The Federal Power Commission (FPC) instituted a proceeding in
1961 to establish an area rate structure for interstate sales of
natural gas produced in the Southern Louisiana area. After
extensive hearings, the FPC in 1968 issued an order establishing
ceiling rates for gas sold by producers in the area and ordering
refunds of rates in excess of the maximum that had been collected
prior to the order. The Court of Appeals upheld the order, but
declared that the affirmance was not to be interpreted to foreclose
the FPC from making such changes in its order, as to both past and
future rates, as it found to be in the public interest. In response
to petitions for rehearing urging that the FPC's authority to
modify its order, after affirmance by the court, could be exercised
only prospectively, the Court of Appeals stated that
"[w]e wish to make crystal clear the authority of the Commission
in this case to reopen any part of its order that circumstances
require be opened,"
that "[t]he Commission can make retrospective as well as
prospective adjustments in this case if it finds that it is in the
public interest to do so," and that, if
"the refunds are too burdensome in light of new evidence to be
in the public interest . . . , the Commission shall have the power
and the duty to remedy the situation by changing its orders."
The FPC thereupon reopened the 1961 proceeding, and, after
considering a settlement proposal that had been agreed to by a
large majority of the parties, issued an order in 1971 establishing
a new rate structure for the Southern Louisiana area superseding
the 1968 order. This 1971 order established,
inter alia,
(1) higher ceiling rates for both "flowing" or "first vintage" gas
(gas delivered after the order's effective date under contracts
dated prior to
Page 417 U. S. 284
October 1, 1968), and "new" or "second vintage" gas (gas
delivered after the order's effective date under contracts dated
after October 1, 1968); (2) two incentive programs, one providing
for refund workoff credits based on a refund obligor's commitment
of additional gas reserves to the interstate market (the producer
being required to offer at least 50% of the new reserves to the
purchaser to whom the refund would otherwise be payable), and the
other providing for contingent escalation of rates based on new
dedications of gas to the market; (3) minimum rates to be paid by
producers to pipelines for transportation of liquids and
liquefiable hydrocarbons; and (4) a moratorium upon the filing of
rate increases for flowing gas until October 1, 1976, and for new
gas until October 1, 1977. The Court of Appeals upheld this order
as an appropriate exercise of administrative discretion supported
by substantial evidence on the authority of
Permian Basin Area
Rate Cases, 390 U. S. 747.
Held:
1. The FPC had the statutory authority to adopt the 1971 order,
notwithstanding the Court of Appeals' affirmance of the 1968 order.
Pp.
417 U. S.
310-315.
(a) Under circumstances where the Court of Appeals' affirmance
of the 1968 order was not "unqualified" or final, and such order
had not been made effective, but was stayed until withdrawn in the
1971 order, the Court of Appeals' action in authorizing the FPC to
reopen the 1968 order did not exceed the court's powers under
§ 19(b) of the Natural Gas Act "to affirm, modify, or set
aside [an] order in whole or in part," or constitute an improper
exercise of the court's equity powers with which it is vested in
reviewing FPC orders. Pp.
417 U. S.
310-312.
(b) The fact that the settlement proposal lacked unanimous
agreement of the parties did not preclude the FPC from adopting the
proposal as an order establishing just and reasonable rates, since
the FPC clearly had the power to admit the agreement into the
record, and indeed was obliged to consider it. Pp.
417 U. S.
312-314.
(c) The fact that the Court of Appeals' opinion on rehearing
regarding the 1968 order authorized modification of the 1968 refund
provisions if the refunds "are too burdensome in light of new
evidence to be in the public interest" did not require the FPC,
before revising the refund terms, to find, based on substantial new
evidence, that the refunds "would substantially and adversely
affect the producers' ability to meet the continuing gas needs of
the interstate market," since the opinion on rehearing was
explicit
Page 417 U. S. 285
that the FPC was to have "great flexibility," and could make
retrospective as well as prospective adjustments; moreover, the
Court of Appeals flatly rejected
"the notion that the label 'affirmance' could possibly impair
FPC's ability to alter or modify any of the provisions,
particularly the refund provisions"
of the 1968 order. Pp.
417 U. S.
314-315.
2. Petitioners' challenges to the established price levels under
the 1971 order are without merit. Pp.
417 U. S.
315-321.
(a) Mobil's attack on the FPC's evidence of costs is clearly
frivolous, since the FPC took extensive evidence of costs in its
1968 order hearings for flowing gas and in both its 1968 and 1971
hearings for new gas, and since the fragments of the record cited
by Mobil do not sustain its heavy burden of showing that the FPC's
choice was outside what the Court of Appeals could have found to be
within the FPC's authority. P.
417 U. S.
316.
(b) With respect to Mobil's argument that inclusion of refund
workoff credits and contingent escalations in the just and
reasonable rates indicates that producers unable to gain part or
all of their share of such payments will receive merely their
"bare-bones" costs, which constitute illegally low prices, the
Court of Appeals did not err in deciding that it was within the
FPC's discretion and expertise to conclude that the refund workoff
credits and contingent escalations could provide an opportunity for
increased prices that would help in generating capital funds and in
meeting rising costs, while assuring that such increases will not
be levied upon consumers unless accompanied by increased supplies
of gas. Pp.
417 U. S.
316-319.
(c) New York's contention that the 1971 order rates for flowing
gas are excessive is predicated on an erroneously limited view of
the permissible range of the FPC's authority. Where the FPC's
justification for increasing the price of flowing gas was the
necessity for increased revenues to expand future production,
rather than new evidence of differing production conditions, the
Court of Appeals, against the background of a serious and growing
domestic gas shortage, could properly conclude that the FPC might
reasonably decide that, as compared with adjustments in rate
ceilings to induce more exploration and production, its
responsibility to maintain adequate supplies at the lowest
reasonable rate could better be discharged by means of contingent
escalation and refund credits. Pp.
417 U. S.
319-321.
3. The claims of all three petitioners, with respect to both the
contingent escalations on flowing gas and the refund credits,
that
Page 417 U. S. 286
even if the 1971 rates are sufficient to satisfy the Natural Gas
Act's minimum requirements as to amount and, on the basis of the
FPC's chosen methodology, are supported by substantial evidence,
they are nevertheless unduly discriminatory and therefore unlawful
under §§ 4 and 5 of the Act, are also without merit. Pp.
417 U. S.
321-327.
(a) Concerning Mobil's argument that undue discrimination
results because producers who had not settled their refund
obligations will receive advantages from the contingent escalations
and refund credits that producers like Mobil, which did settle its
obligations, will not receive, it cannot be said that the Court of
Appeals misapprehended or grossly misapplied the substantial
evidence standard in concluding that the FPC's assessment of the
need for refund credits, compared to the costs and benefits of some
other scheme, was adequately supported. Pp.
417 U. S.
321-325.
(b) Though New York and MDG argue that the refund credit formula
discriminates against pipeline purchasers because it permits
producers to work off refunds by offering 50%, rather than 100%, of
the new reserves to pipeline purchasers other than those owed the
refunds, the Court of Appeals did not err in holding that the
refund credit provision, the purpose of which was to increase the
supply of gas, was within the FPC's discretion, since the FPC could
reasonably conclude that the producers' incentive to explore for
and produce new gas in the area, could result in their dedication
of new reserves that would exceed in benefit the amount of the
refunds. P.
417 U. S.
325.
(c) With respect to New York's argument that some producers
might abandon their normal business of exploring for and developing
new reserves and yet enjoy the increase in their prices for flowing
gas if other producers contribute substantial additional reserves,
the FPC's belief that producers already operating in the area will
continue to do so is at least an equally tenable judgment, and New
York offered nothing to overcome the presumption of validity
attaching to the exercise of the FPC's expertise. Pp.
417 U. S.
326-327.
4. The Court of Appeals' conclusion, contrary to Mobil's
contention, that the FPC's fixing of moratoria on new rate filings
was supported by required findings of fact and by substantial
evidence, did not misapprehend or grossly misapply the substantial
evidence standard. Pp.
417 U. S.
327-328.
5. Mobil's argument that the FPC improperly failed to provide
automatic adjustments in area rates to compensate for
anticipated
Page 417 U. S. 287
higher royalty costs, is hypothetical at this stage and, in any
event, an affected producer is entitled to seek individualized
relief. P.
417 U. S.
328.
6. The Court of Appeals did not err in concluding that the FPC
"acted within the bounds of administrative propriety in abandoning"
as a pragmatic adjustment the distinction in maximum permissible
rates between casinghead gas and gas-well gas so far as new
dedications are concerned, even though casinghead gas was formerly
treated as a byproduct of oil, and therefore costed and priced
lower than gas-well gas. Pp.
417 U. S.
328-330.
7. In arguing that the minimum rates provided by the 1971 order
to be paid by producers to pipelines for transportation of liquids
and liquefiable hydrocarbons are not supported by substantial
evidence, Mobil has not met its burden of demonstrating that the
Court of Appeals misapprehended or grossly misapplied the
substantial evidence standard. P.
417 U. S.
330.
483 F.2d 880, affirmed.
BRENNAN, J., delivered the opinion of the Court, in which all
Members joined except STEWART and POWELL, JJ., who took no part in
the consideration or decision of the cases.
Page 417 U. S. 288
MR. JUSTICE BRENNAN delivered the opinion of the Court.
We review here the affirmance by the Court of Appeals for the
Fifth Circuit of a 1971 order of the Federal Power Commission
[
Footnote 1] that established
an area rate structure for interstate sales [
Footnote 2] of natural gas produced in the
Southern
Page 417 U. S. 289
Louisiana area. The Southern Louisiana area is one of seven
geographical areas defined by the Commission for the purpose of
prescribing area-wide price ceilings. [
Footnote 3] This
Page 417 U. S. 290
is the second area rate case to reach this Court. The first was
the
Permian Basin Area Rate Cases, 390 U.
S. 747 (1968), in which the Court sustained the
constitutional
Page 417 U. S. 291
and statutory authority of the Commission to adopt a system of
area regulation and to impose supplementary requirements in the
discharge of its responsibilities under §§ 4 and 5 of the
Natural Gas Act [
Footnote 4] to
determine whether producers' rates are just and reasonable.
The Court of Appeals affirmed the 1971 order in its
Page 417 U. S. 292
entirety as an appropriate exercise of administrative discretion
supported by substantial evidence on the record as a whole.
Placid Oil Co. v. FPC, 483 F.2d 880 (1973). We granted the
petitions for certiorari in these three cases [
Footnote 5] to review the correctness of the Court
of Appeals' holding sustaining the 1971 order as in all respects
within the Commission's statutory powers, and to determine whether
the Court of Appeals misapprehended or grossly misapplied the
substantial evidence standard. 414 U.S. 1142 (1974). We affirm.
I
The Commission first instituted proceedings to establish an area
rate structure for the Southern Louisiana area on May 10, 1961. 25
F.P.C. 942. The area consists of the southern portion of the State
of Louisiana and the federal and state areas of the Gulf of Mexico
off the Louisiana coast. The area accounts for about one-third of
the Nation's domestic natural gas production
Page 417 U. S. 293
and has been described as "the most important ga producing area
in the country."
Southern Louisiana Area Rate Cases, 428
F.2d 407, 418 (CA5 1970) (hereafter
SoLa I). Proceedings
continued over seven years. [
Footnote 6] On September 25, 1968, the Commission issued
an order establishing an area rate structure, 40 F.P.C. 530, and,
on March 20, 1969, a modified order on rehearing, 41 F.P.C. 301.
[
Footnote 7] Refunds under this
structure for overcharges during the pendency of the proceeding
amounted to some $375 million. [
Footnote 8]
An appeal was taken to the Court of Appeals for the Fifth
Circuit. On March 19, 1970, the Court of Appeals
Page 417 U. S. 294
affirmed the FPC orders but with "serious misgivings,"
SoLa
I, supra, at 439. Noting that " [a] serious shortage, in fact,
may already be unavoidable . . . ,"
id. at 437, the Court
of Appeals was critical of the Commission's failure adequately to
assess "supply and demand in either a semi-quantitative or
qualitative way,"
id. at 436. It was reinforced in this
view by the evidence, including an FPC Staff Report, issued while
the appeal was pending, [
Footnote
9] that the Nation was faced with "a severe gas shortage, with
disastrous effects on consumers and the economy alike."
Id. at 435 n. 87.
Therefore, although determining "that affirmance is the best
course,"
id. at 439, the Court of Appeals declared that
the judgment was not in any wise to foreclose the Commission from
making such changes in its orders, as to both past and future
rates, as it found to be in the public interest. The court noticed
the fact that, while the appeal was pending, the Commission, in
March, 1969, had instituted proceedings to reconsider rates for the
offshore portion of Southern Louisiana,
see 41 F.P.C. 378,
and later that year expanded the procedure to include the entire
area, 42 F.P.C. 1110. Thus, it stated:
"The mandate of this Court should not, however, be interpreted
to interfere with Commission action that would change the rates we
have approved here. We
Page 417 U. S. 295
specifically and emphatically reject the contention advanced . .
. that the Commission has no power to set aside rates once
determined by it to be just and reasonable when it has reason to
believe its determinations may have been erroneous. In fact, the
existence of the new proceedings, which, as we understand them,
will take into account many of the issues whose absence has
concerned us here, has been one of the factors we have considered
in deciding to affirm the Commission's decisions."
428 F.2d at 5.
Pending decision on petitions for rehearing, however, the
Commission advised the Court of Appeals, in a letter requested by
the court, that, unless that court otherwise directed, it did not
believe that it had authority to modify, rescind, or set aside a
rate order or moratorium affirmed by the court. The Court of
Appeals answered in its opinion denying rehearing, 444 F.2d 125,
126-127 (1970):
"We wish to make crystal clear the authority of the Commission
in this case to reopen any part of its order that circumstances
require be reopened. Under section 19(b) of the Natural Gas Act,
this Court has the broad remedial powers that inhere in a court of
equity, and, pursuant to our equitable powers, we make it part of
the remedy in this case that the authority of the Commission to
reopen any part of its orders, including those affecting revenues
from gas already delivered, is left intact. The Commission can make
retrospective as well as prospective adjustments in this case if it
finds that it is in the public interest to do so."
"At the same time, we emphasize that our judgment is an
affirmance, and not a remand. The appropriate place for originally
considering what
Page 417 U. S. 296
parts of the orders must be reopened in light of new evidence is
before the Commission. It may be that the Commission will decide
that the refunds it has ordered are just and reasonable, or at
least that their significance to the public interest is outweighed
by the confusion and delay that would result from their reopening.
In this event, the Commission will allow its refund orders to stand
as they are. Or it may be that the refunds are too burdensome in
light of new evidence to be in the public interest. In that case,
it is our judgment that the Commission shall have the power and the
duty to remedy the situation by changing its orders."
The Commission thereupon formally reopened the 1961 proceeding
and consolidated it with the new proceeding, 44 F.P.C. 1638 (1970).
[
Footnote 10] An extensive
record of many thousands of pages of testimony and more than a
hundred exhibits was compiled between April, 1970, and March, 1971.
[
Footnote 11] Pursuant to
the instructions of the Court of Appeals, much of the evidence
focused on the gas shortage, projected levels of demand, and
estimates of new supply needed to alleviate the problem. Evidence
was also adduced bearing upon rate levels needed to induce
additional supply, the potential industry consequences of any new
order, and new cost trends based on data unavailable at the time of
the earlier proceedings.
Contemporaneously with the hearings, settlement conferences were
instituted, on motion by the Presiding Examiner, 46 F.P.C. 86, 103
(1971), and those conferences were attended by producers,
pipelines, distributors,
Page 417 U. S. 297
state commissions, municipally owned utilities, and the
Commission staff. Eventually, a settlement proposal was submitted
by one of the parties, [
Footnote
12] and, after being placed on the record for comments, it was
agreed to by a large majority of all interests. [
Footnote 13] An intermediate decision of
the Presiding Examiner was waived, and the Commission took up the
case.
At the outset, the Commission stated that it believed that
adoption of the settlement proposal was precluded unless the
Commission found the terms to be in the public interest and
supported by substantial evidence. [
Footnote 14]
Page 417 U. S. 298
Accordingly, the Commission evaluated the proposal in the light
of the massive record that had been compiled in the decade since
1961, including the additional year of hearings directed in large
part to the terms of the settlement proposal and the nature of the
supply shortage. The Commission concluded that the terms of the
proposed settlement were just and reasonable, and found them to be
supported by substantial evidence in the record. [
Footnote 15] The ceiling rates established
in the 1968 orders, which because of Commission and court stays had
never gone into effect, were held "now [to] perform no office," 46
F.P.C. at 102.
The effective date of the 1971 order was August 1, 1971. By the
terms of this order, "flowing gas,"
i.e., gas delivered
after August 1, 1971, under contracts dated prior to October 1,
1968, receives treatment different from "new gas,"
i.e.,
gas delivered after August 1, 1971, under contracts dated after
October 1, 1968. The established flowing gas price ceilings are
22.275� per thousand cubic feet (Mcf) for gas produced
onshore and 21.375� per Mcf for gas produced offshore. The
established new gas price ceilings are 26� for both onshore
and offshore gas.
Flowing gas ceilings automatically increased 0.5� per Mcf
on October 1, 1973, and, as a further incentive for increasing the
gas supply, the Commission also established increases up to
1.5� per Mcf, contingent upon the industry's finding and
dedicating new gas reserves. [
Footnote 16] New
Page 417 U. S. 299
gas rates automatically increase 1� per Mcf on October 1,
1974. A moratorium is imposed upon the filing of producer rate
increases for flowing gas until October 1, 1976, and for new gas
until October 1, 1977.
The Commission also established minimal pipeline rates to be
charged producers by pipelines for the transportation of certain
liquid and liquefiable hydrocarbons, and eliminated the price
differential between casinghead gas (gas dissolved in or associated
with the production of oil) and new gas-well gas that it had
imposed in earlier cases. 46 F.P.C. at 144.
See Permian
Basin, 390 U.S. at
390 U. S.
760-761.
The problem of refunds concerns deliveries of flowing gas prior
to August 1, 1971. The rates established by the 1971 order were
higher than those that would have been established under the 1968
order had they been put into effect. [
Footnote 17] If refunds had been calculated on the basis
of the 1968 order, they would have aggregated over $375 million. If
they had been calculated upon the basis of the 1971 flowing gas
ceiling rates, refunds would have aggregated less than $150
million. However, the proposed settlement stipulated a refund
obligation of $150 million, with a proviso that this could be
worked off by the commitment by a refund obligor of additional gas
reserves to the interstate market. [
Footnote 18] The Commission
Page 417 U. S. 300
adopted this proposal as an integral part of the 1961-1971 rate
structure and established a schedule aggregating $150 million of
refunds from those that were owed but not yet paid by producers who
had collected rates in excess of certain prescribed levels lower
than the established flowing gas rates. [
Footnote 19]
II
Before addressing petitioners' arguments, we must consider
briefly the situation in which the Commission has found itself in
its attempts to regulate the natural gas market; the teachings of
Permian Basin and other decisions of this Court as to the
extent of the Commission's
Page 417 U. S. 301
statutory authority in this area; the limitations upon review by
the Court of Appeals of the Commission's order; and the limitations
upon review by this Court of the Court of Appeals' affirmance of
the order.
The history of the Commission's early experience with the
Natural Gas Act, 15 U.S.C. § 717
et seq., has been
fully developed in our first area rate opinion,
Permian Basin,
supra, at
390 U. S.
755-759, and may be merely summarized here. With the
passage of the Act in 1938, 52 Stat. 821, Congress gave the
Commission authority to determine and fix "just and reasonable
rate[s]," § 5(a), 15 U.S.C. § 717d(a), [
Footnote 20] for the "sale in interstate
commerce of natural gas for resale for ultimate public consumption
for domestic, commercial, industrial, or any other use. . . ."
§ 1(b), 15 U.S.C. § 717(b). [
Footnote 21] The Act was patterned after earlier
regulatory statutes that applied to traditional public utilities
and transportation companies, and that provided for setting rates
equal to such companies' costs of service plus a reasonable rate of
return. [
Footnote 22]
Page 417 U. S. 302
Until 1954, the Commission construed its mandate as requiring
that it regulate the chain of distribution of natural gas only from
the point where an interstate pipeline acquired it. [
Footnote 23] Because such pipelines were
relatively
Page 417 U. S. 303
few in number [
Footnote
24] and fell within the transportation company model, the
Commission was able to apply a traditional regulatory approach,
using individualized costs of service as a basis for determining
price. [
Footnote 25]
In 1954, however, this Court ruled in
Phillips Petroleum Co.
v. Wisconsin, 347 U. S. 672,
that independent producers are "[n]atural gas compan[ies]" within
the meaning of § 2(6) of the Act, 15 U.S.C. § 717a(6).
[
Footnote 26] In response,
the Commission at first attempted to extend to this new industry
its old regulatory methods, including establishment of individual
rates based on each producer's costs of service. [
Footnote 27] The effort foundered on the
sheer
Page 417 U. S. 304
size of the task -- thousands of independent producers being
engaged in jurisdictional sales of gas at that time. [
Footnote 28]
In the early 1960's the Commission discontinued its attempts to
deal with individual companies, [
Footnote 29] and turned to the area rate method. The
Commission established a number of discrete geographical areas
within which it believed that costs and general operating
conditions were reasonably similar, [
Footnote 30] and set out to establish, by convening
hearings and compiling massive records, uniform rate schedules that
would govern all producers within each area. Upon the conclusion of
the first of these undertakings, we reviewed the Commission's
efforts and found no reversible error.
Permian Basin Area Rate
Cases, 390 U. S. 747
(1968).
See Wisconsin v. FPC, 373 U.
S. 294 (1963).
But, the Commission was soon confronted with indications, both
from data available to it, [
Footnote 31] and from criticism of its effort, [
Footnote 32] that its cost emphasis
in rate determination was being accompanied by a severe shortage in
the supply of natural gas being dedicated to the interstate market.
Since the Commission's subsequent area rate orders, [
Footnote 33] including both its 1968 and
1971 orders, are adapted from the initial
Permian Basin
model and are governed by the same statutory provisions
concerning
Page 417 U. S. 305
ratemaking and judicial review, we will preface our discussion
of the Commission's response to these difficulties with a brief
review of the
Permian Basin order and the applicable rules
laid down in our opinion sustaining that order.
Subsequent to its establishment of geographical areas in 1961,
[
Footnote 34] the Commission
consolidated three of those areas to form the
Permian
Basin area. The rate structure devised for this area set two
ceiling prices, the higher one for gas produced from gas wells and
dedicated to interstate commerce after January 1, 1961, and the
other for gas-well gas dedicated to interstate commerce before
January 1, 1961, and all gas produced from oil wells (casinghead
gas) either associated with the production of the oil or dissolved
in it. [
Footnote 35] The
Commission derived the higher rate for the newer "vintage" gas-well
gas from composite cost data obtained both from answers to producer
questionnaires and from published data said to reflect the national
costs of finding and producing gas-well gas in 1960. [
Footnote 36] It derived the lower
rate from Permian Basin historical cost data for the older vintage
gas -- well gas, and applied that rate to both that and casinghead
gas without distinction. [
Footnote 37] To these composite costs, the Commission
added a return of 12% [
Footnote
38] on the producers' average production investment, [
Footnote 39] obtained by examining
the cost data, imputing a rate base, and assuming that gas wells
deplete at a constant rate beginning one year after investment and
ending 20
Page 417 U. S. 306
years later. [
Footnote
40] Finally, an adjustment up or down from the area ceiling
rates was specified for gas of higher or lower quality and energy
content than set by a selected standard. [
Footnote 41] The resulting ceiling rates, including
allowances for state taxes, were 14.5� per Mcf for first
vintage and casinghead gas, and 16.5� for second vintage
gas. For those producers who individually might suffer hardship
under this rate schedule, the Commission indicated that it would on
rare occasions provide special relief, but it declined to specify
what circumstances would justify such action. [
Footnote 42]
On review, the Court of Appeals refused to approve the
Commission's order, holding that certain determinations of the
ultimate effects of the order had not been made as required by
FPC v. Hope Natural Gas Co., 320 U.
S. 591 (1944), that more precise delineation of the
requirements for relief from the order must be set forth, and that
the Commission could not require that producers refund excess
charges during the pendency of the proceeding unless it concluded
that aggregate actual area revenues exceeded aggregate permissible
area revenues, and then apportioned only the excess among producers
on an equitable basis. 375 F.2d 6, 36 (1967).
On certiorari, this Court initially noted that judicial review
of the Commission's orders is extremely limited:
"Section 19(b) of the Natural Gas Act provides without
qualification that the 'finding of the Commission as to the facts,
if supported by substantial
Page 417 U. S. 307
evidence, shall be conclusive.' More important, we have
heretofore emphasized that Congress has entrusted the regulation of
the natural gas industry to the informed judgment of the
Commission, and not to the preferences of reviewing courts. A
presumption of validity therefore attaches to each exercise of the
Commission's expertise, and those who would overturn the
Commission's judgment undertake 'the heavy burden of making a
convincing showing that it is invalid because it is unjust and
unreasonable in its consequences.'
FPC v. Hope Natural Gas Co.,
supra at
320 U. S. 602. We are not
obliged to examine each detail of the Commission's decision; if the
'total effect of the rate order cannot be said to be unjust and
unreasonable, judicial inquiry under the Act is at an end.'
Ibid."
"Moreover, this Court has often acknowledged that the Commission
is not required by the Constitution or the Natural Gas Act to adopt
as just and reasonable any particular rate level; rather, courts
are without authority to set aside any rate selected by the
Commission which is within a 'zone of reasonableness.'
FPC v.
Natural Gas Pipeline Co., 315 U. S. 575,
315 U. S.
585. No other rule would be consonant with the broad
responsibilities given to the Commission by Congress; it must be
free, within the limitations imposed by pertinent constitutional
and statutory commands, to devise methods of regulation capable of
equitably reconciling diverse and conflicting interests."
Permian Basin, 390 U.S. at
390 U. S.
767.
Applying these limitations in the context of review of area rate
regulation,
Permian Basin defined the criteria governing
the scope of judicial review as follows:
"First, [the reviewing court] must determine whether the
Commission's order, viewed in light of
Page 417 U. S. 308
the relevant facts and of the Commission's broad regulatory
duties, abused or exceeded its authority. Second, the court must
examine the manner in which the Commission has employed the methods
of regulation which it has itself selected, and must decide whether
each of the order's essential elements is supported by substantial
evidence. Third, the court must determine whether the order may
reasonably be expected to maintain financial integrity, attract
necessary capital, and fairly compensate investors for the risks
they have assumed, and yet provide appropriate protection to the
relevant public interests, both existing and foreseeable.
The
court's responsibility is not to supplant the Commission's balance
of these interests with one more nearly to its liking, but instead
to assure itself that the Commission has given reasoned
consideration to each of the pertinent factors."
Id. at
390 U. S.
791-792 (emphasis supplied). Where application of these
criteria discloses no infirmities in the Commission's order, the
order cannot be said to produce an "arbitrary result," and must be
sustained.
FPC v. Hope Natural Gas Co., 320 U.S. at
320 U. S.
602.
Applying these criteria,
Permian reversed the Court of
Appeals and sustained the Commission's order, although noting that
the Commission had not adhered rigidly to a cost-based
determination of rates, much less to one that based each producer's
rates on his own costs. [
Footnote 43] Each deviation from cost-based pricing was
found not to be unreasonable and to be consistent with the
Commission's responsibility to consider not merely
Page 417 U. S. 309
the interests of the producers in "maintain[ing] financial
integrity, attract[ing] necessary capital, and fairly
compensat[ing] investors for the risks they have assumed," but also
"the relevant public interests, both existing and foreseeable." 390
U.S. at
390 U. S. 792.
"The Commission's responsibilities necessarily oblige it," the
Court said,
"to give continuing attention to values that may be reflected
only imperfectly by producers' costs; a regulatory method that
excluded as immaterial all but current or projected costs could not
properly serve the consumer interests placed under the Commission's
protection."
Id. at
390 U. S.
815.
Permian Basin teaches that application of the three
criteria of judicial review of Commission orders is primarily the
task of the courts of appeals. For "this [the Supreme] Court's
authority is essentially narrow and circumscribed."
Id. at
390 U. S. 766.
The responsibility to assess the record to determine whether agency
findings are supported by substantial evidence is not ours. Section
19(b) of the Act [
Footnote
44] provides that
"[t]he judgment
Page 417 U. S. 310
and decree of the [Court of Appeals] affirming, modifying, or
setting aside, in whole or in part, any such order of the
Commission, shall be final, subject to review by the Supreme Court
. . . upon certiorari. . . ."
We have held as to a like provision in the National Labor
Relations Act, 29 U.S.C. § 160(e), that thus,
"[w]hether on the record as a whole there is substantial
evidence to support agency findings is a question which Congress
has placed in the keeping of the Courts of Appeals. This Court will
intervene only in what ought to be the rare instance when the
standard appears to have been misapprehended or grossly
misapplied."
Universal Camera Corp. v. NLRB, 340 U.
S. 474,
340 U. S. 491
(1951).
III
Before reviewing the Court of Appeals' affirmance of the
Commission's 1971 order for compliance with
Permian's
requirements, we address contentions that challenge the statutory
authority of the Commission to adopt the order, rather than the
terms of the order itself. The first of these challenges, made by
New York and MDG, is that the Commission had no statutory authority
to change rates and refund obligations fixed in the Commission's
1968 order after that order was affirmed by the Court of Appeals in
SoLa I. Brief for MDG 18; Brief for New York 15. The
argument is that the affirmance was "unqualified," and therefore
exhausted the Court of Appeals' powers of review under §
19(b), thus rendering its authorization to the Commission to reopen
its 1968 orders without legal effect. But the affirmance of the
1968 order was not "unqualified." Although the Commission could not
have reopened the order on its own,
see
Montana-Dakota Utilities Co. v. Northwestern
Page 417 U. S. 311
Public Service Co., 341 U. S. 246,
341 U. S. 254
(1951);
FPC v. Hope Natural Gas Co., 320 U.S. at
320 U. S. 618,
the Court of Appeals' opinion on rehearing made it "crystal clear"
that, despite the form of the court's judgment, the Commission was
fully authorized to reopen any part of the 1968 order that seemed
appropriate and necessary if evidence as to the future supply
problem indicated that this should be done.
The Court of Appeals properly took this step in light of new
information, unavailable at the time of the 1968 order, that
suggested the possible inadequacy of the 1968 determination,
although not necessarily an inadequacy that justified setting aside
the order.
See Baldwin v. Scott County Milling Co.,
307 U. S. 478
(1939). Moreover, the 1968 order had not been made effective, being
continuously stayed until withdrawn by the 1971 order.
See
46 F.P.C. at 101. In these circumstances, we cannot say that the
action of the Court of Appeals exceeded its powers under §
19(b) "to affirm, modify, or set aside [an] order in whole or in
part."
This jurisdiction to review the orders of the Commission is
vested in a court with equity powers,
Natural Gas Pipeline Co.
v. FPC, 128 F.2d 481 (CA7 1942),
see Ford Motor Co. v.
NLRB, 305 U. S. 364,
305 U. S. 373
(1939), and we cannot say that the Court improperly exercised those
powers in the circumstances.
Dolcin Corp. v. FTC, 94
U.S.App.D.C. 247, 255-258, 219 F.2d 742, 750-752 (1954). [
Footnote 45] Indeed, § 19(b)
provides that the Court of
Page 417 U. S. 312
Appeals may authorize the Commission in proper cases to take new
evidence, upon which the Commission may modify its findings of fact
and make recommendations concerning the disposition of its original
order. Under the Court of Appeals disposition, the 1968 order was
therefore not final and thus it was within the power of the
Commission to reconsider and change it.
See United's
Improvement Co. v. Callery Properties, 382 U.
S. 223,
382 U. S. 229
(1965).
Only New York presses the second challenge to the Commission's
statutory authority to adopt the 1971 order. New York contends that
the Commission is without power to adopt as a rate order a
settlement proposal that lacks unanimous agreement of the parties
to the proceeding. That contention has no merit.
The Commission clearly had the power to admit the agreement into
the record -- indeed, it was obliged to consider it. [
Footnote 46] That it was admitted
for the record did
Page 417 U. S. 313
not, of course, establish without more the justness and
reasonableness of its terms. But the Commission did not treat it as
such. As we have noted, [
Footnote 47] the Commission weighed its terms by
reference to the entire record in the Southern Louisiana area
proceeding since 1961, and further supplemented that record with
extensive testimony and exhibits directed at the proposal's terms.
[
Footnote 48] We think that
the Court of Appeals correctly analyzed the situation and stated
the correct legal principles:
"No one seriously doubts the power -- indeed, the duty -- of FPC
to consider the terms of a proposed settlement which fails to
receive unanimous support as a decision on the merits. We agree
with the D.C. Circuit that, even"
"assuming that, under the Commission's rules [a party's]
rejection of the settlement rendered the proposal ineffective
as a settlement, it could not, and we believe should
not,
Page 417 U. S. 314
have precluded the Commission from considering the proposal
on its merits."
"
Michigan Consolidated Gas Co. v. FPC, 1960, 108 U.S.
App D.C. 409, 283 F.2d 204, 224. . . ."
"
* * * *"
"As it should, FPC is employing its settlement power under the
APA, 5 U.S.C.A. § 554(c), and its own rules 18 C.F.R. §
1.18(a), to further the resolution of area rate proceedings. If a
proposal enjoys unanimous support from all of the immediate
parties, it could certainly be adopted as a settlement agreement if
approved in the general interest of the public. But even if there
is a lack of unanimity, it may be adopted as a resolution
on
the merits, if FPC makes an independent finding supported by
'substantial evidence on the record as a whole' that the proposal
will establish 'just and reasonable' rates for the area."
483 F.2d at 893. (Emphasis in original.)
The choice of an appropriate structure for the rate order is a
matter of Commission discretion, to be tested by its effects. The
choice is not the less appropriate because the Commission did not
conceive of the structure independently.
New York presents a final argument against the Commission's
authority. It contends that the Court of Appeals' opinion on
rehearing in
SoLa I authorized modification of the 1968
refund provisions only if the 1968 refunds "are too burdensome in
light of new evidence to be in the public interest." 111 F.2d at
127. It argues that this means the Commission was required first to
find, based on substantial new evidence, that refunds "would
substantially and adversely affect the producers' ability to meet
the continuing gas needs of the interstate market," Brief for New
York 18, and contends that the
Page 417 U. S. 315
revision of the refund terms is therefore unauthorized because
the Commission made no such finding. New York's premise is
unsupportable. The opinion on rehearing is explicit that the
Commission was to have "great flexibility," and could "make
retrospective as well as prospective adjustments in this case if it
finds that it is in the public interest to do so." 444 F.2d at
126-127. Moreover, in the opinion under review, the Court of
Appeals flatly rejected the argument New York has repeated in this
Court.
"[W]e categorically rejected [in
SoLa I] the notion
that the label 'affirmance' could possibly impair FPC's ability to
alter or modify
any of the provisions, particularly the
refund provisions, of its
SoLa I rate scheme if it
believed that the exigencies of the gas industry required more
effective remedial measures."
483 F.2d at 904 (emphasis in original).
IV
We turn now to petitioners' challenges to the rate order itself.
We treat these contentions in three groups: challenges to the
established price levels, challenges to the Commission's allocation
of gas and receipts among pipelines and producers through the
refund credits and contingent escalations, and, finally, claims
that certain specific provisions of the rate order lack substantial
evidence.
A
Petitioner Mobil contends that the rates fixed for both flowing
or first vintage gas and new or second vintage gas are too low. New
York and MDG attack the rates for flowing gas as too high, but do
not attack the new-gas rates. Each of the arguments is premised on
a common error: that certain provisions of the order can be
isolated and viewed without regard to the total effect the order is
designed to achieve.
Page 417 U. S. 316
Mobil's attack on the Commission's evidence of costs is clearly
frivolous. The Commission took extensive evidence of costs in its
1968-order hearings for flowing gas, and in both its 1968-order and
1971-order hearings for new gas. In response to the Commission's
rates, selected from the final cost "range" it found to be
justifiable on the basis of the entire record, Mobil points to
selected fragments of the record. We have examined the testimony
cited, and do not think that it sustains Mobil's heavy burden of
showing that the final Commission choice was outside what the Court
of Appeals could have found to lie within the Commission's
authority.
FPC v. Natural Gas Pipeline Co., 315 U.
S. 575,
315 U. S. 585
(1942).
Mobil further contends that the inclusion of refund workoff
credits and contingent escalations in the Commission's just and
reasonable rates indicates that producers unable to gain part or
all of their share of such payments will receive merely their
"bare-bones" costs, which constitute illegally low prices. We do
not question that such producers may receive less per unit of gas
than will others. But that hardly invalidates the Commission's
order.
See Permian Basin, 390 U.S. at
390 U. S.
818-819. Mobil's argument assumes that there is only one
just and reasonable rate possible for each vintage of gas, and that
this rate must be based entirely on some concept of cost plus a
reasonable rate of return. We rejected this argument in
Permian
Basin, and we reject it again here. The Commission explicitly
based its additional "noncost" incentives on the evidence of a need
for increased supplies. Obviously a price sufficient to maintain a
producer, while not itself necessarily required by the Act,
[
Footnote 49] may not be
sufficient also to encourage an increase
Page 417 U. S. 317
in production. As we said in
Permian Basin, supra, at
390 U. S.
796-798:
"The supply of gas-well gas is therefore relatively elastic, and
its price can meaningfully be employed by the Commission to
encourage exploration and production. . . ."
". . . We have emphasized that courts are without authority to
set aside any rate adopted by the Commission which is within a
'zone of reasonableness.' . . . The Commission may, within this
zone, employ price functionally in order to achieve relevant
regulatory purposes; it may, in particular, take fully into account
the probable consequences of a given price level for future
programs of exploration and production. Nothing in the purposes or
history of the Act forbids the Commission to require different
prices for different sales, even if the distinctions are unrelated
to quality, if these arrangements are 'necessary or appropriate to
carry out the provisions of this Act.' . . . We hold that the
statutory 'just and reasonable' standard permits the Commission to
require differences in price for simultaneous sales of gas of
identical quality, if it has permissibly found that such
differences will effectively serve the regulatory purposes
contemplated by Congress."
Plainly the Court of Appeals did not err in deciding that it was
well within Commission discretion and expertise
Page 417 U. S. 318
to conclude that the refund workoff credits and contingent
escalations could provide opportunity for increased prices that
would help in generating capital funds and in meeting rising costs,
while assuring that such increases would not be levied upon
consumers unless accompanied by increased supplies of gas. It is
true that the Commission concluded that it could not determine the
precise amount of additional gas supply that would be found and
dedicated to interstate sales as a result of this formula. But this
was also true of any change it might have made in gas prices. The
Commission took massive evidence on supply, demand, and the
relation between the two. [
Footnote 50] Its difficulties, while not minor, [
Footnote 51] did not stem from any
failure to seek answers.
Page 417 U. S. 319
Rather, the Commission pointed out that the results of
exploratory activity are by nature dependent to some extent on
chance, and the level of exploratory activity in turn may be
influenced by many other factors besides price, including, the
Commission said,
"monetary inflation, changes in real cost of input resources,
availability of input resources, changes in alternative investment
opportunities, development of new producing areas, size of
prospective reservoirs, changes in business confidence, degree of
directionality of exploratory effort [toward gas or oil], changes
in industry technology, and other factors influencing business
decisions. [
Footnote
52]"
We think the record sufficiently supports the Commission's
conclusion:
"Summarizing, there exists a positive relationship between gas
contract price levels and exploratory effort; no reliable
quantitative forecasts may be made by increments of additional gas
supply resulting from specific increased gas prices; increases in
ceiling prices which yield increases in producer revenues will
result in expanded gas exploration activity; and the adequacy of
expanded gas exploratory activity in terms of sufficiency of gas
supply in relation to gas demands must be determined by continued
Commission observation of the results of our decisions."
46 F.P.C. at 124.
New York's contention that the rates on flowing or first vintage
gas are not supported by substantial evidence is also predicated on
an erroneously limited view of the permissible range of the
Commission's authority to employ price to encourage exploration or
production. Reduced to simplest form, New York's contention is that
the 1968 order set just and reasonable rates for first vintage gas,
that no new evidence was introduced as to the
Page 417 U. S. 320
cost of that gas, and that the 1971-order prices for that gas
are consequently excessive. Again, as we said in
Permian,
the Commission is not so limited in its construction of rate
formulae. Its justification here for increasing the price of
flowing or first vintage gas was not that new evidence showed that
the conditions of producing that gas differed from the conditions
found in the 1968 opinion, but, as the Commission frankly
acknowledged, new revenues were deemed necessary to expand future
production. As between placing the burden of that expansion on new
or second vintage gas alone or spreading it over both old and new
gas, it judged the latter more equitable and more likely to lead to
the immediately increased capital necessary in the face of a
crisis. We see nothing in New York's argument to suggest that the
Commission could not -- in view of its finding that increased
revenues were necessary -- place the burden of those payments on
all users, rather than on those alone who purchased gas in the
future. Indeed, it is worth noting that the Commission's rate
orders in
Permian included in the cost components of gas a
noncost price element for future expansion of exploratory effort.
[
Footnote 53]
In this situation, the Commission could reasonably choose its
formula as an appropriate mechanism for protecting the public
interest. And, against the background of a serious and growing
domestic gas shortage, the Court
Page 417 U. S. 321
of Appeals could certainly conclude that the Commission might
reasonably decide that, as compared with adjustments in the rate
ceilings for gas produces to induce more exploration and
production, its responsibility to maintain adequate supplies at the
lowest reasonable rate could better be discharged by means of the
contingent escalation and refund credit provisions. We therefore
agree with the Court of Appeals' holding that
"these periodic escalations were a proper subject for the
exercise of administrative discretion and clearly fall within that
'zone of reasonableness' which we allow FPC on review."
483 F.2d at 908.
B
Mobil, New York, and MDG all raise claims that, even if the
Commission's rates are sufficient to satisfy the Act's minimum
requirements as to amount and, on the basis of the Commission's
chosen methodology, are supported by substantial evidence, they are
nonetheless unduly discriminatory, and therefore unlawful under
§§ 4 and 5 of the Act. This attack is directed both to
the contingent escalations on flowing or first vintage gas and to
the refund credits.
The background to Mobil's argument is a Commission program
inaugurated after promulgation in 1960 of guidelines for area rate
regulation.
Statement of General Policy No. 61-1, 24
F.P.C. 818 (1960);
Fourth Amendment to Statement of General
Policy No. 61-1, 26 F.P.C. 661 (1961). That program was aimed
at disposing of claims arising from rates that exceeded guideline
levels. The program encouraged settlement of contested rate dockets
and resulted in substantial producer refunds, reduction of producer
rates to guideline levels, and moratoria on producer rate increases
for substantial periods. Major producers like Mobil that cooperated
with the program thus had little if any refund obligation to
"work
Page 417 U. S. 322
off" among the $150 million refunds directed by the 1971 order,
whereas producers who for over a decade had not cooperated with FPC
but had continued collection of higher rates, had high refund
liabilities, and thus enjoyed the benefits of the refund credit
formula. Mobil contends undue discrimination results because these
producers earn refund credits by dedicating new natural gas
reserves which are not counted toward industry escalations, yet
also receive all escalations in flowing gas ceiling rates earned by
dedication of new natural gas reserves by other producers.
Moreover, Mobil's argument continues, the refund credits provide
the noncooperating producers with working capital they may use, for
example, in competitive lease biddings and other corporate
activities, while cooperating producers like Mobil are not allowed
comparable allowances in the revenues to be realized from the area
rates.
T he Commission squarely faced up to the Mobil argument as
follows, 46 F.P.C. at 109-110:
"The substance of their argument is that the rate design in the
settlement proposal unlawfully discriminates against producers who
in the past cooperated with the Commission and consumer and
distributor interests by executing company-wide settlements, and
made refunds which reduced their revenues to the general level of
the Commission's Section 7 guideline level, and in favor of
producers who did not enter into such rate settlements or otherwise
reduce their contested Section 4 and Section 7 rates. The latter .
. . in the meantime have collected rates considerably higher than
those realized by the group which settled. Under the proposed
settlement, as Mobil points out, one group is in effect rewarded
for their relative intransigence -- they will be able to retain
revenues collected up to the agreed 22.375�
Page 417 U. S. 323
(where their contracts permit) and achieve a favored revenue
position."
"
* * * *"
"The logic of this [Mobil's] position cannot be assailed. Candor
requires us to admit that some of the predicted inequities as among
producers will surely occur, and those who have attempted to work
'within the system' are comparatively disadvantaged. We have chosen
to go the route of the alternative rate design suggested in the
[settlement] proposal. The inequitable consequences which might
flow from it have to be compared with its advantages, and . . . no
scheme can be free of some inequities. The broader acceptability of
the [settlement] proposal with the distributor group impels us to
act as we do."
In other words, it was the Commission's judgment that, even
though the refund credit device does not operate as favorably for
producers who paid refunds and lowered rates, the advantages in the
public interest that could result from encouraging exploration and
increased production overrode such possible inequitable
consequences. The Court of Appeals held that, in thus striking the
balance, the Commission acted within its statutory authority upon
substantial evidence. The Court of Appeals stated, 483 F.2d at
905:
"FPC concluded that the overall structure would stimulate
greater exploration and development and have a general
pro-competitive effect. We will not reject an administrative
decision merely because one producer's piece of cake is iced and
another's is not. The crucial factor, in total alignment with both
Permian and
SoLa I, is that both get
some cake.
Given the wisdom of the administrative desire
Page 417 U. S. 324
to elicit new supply, and accepting the proposition that the
incalculable relationship between rate and supply is positive, we
refuse to tamper with an overall program which effectively exploits
that relationship. FPC's order setting the total refund obligation
of all gas producers in [the Southern Louisiana area] is therefore
fully sustained."
The question ultimately becomes whether this degree of
discrimination in some of the provisions of the rate order renders
the order unjust and unreasonable as a whole, despite its overall
balance of effects and purposes. Obviously, some discrimination
arises from the mere fact of area, rather than individual producer,
regulation, but
Permian held such effects justified.
Similarly, departure from cost basing in setting rates can, on
Mobil's theory of the meaning of "discrimination," be said to be
discriminatory, but
Permian held that this too may be
justified by other regulatory concerns. Here, although the impact
on Mobil exists, the size of that impact will depend on the
fortuity of other producers' success in future exploratory efforts,
and, of course, the favorable terms of its settlement would have to
be considered in mitigation of that impact.
We cannot say that the Court of Appeals misapprehended or
grossly misapplied the substantial evidence standard in concluding
that the Commission's assessment of the need for the refund
credits, compared to the costs and benefits of some other scheme,
was adequately supported. Mobil voluntarily exercised a business
judgment in deciding early in the course of the proceedings to
compromise in advance refund liabilities that might be imposed upon
it at the conclusion of the various rate proceedings. In a sense,
therefore, the claimed discrimination arises solely from its
voluntary decision. This was part of the Commission's answer to
Mobil's contention,
Page 417 U. S. 325
46 F.P.C. at 135,
"Parties who enter into settlements or those who refuse to do
so, always run the risk that the ultimate Commission determination
may be higher or lower than the settlement levels."
And the Court of Appeals pointed out, 483 F.2d at 906 n. 31:
"If the [1971] rates were lower than those established in these
agreements, the private settlements would have been worthwhile. As
it turns out, FPC was more generous in [1971] than was anticipated.
But this clearly furnishes no basis for attack."
Moreover, it is a matter of speculation whether Mobil's gain
from its settlement actually might be less advantageous than its
hypothetical gains from refund credits.
New York and MDG argue that the refund credit formula is
discriminatory against pipeline purchasers because it permits
producers to work off refunds by offering 50%, rather than 100%, of
the new reserves to pipeline purchasers other than those owed the
refunds. It may suffice to answer that the pipeline purchasers
affected make no complaint. In any event, since the purpose of the
device is to increase supply, we cannot say that the Court of
Appeals erred in holding that the provision was within Commission
discretion. The record shows that two-thirds of the refund
obligations are owed to three of the 14 pipeline companies serving
the area. [
Footnote 54] The
Commission could reasonably conclude that, in guaranteeing that 50%
of the new reserves must be offered to these three companies, their
producers' incentive to explore for and produce new gas anywhere in
the area, could result in their dedication of new reserves that
would exceed in benefit the amount of the refunds.
It is also contended that, because the work-off provision of the
order applies entirely to present producers, the
Page 417 U. S. 326
work-off provision
"imperil[s] the entry of new producer entrants and [gives] a
competitive advantage to producers who had charged the most
unreasonable rates in the past."
Brief for MDG 47. The 0.5� per Mcf incentive increases on
flowing gas are attacked on the same ground. Brief for New York 37.
The Court of Appeals, addressing this attack upon both the
contingent escalation provisions and the refund work-offs,
sufficiently answered these arguments:
"And for that unnamed new market entrant, for whom much concern
is expressed, we fail to see why he would be in the least bit
dissuaded from committing new reserves at 26�/Mcf by the
fact that it might allow some of his competitors to raise their
22.375�/Mcf flowing gas price by a half-penny."
483 F.2d at 908.
Finally, New York argues that some producers might abandon their
normal business of exploring for and developing new reserves and
yet enjoy the 0.5� per Mcf increase in their prices for
flowing gas if other producers go ahead and contribute substantial
additional reserves. We are not persuaded. The Commission's belief
that producers already operating in the area will continue to do so
is certainly at least an equally tenable judgment.
The Commission's purpose is to obtain increasing production of
gas, and its targets are not so demonstrably unrelated as to
justify acceptance of New York's fears that contingent escalations
will have a negative effect on overall exploratory effort. In any
event, other than the expressed fears, New York offered nothing to
overcome the
"presumption of validity [that] attaches to each exercise of the
Commission's expertise. . . . [T]hose who would overturn the
Commission's judgment undertake 'the heavy burden of making a
convincing showing
Page 417 U. S. 327
that it is invalid because it is unjust and unreasonable in its
consequences.'"
Permian Basin, 390 U.S. at
390 U. S.
767.
C
We come last in our consideration of the Commission's order to a
series of more narrowly drawn objections raised by the various
parties. Mobil objects to the Commission's fixing of moratoria on
new rate filings until October 1, 1976, for flowing or first
vintage gas contracts, and until October 1, 1977, for new or second
vintage gas contracts. It contends that those provisions are
unsupported by required findings of fact and by substantial
evidence. The Court of Appeals reached a contrary conclusion, and
we are not able to say that this conclusion misapprehended or
grossly misapplied the substantial evidence standard. We pointed
out in
Permian Basin that, unless raised as an attack on
the viability of the entire order, such claims are, at best,
premature. It is true, as Mobil argues, that the underlying
conditions of stability justifying the moratorium in
Permian have been found by the Commission to be no longer
true. But the Commission has responsively shifted from reliance
upon stable prices to reliance upon automatic escalations together
with refund credits and contingent escalations. Even as to
producers like Mobil that settled (for a yet-unknown financial
benefit) their refund obligations, the contingent escalations and
automatic escalations introduced for the purpose of both
encouraging increased exploratory activity and covering inflation
costs offer adequate assurances of keeping those producers above
that line where a moratorium might run afoul of the minimum return
required under the Act and the Constitution.
See Permian Basin,
supra, at
390 U. S.
769-771.
In addition, as the Court of Appeals said:
"[T]here are several alternative methods by which
Page 417 U. S. 328
a single aggrieved producer may establish higher rates as his
circumstances warrant. . . . Thus, the system is so structured that
FPC can retain industry and area-wide rate stability for a period
of at least five years while simultaneously protecting the
financial integrity of the individual producer. And if the change
in circumstances is so widespread that the area rate is no longer
economically feasible as set, FPC has the power to lift its
moratorium or establish new area rates, or both."
483 F.2d at 909.
Mobil also complains that the Commission failed to provide
automatic adjustments in area rates to compensate for anticipated
higher royalty costs. It relies on
Mobil Oil Corp. v. FPC,
149 U.S.App.D.C. 310, 463 F.2d 256 (1972), where the Court of
Appeals for the District of Columbia Circuit reversed a Commission
holding that subjected royalties to FPC administrative ceilings.
Mobil argues that, under that decision, the 1971 rate schedules
must take into account the possibility of higher royalty
obligations. We agree with the Court of Appeals that Mobil's
argument is hypothetical at this stage, and that, in any event, an
affected producer is entitled to seek individualized relief. The
Court of Appeals said:
"[W]e are not willing to alter or stay the implementation of
area-wide rates for the entire industry merely on the basis of what
might happen to
some producers' costs
if
[the District of Columbia Circuit's] statement of the law
prevails."
"If, as subsequent events develop, the producers are put in a
bind by their royalty obligations, they may certainly petition FPC
for individualized relief.
Permian contemplated it."
483 F.2d at 911 (emphasis in original).
New York objects to the Commission's elimination of
Page 417 U. S. 329
the distinction in maximum permissible rates between casinghead
gas and gas-well gas so far as new dedications are concerned.
Casinghead gas has traditionally been treated as a byproduct of
oil, and therefore costed and priced lower than gas-well gas. The
Court of Appeals held that "FPC acted within the bounds of
administrative propriety in abandoning any such distinction."
Id. at 910. We cannot say that this conclusion, supported
by the following reasoning, was error:
"We believe that several considerations support this course of
action: (i) "the exigencies of administration demand the smallest
possible number of separate area rates,"
Permian, supra,
390 U.S. at
390 U. S. 761,
. . . (ii) there is a serious problem of allocating the proper
amount of exploration and development expenses between oil and gas,
see SoLa I: 428 F.2d 422 n. 30, (iii) imposing a lower
price on casinghead gas might "
invite the divergence of such
gas to the intrastate market,'" Op: 598, � 167, and (iv)
making the production of casinghead gas economically unfeasible
might encourage profit-minded producers to flare it, rather than
market it -- thus making natural gas in [the Southern Louisiana
area] not merely a wasting, but a wast
ed, asset. . .
."
483 F.2d at 909 (emphasis in original). [
Footnote 55] Such pragmatic adjustments were
used in
Permian Basin as a way of equating first vintage
gas and all casinghead gas, new and old. All that the Commission
has done
Page 417 U. S. 330
here is to equate all new casinghead gas with all new gas just
as old casinghead gas has always been equated with old gas-well
gas.
Mobil complains of the provision of the order that established
minimum rates to be paid by producers to pipelines for
transportation of liquids and liquefiable hydrocarbons. Mobil
argues that these minimum rates are not supported by substantial
evidence. The Court of Appeals disagreed.
"We have examined the testimony regarding this matter and
conclude that FPC had a substantial evidentiary basis from which it
could conclude that the particular rates which it established
should supply a reasonable floor on these charges. This answers
Mobil's objection."
Id. at 911. Mobil has not met its burden of
demonstrating that the Court of Appeals misapprehended or grossly
misapplied the substantial evidence standard.
V
The overriding objective of the Commission was, as the Court of
Appeals observed, to adopt "a total rate structure to motivate
private producers to fully develop [the Southern Louisiana area's]
resources."
Id. at 891. The Commission's findings, 46
F.P.C. at 102, emphasize that goal:
"Our duty is to take all the action we believe necessary to
reverse a downtrend of the exploration and development effort,
thereby to increase the likelihood of augmenting the national
inventory of proved reserves of natural gas. We would be derelict
-- we can think of no softer word -- if we were to be guided by the
legalisms of the past in seeking solutions to the problems which
have grown like
Page 417 U. S. 331
barnacles as this case has aged and its size has mounted."
Features of the 1971 order designed to increase supplies of
natural gas may strike some as novel but we have emphasized that
the Commission "must be free . . . to devise methods of regulation
capable of equitably reconciling diverse and conflicting
interests."
Permian, 390 U.S. at
390 U. S. 767.
That principle has obvious applicability in this time of acute
energy shortage. This accents the observation, apparently still the
case, that "area regulation of producer prices is avowedly still
experimental in its terms and uncertain in its ultimate
consequences."
Id. at
390 U. S. 772.
For, as the Court of Appeals said:
"Cast in the perspective of the human travail, some might say
that the dozen year experience with area rate regulation should
arguably justify a holding that the experimental phase has passed.
In 1971, . . . however, FPC had only twice been the beneficiary of
the judicial function to declare 'what the law is.' No one can
honestly say that judges have been any more sure than
commissioners, as all struggle with a problem that grows out of the
peculiar mixture of a simultaneous service and exhaustion of a
depletable asset. All have been groping. The day for groping is not
yet over. And it does not denigrate what FPC has done to say that
much may yet be imperfect and much remains to be done or redone. So
we can find that FPC has conscientiously attempted to establish
'just and reasonable' rates within the framework allowed by
judicial precedent, yet, it is still experimenting."
483 F.2d at 889.
We cannot now hold that, in these circumstances, the Court of
Appeals erred in deciding that the Commission's
Page 417 U. S. 332
1971 order was an appropriate exercise of administrative
discretion supported by substantial evidence.
Affirmed.
MR. JUSTICE STEWART and MR. JUSTICE POWELL took no part in the
consideration or decision of these cases.
* Together with No. 73-457,
Public Service Commission of New
York v. Federal Power Commission et al., and No. 73-464,
Municipal Distributors Group v. Federal Power Commission et
al., also on certiorari to the same court.
[
Footnote 1]
Opinion No. 598, 46 F.P.C. 86 (1971), together with the
Commission's order correcting certain errors and denying rehearing
as to all other issues, Opinion No. 59A, 46 F.P.C. 633 (1971).
[
Footnote 2]
As in
Permian Basin Area Rate Case, 390 U.
S. 747,
390 U. S. 754
n. 2 (1968), sales within the Commission's jurisdiction will, for
convenience, be termed "jurisdictional" or "interstate" sales.
See n 17,
infra.
[
Footnote 3]
The Court of Appeals reported the status of area rate
proceedings in 483 F.2d 880, 886 n. 3. The Commission has updated
that information as follows:
"1.
Permian Basin Area"
"Opinion Nos. 468 and 468-A, 34 FPC 159, and 1068, respectively
(1965),
affirmed, Permian Basin Area Rate Cases,
390 U. S.
747 (1968)"
"New rates for this area were established in:"
"Opinion Nos. 662 and 662-A (
Area Rate Proceeding, Permian
Basin Area), ___ FPC ___ (Docket No. AR70-1 (Phase I), issued
August 7, 1973, and September 28, 1973, respectively);
pending
review sub nom. Chevron Oil Co., Western Division, et al. v.
F.P.C. (9th Cir. Nos. 73-2861,
et al., filed
September 28, 1973)"
"2.
Southern Louisiana Area"
"Opinion Nos. 546 and 546-A, 40 FPC 530, 41 FPC 301,
respectively (1968),
affirmed sub nom. Austral Oil Co., et al.
v. F.P.C., 428 F.2d 407 (5th Cir.1970),
on rehearing,
494 F.2d 125 (1970);
certiorari denied sub nom. Municipal
Distributors Group v. F.P.C. 400 U.S. 950 (1970)"
"New rates for this area were established in:"
"Opinion Nos. 598 and 598-A, 46 FPC 86 and 633, respectively
(1971),
affirmed sub nom. Placid Oil Co., et al. v.
F.P.C., 483 F.2d 880 (1973) [the instant case]."
"3.
Texas Gulf Coast Area"
"Opinion Nos. 595 and 595-A, 45 FPC 674 and 46 FPC 827,
respectively (1971),
reversed and remanded sub nom. Public
Service Commission of the State of New York, et al. v. F.P.C.,
487 F.2d 1043 (D.C. Cir.1973),
certiorari pending sub nom.
Shell Oil Co., et al. v. Public Service Commission of the State of
New York, et al. (Sup.Ct. Nos. 73-966,
et al., filed
December 22, 1973)."
"4.
Hugoton-Anadarko Area"
"Opinion No. 586, 44 FPC 761 (1970),
affirmed sub nom.
People of the State of California, et al. v. F.P.C., 466 F.2d
974 (9th Cir.1972)."
"5.
Other Southwest Area"
"Opinion Nos. 607 and 607-A, 46 FPC 900 and 47 FPC 99,
respectively (1971),
affirmed sub nom. Shell Oil Co., et al. v.
F.P.C., 984 F.2d 969 (5th Cir.1973),
certiorari pending
sub nom. Mobil Oil Corp. v. F.P.C. (Sup.Ct. No. 73-438, filed
September 6, 1973)."
"6.
Appalachian and Illinois Basin"
"Order Nos. 411, 411-A and 411-B, 44 FPC 1112, 1334 and 1487,
respectively (1970) (these orders were never appealed)."
"The Commission declined to establish new area rates for this
area in Opinion No. 639, 48 FPC 1299 (1972),
affirmed sub nom.
Shell Oil Co., et al. v. F.P.C., ___ F.2d ___ (5th Cir. Nos.
73-1369,
et al., decided March 14, 1974)."
"7.
Rocky Mountain Area"
"Opinion Nos. 658 and 658-A, 49 FPC 924 and ___ FPC ___,
respectively (1973),
petition for review filed and dismissed on
motion of petitioner sub nom. Exxon Corporation v. F.P.C.
(D.C.Cir. No. 73-1854, dismissed February 22, 1974)."
"Opinion Nos. 658 and 658-A prescribed just and reasonable rates
for gas produced in this area from wells commenced prior to January
1, 1973 and sold under contracts dated prior to October 1, 1968.
Sales from this area which are not covered by the rates established
in Opinion Nos. 658 and 658-A will be governed by the rates
prescribed in the Commission's pending nationwide rate proceedings
(see below). Pending completion of the nationwide proceedings, such
sales are being permanently certified under Section 7 of the
Natural Gas Act, 15 U.S.C. 717f, at the initial rates prescribed in
Order No. 435, 46 FPC 68 (1971),
sub nom. American Public Gas
Association, et al. v. F.P.C. (D.C. Cir. Nos. 72-1812,
et
al., May 23, 1974)."
The Commission further advises that
"[p]roceedings to establish uniform nationwide rates for all
jurisdictional producer sales have been instituted at the
Commission. When these proceedings are completed, the rates
prescribed therein will supersede all area rates. As to gas from
wells commenced on or after January 1, 1973,
see"
"
Notice of Proposed Rulemaking and Order Prescribing
Procedures, 38 Fed.Reg. 10014 (Docket No. R-389-B, issued
April 11, 1973)."
"As to gas from wells commenced prior to January 1, 1973,
see"
"
Notice of Proposed Rulemaking and Order Prescribing
Procedures, 38 Fed.Reg. 14295 (Docket No. R-478, issued May
23, 1973)."
Memorandum from General Counsel, FPC (May 17, 1974).
As to the Commission's shift from individual ratemaking through
an adjudicative procedure to area ratemaking through a rulemaking
procedure,
see Dakin, Ratemaking as Rulemaking -- The New
Approach at the FPC: Ad Hoc Rulemaking in the Ratemaking Process,
1973 Duke L.J. 41.
[
Footnote 4]
Sections 4(a) and 5(a), 15 U.S.C. §§ 717c(a) and
717d(a), respectively provide:
§ 4(a)
"All rates and charges made, demanded, or received by any
natural gas company for or in connection with the transportation or
sale of natural gas subject to the jurisdiction of the Commission,
and all rules and regulations affecting or pertaining to such rates
or charges, shall be just and reasonable, and any such rate or
charge that is not just and reasonable is declared to be
unlawful."
§ 5(a)
"Whenever the Commission, after a hearing had upon its own
motion or upon complaint of any State, municipality, State
commission, or gas distributing company, shall find that any rate,
charge, or classification demanded, observed, charged, or collected
by any natural gas company in connection with any transportation or
sale of natural gas, subject to the jurisdiction of the Commission,
or that any rule, regulation, practice, or contract affecting such
rate, charge, or classification is unjust, unreasonable, unduly
discriminatory, or preferential, the Commission shall determine the
just and reasonable rate, charge, classification, rule, regulation,
practice, or contract to be thereafter observed and in force, and
shall fix the same by order:
Provided, however, That the
Commission shall have no power to order any increase in any rate
contained in the currently effective schedule of such natural gas
company on file with the Commission, unless such increase is in
accordance with a new schedule filed by such natural gas company;
but the Commission may order a decrease where existing rates are
unjust, unduly discriminatory, preferential, otherwise unlawful, or
are not the lowest reasonable rates."
[
Footnote 5]
Petitioner in No. 73-437, Mobil Oil Corp., is a major producer
of natural gas in the Southern Louisiana area. Petitioner in No.
73-457, Public Service Commission of the State of New York and
petitioner in No. 73-464, Municipal Distributors Group -- a group
of approximately 200 municipally owned gas distributors --
represent major consumer interests. Hereafter in this opinion they
will be referred to respectively as "Mobil," "New York," and "MDG."
Although all three attack at times the same provisions of the 1971
order, the attacks make different arguments as best serve the
self-interest of the particular petitioner. Thus, the ceiling rate
for flowing gas established by the Commission includes a noncost
factor designed to facilitate investment by producers in
exploration and development of new gas reserves. Mobil,
understandably concerned with higher prices, argues that the
noncost addition is not enough; indeed, that the rates fixed both
for flowing gas and for new gas are too low. New York and MDG, on
the other hand, concerned with lower prices, object that the rates
for flowing gas are too high and reduce the level of refund
obligations.
[
Footnote 6]
Approximately five years were consumed by hearings, and the
trial examiner's opinion issued on December 30, 1966, 40 F.P.C.
703.
[
Footnote 7]
Pursuant to its authority, upheld in
Permian, to use
price flexibly, the Commission established three "vintages" for
onshore gas delivered under contracts made, respectively, (1)
before 1961, (2) between January 1, 1961, and October 1, 1968, and
(3) after October 1, 1968. It set price ceilings for the three
vintages, respectively, at 18.5� per thousand cubic feet
(Mcf).19.5� per Mcf, and 20� per Mcf. For offshore
gas in the federal domain, which is not subject to the Louisiana
severance tax, the ceilings were 1.5� per Mcf below onshore
levels. The Commission also ordered refunds aggregating
approximately $375 million for gas sold and delivered between the
initiation of the proceedings and the effective date of its
opinion, October 1, 1968, at prices above the established
pre-October 1 ceilings. Finally, it established, subject to the
right of individual producers to petition for exceptions, an
indefinite moratorium on rate increases above the pre-October 1
ceilings, and a moratorium until January 1, 1974 (over five years),
on rate increases above the post-October 1 maximum. Such moratoria
provide for automatic suspension of any rate filing, without
determination of justness and reasonableness.
See, e.g., United
Gas v. Callery Properties, 382 U. S. 223
(1965).
[
Footnote 8]
As of the end of 1970, the precise amount of these refunds was
$376,428,000,
see 5 App. 237e, but they were accruing
interest under terms of the Commission's order. Opinion No. 546, 40
F.P.C. 530 (1968).
[
Footnote 9]
See SoLa I, 428 F.2d 407, 435 n. 87 (CA5 1970). This
report was updated by FPC Staff Report No. 2, National Gas Supply
and Demand 1971-1990 (1972), which states in part:
"'The emergence of a natural gas shortage during the past two
years marks a historic turning point -- the end of natural gas
industry growth uninhibited by supply considerations. . . . For
practical short-term purposes, we are confronted with the fact that
current proven reserves in the lower 48 states . . . have dropped
from 289.3 trillion cubic feet [Tcf] in 1967 to 259.6 in 1970, a
10.3 percent drop within a three-year period. . . .'"
FPC v. Louisiana Power & Light Co., 406 U.
S. 621,
406 U. S. 626
n. 2 (1972).
[
Footnote 10]
On January 26, 1971, the consolidated proceeding was expanded to
include all rate certification proceedings that had been, or would
have been, initiated in the Southern Louisiana area during the
pendency of the case. Pet. for Cert. of New York 9.
[
Footnote 11]
46 F.P.C. at 101.
[
Footnote 12]
United Distribution Companies, a group of 32 major distribution
companies.
Id. at 103 n. 25.
[
Footnote 13]
The Commission's tabulation stated:
"In support of the settlement proposal are 32 major distribution
companies representing 25 percent of the gas distribution
operations in the United States, serving about 10.3 million
customers at retail; 55 gas distribution companies which supply gas
service to more than 10 million customers; all interstate pipelines
purchasing gas from the Southern Louisiana area; and 46 natural gas
producers, comprising 80 percent of the total gas production
flowing from the area. . . . The Commission staff likewise
supported the settlement proposal."
Id. at 103.
[
Footnote 14]
The Commission opinion states:
"We have more than a settlement proposal before us. We have the
entire record made in the original Southern Louisiana proceedings,
plus the record opened with the institution of Docket No. AR 69-1
and concluded after Docket No. AR 61-2 was consolidated with it.
The settlement proposal was obviously heavily influenced by the
teachings of [
SoLa I], as the parties perceived those
teachings, and so was the record made in conjunction with it. It is
our duty to review that record and to make findings thereon, and to
come to conclusions therefrom. Only if substantial evidence
supports it can we approve the settlement proposal, and this means
that we must analyze supply and demand, supply cost relationships,
and costing methodology. Rate design, incentives, refunds, and
economic considerations, as the record permits insight into these
matters, must also be discussed."
Id. at 106.
[
Footnote 15]
The Commission's conclusion that the rates were just and
reasonable is to be found in 46 F.P.C. at 110. Conclusions that
they were supported by substantial evidence appear throughout the
opinion following appropriate examination of the record evidence.
See, e.g., id. at 131, 137-138, 142.
[
Footnote 16]
Under the formula, if, before October 1, 1977, the industry as a
whole finds and dedicates to the interstate market new gas reserves
in the Southern Louisiana area of seven and one-half Tcf, the rate
for flowing gas will escalate by 0.5�; if, prior to that
date, such reserves equal eleven and one-quarter Tcf, the rate will
increase by an additional 0.5�; if, prior to the same date,
such reserves equal 15 Tcf, a final 0.5� escalation will
become effective.
Id. at 143.
[
Footnote 17]
The rates that would have been established had the 1968 orders
become effective ranged from 17� per Mcf to 20� per
Mcf.
[
Footnote 18]
The Commission's formula works thus: any company with a "refund
obligation" to any natural gas pipeline company is allowed to
reduce the refund obligation by one cent for each Mcf of new gas
reserves committed to the interstate market in the Southern
Louisiana area during the period ending October 1, 1977. Any
portion of the "refund obligation" not so discharged is payable in
cash with interest, subject to certain special relief provisions
for producers who either achieve 65% of their obligations by August
1, 1976, or who have nonetheless made a "sincere and diligent
effort" to discharge them. Opinion No. 598-A, 46 F.P.C. 633, 641
(1971). The producer is required to commit, or give right of first
refusal to, at least 50% of the new reserves to the purchaser to
whom the refund would otherwise be payable. The reserves committed
to reduce the refund obligation may not be counted by the producer
committing those reserves as a part of the industry reserves
required to trigger the escalated prices for flowing gas referred
to in
n 16 above.
[
Footnote 19]
The rate levels for refund purposes are as follows:
(a) For deliveries prior to January 1, 1965, 20.625� per
Mcf for onshore gas and 19.625� per Mcf for offshore
gas.
(b) For deliveries from January 1, 1965, to September 30, 1968,
21.25� per Mcf for onshore gas and 20.25� per Mcf for
offshore gas.
(c) For deliveries from October 1, 1968, to January 1, 1971,
30.5% of the difference between revenues during this period based
on rates prior to October 1, 1970, and the revenues that would have
resulted during this period through the application of rates
established in
SoLa I, as modified. This percentage factor
of 30.5 may be increased to as high as 33% to produce the $150
million refund total.
(d) For deliveries after January 1, 1971, base area rates
prescribed in the 1971 order,
see 46 F.P.C. at 140.
[
Footnote 20]
See n 4,
supra.
[
Footnote 21]
Section 717(b) provides:
"The provisions of this chapter shall apply to the
transportation of natural gas in interstate commerce, to the sale
in interstate commerce of natural gas for resale for ultimate
public consumption for domestic, commercial, industrial, or any
other use, and to natural gas companies engaged in such
transportation or sale, but shall not apply to any other
transportation or sale of natural gas or to the local distribution
of natural gas or to the facilities used for such distribution or
to the production or gathering of natural gas."
[
Footnote 22]
See, e.g., Interstate Commerce Act, 49 U.S.C. § 1
et seq. See Kitch, Regulation of the Field Market
for Natural Gas by the Federal Power Commission, 11 J.Law and Econ.
243 (1968); Note, Legislative History of the Natural Gas Act, 44
Geo.L.J. 695, 702, 704 (1956).
The contention was early made that, in regulating the ultimate
source of a production, here the natural gas producer, the problem
is not to ensure a reasonable rate of return, but to use prices
functionally to produce a supply that will satisfy a socially
selected level of demand, and efficiently to allocate that supply.
See FPC v. Hope Natural Gas Co., 320 U.
S. 591,
320 U. S. 629
(1944) (separate opinion of Jackson, J.):
"The heart of this problem is the elusive, exhaustible, and
irreplaceable nature of natural gas itself. Given sufficient money,
we can produce any desired amount of railroad, bus, or steamship
transportation, or communications facilities, or capacity for
generation of electric energy, or for the manufacture of gas of a
kind. In the service of such utilities one customer has little
concern with the amount taken by another, one's waste will not
deprive another, a volume of service can be created equal to
demand, and today's demands will not exhaust or lessen capacity to
serve tomorrow. But the wealth of Midas and the wit of man cannot
produce or reproduce a natural gas field."
Compare, for a review of the possible purposes of
natural gas regulation and the arguments for and against the scheme
of the Natural Gas Act, Breyer & MacAvoy, The Natural Gas
Shortage and the Regulation of Natural Gas Producers, 86
Harv.L.Rev. 941, especially 944-952 (1973).
[
Footnote 23]
See Columbian Fuel Corp., 2 F.P.C. 200 (1940); cases
cited in
Permian Basin, 390 U.S. at
390 U. S. 756
n. 7. Section 1(b), 15 U.S.C. § 717(b), exempts "the
production or gathering of natural gas" from the Act.
Both the reason for the Commission's view and the logical
infirmity in it appear in the legislative history of the Act. The
growing concentration of natural gas pipelines had led to
traditional abuses associated with monopoly power -- limitation of
supply, discriminatory pricing, and barriers to entry. Hearings on
H.R. 4008 before the House Committee on Interstate and Foreign
Commerce, 75th Cong., 1st Sess., 47, 70-73, 89-91, 101-103 (1937).
The States first proved incapable of combating these foreign
corporations,
id. at 50, 93, and then were barred by
decisions of this Court holding that such regulation violated the
Interstate Commerce Clause.
See, e.g., Peoples Natural Gas Co.
v. Public Service Comm'n, 270 U. S. 550
(1926).
Congress' response was to take over where the States' power
ceased, following the chain of distribution back into the
interstate market, and it quite naturally used a public utility
model. But, once begun, prevention of the circumvention of such
regulation virtually compelled extension of control to the
source.
Although the debate continues today as to whether the production
of natural gas is, or has the potential to be, competitive,
compare Diener, Area Price Regulation in the Natural Gas
Industry of Southern Louisiana, 46 Tul.L.Rev. 695 (1972) (not
competitive), with Breyer & MacAvoy, The Natural Gas Shortage
and the Regulation of Natural Gas Producers, 86 Harv.L.Rev. 941
(1973) (competitive), revision of the regulation required by the
Act is a matter for consideration by the Congress, not by this
Court.
See FPC v. Texaco, post at
417 U. S.
400-401.
[
Footnote 24]
Prior to the
Phillips case there were fewer than 200
pipeline companies subject to Commission regulation. Statement of
General Policy No. 61-1, 24 F.P.C. 818 (1960). Immediately prior to
passage of the Act, four holding company groups controlled over 55%
of the Nation's pipeline mileage. Hearings on H.R. 11662 before a
Subcommittee of the House Committee on Interstate and Foreign
Commerce, 74th Cong., 2d Sess., 12, 52 (1936).
[
Footnote 25]
See Phillips Petroleum Co., 24 F.P.C. 537, 542
(1960).
[
Footnote 26]
Section 717a provides:
"When used in this chapter, unless the context otherwise
requires --"
"
* * * *"
"(6) 'Natural-gas company' means a person engaged in the
transportation of natural gas in interstate commerce, or the sale
in interstate commerce of such gas for resale."
[
Footnote 27]
See Phillips Petroleum Co., supra, at 542.
[
Footnote 28]
Various statistics presented by the Commission in its
Phillips opinion on remand indicated a total of 3,372
independent producers with rates on file and an estimated backlog
so large that, if the staff of the Commission were tripled, it
would take over 82 years to reach current status. 24 F.P.C. at
545-546.
[
Footnote 29]
Statement of General Policy No. 61-1, 24 F.P.C. 818 (1960).
[
Footnote 30]
Ibid.
[
Footnote 31]
See Opinion No. 598, 46 F.P.C. at 112-114 (American Gas
Association, Committee on Natural Gas Reserves, Annual
Reports).
[
Footnote 32]
See, e.g., Kitch,
supra, n 22, at 276-280.
See also Permian
Basin, 390 U.S. at
390 U. S.
816-817.
[
Footnote 33]
See n 3,
supra.
[
Footnote 34]
Statement of General Policy No. 61-1,
supra.
[
Footnote 35]
Permian Basin, supra, at
390 U. S.
759-760.
[
Footnote 36]
Id. at
390 U. S.
761.
[
Footnote 37]
Ibid.; cf. infra at
417 U. S.
329-330.
[
Footnote 38]
The Commission has raised the rate of return to 15% in the
instant case. 46 F.P.C. at 131.
[
Footnote 39]
Cf. ibid.
[
Footnote 40]
Cf. ibid.
[
Footnote 41]
See 46 F.P.C. at 143: "The maximum standard will be
1050 Btu's per cubic foot of gas, . . . and the minimum standard
will be 1000 Btu's per cubic foot of gas." Adjustments outside this
range are to be on a proportional basis. This was the standard used
in
Permian Basin, see 390 U.S. at
390 U. S.
762-763.
[
Footnote 42]
Id. at
390 U. S.
770-771
[
Footnote 43]
Indeed, in addition to its general approval of such an approach,
see 390 U.S. at
390 U. S.
814-815, the Court in
Permian Basin listed each
of the noncost factors used by the Commission and approved them.
See id. at
390 U. S. 815
n. 98.
[
Footnote 44]
Section 19(b), 15 U.S.C. § 717r(b), states:
"(b) Any party to a proceeding under this chapter aggrieved by
an order issued by the Commission in such proceeding may obtain a
review of such order in the court of appeals of the United States
for any circuit wherein the natural gas company to which the order
relates is located or has its principal place of business, or in
the United States Court of Appeals for the District of Columbia, by
filing in such court, within sixty days after the order of the
Commission upon the application for rehearing, a written petition
praying that the order of the Commission be modified or set aside
in whole or in part. . . . Upon the filing of such petition such
court shall have jurisdiction, which upon the filing of the record
with it shall be exclusive, to affirm, modify, or set aside such
order in whole or in part. . . . The finding of the Commission as
to the facts, if supported by substantial evidence, shall be
conclusive. . . . The judgment and decree of the court, affirming,
modifying, or setting aside, in whole or in part, any such order of
the Commission, shall be final, subject to review by the Supreme
Court of the United States upon certiorari. . . ."
[
Footnote 45]
New York asserts (Brief 17-18) that the Court of Appeals "does
not sit as a court of equity in reviewing actions of an
administrative agency. . . ." We agree with and adapt the
Commission's answer to that contention, Brief for Federal Power
Commission 24 n. 20:
"But the case it cites for that proposition,
Federal Radio
Commission v. General Electric Co., 281 U. S.
464, is wholly inapposite. The issue there was whether
[the Supreme] Court had jurisdiction to review a decision of the
Court of Appeals for the District of Columbia setting aside an
order of the Federal Radio Commission. [The] Court held that it did
not have jurisdiction, because under the pertinent statute the
court of appeals, as a legislative court, was in effect 'a superior
and revising agency' 281 U.S. at
281 U. S.
467. The proceeding in the court of appeals thus"
"was not a case or controversy in the sense of the judiciary
article, but was an administrative proceeding, and therefore . . .
the decision therein is not reviewable by [the Supreme] Court."
"(
Id. at
281 U. S. 470)."
"[The Supreme] Court's statement that the court of appeals in
such cases does not exercise 'ordinary jurisdiction at law or in
equity' (
id. at 468) refers only to that court's former
special role as a legislative court. It does not mean, as New York
mistakenly infers, that reviewing courts exercising judicial,
rather than administrative jurisdiction do not sit as courts of
equity. As [that] Court stated, the jurisdiction of reviewing
courts under statutes similar to the Natural Gas Act is 'quite
unlike the jurisdiction exercised on appeals from the Radio
Commission' (
id. at
281 U. S.
470)."
[
Footnote 46]
Title 18 CFR § 1.18(a) provides:
"(a)
To adjust or settle proceedings. In order to
provide opportunity for the submission and consideration of facts,
arguments, offers of settlement, or proposals of adjustment, for
settlement of a proceeding, or any of the issues therein, or
consideration of means by which the conduct of the hearing may be
facilitated and the disposition of the proceeding expedited,
conferences between the parties to the proceeding and staff for
such purposes may be held at any time prior to or during such
hearings before the Commission or the officer designated to preside
thereat as time, the nature of the proceeding, and the public
interest may permit."
[
Footnote 47]
See text accompanying nn.
7-8 supra.
[
Footnote 48]
The Appendix filed in this Court, and containing only those
portions of the record designated by the parties, includes over 800
pages of testimony and over 300 pages of exhibits from the reopened
proceedings. We note that four different cost studies were
presented. These studies estimated costs of production ranging from
18.2� to 24.03� per Mcf for gas flowing under
contracts dated prior to October 1, 1968. With respect to gas sold
under contracts dated on or after October 1, 1968, the cost
estimates based on a 1969 test year ranged from 19.39� to
38.02�. The rates ultimately fixed by the Commission, even
including incentive increments, were within the range of cost
estimates.
[
Footnote 49]
See Permian Basin, 390 U.S. at
390 U. S.
769-770. We said there:
"[T]he just and reasonable standard of the Natural Gas Act
'coincides' with the applicable constitutional standards,
FPC v.
Natural Gas Pipeline Co., [
315
U.S. 575,]
315 U. S. 586, and any rate
selected by the Commission from the broad zone of reasonableness
permitted by the Act cannot properly be attacked as
confiscatory."
Id. at
390 U. S. 770.
The Court then refused to invalidate, without reference to
particular cases, a Commission plan to provide
"'appropriate relief' if [a producer] establishes that its
'out-of-pocket expenses in connection with the operation of a
particular well' exceed its revenue from the well under the
applicable area price."
Id. at
390 U. S.
770-771.
[
Footnote 50]
See n 48,
supra. The evidence is set out at length and discussed in
46 F.P.C. at 110-123.
[
Footnote 51]
This is well exemplified by the problems arising from the fact
that many costs are jointly incurred in the production of oil, gas,
and other hydrocarbons. One witness testified that any number of
accounting methods may be used to allocate such costs, and listed
10 of them. 4 App. 635-637. He further testified that these methods
would produce a widely varying range of results, and that a choice
of one of them was largely a matter of preference. The Commission's
determination to use a "modified Btu" approach, whereby a Btu of
natural gas is assumed to be "worth" only a selected fraction of a
Btu of oil, is a policy choice having significant consequences for
the industry. The same witness testified that switching from the
Commission's assumption in its 1968 opinion that a Btu of oil is
worth 3.5 times a Btu of natural gas to a 2.34 factor would make
several cents' difference in the ceiling rates.
Id. at
550. An assumption of equality would thus appear likely to have a
large impact. Yet no market price comparison of the values of oil
and gas is available for the interstate market, since the
Commission sets the price of natural gas.
Moreover, another witness testified that, since natural gas
competes with oil in many markets, producers of both harm
themselves when they expand their production of natural gas under
the restraint of price ceilings.
Id. at 476-481.
Cf. n 23,
supra.
[
Footnote 52]
46 F.P.C. at 121.
[
Footnote 53]
See Permian Basin, 390 U.S. at
390 U. S. 815
n. 98. With the introduction of the formula used in this case, the
Commission stated:
"
Adjustment for Exploration in Excess of Production.
This adjustment was designed in prior cases, to continue to provide
findings in excess of production. At the present time, findings of
nonassociated gas are substantially less than production. . . . As
we indicated in
Texas Gulf Coast, our concept of economic
costing includes the costs of eliciting the required exploratory
and drilling effort. Thus, there is no reason to consider special
allowance categories."
46 F.P.C. at 133.
[
Footnote 54]
See 5 App. 266e.
[
Footnote 55]
In its opinion on rehearing the Commission stated, 46 F.P.C. at
636-637:
"We note, again, that the Btu content of casinghead and gas-well
gas is about the same, and the record shows that substantial
volumes of casinghead gas are being flared in Southern Louisiana --
reason, in itself, for eliminating the price discrimination."