of money involved.
The court observed that the complex nature of the remaining claims
could, without certification, mean a delay that "would span many
months, if not years."
The court found that solvency of the parties was not a
significant factor, since each appeared to be financially sound.
Although the presence of General Electric's counterclaims and the
consequent possibility of a setoff recovery were factors which
weighed against certification, the court, in balancing these
factors, determined that they were outweighed by the other factors
in the case. Accordingly, it granted Rule 54(b) certification. It
also granted General Electric's motion for a stay without bond
pending appeal.
A divided panel of the United States Court of Appeals for the
Third Circuit held that the case was controlled by its decision in
Allis-Chalmers Corp. v. Philadelphia Electric Co., 521
F.2d 360 (1975), where the court had stated:
"In the absence of unusual or harsh circumstances, we believe
that the presence of a counterclaim, which could result in a
set-off against any amounts due and owing to the plaintiff, weighs
heavily against the grant of 54(b) certification."
Id. at 366 (footnote omitted). In Allis-Chalmers, the
court defined unusual or harsh cir
Page 446 U. S. 7
circumstances as those factors "involving considerations of
solvency, economic duress, etc."
Id. at 366, n. 14.
In the Third Circuit's view, the question was which of the
parties should have the benefit of the amount of the balance due
pending final resolution of the litigation. The court held that
Allis-Chalmers dictated
"that the matter remain in
status quo when nonfrivolous
counterclaims are pending, and in the absence of unusual or harsh
circumstances."
597 F.2d 35, 36 (1970) (per curiam). The Court of Appeals
acknowledged that Curtiss-Wright's inability to have use of the
money from the judgment might seem harsh, but noted that the same
could be said for General Electric if it were forced to pay
Curtiss-Wright now, but later prevailed on its counterclaims.
Ibid. .
The Court of Appeals concluded that the District Court had
abused its discretion by granting Rule 54(b) certification in this
situation, and dismissed the case for want of an appealable order;
it also directed the District Court to vacate its Rule 64(b)
determination of finality. Curtiss-Wright's petition for rehearing
and suggestion for rehearing en bane were denied. 599 F.2d 1259
(1979). Four judges dissented from that denial, observing that the
case was in conflict with
United Bank of Pueblo v. Hartford
Accident & Indemnity Co., 529 F.2d 490 (CA10 1976). We
reverse.
II
Nearly a quarter of a century ago, in
Sears, Roebuck &
Co. v. Mackey, 351 U. S. 427
(1956), this Court outlined the steps to be followed in making
determinations under Rule 54(b). A district court must first
determine that it is dealing with a "final judgment." It must be a
"judgment" in the sense that it is a decision upon a cognizable
claim for relief, and it must be "final" in the sense that it is
"an ultimate disposition of an individual claim entered in the
course of a multiple claims action." 351 U.S. at
351 U. S.
436.
Page 446 U. S. 8
Once having found finality, the district court must go on to
determine whether there is any just reason for delay. Not all final
judgments on individual claims should be immediately appealable,
even if they are in some sense separate from the remaining
unresolved claims. The function of the district court under the
Rule is to act as a "dispatcher."
Id. at
351 U. S. 435.
It is left to the sound judicial discretion of the district court
to determine the "appropriate time" when each final decision in a
multiple claims action is ready for appeal.
Ibid. This
discretion is to be exercised "in the interest of sound judicial
administration."
Id. at
351 U. S.
437.
Thus, in deciding whether there are no just reasons to delay the
appeal of individual final judgments in a setting such as this, a
district court must take into account judicial administrative
interests, as well as the equities involved. Consideration of the
former is necessary to assure that application of the Rule
effectively "preserves the historic federal policy against
piecemeal appeals."
Id. at
351 U. S. 438.
It was therefore proper for the District Judge here to consider
such factors as whether the claims under review were separable from
the others remaining to be adjudicated and whether the nature of
the claims already determined was such that no appellate court
would have to decide the same issues more than once, even if there
were subsequent appeals. [
Footnote
2]
Here the District Judge saw no sound reason to delay appellate
resolution of the undisputed claims already adjudicated. The
contrary conclusion of the Court of Appeals was strongly
Page 446 U. S. 9
influenced by the existence of nonfrivolous counterclaims. The
mere presence of such claims, however, does not render a Rule 54(b)
certification inappropriate. If it did, Rule 54(b) would lose much
of its utility. In
Cold Metal Process Co. v. United Engineering
& Foundry Co., 351 U. S. 445
(1956), this Court explained that counterclaims, whether compulsory
or permissive, present no special problems for Rule 54(b)
determinations; counterclaims are not to be evaluated differently
from other claims. 351 U.S. at
351 U. S. 452.
Like other claims, their significance for Rule 54(b) purposes turns
on their interrelationship with the claims on which certification
is sought. Here, the District Judge determined that General
Electric's counterclaims were severable from the claims which had
been determined in terms of both the factual and the legal issues
involved. The Court of Appeals did not conclude otherwise.
What the Court of Appeals found objectionable about the District
Judge's exercise of discretion was the assessment of the equities
involved. The Court of Appeals concluded that the possibility of a
setoff required that the
status quo be maintained unless
petitioner could show harsh or unusual circumstances; it held that
such a showing had not been made in the District Court.
This holding reflects a misinterpretation of the standard of
review for Rule 54(b) certifications and a misperception of the
appellate function in such cases. The Court of Appeals relied on a
statement of the Advisory Committee on the Rules of Civil
Procedure, and its error derives from reading a description in the
commentary as a standard of construction. When Rule 54(b) was
amended in 1946, the Notes of the Advisory Committee which
accompanied the suggested amendment indicated that the entire
lawsuit was generally the appropriate unit for appellate
review,
"and that this rule needed only the exercise of a discretionary
power to afford a remedy in the infrequent harsh case to provide a
simple, definite, workable rule."
28 U.S.C.App. p. 484; 5 F.R.D. 433, 473 (1946).
Page 446 U. S. 10
However accurate it may be as a description of cases qualifying
for Rule 54(b) treatment, the phrase "infrequent harsh case," in
isolation, is neither workable nor entirely reliable as a benchmark
for appellate review. There is no indication it was ever intended
by the drafters to function as such.
In
Sears, the Court stated that the decision to certify
was, with good reason, left to the sound judicial discretion of the
district court. At the same time, the Court noted that, "[w]ith
equally good reason, any
abuse of that discretion remains
reviewable by the Court of Appeals." 351 U.S. at
351 U. S. 437
(emphasis added). The Court indicated that the standard against
which a district court's exercise of discretion is to be judged is
the "interest of sound judicial administration."
Ibid.
Admittedly this presents issues not always easily resolved, but the
proper role of the court of appeals is not to reweigh the equities
or reassess the facts, but to make sure that the conclusions
derived from those weighings and assessments are juridically sound
and supported by the record.
There are thus two aspects to the proper function of a reviewing
court in Rule 54(b) cases. The court of appeals must, of course,
scrutinize the district court's evaluation of such factors as the
interrelationship of the claims so as to prevent piecemeal appeals
in cases which should be reviewed only as single units. But once
such juridical concerns have been met, the discretionary judgment
of the district court should be given substantial deference, for
that court is "the one most likely to be familiar with the case and
with any justifiable reasons for delay."
Sears, supra at
351 U. S. 437.
The reviewing court should disturb the trial court's assessment of
the equities only if it can say that the judge's conclusion was
clearly unreasonable.
Plainly, sound judicial administration does not require that
Rule 54(b) requests be granted routinely. That is implicit in
commending them to the sound discretion of a district court.
Because this discretion "is, with good reason, vested by the rule
primarily" in the district courts,
Sears, supra at
351 U. S. 437,
and because the number of possible situations is large, we are
Page 446 U. S. 11
reluctant either to fix or sanction narrow guidelines for the
district courts to follow. We are satisfied, however, that, on the
record here, the District Court's assessment of the equities was
reasonable.
One of the equities which the District Judge considered was the
difference between the statutory and market rates of interest.
Respondent correctly points out that adjustment of the statutory
prejudgment interest rate is a matter within the province of the
legislature, but that fact does not make the existing differential
irrelevant for Rule 54(b) purposes. If the judgment is otherwise
certifiable, the fact that a litigant who has successfully reduced
his claim to judgment stands to lose money because of the
difference in interest rates is surely not a "just reason for
delay."
The difference between the prejudgment and market interest rates
was not the only factor considered by the District Court. The court
also noted that the debts in issue were liquidated and large, and
that absent Rule 54(b) certification they would not be paid for
"many months, if not years," because the rest of the litigation
could be expected to continue for that period of time. The District
Judge had noted earlier in his opinion on the merits of the release
clause issue that respondent General Electric contested neither the
amount of the debt nor the fact that it must eventually be paid.
App. 164a-172a. The only contest was over the effect of the release
clause on the timing of the payment, an isolated and strictly legal
issue on which summary judgment had been entered against
respondent.
The question before the District Court thus came down to which
of the parties should get the benefit of the difference between the
prejudgment and market rates of interest on debts admittedly owing
and adjudged to be due while unrelated claims were litigated. The
central factor weighing in favor of General Electric was that its
pending counterclaims created the possibility of a setoff against
the amount it owed petitioner.
Page 446 U. S. 12
This possibility was surely not an insignificant factor,
especially since the counterclaims had survived a motion to dismiss
for failure to state a claim.
Id. a 173a-174a. But the
District Court took this into account when it determined that both
litigants appeared to be in financially sound condition, and that
Curtiss-Wright would be able to satisfy a judgment on the
counterclaims should any be entered.
The Court of Appeals concluded that this was not enough, and
suggested that the presence of such factors as economic duress and
insolvency would be necessary to qualify the judgment for Rule
54(b) certification. 597 F.2d at 36. But if Curtiss-Wright were
under a threat of insolvency, that factor alone would weigh against
qualifying; that very threat would cast doubt upon Curtiss-Wright's
capacity to produce all or part of the $19 million should General
Electric prevail on some of its counterclaims. Such a showing would
thus, in fact, be self-defeating.
Nor is General Electric's solvency a dispositive factor; if its
financial position were such that a delay in entry of judgment on
Curtiss-Wright's claims would impair Curtiss-Wright's ability to
collect on the judgment, that would weigh in favor of
certification. But the fact that General Electric is capable of
paying either now or later is not a "just reason for delay." At
most, as the District Court found, the fact that neither party is
or will become insolvent renders that factor neutral in a proper
weighing of the equities involved.
The question in cases such as this is likely to be close, but
the task of weighing and balancing the contending factors is
peculiarly one for the trial judge, who can explore all the facets
of a case. As we have noted, that assessment merits substantial
deference on review. Here, the District Court's assessment of the
equities between the parties was based on an intimate knowledge of
the case, and is a reasonable one. The District Court having found
no other reason justifying delay, we conclude that it did not abuse
its discretion in
Page 446 U. S. 13
granting petitioner's motion for certification under Rule 54(b).
[
Footnote 3]
Accordingly, the judgment of the Court of Appeals is vacated,
and the case is remanded for proceedings consistent with this
opinion.
It is so ordered.
[
Footnote 1]
This was the second motion by Curtiss-Wright for Rule 54(b)
certification. An earlier motion was denied by the District Court
because, at that time, the matter of prejudgment interest had not
yet been resolved.
[
Footnote 2]
We do not suggest that the presence of one of these factors
would necessarily mean that Rule 54(b) certification would be
improper. It would, however, require the district court to find a
sufficiently important reason for nonetheless granting
certification. For example, if the district court concluded that
there was a possibility that an appellate court would have to face
the same issues on a subsequent appeal, this might perhaps be
offset by a finding that an appellate resolution of the certified
claims would facilitate a settlement of the remainder of the
claims.
See Cold Metal Process Co. v. United Engineering &
Foundry Co., 351 U. S. 445,
351 U. S. 450,
n. 5 (1956) .
[
Footnote 3]
We note that Federal Rule of Civil Procedure 62(h) allows a
court certifying a judgment under Rule 54(b) to stay its
enforcement until the entering of a subsequent judgment or
judgments. Rule 62(h) also states that the court "may prescribe
such conditions as are necessary to secure the benefit thereof to
the party in whose favor the judgment is entered." Under this Rule,
we assume it would be within the power of the District Court to
protect all parties by having the losing party deposit the amount
of the judgment with the court, directing the Clerk to purchase
high yield government obligations and to hold them pending the
outcome of the case. In this way, valid considerations of economic
duress and solvency, which do not affect the juridical
considerations involved in a Rule 54(b) determination, can be
provided for without preventing Rule 54(b) certification.
In the instant case, after certifying the judgment as final
under Rule 54(b), the District Court granted respondent's motion
for a stay of judgment without bond, but only pending resolution of
the appeal.