Page 417 U. S. 117
project as the same as on many other similar projects; hence it
would have been easy for Rich to secure itself from loss as a
result of Cerpac's default. Pp.
417 U. S.
121-124.
2. Venue for suit on the South Carolina shipment properly lay in
the Eastern District of California, since there was clearly a
sufficient nexus for satisfaction of § 270b(b)'s venue
requirements. The contract between Cerpac and respondent was
executed in California, all materials thereunder to be delivered to
the California worksite. California remained the site for
performance of the original contract despite the diversion of one
shipment to South Carolina. There was no showing of prejudice
resulting from the case's being heard in California, and
considerations of judicial economy and convenience supported venue
in the court where all of respondent's claims could be adjudicated
in a single proceeding. Pp.
417 U. S.
124-126.
3. Attorneys' fees were improperly awarded respondent. Pp.
417 U. S.
126-131.
(a) The Court of Appeals erred in construing the Miller Act to
require the award by reference to the "public policy" of the State
in which suit was brought, since the Act provides a federal cause
of action and there is no evidence of any congressional intent to
incorporate state law to govern such an important element of Miller
Act litigation as liability for attorneys' fees. Pp.
417 U. S.
127-128.
(b) The provision of the Miller Act in 40 U.S.C. § 270b(a)
that claimants should recover the "sums justly due," does not
require the award of attorneys' fees on the asserted ground that,
without such fee-shifting, claimants would not be fully
compensated. To hold otherwise would amount to judicial obviation
of the "American Rule" that attorneys' fees are not ordinarily
recoverable in federal litigation in the absence of a statute or
contract providing therefor, in the context of everyday commercial
litigation, where the policies which underlie the limited
judicially created departures from the rule are inapplicable. Pp.
417 U. S.
128-131.
473 F.2d 720, affirmed in part and reversed in part.
MARSHALL, J., delivered the opinion of the Court, in which
BURGER, C.J., and BRENNAN, STEWART, WHITE, BLACKMUN, POWELL, and
REHNQUIST, JJ., joined. DOUGLAS, J., filed an opinion dissenting in
part,
post, p.
417 U. S.
131.
Page 417 U. S. 118
MR. JUSTICE MARSHALL delivered the opinion of the Court.
The Miller Act, 49 Stat. 793, as amended, 80 Stat. 1139, 40
U.S.C. § 270a
et seq., requires a Government
contractor [
Footnote 1] to post
a surety bond "for the protection of all persons supplying labor
and material in the prosecution of the work provided for" in the
contract. The Act further provides that any person who has so
furnished labor or material and who has not been paid in full
within 90 days after the last labor was performed or material
supplied may bring suit on the payment bond for the unpaid balance.
40 U.S.C. § 270b(a). This case presents several unresolved
issues of importance in the administration of the Act.
I
Between 1961 and 1968, petitioner F. D. Rich Co. was the prime
contractor on numerous federal housing projects. During the years
1963-1966, much if not all of the plywood and millwork for these
projects was supplied by Cerpac Co. The Cerpac organization was
closely intertwined with Rich. The principals of Rich held a
substantial voting interest in Cerpac stock, supplied a major share
of its working capital, and were thoroughly familiar with its
operations and financial condition.
On October 18, 1965, Rich contracted with the United States to
build 337 family housing units at Beale Air
Page 417 U. S. 119
Force Base, California. Rich's Miller Act surety, petitioner
Transamerica Insurance Co., posted the payment bond required by the
Act. Rich then awarded Cerpac two contracts on the project, one to
select, modify, detail, and install all custom millwork, and one
merely to supply all standard exterior plywood, each contract
incorporating by reference terms of the prime contract. A similar
arrangement was employed by Rich and Cerpac on other projects
during this period.
On February 22, 1966, Cerpac placed a single order with
respondent Industrial Lumber Co. for all exterior plywood required
under its plywood contract for the Beale project. Industrial is a
broker, purchasing wood products and materials for resale. It
acknowledged the complete Cerpac order, purchased the plywood from
its own suppliers and arranged for deliveries at the Beale site to
begin on March 10, 1966. Each shipment was receipted as it arrived
on the site by a Rich representative.
Shortly after Industrial's shipments began, Rich informed Cerpac
that more plywood was needed for another Government project being
constructed in Charleston, South Carolina, for which Cerpac had
also contracted to supply Rich with all exterior plywood. Rich and
Cerpac decided to divert some of the Beale lumber to Charleston.
Accordingly, Industrial was advised to supply a shipment of the
plywood called for under its Beale contract with Cerpac to the
South Carolina site. Industrial arranged for the wood to be shipped
by one of its suppliers to a railhead near Charleston. The shipment
diverted to South Carolina was one of 22 called for by Industrial's
Beale Contract. [
Footnote 2]
There were several subsequent shipments to the California site
under that contract.
Page 417 U. S. 120
During April and May, 1966, Cerpac fell behind in its payments
to Industrial, and on July 13, 1966, having not received payment on
invoices for nine separate shipments, Industrial gave notice to
Rich and its surety of a Miller Act claim, and thereafter brought
the instant action in the Federal District Court for the Eastern
District of California. [
Footnote
3] The District Court recognized that, under our decision in
MacEvoy Co. v. United States ex rel. Tomkins Co.,
322 U. S. 102
(1944), Rich's liability turned on whether Cerpac was a
"subcontractor" within the meaning of the Act, or merely a
materialman. The District Court found that Cerpac was a
subcontractor; hence Industrial, as its supplier, could assert a
Miller Act claim against Rich, the prime contractor on the project.
The District Court also rejected Rich's claim that venue for suit
on the South Carolina shipment was improper in the Eastern District
of California. Accordingly, the District Court granted judgment for
Industrial, holding Cerpac [
Footnote 4] and Rich as primary obligees and Transamerica
on its bond, jointly and severally liable for the amount of all
nine unpaid invoices, $31,402.97, including the amount
Page 417 U. S. 121
due on the shipment diverted to South Carolina. The District
Court, however, denied Industrial's claim for attorneys' fees.
Both Rich and Industrial appealed. The Court of Appeals affirmed
the judgment against Rich in large part. [
Footnote 5] On Industrial's cross-appeal, the court
reversed, holding that attorneys' fees should have been awarded to
Industrial as a successful plaintiff under the Miller Act, and
remanded to the District Court for consideration of the amount of
attorneys' fees to be awarded. 473 F.2d 720 (CA9 1973). We granted
certiorari. [
Footnote 6] 414
U.S. 816 (1973). We affirm the judgment below to the extent it
holds that Cerpac was a "subcontractor" for Miller Act purposes and
that there was proper venue, but reverse as to the propriety of an
award of attorneys' fees.
II
Section 270a(a)(2) of the Miller Act establishes the general
requirement of a payment bond to protect those who supply labor or
materials to a contractor on a federal
Page 417 U. S. 122
project. Ordinarily, a supplier of labor or materials on a
private construction project can secure a mechanic's lien against
the improved property under state law. But a lien cannot attach to
Government property,
see Illinois Surety Co. v. John Davis
Co., 244 U. S. 376,
244 U. S. 380
(1917), so suppliers on Government projects are deprived of their
usual security interest. The Miller Act was intended to provide an
alternative remedy to protect the rights of these suppliers.
The rights afforded by the Act are limited, however, by the
proviso of § 270b(a). In
MacEvoy Co. v. United States ex
rel. Tomkins Co., supra, this Court construed § 270b(a)
to limit the protection of a Miller Act bond to those who had a
contractual agreement with the prime contractor or with a
"subcontractor." Those in more remote relationships, including
persons supplying labor or material to a mere materialman, were
found not to be protected. 322 U.S. at
322 U. S.
109-111. Industrial was a supplier of materials to
Cerpac. Thus, if Cerpac were a subcontractor for purposes of the
Act, Industrial, having given the required statutory notice, could
assert a Miller Act claim against Rich, the prime contractor. But
if Cerpac were merely a materialman, Industrial could not assert
its Miller Act claim, since it would be merely a supplier of
materials to a materialman, a relationship found too remote in
MacEvoy to enjoy the protections of the Act.
Petitioners assert that the courts below erred in finding Cerpac
a subcontractor. Cerpac's role under the plywood contract alone was
that of a broker receiving standard lumber supplied by Industrial
and, in turn, supplying it without modification to Rich.
Petitioners argue that the court should not have looked beyond the
plywood contract to determine Cerpac's status under the Act.
Page 417 U. S. 123
In
MacEvoy, supra, the Court adopted a functional,
rather than a technical, definition for the term subcontractor as
used in the proviso. The Court noted that a subcontractor is "one
who performs for and takes from the prime contractor a specific
part of the labor or material requirements of the original
contract. . . ." 322 U.S. at
322 U. S. 109.
The Court went on to explain the reason for the exclusion from the
protections of the Act of suppliers of mere materialmen, as opposed
to those who supply subcontractors:
"The relatively few subcontractors who perform part of the
original contract represent in a sense the prime contractor, and
are well known to him.
It is easy for the prime contractor to
secure himself against loss by requiring the subcontractors to give
security by bond, or otherwise, for the payment of those who
contract directly with the subcontractors. . . . But this
method of protection is generally inadequate to cope with remote
and undeterminable liabilities incurred by an ordinary materialman,
who may be a manufacturer, a wholesaler or a retailer."
Id. at
322 U. S. 110.
(Emphasis added.)
The Court of Appeals properly construed our holding in
MacEvoy to establish as a test for whether one is a
subcontractor the substantiality and importance of his relationship
with the prime contractor. [
Footnote 7] It is the substantiality of the relationship
which will usually determine whether the prime contractor can
protect himself, since he can easily require bond security or other
protection from those few "subcontractors" with whom he has a
Page 417 U. S. 124
substantial relationship in the performance of the contract.
Measured against that test, Cerpac was clearly a subcontractor
for the purposes of the Act. The Miller Act is
"highly remedial, [and] entitled to a liberal construction and
application in order properly to effectuate the Congressional
intent to protect those whose labor and materials go into public
projects."
MacEvoy, supra, at
322 U. S. 107.
It is consistent with that intent to look at the total relationship
between Cerpac and Rich, not just the contract to supply exterior
plywood, to determine whether Cerpac was a subcontractor. [
Footnote 8] Cerpac had not only agreed
to supply standard plywood, but also had a separate contract to
select, modify, detail, and install all custom millwork for the
Beale project. Cerpac, in effect, took over a substantial part of
the prime contract itself. Moreover, the management and financial
structures of the two companies were closely interrelated, and
their relationship on the Beale project was the same as on many
other similar Government projects during the same period. Cerpac
was, as the Court of Appeals observed, "in a special, integral,
almost symbiotic relationship [with] Rich." 473 F.2d at 724. It
would have been easy for Rich to secure itself from loss as a
result of a default by Cerpac.
III
We also agree with the courts below that venue under the Miller
Act for suit on the shipment diverted to South Carolina properly
lay in the Eastern District of California. The Act provides:
"Every suit instituted under this section shall be brought in .
. . the United States District Court for
Page 417 U. S. 125
any district in which the contract was to be performed and
executed and not elsewhere. . . ."
40 U.S.C. § 270b(b). Petitioners argue that this provision
bars a district court in California [
Footnote 9] from adjudicating respondent's claims arising
from the shipments of plywood delivered in South Carolina. But
§ 270b(b) is merely a venue requirement, [
Footnote 10] and there was clearly a sufficient
nexus for its satisfaction. The "Beale 647" contract between Cerpac
and Industrial was executed in California, all of the materials
described therein to be delivered to a worksite in that State.
Although one of the 22 shipments made pursuant to the contract was
later diverted to South Carolina for petitioner Rich's convenience,
the site for performance of the original contract remained the same
for Miller Act purposes. [
Footnote 11] Several shipments to the Beale site were
made after the South Carolina shipment. Moreover, petitioners have
pointed to no prejudice resulting from the case's being heard in
the California court and considerations of judicial economy and
convenience clearly support venue in the
Page 417 U. S. 126
District Court where all of respondent's claims arising from the
"Beale 647" contract could be adjudicated in a single
proceeding.
IV
We turn now to the question of whether attorneys' fees were
properly awarded respondent as a successful Miller Act plaintiff.
The so-called "American Rule" governing the award of attorneys'
fees in litigation in the federal courts is that attorneys' fees
"are not ordinarily recoverable in the absence of a statute or
enforceable contract providing therefor."
Fleischmann
Distilling Corp. v. Maier Brewing Co., 386 U.
S. 714,
386 U. S. 717
(1967). There was no contractual provision concerning attorneys'
fees in this case. Nor does the Miller Act explicitly provide for
an award of attorneys' fees to a successful plaintiff. But the
Court of Appeals construed the Act to require an award of
attorneys' fees where the "public policy" of the State in which
suit was brought allows for the award of fees in similar contexts.
The court reasoned that the Act provides remedies
"'in lieu of the lien upon land and buildings customary where
property is owned by private persons.' . . . The federal remedy was
intended to substitute for the unavailable state remedy of the
lien. Therefore, if state [law] allows a supplier on private
projects to recover such fees, there is no reason for a different
rule to apply to federal projects. . . . [
Footnote 12]"
Looking to California law, the Court of Appeals found an award
of attorneys' fees proper because Cal.Govt.Code § 4207 (1966)
allowed for the recovery of attorneys'
Page 417 U. S. 127
fees in state actions on the bonds of contractors for state and
municipal public works projects. [
Footnote 13]
We think the Court of Appeals erred in its construction of the
statute. The Miller Act provides a federal cause of action, and the
scope of the remedy as well as the substance of the rights created
thereby is a matter of federal, not state, law. Neither respondent
nor the court below offers any evidence of congressional intent to
incorporate state law to govern such an important element of Miller
Act litigation as liability for attorneys' fees. Many federal
contracts involve construction in more than one State, and often,
as here, the parties to Miller Act litigation have little or no
contact, other than the contract itself, with the State in which
the federal project is located. The reasonable expectations of such
potential litigants are better served by a rule of uniform national
application.
A uniform rule also avoids many of the pitfalls which have
already manifested themselves in using state law referents. For
example, California law does not provide for awards of attorneys'
fees in suits arising from private construction projects. And a
California court had held that the state statute providing for
awards of attorneys' fees in suits on the bonds of state and
municipal public works contractors is inapplicable to construction
projects of the United States. [
Footnote 14] The Court of Appeals nonetheless
Page 417 U. S. 128
held that, since federal law controls Miller Act recoveries, it
was free to look to "state policy", rather than state law, and
proceeded to find an award of attorneys' fees appropriate. Although
the court below premised its decision on the theory that a Miller
Act remedy is afforded "
in lieu of the lien upon land and
buildings customary where property is owned by private persons,'"
it gave respondent more protection than California law affords
litigants involved in disputes arising from private construction
projects who are not entitled to an award of attorneys' fees. We
think it better to extricate the federal courts from the morass of
trying to divine a "state policy" as to the award of attorneys'
fees in suits on construction bonds.
Finally, the Court of Appeals intimates that, in providing that
Miller Act claimants should recover the "sums justly due," 40
U.S.C. 270b(a), Congress must have intended to provide for the
award of attorneys' fees because without such fee-shifting, Miller
Act claimants would not be fully compensated -- the claimant's
recovery would always be diminished by the cost of his legal
representation. This argument merely restates one of the
oft-repeated criticisms of the American Rule. [
Footnote 15] Almost a half century ago, the
Massachusetts Judicial Council pleaded for reform, asking
"On what principle of justice can a plaintiff wrongfully run
down on a public highway recover
Page 417 U. S. 129
his doctor's bill but not his lawyer's bill? [
Footnote 16]"
We recognize that there is some force to the argument that a
party who must bear the costs of his attorneys' fees out of his
recovery is not made whole. But there are countervailing
considerations as well. We have observed that
"one should not be penalized for merely defending or prosecuting
a lawsuit, and that the poor might be unjustly discouraged from
instituting actions to vindicate their rights if the penalty for
losing included the fees of their opponents' counsel."
Fleischmann Distilling Corp. v. Maier Brewing Co.,
386 U. S. 714,
386 U. S. 718
(1967). Moreover, "the time, expense, and difficulties of proof
inherent in litigating the question of what constitutes reasonable
attorney's fees,"
ibid., has given us pause, even though
courts have regularly engaged in that endeavor in the many contexts
where fee-shifting is mandated by statute, policy, or contract.
Finally, there is the possibility of a threat being posed to the
principle of independent advocacy by having the earnings of the
attorney flow from the pen of the judge before whom he argues.
The American Rule has not served, however, as an absolute bar to
the shifting of attorneys' fees even in the absence of statute or
contract. The federal judiciary has recognized several exceptions
to the general principle that each party should bear the costs of
its own legal representation. We have long recognized that
attorneys' fees may be awarded to a successful party when his
opponent has acted in bad faith, vexatiously, wantonly or for
oppressive reasons, [
Footnote
17] or where a successful litigant
Page 417 U. S. 130
conferred a substantial benefit on a class of persons and the
court's shifting of fees operates to spread the cost
proportionately among the members of the benefited class. [
Footnote 18] The lower courts have
also applied a rationale for fee-shifting based on the premise that
the expense of litigation may often be a formidable if not
insurmountable obstacle to the private litigation necessary to
enforce important public policies. [
Footnote 19] This "private attorney general" rationale
has not been squarely before this Court, and it is not so now; nor
do we intend to imply any view either on the validity or scope of
that doctrine. It is sufficient for our purposes here to observe
that this case clearly does not fall within any of these
exceptions. Miller Act suits are plain and simple commercial
litigation. In effect, then, we are being asked to go the last mile
in this case, to judicially obviate the American Rule in the
context of everyday commercial litigation, where
Page 417 U. S. 131
the policies which underlie the limited judicially created
departures from the rule are inapplicable. This we are unprepared
to do. The perspectives of the profession, the consumers of legal
services, and other interested groups should be weighed in any
decision to substantially undercut the application of the American
Rule in such litigation. Congress is aware of the issue. [
Footnote 20] Thus, whatever the
merit of arguments for a further departure from the American Rule
in Miller Act commercial litigation, those arguments are properly
addressed to Congress.
The judgment of the Court of Appeals is affirmed insofar as it
holds that Cerpac is a subcontractor for Miller Act purposes and
that there was proper venue for suit on the shipment diverted to
South Carolina, but reversed insofar as it holds that an award of
attorneys' fees to respondent Industrial is required by the
Act.
It is so ordered.
[
Footnote 1]
Government contracts of less than $2,000 in value are excepted
from the statute's coverage.
[
Footnote 2]
Shipments under the contract were invoiced by the truckload. The
South Carolina shipment involved two such truckloads, while the
other 21 shipments were each of only one truckload of lumber.
[
Footnote 3]
When Cerpac fell behind in its payments, Industrial indicated it
would not deliver the final two truckloads of wood to the Beale
project until it received satisfactory assurances of payment. Rich
agreed to pay Industrial directly for the last two shipments, with
Cerpac to receive its customary profit as a commission from
Industrial. The last two shipments were made on May 18 and June 23,
1966, invoices being payable in full 30 days thereafter. The
shipments were invoiced directly to Rich with copies to Cerpac, the
invoices showing the shipments as being under the original "Beale
647" contract between Industrial and Cerpac. Rich nonetheless
refused to pay the full invoice price of the two final shipments.
Rich has since conceded its obligation to pay Industrial's claim
for these two shipments, so there is no longer any controversy in
regard to the amounts due on those invoices.
[
Footnote 4]
Cerpac subsequently filed for discharge in bankruptcy, and is no
longer a party.
[
Footnote 5]
All invoices under the Beale contract between Industrial and
Cerpac were payable within 30 days with interest at an annual rate
of eight percent after the due date. The District Court awarded
Industrial seven percent interest on all "unliquidated claims." The
Court of Appeals, however, ruled that the amounts due under the
terms of the contract were liquidated damages, and should bear an
interest rate of eight percent.
The District Court had also given judgment against Transamerica
on its bond for the shipment which was sent to the South Carolina
site. The Court of Appeals held that judgment should not have been
rendered against Transamerica for material not delivered to the
project for which it served as surety.
[
Footnote 6]
Petitioners also raise issues in their brief concerning the
timeliness of the Miller Act notice and the amount of prejudgment
interest awarded respondent. Those issues were not raised in the
petition for certiorari, hence are not properly before the Court.
See, e.g., Namet v. United States, 373 U.
S. 179,
373 U. S. 190
(1963); Rule 23.1(c) of the Rules of this Court.
[
Footnote 7]
See, e.g., Aetna Casualty & Surety Co. v. United States
ex rel. Gibson Steel Co., 382 F.2d 615, 617 (CA5 1967);
Basich Bros. Construction Co. v. United States ex rel.
Turner, 159 F.2d 182 (CA9 1946);
cf. United States ex rel.
Bryant v. Lembke Construction Co., 370 F.2d 293 (CA10
1966).
[
Footnote 8]
Travelers Indemnity Co. v. United States ex rel. Western
Steel Co., 362 F.2d 896, 898 (CA9 1966);
United States ex
rel. Wellman Engineering Co. v. MSI Corp., 350 F.2d 285, 286
(CA2 1965).
[
Footnote 9]
Beale Air Force Base is located in the jurisdiction of the
Federal District Court for the Eastern District of California;
hence respondent brought suit on the Beale contract in that
court.
[
Footnote 10]
United States ex rel. Capolino Sons, Inc. v. Electronic
& Missile Facilities, Inc., 364 F.2d 705 (CA2 1966);
see cases collected,
id. at 707.
[
Footnote 11]
The Court of Appeals reversed the judgment against Transamerica,
on its bond, as to the shipment of wood diverted to South Carolina,
because a Miller Act surety is liable only for material supplied
for use on the bonded project. But a decision on the ultimate
question of the surety's liability involves different
considerations from the questions of whether venue for suit on the
bond is proper. Petitioner Rich's liability for the amount due on
the South Carolina shipment was based on a pendent claim, the
substance of which was not challenged in this Court or in the Court
of Appeals.
[
Footnote 12]
473 F.2d 720, 727 (1973). The same analysis has been accepted in
several other cases;
see Transamerica Insurance Co. v. Red Top
Metal, Inc., 384 F.2d 752 (CA5 1967);
United States ex
rel. White Masonry, Inc. v. F.D. Rich Co., 434 F.2d 855, 859
(CA9 1970);
Arnold v. United States ex rel. Bowman Mechanical
Contractors, Inc., 470 F.2d 243, 245 (CA10 1972).
[
Footnote 13]
After the decision in the District Court, but prior to the Court
of Appeals' opinion, Cal.Govt.Code § 4207 (1966) was replaced,
and the effective provisions transferred to Cal.Civ.Code §
3250 (Supp. 1974), by an act of the California Legislature, dated
August 31, 1969, that took effect on January 1, 1971. Given our
reasoning, however, the revision in language of the applicable
California law is of no relevance to the result reached herein.
[
Footnote 14]
B.C. Richter Contracting Co. v. Continental Casualty
Co., 230 Cal. App.
2d 491, 41 Cal. Rptr. 98 (1964) (construing the former law,
see n 13,
supra).
[
Footnote 15]
The American Rule has come under repeated criticism over the
years.
See generally Ehrenzweig, Reimbursement of Counsel
Fees and the Great Society, 54 Calif.L.Rev. 792 (1966); Kuenzel,
The Attorney's Fee: Why Not a Cost of Litigation?, 49 Iowa L.Rev.
75 (1963); McLaughlin, The Recovery of Attorney's Fees: A New
Method of Financing Legal Services, 40 Ford.L.Rev. 761 (1972);
McCormick, Counsel Fees and Other Expenses of Litigation as an
Element of Damages, 15 Minn.L.Rev. 619 (1931); Stoebuck, Counsel
Fees Included in Costs: A Logical Development, 38 U.Colo.L.Rev. 202
(1966); Note, Attorney's Fees: Where Shall the Ultimate Burden
Lie?, 20 Vand.L.Rev. 1216 (1967).
[
Footnote 16]
Judicial Council of Massachusetts, First Report, 11 Mass. L.Q.
1, 64 (1925).
[
Footnote 17]
See, e.g., Vaughan v. Atkinson, 369 U.
S. 527 (1962);
McEnteggart v. Cataldo, 451 F.2d
1109 (CA1 1971);
Bell v. School Bd. of Powhatan County,
321 F.2d 494 (CA4 1963);
Rola v. Atlantic Coast Line R.
Co., 186 F.2d 473 (CA4 1951); 6 J. Moore, Federal Practice
54.77[2], p. 1709 (2d ed.1974).
[
Footnote 18]
See, e.g., Hall v. Cole, 412 U. S.
1 (1973);
Mills v. Electric Auto-Lite Co.,
396 U. S. 375
(1970);
Natural Resources Defense Council v. EPA, 484 F.2d
1331 (CA1 1973);
Callahan v. Wallace, 466 F.2d 59 (CA5
1972);
Bright v. Philadelphia-Baltimore-Washington Stock
Exchange, 327 F.
Supp. 495, 506 (ED Pa.1971);
cf. Nussbaum, Attorney's
Fees in Public Interest Litigation, 48 N.Y.U.L.Rev. 301 (1973);
Comment, The Allocation of Attorney's Fees After
Mills v.
Electric Auto-Lite Co., 38 U.Chi.L.Rev. 316 (1971)
[
Footnote 19]
See, e.g., Cooper v. Allen, 467 F.2d 836 (CA5 1972);
Knight v. Auciello, 453 F.2d 852 (CA1 1972);
Lee v.
Southern Home Sites Corp., 444 F.2d 143 (CA5 1971);
La
Raza Unida v. Volpe, 57 F.R.D. 94 (ND Cal.1972);
Ross v.
Goshi, 351 F.
Supp. 949 (Haw.1972);
Sims v. Amos, 340 F.
Supp. 691 (MD Ala.1972);
cf. Bradley v. School Bd. of the
City of Richmond, 416 U. S. 696
(1974);
Northcross v. Memphis Bd. of Education,
412 U. S. 427
(1973);
Newman v. Piggie Park Enterprises, Inc.,
390 U. S. 400
(1968); Nussbaum,
n 18,
supra; Note, Awarding Attorneys' Fees to the "Private
Attorney General": Judicial Green Light to Private Litigation in
the Public Interest, 24 Hastings L.J. 733 (1973).
[
Footnote 20]
A congressional committee charged with making a broad-based
inquiry about legal services is currently studying,
inter
alia, the general issue of attorneys' fees. Hearings on Legal
Fees before the Subcommittee on Representation of Citizen Interests
of the Senate Committee on the Judiciary, 93d Cong., 1st Sess.
(1973);
cf. S.Rep. No. 93-146 (1973), accompanying S.Res.
101.
MR. JUSTICE DOUGLAS, dissenting in part.
The Court, dealing with the Miller Act's predecessor, held in
Illinois Surety Co. v. John Davis Co., 244 U.
S. 376,
244 U. S. 380,
that the Heard Act "must be construed liberally." That same
principle applies to the Miller Act.
Fleisher Co. v. United
States ex rel. Hallenbeck, 311 U. S. 15,
311 U. S. 17-18.
The Act is silent as to attorneys' fees, saying only that the
payment bond shall allow the supplier "to prosecute said action to
final execution and judgment for the sum or sums justly due him."
40 U.S.C. § 270b(a).
Page 417 U. S. 132
The Miller Act is unlike the Lanham Act involved in
Fleischmann Distilling Corp. v. Maier Brewery Co.,
386 U. S. 714.
That Act itemized the components of the remedy which the Act
afforded: injunctive relief, treble damages, and "costs" (which by
federal statute did not include attorneys' fees).
Id. at
386 U. S.
719-720. Moreover, attempts to amend the Lanham Act to
include attorneys' fees had never succeeded,
id. at
386 U. S. 721.
Here there is no such legislative history; nor does the Miller Act
itemize the components of the "sum or sums justly due."
The Court says that dependence on state law is inappropriate,
for we deal with a federal standard that should be uniform. That
takes great liberties with the Miller Act. Here, the contract and
law were made in California and were to be performed there. In
Illinois Surety Co. v. John Davis Co., supra, the contract
and law were made in Illinois, and were to be performed there. "
Questions of liability for interest must therefore be determined by
the law of that State," said Mr. Justice Brandeis speaking for the
Court, 244 U.S. at
244 U. S. 381.
If state law would give the claimant interest, it should give him
attorneys' fees based on the purpose of the Miller Act. Judge
Carter writing for the Court of Appeals pointed out that the Miller
Act is the federal equivalent of state lien laws.
See 473
F.2d 720, 727. The remedy in a federal suit is therefore properly
composed of the same elements as would be available to lien
claimants in a state court collecting for labor and materials
furnished on nonfederal projects. One of the elements of recovery
permitted in a California court is attorneys' fees. The "sum or
sums justly due" should as a matter of federal law be construed to
be the same as that due a claimant whose remedy is based on a state
statute, when the federal remedy was intended to be the equivalent
of the state remedy.
Page 417 U. S. 133
What Mr. Justice Brandeis said of interest is equally applicable
to attorneys' fees under the Miller Act.
* Under the
circumstances present here it would seem quite unjust not to
include in the sum that is due the cost of collecting that sum.
* The Court of Appeals for the Fifth Circuit awarded attorneys'
fees under a Florida statute where suit was brought under the
Miller Act,
United States ex rel. Weyerhaeuser Co. v. Bucon
Construction Co., 430 F.2d 420, 425.
And see United States
ex rel. White Masonry, Inc. v. F.D. Rich Co., 434 F.2d 855,
859, where the Court of Appeals for the Ninth Circuit followed
Alaska law.