Application for stay, pending disposition of appeal by Court of
Appeals, of District Court's order denying applicants' motion for a
preliminary injunction to halt construction of the Warm Springs Dam
Project in California on the ground that the Environmental Impact
Statement (EIS) filed by the Army Corps of Engineers concerning the
project did not adequately deal with alleged seismic and water
poisoning problems presented by the project and failed to comply
with the National Environmental Policy Act (NEPA), is granted, the
Council on Environmental Quality, the agency ultimately responsible
for administration of the NEPA, in a letter applicants filed with
this Court, taking the position that the EIS is deficient in the
respects noted.
MR. JUSTICE DOUGLAS, Circuit Justice.
Applicants brought an action on March 22, 1974, in the United
States District Court for the Northern District of California and
sought a preliminary injunction to halt further construction in
connection with the Warm Springs Dam-Lake Sonoma Project on Dry and
Warm Springs Creeks in the Russian River Basin, Sonoma County,
California. The applicants alleged,
inter alia, that the
Environmental Impact Statement filed by the Army Corps of Engineers
concerning the project did not comply with the requirements of the
National Environmental Policy Act of 1969, 42 U.S.C. § 4321
et seq. A hearing was held in the District Court on the
motion for a preliminary injunction. On May 23, 1974, the
District
Page 417 U. S. 1302
Court rendered an oral ruling denying applicants' motion for the
injunction. [
Footnote 1] A
written opinion was filed thereafter. Applicants filed an
application in the Court of Appeals for the Ninth Circuit for an
injunction pending appeal, which was denied on May 24, 1974.
Application was then made to me as Circuit Justice for the Ninth
Circuit seeking a stay of the order of the District Court as well
as a stay restraining further construction work on the Warm Springs
Dam Project. Because of the seriousness of the claims made by the
applicants, I issued an order, on May 30, 1974, staying further
disturbance of the soil in connection with the dam (other than
research, investigation, planning and design activity) "pending
reconsideration of the application when the memoranda of the
Solicitor General and the Environmental Protection Agency are
received."
A response has been filed, along with further materials
submitted by the applicants supporting their request for a stay.
After consideration of these submissions, I have entered an order
continuing my earlier stay order pending disposition of the appeal
in this case by the Court of Appeals for the Ninth Circuit.
The Warm Springs Dam will be an earth-fill dam, holding back a
reservoir of water, across Dry Creek, a major tributary of the
Russian River in Sonoma County. The dam was first authorized, in
smaller form than is now contemplated, in the Flood Control Act of
1962, Pub.L. 87-874, 76 Stat. 1173, 1192. On January 1, 1970, the
National Environmental Policy Act, which requires the filing of an
Environmental Impact Statement (EIS) for major federal actions
significantly affecting the quality of the human environment, 42
U.S.C. § 4332(2)(C),
Page 417 U. S. 1303
became law. A draft EIS was not distributed until June, 1973,
and the final EIS was not filed with the Council on Environmental
Quality until December 4, 1973. I am informed that approximately
$35 million has been expended on the project already, and that
another $7 million will be expended before this case will be heard
and determined by the Court of Appeals.
The applicants for this stay focus on two extremely serious
challenges to the adequacy of the EIS.
First, they note that the dam will sit atop a geologic fault
running along Dry Creek. There are other faults nearby. A town of
5,000 people is nestled below the dam and the wall of water it will
restrain. At the District Court hearing on applicants' motion for a
preliminary injunction, substantial questions were raised about the
integrity of the dam should an earthquake occur. There seems to be
a recognized "credibility gap" as to the safety of the project;
recommendations were received by the Corps from its own staff for
further study; and reservations about the safety factor were
expressed by the State of California. A contract has been made for
further dynamic analysis of the safety of the dam. Should that
analysis indicate that the dam is potentially risky, the Corps
would have "no choice" but to consider abandoning the entire
project. Tr. 1828-1829, 1832.
Second, challenges were made at the hearing to the adequacy of
the EIS regarding expected poisoning of water in the reservoir
behind the dam. The water will be used by consumers in the
surrounding county. There were allegations at the hearing that the
waters will be poisoned by mercury carried from an abandoned
mercury mine which will be inundated when the dam is built, and
that asbestos, fluoride, and boron particles will also leach into
the waters. It is contended that the EIS is deficient in its
treatment of these significant environmental effects.
Page 417 U. S. 1304
The District Court rejected these contentions, finding that the
Corps adequately dealt with the seismic problem and the water
poisoning problem. It found the EIS adequate. The Solicitor General
argues that the District Court's findings are not "clearly
erroneous" and will be upheld by the Court of Appeals, and that,
therefore, I should deny the requested stay.
Here, however, the views of the two federal agencies most
intimately familiar with environmental issues and the requirements
of the National Environmental Policy Act have been filed with the
Court. They undermine the determination of the District Court.
The Environmental Protection Agency (EPA) has written to the
Solicitor General expressing some doubt about the treatment of the
water poisoning issues in the final EIS. [
Footnote 2] The EPA goes on to say, however, that:
"We wish to emphasize that the CEQ [Council on
Page 417 U. S. 1305
Environmental Quality] is the Executive Office charged with NEPA
administration and ultimately with evaluating the performance of
Federal agencies in complying with the Act. We understand that the
Council has expressed concern over the adequacy of the final
environmental statement on the Warm Springs project, and the issues
raised by the Council clearly fall under its administrative
responsibilities relative to NEPA."
Letter of June 4, 1974, from Alan G. Kirk II, Assistant
Administrator for Enforcement and General Counsel, Environmental
Protection Agency, to Robert H. Bork, Solicitor General.
The applicants have filed with this Court a letter from the
General Counsel of the CEQ to the Solicitor General expressing the
views of the Council on the adequacy of the Warm Springs Dam final
EIS. Letter of June 11, 1974, from Gary Widman, General Counsel,
Council on Environmental Quality, to Robert H. Bork, Solicitor
General. In that letter, the Council expresses the view that the
plaintiffs and the public are likely to be irreparably harmed if an
injunction pending appeal is denied. The Council continues:
"It is the Council's position that the best interests of the
Government would be served by halting construction work (excluding
environment study and testing) until the appeal is decided on the
merits."
"In its letter of February 14, 1974, the Council advised the
Corps that its Environmental Impact Statement ('EIS') was not
adequate in several respects. The Council asked for further study
and consideration of the earthquake hazard, the problems of
stimulating population growth in the area,
Page 417 U. S. 1306
the calculation of benefits and costs, and further asked
consideration of an alternative project (enlargement of the
existing Coyote Dam) that would not raise similar environmental
problems. The letter asked the Corps to delay action on the project
until such further study and consideration was completed."
"Information revealed at trial strongly reinforced our original
reservations about the seismic and other problems, and raised new
concerns over potential hazards created by chemicals in the water,
and in the fish. In its letter to you, the EPA now agrees that the
project's adverse environmental effects were not adequately raised
or discussed in the EIS. The alternative projects (one of which was
mentioned in our letter of February 14) have apparently not
received the further study which we suggested. Therefore, if asked,
CEQ would reaffirm its original advice to the Corps, that sound
policy would require construction work on this project to be
halted, pending further analysis of the problems and consideration
of available alternatives."
The Council goes on to express in more detail its reasons for
concluding that the EIS is deficient:
"At the hearing in the District Court, plaintiffs questioned
highly responsible experts, including one originally retained by
the Corps, and others who were associated with State and Federal
Government agencies who testified to professional reservations
about the hazards that could be created by the dam. . . ."
"
* * * *"
"Upholding the District Court's finding of adequacy of the
statement, and the Court's approval of the Corps decision to
proceed, will permit construction
Page 417 U. S. 1307
of a dam in the face of statements by responsible experts that
the EIS information is insufficient to answer problems of
earthquake hazards created by a fault underlying the dam, and water
quality hazards raised by the presence of mercury, boron, fluoride
and asbestos in the site area (all of which may be carried into
reservoir water by underlying hot springs). Whatever disagreement
there may have been on this issue of adequacy of information, the
Corps nevertheless stated during and after the hearing that there
would be additional studies on the issues of seismicity, water
quality and archaeology, and it recognized that the results of
those studies may lead to a conclusion that the dam should not be
built."
The Council cites numerous ways in which the Warm Springs EIS
may flout Council guidelines, including lack of research and
analysis supporting its conclusions and lack of presentation of
responsible opposing scientific opinion and of critical comments by
responsible governmental agencies. It is the view of the CEQ that
denial of an injunction could further jeopardize the possibility of
obtaining objective agency choice between alternative projects
should an appellate court overturn the decision of the District
Court, [
Footnote 3] that
further construction could
Page 417 U. S. 1308
impair the freedom of choice of local voters who will be
considering the project, and that "it is both contrary to law and
an irreparable detriment to plaintiffs and the public to permit the
construction to proceed in such circumstances."
The mandate of the National Environmental Policy Act regarding
Environmental Impact Statements is stated in the Senate Report:
"(c) Each agency which proposes any major actions, such as
project proposals, proposals for new legislation, regulations,
policy statements, or expansion or revision of ongoing programs,
shall make a determination as to whether the proposal would have a
significant effect upon the quality of the human environment. If
the proposal is considered to have such an effect, then the
recommendation or report supporting the proposal must include
statements by the responsible official of certain findings as
follows:"
"(i) A finding shall be made that the environmental impact of
the proposed action has been studied and that the results of the
studies have been given consideration in the decisions leading to
the proposal."
"(ii) Wherever adverse environmental effects are found to be
involved, a finding must be made that those effects cannot be
avoided by following reasonable alternatives which will achieve the
intended purposes of the proposal. Furthermore, a finding
Page 417 U. S. 1309
must be made that the action leading to the adverse
environmental effects is justified by other considerations of
national policy and those other considerations must be stated in
the finding."
"(iii) Wherever local, short-term uses of the resources of man's
environment are being proposed, a finding must be made that such
uses are consistent with the maintenance and enhancement of the
long-term productivity of the environment."
"(iv) Wherever proposals involve significant commitments of
resources and those commitments are irreversible and irretrievable
under conditions of known technology and reasonable economics, a
finding must be made that such commitments are warranted."
S.Rep. No. 91-296, pp. 221 (1969). The tendency has been to
downgrade this mandate of Congress, to use shortcuts to the desired
end, and to present impact statements after a project has been
started, when there is already such momentum that it is difficult
to stop. There are even cases where the statement is not prepared
by a Government agency, but by a contractor who expects to profit
from a project. [
Footnote 4]
One hesitates to interfere once a project is started, but if the
congressional mandate is to be meaningful, it must be done
here.
As the EPA observed, the CEQ is the Executive Office charged
with administration of the National Environmental Policy Act (NEPA)
and the Environmental Impact Statements. The NEPA requires all
federal agencies both to consult with the CEQ to insure that
environmental factors are adequately considered and to assist
Page 417 U. S. 1310
the CEQ. 42 U.S.C. §§ 4332(2)(B) and (H). The CEQ is
given the authority under NEPA to
"review and appraise the various programs and activities of the
Federal Government in the light of the policy set forth in
subchapter I of this chapter [which includes the EIS requirement]
for the purpose of determining the extent to which such programs
and activities are contributing to the achievement of such policy,
and to make recommendations to the President with respect
thereto."
42 U.S.C. § 4344(3). The Council's members must be
qualified "to appraise programs and activities of the Federal
Government in the light of the policy" set forth in subchapter I of
the Act. 42 U.S.C.§ 4342.
The Council, ultimately responsible for administration of the
NEPA and most familiar with its requirements for Environmental
Impact Statements, has taken the unequivocal position that the
statement in this case is deficient, despite the contrary
conclusions of the District Court. That agency determination is
entitled to great weight,
see, e.g., Trafficante v.
Metropolitan Life Ins., 409 U. S. 205,
409 U. S. 210;
Griggs v. Duke Power Co., 401 U.
S. 424,
401 U. S.
433-434;
Udall v. Tallmam, 380 U. S.
1,
380 U. S. 16, and
it leads me to grant the requested stay pending appeal in the Court
of Appeals to maintain the
status quo in the construction
of the Warm Springs Dam.
[
Footnote 1]
The order did prohibit respondents from disturbing certain
archaeological sites pending compliance with Executive Order 11593,
36 Fed.Reg. 8921, 3 CFR 154 (1971 Comp.).
[
Footnote 2]
"[C]ertain water quality related issues, which potentially
impact the environment and which were not analyzed in the final
environmental impact statement, came to light during the hearing on
plaintiffs' motion for a preliminary injunction. These issues
include potential contamination of the reservoir water by boron and
fluoride concentrations in the streams which would feed the
reservoir and by asbestos concentrations in the serpentine rock
underlying the reservoir site. Moreover, with respect to mercury
contamination, we understand from a hasty and admittedly incomplete
reading of the transcripts of the hearing and the affidavits
submitted, that the Corps has agreed to perform pre-inundation
studies to predict the biomagnification effect of mercury
concentrations in sediments and algae in the reservoir site."
"We believe that the foregoing issues should have been raised
and should have been discussed in the final impact statement. We
cannot say, however, because we were not present during the
proceedings and have not had sufficient opportunity to review the
evidence, that these issues would, at the same time, have caused
EPA to express environmental reservations as to the construction of
the project, within the context of our own NEPA review
procedures."
Letter of June 4, 1974, from Alan G. Kirk II, Assistant
Administrator for Enforcement and General Counsel, Environmental
Protection Agency, to Robert H. Bork, Solicitor General.
[
Footnote 3]
See Power Reactor Co. v. Electricians, 367 U.
S. 396,
367 U. S. 417
(DOUGLAS, J., dissenting):
"But when that point is reached, when millions have been
invested, the momentum is on the side of the applicant, not on the
side of the public. The momentum is not only generated by the
desire to salvage an investment. No agency wants to be the
architect of a 'white elephant.'"
See also Arlington Coalition on Transportation v.
Volpe, 468 F.2d 1323, 1333 (CA4 1972):
"Further investment of time, effort, or money in the proposed
route would make alteration or abandonment of the route
increasingly less wise and, therefore, increasingly unlikely. If
investment in the proposed route were to continue prior to and
during the Secretary's consideration of the environmental report,
the options open to the Secretary would diminish, and at some point
his consideration would become a meaningless formality."
[
Footnote 4]
See Life of the Land v. Brinegar, 414 U.
S. 1052;
Power Reactor Co. v. Electricians,
367 U. S. 396.