Because of a claimed natural gas shortage, respondent pipeline
company submitted to the Federal Power Commission (FPC) for
approval an interim curtailment plan which resulted from a
settlement agreement between respondent company and its customers
providing for allocation of natural gas supplies among the
customers during shortage periods and a monetary compensation
scheme whereby customers receiving more gas than the systemwide
average would compensate customers receiving less. The FPC rejected
the plan on the ground that the compensation scheme would violate
various provisions of the Natural Gas Act. Thereafter, respondent
company and several of its customers sought review of the FPC's
order. The Court of Appeals entered an interlocutory order
directing the FPC to investigate the company's claims of reduced
gas reserves and to report the result of the investigation directly
to the court.
Held:
1. The Court of Appeals' order, although interlocutory, is
properly reviewable by this Court on certiorari pursuant to 28
U.S.C. § 1254(1), since its effect is immediate and
irreparable and any review by the Court of its propriety must be
immediate to be meaningful.
2. An actual gas shortage is a necessary predicate to the FPC's
assertion of authority under its transportation jurisdiction to
approve curtailment of gas already contracted for, and the Court of
Appeals could properly conclude that the FPC would have abused its
discretion had it approved curtailment plans absent evidence
whereby it "could have reasonably believed" the shortage to exist,
and that "substantial evidence" in the record is necessary to
support any such finding.
3. The Court of Appeals, however, exceeded its reviewing
authority in ordering the gas shortage investigation, since §
19(b) of the Natural Gas Act providing for judicial review of
FPC
Page 423 U. S. 327
decisions contemplates a mode of review that considers only the
agency's decision and the evidence on which it is based, and not
some new record initially made by the reviewing court. If new
evidence is needed, the case must be remanded so that the agency
can decide in its discretion how best to develop the needed data
and how its prior decision should be modified in the light
thereof.
4. Since it cannot be determined from the record whether
evidence regarding respondent company's actual gas shortage is
absolutely essential for the Court of Appeals' review, that court
is free on remand either to consider the merits of the issues
presented by the compensation scheme, and only thereafter to deal
with the adequacy of the record evidence as to the shortage, or
immediately to remand the case to the FPC for the required
inquiry.
5. In light of the immediacy of the gas shortage problem, the
protracted nature of the review proceedings, and the potential
importance of a resolution on the merits of the compensation scheme
issues, the Court of Appeals should give priority consideration to
the case on remand.
Certiorari granted; 171 U.S.App.D.C. 66, 518 F.2d 459, vacated
and remanded.
PER CURIAM.
The Federal Power Commission seeks certiorari from an
interlocutory order of the Court of Appeals for the District of
Columbia Circuit which defers that court's review of the Commission
order at issue pending completion of a certain evidentiary
investigation by the Commission directed by the court. The
Commission challenges the authority of the Court of Appeals to
order the investigation under the statutory review provision
involved, § 19(b) of the Natural Gas Act, 52 Stat. 831, as
amended, 15 U.S.C. § 717r(b), and, in any event, contends that
the Court of Appeals abused its discretion in the circumstances of
this case.
The underlying case involves plans for coping with a natural gas
shortage being experienced by respondent Transcontinental Gas Pipe
Line Corp. (Transco). The
Page 423 U. S. 328
shortage is said to require curtailment of contracted natural
gas deliveries by Transco to its customers during periods of high
demand. The curtailment plans concern methods of allocating the
shortfall among the various customers. The curtailment plan
immediately at issue was submitted by Transco to cover the period
of November, 1974, to November, 1975. This interim plan was filed
in September, 1974, and was the result of a settlement agreement
negotiated between Transco and its various customers. The agreement
provided for a plan of allocation of natural gas supplies among
Transco's customers during periods of shortage, and a monetary
compensation scheme under which customers receiving more gas than
the systemwide average would compensate customers who received less
natural gas than the average. The Commission rejected the proposed
plan, determining that the compensation scheme would be violative
of the Natural Gas Act. The Commission held that the compensation
scheme would violate (1) § 4(a) of the Act, 15 U.S.C. §
717c(a), which requires a pipeline's jurisdictional rate to be
based on the pipeline's cost of service plus a reasonable rate of
return; (2) § 4(b) of the Act, 15 U.S.C. § 717c(b), which
prohibits undue discrimination in rates among similarly situated
customers; and (3) § 7(c) of the Act, 15 U.S.C. §
717f(c), which requires persons engaging in resales of natural gas
in interstate commerce first to obtain a certificate of public
convenience and necessity.
Thereafter, Transco and several of the parties to the settlement
agreement sought review of the Commission's determination.
[
Footnote 1] Following oral
argument on the petition
Page 423 U. S. 329
for review, the Court of Appeals, "desiring to be more fully
informed about the
crisis' on the Transco system before
reviewing questions pertaining to its solution," entered an order
sua sponte directing the parties to submit certain
information concerning Transco's natural gas reserves. After
receiving responses to this order, and noting the refusal of the
Commission to certify the accuracy of the data supplied by Transco
regarding its reserves of natural gas, the court directed the
parties to show cause why it should not order the Commission to
conduct an immediate investigation of Transco's claim of reduced
reserves. Thereafter, the Court of Appeals, observing that evidence
of "actual shortage both underlies the concept of curtailment and
justifies its application," issued the proposed order. That order
directed the Commission to complete and report to the court an
investigation
"of Transco's claims of reduced reserves by immediate subpoena
of Transco's books and records pertaining to all gas supplies in
which it has any legal interest . . . and by field investigation
[which] has determined the extent of the reduced reserves and the
bona fides of Transco and its suppliers in meeting their
past and future contract commitments. . . ."
The court further directed that its decision reviewing
Page 423 U. S. 330
the Commission's order would be deferred pending the
investigation and report, and that the investigation and report
should be made by the Commission within 30 days.
It is this interlocutory order for which the Commission
petitions for review by this Court. The Commission first argues
that the Court of Appeals has overstepped the bounds of its
reviewing authority in ordering this investigation by the
Commission, and that, in doing so the court has unwarrantedly
interfered with the internal functional autonomy of an independent
administrative agency. Additionally, the Commission argues, the
Court of Appeals has abused its discretion in ordering the factual
inquiry by the Commission in the circumstances presented by this
case. The Commission maintains that the extent of Transco's natural
gas shortage is not material to the legal issues -- concerning the
lawfulness of the proposed compensation scheme -- which presently
confront the Court of Appeals. This is said to be particularly true
where, as here, the Commission has disapproved the proposed interim
plan for dealing with the alleged shortage of gas. [
Footnote 2] Finally, the Commission argues
that it is impossible to comply with the order, as such a complex
investigation would require much longer than the 30 days
allowed.
First. We agree with the Commission that the challenged
order, although interlocutory in nature, is properly
Page 423 U. S. 331
reviewable by this Court pursuant to 28 U.S.C. § 1254(1).
Clearly the effect of the order is immediate and irreparable, and
any review by this Court of the propriety of the order must be
immediate to be meaningful.
Second. We agree with the Court of Appeals that the
existence of an actual shortage of gas supplies forms the factual
predicate necessary to the Commission's assertion of authority
under its transportation jurisdiction, § 1(b) of the Act, 15
U.S.C. § 717(b), to approve the curtailment of gas already
contracted for.
FPC v. Louisiana Power & Light Co.,
406 U. S. 621
(1972). Certainly that court could properly conclude that the
Commission would have abused its discretion had it approved
curtailment plans in the absence of evidence whereby it "could have
reasonably believed" the shortage to exist,
Citizens to
Preserve Overton Park v. Volpe, 401 U.
S. 402,
401 U. S. 416
(1971), and that "substantial evidence" in the record is necessary
to support any such finding by the Commission.
Third. We are of the view, however, that the Court of
Appeals overstepped the bounds of its reviewing authority in
issuing the order presently before us. First, we have consistently
expressed the view that ordinarily review of administrative
decisions is to be confined to "consideration of the decision of
the agency . . . and of the evidence on which it was based."
United States v. Carlo Bianchi & Co., 373 U.
S. 709,
373 U. S.
714-715 (1963).
"[T]he focal point for judicial review should be the
administrative record already in existence, not some new record
made initially in the reviewing court."
Camp v. Pitts, 411 U. S. 138,
411 U. S. 142
(1973). If the decision of the agency
"is not sustainable on the administrative record made, then the
. . . decision must be vacated and the matter remanded . . . for
further consideration."
Id. at
411 U. S. 143.
Clearly it is this mode of review that is contemplated
Page 423 U. S. 332
by the statute providing for judicial review of Commission
decisions, § 19(b) of the Act, 15 U.S.C. § 717r(b).
[
Footnote 3] Secondly, although
we have recognized that
Page 423 U. S. 333
a court reviewing decisions of the Federal Power Commission sits
as a court vested with equity powers and "may authorize the
Commission in proper cases to take new evidence,"
Mobil Oil
Corp. v. FPC, 417 U. S. 283,
417 U. S.
311-312 (1974), it is nevertheless true that ordinarily
this will require a remand to the agency in order that it can
exercise its administrative discretion in deciding how, in light of
internal organizational considerations, it may best proceed to
develop the needed evidence and how its prior decision should be
modified in light of such evidence as develops. Certainly this is
the procedure contemplated by the review statute, which provides
that the Commission "may modify its findings as to the facts by
reason of the additional evidence so taken," and that "such
modified or new findings, . . . if supported by substantial
evidence, shall be conclusive. . . ." 15 U.S.C. § 717r(b). At
least in the absence of substantial justification for doing
otherwise, [
Footnote 4] a
reviewing court may not, after determining that additional evidence
is requisite for adequate review, proceed by dictating to the
agency the methods, procedures, and time dimension of the needed
inquiry and ordering the results to be reported to the court
without opportunity for further consideration on the basis of the
new evidence by the agency. Such a procedure clearly runs the risk
of "propel[ling] the court into the domain which Congress has set
aside exclusively for the administrative agency."
SEC v.
Chenery Corp., 332 U. S. 194,
332 U. S. 196
(1947).
"The Court, it is true, has power 'to affirm, modify, or set
aside' the order of the
Page 423 U. S. 334
Commission 'in whole or in part.' . . . But that authority is
not power to exercise an essentially administrative function."
FPC v. Idaho Power Co., 344 U. S.
17,
344 U. S. 21
(1952).
Fourth. We are unable to determine with certainty, from
this vantage point and on the partial record now before us, whether
the evidence regarding Transco's actual shortage with which the
instant order is concerned is absolutely essential to a decision by
the Court of Appeals on the issues presently before that court for
review. Although Judge MacKinnon, in his separate statement, was
apparently of the view that it was not, it is at least conceivable
that the Court of Appeals could determine that the lawfulness of
the proposed compensation scheme is partially a function of the
actual severity of the shortage.
Cf. FPC v. Louisiana Power
& Light Co., supra. Accordingly, the court below is free
on remand either to proceed to the merits of the issues presented
by the compensation scheme, and only thereafter deal with the
adequacy of the record in regard to the evidence of shortage, or
immediately to remand the case to the Commission for the required
inquiry. It is apparent that, under neither alternative need the
Court of Appeals' ability fully and effectively to review the
administrative process regarding the implementation of curtailment
plans and their underlying factual premises be relinquished.
Fifth. In light of the immediacy of the natural gas
shortage problem with which the Commission is attempting to cope,
the already protracted nature of review proceedings in this case,
and the potential importance of a resolution on the merits of the
compensation issues presented by the instant case, [
Footnote 5] swift and priority
consideration
Page 423 U. S. 335
of this case by the Court of Appeals on remand is merited.
Accordingly, the petition for certiorari is granted, the order
of the Court of Appeals is vacated, and the case is remanded to
that court for further proceedings consistent with this
opinion.
It is so ordered.
MR. JUSTICE STEWART and MR. JUSTICE POWELL took no part in the
consideration or decision of this case.
[
Footnote 1]
Although neither the petitioning Commission nor the two
respondents who have filed responses to the petition for certiorari
have addressed the issue, it appears that the underlying
controversy is not now moot even though it concerns an interim plan
covering a period of time that has by now expired. The Court of
Appeals earlier granted a motion by Transco and ordered the interim
plan into effect pending that court's review of the Commission's
order disallowing the plan.
Consolidated Edison Co. v.
FPC, 167 U.S.App.D.C. 134, 143, 511 F.2d 372, 381 (1974). The
court ordered that the compensation payments under the plan be paid
into an escrow account pending review of the Commission's
determination that the compensation scheme was unlawful.
Ibid. Therefore, it appears that, at the least, the
disposition of these payments into the escrow account will be
affected by the Court of Appeals' ultimate judgment on the merits
of the case.
[
Footnote 2]
This argument appears to accord with the views of Judge
MacKinnon which are set forth in a separate statement accompanying
the challenged order. Judge MacKinnon expressed the view that the
extent of the shortage is "peripheral," although "not wholly
irrelevant" to the legal issues confronting the Court of Appeals.
He indicated that he would instead first reach the merits, affirm
the order of the Commission, and then direct that the Commission
make the complex factual inquiry regarding the shortage "prior to
passing on any subsequent curtailment plan."
[
Footnote 3]
Section 19(b) of the Natural Gas Act provides:
"Any party to a proceeding under this chapter aggrieved by an
order issued by the Commission in such proceeding may obtain a
review of such order in the court of appeals of the United States
for any circuit wherein the natural gas company to which the order
relates is located or has its principal place of business, or in
the United States Court of Appeals for the District of Columbia
[Circuit], by filing in such court, within sixty days after the
order of the Commission upon the application for rehearing, a
written petition praying that the order of the Commission be
modified or set aside in whole or in part. A copy of such petition
shall forthwith be transmitted by the clerk of the court to any
member of the Commission and thereupon the Commission shall file
with the court the record upon which the order complained of was
entered, as provided in section 2112 of Title 28. Upon the filing
of such petition such court shall have jurisdiction, which upon the
filing of the record with it shall be exclusive, to affirm, modify,
or set aside such order in whole or in part. No objection to the
order of the Commission shall be considered by the court unless
such objection shall have been urged before the Commission in the
application for rehearing unless there is reasonable ground for
failure so to do. The finding of the Commission as to the facts, if
supported by substantial evidence, shall be conclusive. If any
party shall apply to the court for leave to adduce additional
evidence, and shall show to the satisfaction of the court that such
additional evidence is material and that there were reasonable
grounds for failure to adduce such evidence in the proceedings
before the Commission, the court may order such additional evidence
to be taken before the Commission and to be adduced upon the
hearing in such manner and upon such terms and conditions as to the
court may seem proper. The Commission may modify its findings as to
the facts by reason of the additional evidence so taken, and it
shall file with the court such modified or new findings, which if
supported by substantial evidence, shall be conclusive, and its
recommendation, if any, for the modification or setting aside of
the original order. The judgment and decree of the court,
affirming, modifying, or setting aside, in whole or in part, any
such order of the Commission, shall be final, subject to review by
the Supreme Court of the United States upon certiorari or
certification as provided in sections 346 and 347 of Title 28."
[
Footnote 4]
We do not find the reasons stated by the Court of Appeals,
largely that the Commission "has been long on notice" that data
supporting the claimed existence of shortage was necessary, to be,
in the circumstances presented, sufficient justification for the
court's order.
[
Footnote 5]
See Mississippi Pub. Serv. Comm'n v. FPC, 555 F.2d 1345
(CA5 1975).