Respondents, whose profits on defense contracts are undergoing
renegotiation pursuant to the Renegotiation Act of 1951, sued in
the District Court under the Freedom of Information Act (FOIA) to
enjoin petitioner Board from withholding documents that respondents
had requested and from conducting any further renegotiation
proceedings until the documents were produced. The District Court
in each case granted injunctive relief. The cases were consolidated
on appeal and the Court of Appeals affirmed, holding that the
District Court had jurisdiction under the FOIA to enjoin
administrative proceedings before petitioner and to order
production of the documents. Though noting that the FOIA nowhere
authorizes injunctions of agency proceedings, the court concluded
that Congress intended to confer broad equitable jurisdiction upon
the district courts, and that "temporary stays of pending
administrative procedures may be necessary on occasion to enforce
[FOIA] policy." The court also concluded that contractors had to
exhaust their administrative remedies only under the FOIA, but not
under the Renegotiation Act, before they were able to request
injunctive relief against renegotiation proceedings, and that
contractors' remedies before petitioner
Page 415 U. S. 2
and
de novo proceedings in the Court of Claims as
provided under the Renegotiation Act were inadequate to prevent
irreparable harm. Petitioner contends that the FOIA's provision in
5 U.S.C. § 552(a)(3) for enjoining an agency from withholding
its records and ordering the production of records improperly
withheld from a complainant is the sole method of judicial
enforcement.
Held:
1. The FOIA does not limit the inherent powers of an equity
court to grant relief, as is manifest from the broad statutory
language that Congress used, with its emphasis on disclosure, its
carefully delineated exemptions, and the fact that § 552(a)
vests equitable jurisdiction in the district courts. Pp.
415 U. S.
16-20.
2. In a renegotiation case, a contractor must pursue its
administrative remedy under the Renegotiation Act, and cannot,
through resort to preliminary litigation over an FOIA claim, obtain
judicial interference with the procedures set forth in the
Renegotiation Act.
Aircraft & Diesel Equipment Corp. v.
Hirsch, 331 U. S. 752;
Lichter v. United States, 334 U.
S. 742;
Macauley v. Waterman S.S. Corp.,
327 U. S. 540. Pp.
415 U. S.
20-25.
(a) It would contravene the Act's legislative purpose if
judicial review by way of injunctive relief under FOIA were allowed
to interrupt the process of bargaining that inheres in the
statutory renegotiation scheme, and would delay the Government's
recovery of excessive profits. Pp.
415 U. S.
20-23.
(b) The contractor, through a
de novo proceeding in the
Court of Claims, where discovery procedures are available, is not
limited in exercising its normal litigation rights. Pp.
415 U. S.
23-24.
151 U.S.App.D.C. 174, 466 F.2d 345, reversed and remanded.
BLACKMUN, J., delivered the opinion of the Court, in which
BURGER, C.J., and BRENNAN, WHITE, and REHNQUIST, JJ., joined.
DOUGLAS, J., filed a dissenting opinion, in which STEWART,
MARSHALL, and POWELL, JJ., joined,
post, p.
415 U. S. 26.
Page 415 U. S. 3
MR. JUSTICE BLACKMUN delivered the opinion of the Court.
Three cases, consolidated for hearing in the court below, raise
the issue of the effect of the Freedom of Information Act (FOIA), 5
U.S.C. § 552, upon proceedings pending under the Renegotiation
Act of 1951, C. 15, 65 Stat. 7, as amended, 50 U.S.C.App. §
1211
et seq. In particular, they concern the jurisdiction
of a federal district court to enjoin the renegotiation process
until an FOIA claim is resolved.
I
The three respondents, Bannercraft Clothing Company, Inc., Astro
Communication Laboratory, a division of Aiken Industries, Inc., and
David B. Lilly Co., Inc., successor to Delaware Fastener
Corporation, all possessed national defense contracts with a
"Department" of the United States, as defined in § 103(a) of
the Renegotiation Act, 50 U.S.C.App. § 1213(a). These
agreements, therefore, under § 102 of that Act, 50 U.S.C.App.
§ 1212, were subject to renegotiation.
A.
Bannercraft. In 1966 and 1967, this respondent
manufactured uniforms at a plant in Philadelphia. Its fiscal year
was the calendar year. Because most of its production was subject
to renegotiation, the company, for each of the two years, timely
filed with the Renegotiation Board the financial statement required
under § 105(e)(1) of the Act, 50 U.S.C.App. § 1215(e)(1).
Representatives
Page 415 U. S. 4
of the Eastern Regional Renegotiation Board then reviewed
Bannercraft's operations and conferred with its president. On
February 20, 1970, the Regional Board, by letter, advised the
contractor that it was recommending that Bannercraft in 1967 had
realized excessive profits in the amount of $1,400,000, subject to
the usual adjustment for state taxes measured by income and for any
tax credit to which the contractor was entitled under § 1481
of the Internal Revenue Code of 1954, 26 U.S.C. § 1481.
[
Footnote 1]
Bannercraft promptly requested that it be furnished, pursuant to
32 CFR § 1477.3 (1970) [
Footnote 2] with a "written summary of the facts and
reasons" upon which the determination was based. It asserted,
however, that
"it is not possible to state [as the Regulation's proviso
required] whether all relevant evidence has been submitted, since
we have never had in writing the basis upon which you made this
determination."
The Regional Board replied that, because "the statement required
by the regulation" was not submitted, "your request for a summary
is defective."
Bannercraft's response was that it had "submitted all of the
evidence which it believes to be relevant to the
Page 415 U. S. 5
renegotiation proceedings," but that this was "without prejudice
to an opportunity to offer evidence on the issues disclosed by the
[Regional Board's] Summary of Facts and Reasons," and that the
required statement was "somewhat meaningless when we do not have a
written statement of the issue upon which you have made your
finding."
On March 16, Bannercraft, pursuant to the FOIA, made a written
request of the Renegotiation Board that six categories of documents
be produced. [
Footnote 3] No
response to this request was forthcoming.
In late April, the Board, by letters, notified Bannercraft of
its determinations that the contractor had realized excessive
profits in the amount of $75,000 for 1966 (the same figure
determined by the Regional Board) and
Page 415 U. S. 6
$1,450,000 for 1967 (an increase of $50,000 over the Regional
Board's determination).
Bannercraft then went to court. On May 1, it filed a complaint
against the Board in the United States District Court for the
District of Columbia, praying that the Board be enjoined from
withholding the documents requested and from conducting any further
renegotiation proceedings with Bannercraft for 1966 and 1967 until
the documents were produced. The Board opposed the application for
temporary relief and moved to dismiss. Judge Smith issued a
temporary restraining order and, thereafter, a preliminary
injunction, each without opinion, and stayed further Board
proceedings.
In May, the Board issued a Statement of Facts and Reasons for
Bannercraft's years 1966 and 1967. Bannercraft then made a further
request for documents related to the factual basis for the Board's
conclusions reflected in the Statement. In July, the Board
responded. It produced some documents and, with respect to others,
claimed exemption under 5 U.S.C. § 552(b) [
Footnote 4] or asserted that the information
sought was not covered by the Act. [
Footnote 5]
Page 415 U. S. 7
On August 4, the Board moved to dissolve the preliminary
injunction. It took the position that its response to Bannercraft's
requests fulfilled its obligations under the FOIA. The District
Court denied the motion. The Board then appealed.
B.
Astro. This respondent's factual case is essentially
the same as Bannercraft's. The year at issue is the fiscal year
ended September 30, 1967. Astro, pursuant to the FOIA, requested
production by the Board of five categories of material. [
Footnote 6] At a conference held on May
12, 1970, Astro was advised that the Board had made a tentative
determination of excessive profits for the year in the amount of
$225,000. In July, the Board denied Astro's FOIA request.
Page 415 U. S. 8
On August 12, Astro filed its complaint against the Board in the
United States District Court for the District of Columbia. I t
prayed for relief similar to that sought by Bannercraft. Judge
Pratt enjoined the Board from continuing renegotiation proceedings
with Astro. The court also ordered the Board to allow Astro, within
30 days, to inspect and obtain copies of all documents requested by
Astro that the Board had no objection to turning over, and to
submit to the court,
in camera, all documents the Board
objected to producing, with a statement of reasons for each
objection. The Board appealed.
C.
Lilly. This respondent's case is similar to the
other two. In June 1970, Lilly and its predecessor in interest,
Delaware Fastener Corporation, were advised by their renegotiator
that he had made determinations of excessive profits for 1967 for
Lilly in the amount of $200,000 and for Fastener in the amount of
$500,000. [
Footnote 7] On June
29, the two corporations asked the Board to furnish certain
categories of information. [
Footnote 8]
No response was immediately forthcoming from the Board. On July
9, Lilly filed its complaint against the Board in the United States
District Court for the District
Page 415 U. S. 9
of Columbia, praying for an order compelling the Board to
produce the documents demanded and restraining the Board from
acting and, in particular, from requiring the contractors to elect
a procedure until the documents had been produced and the
contractors had been given a reasonable time to study them.
Thereafter, the Board denied the request for information.
On July 31, Judge Jones issued an order temporarily restraining
the Board from continuing renegotiation with Lilly and Delaware.
Subsequently, the Board moved to dismiss the complaint or, in the
alternative, for summary judgment. On September 1, a preliminary
injunction was issued. The Board appealed.
The three appeals were consolidated and heard together in the
United States Court of Appeals for the District of Columbia
Circuit. The Court of Appeals, one judge dissenting, affirmed all
three decisions. 151 U.S.App.D.C. 174, 466 F.2d 345 (1972). It held
that the District Court possessed jurisdiction under the FOIA to
enjoin administrative proceedings before the Board and to order the
production of appropriate documents. It concluded that, "although
it is undeniably true that Congress was principally interested in
opening administrative processes to the scrutiny of the press and
general public" when it enacted the FOIA, "Congress was also
troubled by the plight of those forced to litigate with agencies on
the basis of secret laws or incomplete information."
Id.
at 181, 466 F.2d at 352. The court then described this latter
congressional concern as a "subsidiary statutory purpose," citing
excerpts from S.Rep. No. 813, 89th Cong., 1st Sess., 7 (1965), and
from H.R.Rep. No. 1497, 89th Cong., 2d Sess., 8 (1966), and also
citing 5 U.S.C. § 552(a)(2).
See infra at 12 n. 9. It
reasoned that, despite "the fact that the Act nowhere in terms
authorizes . . . injunctions" against agency proceedings, in
enacting the statute, Congress intended to confer broad
Page 415 U. S. 10
equitable jurisdiction upon the district courts, and that
"temporary stays of pending administrative procedures may be
necessary on occasion to enforce the policy" of the FOIA. 151
U.S.App.D.C. at 181-183, 466 F.2d at 352-354.
The court then turned to the exhaustion of administrative
remedies question. It observed that there is no general rule that
it is always improper for a court to interfere with pending
administrative proceedings, citing
McKart v. United
States, 395 U. S. 185,
395 U. S. 193
(1969). It concluded that,
"when the purposes of the doctrine are individually measured
against the facts of these cases, it is plain that no legitimate
judicial policy would be served by depriving these appellees of the
relief they seek."
151 U.S.App.D.C. at 184, 466 F.2d at 355. In effect, the court
reasoned that contractors need exhaust only their administrative
remedies under the FOIA, and not their administrative remedies
under the Renegotiation Act, as a condition precedent to requesting
injunctive relief against renegotiation proceedings. The court
found the contractors' remedies before the Board and
de
novo proceedings in the Court of Claims inadequate to prevent
irreparable harm.
The dissenting judge began with the accepted proposition that
federal courts have only limited jurisdiction, and stated that the
majority's observation, to the effect that the "existence of
present need for judicial intervention does have a bearing on both
jurisdiction and exhaustion," is "an error bordering on
constitutional dimensions," for the appellees' need "is wholly
irrelevant to determination of the jurisdiction of the District
Courts in these cases."
Id. at 191, 466 F.2d at 362.
The dissent then turned to the principle that, where a statute
creates a right and provides a special remedy, that remedy is
exclusive. Thus, in the FOIA, Congress
Page 415 U. S. 11
gave the general public an express right of access to all
Federal Government information not within the exempted categories.
This right was enforceable by
"the specific, narrow, remedies of an injunction against
withholding agency records and an affirmative order to produce such
records improperly withheld."
Ibid. The dissent concluded that no jurisdiction to
grant any other remedy was conferred by Congress, and that the
District Court, therefore, was without jurisdiction to enjoin the
proceedings before the Renegotiation Board. Nothing in the
congressional reports cited by the majority justified its contrary
conclusion. The dissent further concluded that there was no
suggestion that Congress had any concern with litigants before the
administrative agencies, and that what they were concerned with was
to make information available "to any member of the public without
requiring any showing of need therefor."
Id. at 192, 466
F.2d at 363.
The dissent also was at odds with the majority's disposition of
the exhaustion issue. It asserted that the majority seriously
misconstrued the intended functioning of the Renegotiation Board's
procedures, namely, that controlled access to information
concerning the Government's position plays a significant role in
the administrative process; that interruption of the administrative
proceedings totally destroys the balance of negotiating strength;
and that the attempt to enjoin the ongoing negotiations was really
not a request for relief under the FOIA, but was a challenge to the
Board's procedures themselves.
Id. at 194-195, 466 F.2d at
365-366.
We granted certiorari, 410 U.S. 907 (1973), because of the
importance of the issue of the impact of the FOIA upon
long-established procedures of the Renegotiation Board.
Page 415 U. S. 12
II
Before considering the issue of the District Court's
jurisdiction to enjoin a proceeding pending in the Renegotiation
Board, it is helpful to review the provisions of the FOIA and of
the Renegotiation Act of 1951:
A.
The FOIA. This statute, 5 U.S.C. § 552, was
enacted in 1966, 80 Stat. 383, as a revision of § 3 of the
Administrative Procedure Act, 5 U.S.C. § 1002 (1964 ed.).
S.Rep. No. 813, 89th Cong., 1st Sess., 3-4 (1965); H.R.Rep. No.
1497, 89th Cong., 2d Sess., 1-6 (1966). It was amended by Pub.L.
90-23, adopted June 5, 1967, 81 Stat. 54.
Section 552(a) states, "Each agency shall make available to the
public" certain information of enumerated categories. This covers
virtually all information not specifically exempted by §
552(b). Section 552(a)(2) [
Footnote
9] provides the sanction that a "final order, opinion,
statement of policy, interpretation, or staff manual or
instruction"
Page 415 U. S. 13
may not be relied upon as precedent by the agency against a
party unless "it has been indexed and either made available or
published," or unless a party has "actual and timely notice of the
terms thereof." Section 552(a)(3) specifically vests the District
Court with jurisdiction "to enjoin the agency from withholding
agency records and to order the production of any agency records
improperly withheld." It places the burden on the agency to sustain
its action; it empowers the District Court to punish the
responsible employee for contempt in the event of noncompliance;
and it provides that the FOIA suit generally is to take precedence
on the court's docket and is to be expedited on the calendar.
[
Footnote 10]
B.
The Renegotiation Act of 1951. [
Footnote 11] This statute, 50 U.S.C.App.
§§ 1211-1233, enacted shortly after the close of World
War II and at the height of the Korean conflict, recites that
Congress had made available "extensive funds" for the execution of
the national defense program and that "sound execution" of the
program requires "the elimination of excessive profits from
contracts made with the United States, and from related
subcontract." § 101, 50 U.S.C.App. § 1211. The
Renegotiation
Page 415 U. S. 14
Board is established as an independent agency in the Executive
Branch to accomplish this objective. § 107, 50 U.S.C.App.
§ 1217(a). The Board's functions are excluded from the
operation of the Administrative Procedure Act (5 U.S.C. § 551
et seq., and § 701
et seq.) except the
public information section thereof (5 U.S.C. § 552). §
111, 50 U.S.C.App. § 1221.
The Board operates primarily by informal negotiation with the
contractor, and not by formal hearing. It is directed to "endeavor
to make an agreement with the contractor . . . with respect to the
elimination of excessive profits." § 105(a), 50 U.S.C.App.
§ 1215(a). The contractor subject to the Act must file, for
its fiscal year, a detailed financial statement. § 105(e)(1),
50 U.S.C.App. § 1215(e)(1). On the basis of this statement, an
initial determination of excessive profits is made. From the date
of filing of the statement, the Board has one year to commence
proceedings, [
Footnote 12]
and, with stated exceptions, the renegotiation is to be completed
within two years following its commencement or "all liabilities of
the contractor . . . for excessive profits with respect to which
such proceeding was commenced shall thereupon be discharged."
[
Footnote 13] § 105(c),
50 U.S.C.App. § 1215(c).
If the Board and the contractor do not agree, the Board, by
order, determines the excessive profits. § 105(a), 50
U.S.C.App. § 1215(a). At the request of the contractor, the
Board shall furnish it "with a statement of such determination, of
the facts used as a basis
Page 415 U. S. 15
therefor, and of its reasons for such determination."
Ibid. The contractor then may initiate a
de novo
proceeding in the Court of Claims, [
Footnote 14] which has exclusive jurisdiction to
determine the contractor's excessive profits. § 108, 50
U.S.C.App. § 1218 (1970 ed., Supp. II). The action "shall not
be treated as a proceeding to review the determination of the
Board,"
ibid., and the Board's statement "shall not be
used in the Court of Claims as proof of the facts or conclusions
stated therein," § 105(a), 50 U.S.C.App. § 1215(a) (1970
ed., Supp. II).
The renegotiation process itself is initiated by notice to the
contractor and by assignment of the contractor's report to the
appropriate Regional Board. 32 CFR § 1472.2 (1972). [
Footnote 15] Personnel of the
Regional Board then prepare a "Report of Renegotiation" which
includes a "recommendation with respect to the amount, if any, of
excessive profits for the fiscal year under review." 32 CFR §
1472.3(d). This is only the first of several steps within the
agency structure. Thereafter the statement is reviewed,
successively, by a panel of the Regional Board, by the Regional
Board itself, and finally by the Renegotiation Board. At each
level, there is consultation with the contractor, the preparation
of a report and analysis, and submission to the next higher level
of a recommendation as to excessive profits. 32 CFR §§
1472.3(d) and (f)-(i), and §§ 1472.4(b)-(d). At each
stage, the contractor is entitled to a statement of the basis for
the recommendation. Each level is free to make new findings, and no
level is bound by the determination
Page 415 U. S. 16
of the level below; the recommended settlement may decrease or
increase at each level.
Ibid.
III
It is clear, we think, that the Renegotiation Board, as an
entity, is not exempt from applicable provisions of the FOIA. The
Board, of course, is an "independent establishment" in the
Executive Branch. § 107(a) of the Renegotiation Act, 50
U.S.C.App. § 1217(a). But "agency" is broadly defined to mean
"each authority of the Government of the United States," except the
Congress, the courts, territorial governments, the government of
the District of Columbia, and, with respect to 5 U.S.C. § 552,
certain other specifically described entities and functions. 5
U.S.C. § 551(1). The Renegotiation Board is not among those
excepted. Further, the House Committee's discussion of the
requirement of § 552(a)(2), that an agency's concurring and
dissenting opinions, as well as final opinions, be made available,
discloses that a reason for this provision was that "a recent
survey indicated that five agencies -- including . . . the
Renegotiation Board -- do not make public the minority views of
their members." H.R.Rep. No. 1497,
supra, at 8. Thus,
despite its unique operational methods, the Board falls within the
definition of "agency" in § 551(1). [
Footnote 16]
So to conclude, however, does not provide automatically the
answer to the question whether the FOIA authorizes a district court
to enjoin Renegotiation Board
Page 415 U. S. 17
proceedings until the court determines that the contractor is or
is not entitled to information it claims under the FOIA.
As to this question, the respondent contractors assert that,
although the FOIA does not grant this injunctive power in express
terms, the power is to be implied from the court's inherent
capacity to provide appropriate equitable relief. The Board, on the
other hand, emphasizes that Congress in the Act expressly
authorized the court to compel the production of agency records
improperly withheld, placed the burden on the agency to sustain its
action, and directed precedence on the docket for suits under the
Act "over all other causes" and expedition of those suits "in every
way." 5 U.S.C. § 552(a)(3). The Board then contends that these
provisions constitute the exclusive method for enforcing the
disclosure requirements of the Act and that any implication of
other injunctive power, at the behest of a litigant before the
agency, would be inconsistent with the statutory language.
Clearly, as the Court of Appeals held, 151 U.S.App.D.C. at 181,
466 F.2d at 352, the Congress "was principally interested in
opening administrative processes to the scrutiny of the press and
general public when it passed the Information Act." The Second
Circuit has described the Act's "ultimate purpose" as one
"to enable the public to have sufficient information in order to
be able, through the electoral process, to make intelligent,
informed choices with respect to the nature, scope, and procedure
of federal governmental activities"
(footnote omitted).
Frankel v. SEC, 460 F.2d 813, 816,
cert. denied, 409 U.S. 889 (1972). The Senate Report too,
expressed concern for "an informed electorate." S.Rep. No. 813,
89th Cong., 1st Sess., 3 (1965). [
Footnote 17]
Page 415 U. S. 18
The FOIA, 5 U.S.C. § 552(a)(3), explicitly confers
jurisdiction [
Footnote 18]
to grant injunctive relief of a described type, namely,
"to enjoin the agency from withholding agency records and to
order the production of any agency records improperly withheld from
the complainant."
In addition, it provides a specific remedy for noncompliance.
This primary purpose of the FOIA, and this express grant of
jurisdiction to enjoin in a specific way, coupled with a limited
sanction, might suggest that the Act's provision for compelled
production was intended to be the exclusive enforcement method. It
has been held that "where a statute creates a right and provides a
special remedy, that remedy is exclusive."
United States v.
Babcock, 250 U. S. 328,
250 U. S. 331
(1919). And
"Congress, for reasons of its own, decided upon the method for
the protection of the 'right' which it created. It selected the
precise machinery and fashioned the tool which it deemed suited to
that end."
Switchmen's Union v.
NMB,
Page 415 U. S. 19
320 U. S. 297,
320 U. S. 301
(1943).
See National Railroad Passenger Corp. v. National Assn.
of Railroad Passengers, 414 U. S. 453,
414 U. S. 458
(1974). One therefore may argue, as the Board has argued here, that
this is not a situation where
"Congress has utilized . . . the broad equitable jurisdiction
that inheres in courts and where the proposed exercise of that
jurisdiction is consistent with the statutory language and policy,
the legislative background and the public interest.
Porter v.
Warner Holding Co., 328 U. S. 395,
328 U. S.
403 (1946)."
There is significant authority, however, that points to the
opposite conclusion.
Porter itself, although recognizing
the kind of situation to which
Babcock is applicable, 328
U.S. at
328 U. S. 403,
upheld broad equitable power in the District Court under a statute
authorizing the court to grant injunctive and restraining relief
"or other order," and did so, not only because of the presence of
the "other order" language, but because of the "traditional equity
powers of a court."
Id. at
328 U. S. 400.
Emphasis on broad equity power, even in the face of a silent
statute, also appears in
Mitchell v. Robert DeMario Jewelry,
Inc., 361 U. S. 288,
361 U. S.
290-291 (1960);
Scripps-Howard Radio, Inc. v.
FCC, 316 U. S. 4 (1942);
Arrow Transportation Co. v. Southern R. Co., 372 U.
S. 658,
372 U. S. 671
n. 22 (1963);
see L. Jaffe, Judicial Control of
Administrative Action 659 (1965), and is sometimes related to the
All Writs Act, 28 U.S.C. § 1651(a).
FTC v. Dean Foods
Co., 384 U. S. 597,
384 U. S.
603-604 (1966).
The broad language of the FOIA, with its obvious emphasis on
disclosure and with its exemptions carefully delineated as
exceptions; the truism that Congress knows how to deprive a court
of broad equitable power when it chooses so to do,
Scripps-Howard, supra, 316 U.S. at
316 U. S. 17; and
the fact that the Act, to a definite degree, makes the district
courts the enforcement arm of the statute, 5 U.S.C. §
552(a)(3), persuade us that the
Babcock and
Page 415 U. S. 20
Switchmen's Union principle of a statutorily prescribed
special and exclusive remedy is not applicable to FOIA cases. With
the express vesting of equitable jurisdiction in the district court
by § 552(a), there is little to suggest, despite the Act's
primary purpose, that Congress sought to limit the inherent powers
of an equity court.
IV
We find it unnecessary, however, to decide in these cases,
whether, or under what circumstances, it would be proper for the
District Court to exercise jurisdiction to enjoin agency action
pending the resolution of an asserted FOIA claim. We hold only
that, in a renegotiation case, the contractor is obliged to pursue
its administrative remedy and, when it fails to do so, may not
attain its ends through the route of judicial interference. The
nature of the renegotiation process mandates this result, and, were
it otherwise, the effect would be that renegotiation, and its aims,
would be supplanted and defeated by an FOIA suit. [
Footnote 19]
Before the adoption of the FOIA, this Court consistently held
that the design of the Renegotiation Act was to have renegotiation
proceed expeditiously without interruption for judicial review, and
that the Board's proceedings were not to be enjoined prior to the
exhaustion of the administrative process. This was the result where
the proceedings were challenged on constitutional grounds,
Aircraft & Diesel Equipment Corp. v. Hirsch,
331 U. S. 752
(1947);
Lichter v. United States, 334 U.
S. 742,
334 U. S.
789-793 (1948), on statutory grounds,
Macauley v.
Waterman S.S. Corp., 327 U. S. 540
(1946), and on procedural grounds,
Lichter, 334 U.S. at
334 U. S. 791.
The
Page 415 U. S. 21
Court's emphasis was on the absence of any "lawful function" on
the part of the courts "to anticipate the administrative decision
with their own,"
Aircraft, 331 U.S. at
331 U. S. 767;
on the availability of a due process hearing in the
post-administrative
de novo proceeding in the Tax Court,
Macauley, 327 U.S. at
327 U. S. 543,
where constitutional as well as nonconstitutional issues could be
resolved,
Aircraft, 331 U.S. at
331 U. S. 769
n. 30, citing 89 Cong.Rec. 9930 (1943), [
Footnote 20] and at 771; and on the Act's provisions
for expeditious settlement in informal negotiation free "from the
tedious burden of litigation."
Id. at 770.
In
Aircraft, the Court rejected arguments substantially
the same as those advanced by the respondents here,
id. at
758 n. 12 (inability to participate effectively because of lack of
information upon which the Board had relied,
see No. 95,
O.T. 1946, Tr. of R., Vol. I, p. 141), and refused to permit
renegotiation to be enjoined.
"To countenance short-circuiting of the Tax Court proceedings
here would be, under all the circumstances but more especially in
view of Congress' policy and command with respect to those
proceedings, a long overreaching of equity's strong arm."
331 U.S. at
331 U. S.
781.
Reflection upon the nature of the Renegotiation Board's process
fortifies these conclusions. The character and the entire
atmosphere of the process is negotiation -- that is, renegotiation
-- of an existing contract. And negotiation is a bargaining
process, with give and
Page 415 U. S. 22
take, and with stress upon and use of the strengths of one's own
position and the weaknesses of the position of the other party. It
is in a process such as this where the phrase "leading from
strength" has been so effectively transferred in practical
application from the card table to the world of commerce. It is
part of the warp and woof of production. It is pure bargaining --
permitted by the statute with respect to contracts already made --
the same kind of bargaining that produces the union-employer
agreement or the transfer of substantial property from the willing
seller to the interested buyer.
We see nothing in the adoption of the FOIA in 1966 that impinges
upon the settled law of the
Aircraft-Lichter-Macauley
cases or that warrants an exception to the principle they espouse.
Nothing new by way of due process emerged with the FOIA. Nothing
therein indicates that Congress wished to change the Renegotiation
Act's purposeful design of negotiation without interruption for
judicial review. FOIA's stress was on disclosure, to be sure, but
it was on disclosure for the public,
EPA v. Mink,
410 U. S. 73,
410 U. S. 80
(1973), and not for the negotiating self-interested contractor.
Id. at
410 U. S. 86;
see K. Davis, Administrative Law Treatise § 3 A. 4,
p. 120, § 3 A. 29, p. 171 (Supp. 1970). And when Congress in
1971 reviewed the Renegotiation Act and substituted the Court of
Claims for the Tax Court, no other significant change in the
existing process was effected.
See S.Rep. No. 92-245
(1971), accompanying H.R. 8311, which became the amending statute,
Pub.L. 92-41, 85 Stat. 97.
It is no answer to say, as Bannercraft and Astro urge, that
Aircraft, Lichter, and
Macauley relate only to
issues on the merits over which Congress had vested jurisdiction in
the first instance in the Board and then in the Tax Court. We read
those decisions otherwise.
Page 415 U. S. 23
Seeking injunctive relief during the pendency of renegotiation
encourages delay through resort to preliminary litigation over an
FOIA claim. The delay is not imaginary, or without ultimate
consequence. The present cases provide an example of this, for each
has been pending now for more than three years. The Government is
foreclosed from taking action to recover excessive profits until
the Board's final order is entered; even then, interest does not
begin to run until 30 days after the entry of that order. 50
U.S.C.App. §§ 1215(b)(1) and (2). The contractor, by
delay, has little to lose and much to gain.
There is no limitation or denial of the contractor's normal
litigation rights when the renegotiation process is at end. The
contractor may institute its
de novo proceeding in the
Court of Claims, unfettered by any prejudice from the agency
proceeding and free from any claim that the Board's determination
is supported by substantial evidence. There, the usual rights of
discovery are available. [
Footnote 21] And there the parties are not bound by a
prior determination made at any level of the Renegotiation Board
structure. 50 U.S.C.App. § 1218. That proceeding is the
judicial remedy at law provided by the Renegotiation Act, and is
adequate protection against injury. Note, 41 Geo.Wash.L.Rev. 1072,
1084 (1973). We note that a contractor does not become obligated to
remit excessive profits until termination of the Court of Claims
suit, if it elects that course. The injury suffered, absent an
injunction, is no more than the risk of being
Page 415 U. S. 24
unsuccessful in the
de novo bargaining process and the
incurrence of the expense incident to renegotiation. [
Footnote 22] Mere litigation
expense, even substantial and unrecoupable cost, does not
constitute irreparable injury.
Myers v. Bethlehem Shipbuilding
Corp., 303 U. S. 41,
303 U. S. 51-52
(1938); L. Jaffe, Judicial Control of Administrative Action 429
(1965). Without a clear showing of irreparable injury,
see
Virginia Petroleum Jobbers Assn. v. FPC, 104 U.S.App.D.C. 106,
111, 259 F.2d 921, 926 (1958), failure to exhaust administrative
remedies serves as a bar to judicial intervention in the agency
process.
Myers, supra; Sears, Roebuck & Co. v. NLRB,
153 U.S.App.D.C. 380, 382, 473 F.2d 91, 93 (1972).
Interference with the agency proceeding opens the way to the use
of the FOIA as a tool of discovery,
see Sears, Roebuck &
Co. v. NLRB, 433 F.2d 210, 211 (CA6 1970), over and beyond
that provided by the regulations issued by the Renegotiation Board
for its proceedings.
See 32 CFR §§
1480.1-1480.12 (1972). [
Footnote
23] Discovery for litigation purposes is not an expressly
indicated purpose of the Act. Protection for the contractor in the
renegotiation process is afforded through the injunctive power
specifically bestowed by 5 U.S.C. § 552(a)(3).
The Renegotiation Act and its predecessors obviously emerged
from congressional awareness that, with the vastness of defense
expenditure, overcharging and misappropriation of public funds by
unscrupulous contractors and those fortuitously placed to perform
needed work were almost inevitable. The target of the
legislation
Page 415 U. S. 25
was excessive profit, not the fair and reasonable one. The
latter was anticipated and accepted. The line between a reasonable
profit and excessive profit is not always easily ascertained or
brightly lit. But the ascertainment of excessive profits was a duty
vested by the Congress in the Renegotiation Board in the first
instance. The Board thus is the fulcrum of a process that enables
the Government initially to consult a contractor, to make a
contract with it, and then to have the contract subject to
modification for excessive profits, whenever they materialize,
without violation of the Due Process Clause of the Fifth Amendment.
The disgorging of excessive profits is not by way of a tax, but the
process is not unlike the imposition of a tax equivalent to the
excessive profits. Congress' initial placing of the
contractor-initiated final proceeding in the Tax Court is
indicative of the relationship.
Of course, there is uncertainty in the renegotiation process.
And, of course, that uncertainty is lessened or eliminated if the
contractor, like the poker player, is able to ascertain all the
cards in the Board's hand. There is risk, also, when the contractor
accepts the determination of excessive profits made at any level of
the renegotiation process. These risks, however, are the same risks
that are inherent in the negotiation and voluntary settlement of
any dispute. The one who pays possibly might pay less if he resorts
to the factfinder instead of making the settlement. But he might
pay more. That is the calculated risk he takes. It is the
calculated risk provided for by Congress in the administrative
process it prescribed in the Renegotiation Act. It is not a risk
ungenerously laid upon the contractor, for it is counterbalanced by
the profound interest of the public in the recapture of excessive
profits that may flow to the contractor under its government
contracts.
Page 415 U. S. 26
We stress, in conclusion, that the merits are not before us.
They are yet to be decided by the District Court. Whether any
demand made by these contractors is so vague as not to constitute a
"request for identifiable records," 5 U.S.C. § 552(a)(3), or
is for material exempt from disclosure under 5 U.S.C. §
552(b), are questions that remain open for decision on remand.
The judgment of the Court of Appeals is reversed, and the case
is remanded for further proceedings consistent with this
opinion.
It is so ordered.
[
Footnote 1]
Shortly prior thereto, the Regional Board advised the contractor
that it had determined its excessive profits for 1966 to be
$75,000.
[
Footnote 2]
"§ 1477.3 Furnishing of other statements."
"When a Regional Board has made . . . a final recommendation in
a Class A case . . . and the contractor is unable to decide whether
to enter into an agreement for the refund of excessive profits so
determined or recommended, the Regional Board . . . will furnish
the contractor a written summary of the facts and reasons upon
which such final determination or recommendation is based in order
to assist the contractor in determining whether or not it will
enter into an agreement:
Provided, That the contractor
requests such a statement within a reasonable time after it has
been advised of such final determination or recommendation, and
states that it has submitted all the evidence which it believes to
be relevant to the renegotiation proceedings."
[
Footnote 3]
The request was based on the decision, only six days earlier, in
Grumman Aircraft Engineering Corp. v. Renegotiation Board,
138 U.S.App.D.C. 147, 425 F.2d 578 (1970), that the Renegotiation
Board was subject to the FOIA and that certain Board orders and
opinions were accessible to the contractor after deletions made in
the light of the Act's exemption provisions.
See the same
case on remand, 325 F. Supp. 1146,
aff'd, 157 U.S.App.D.C.
121, 482 F.2d 710 (1973).
The documents Bannercraft requested were: (1) communications
between the Board and other Government agencies with respect to
Bannercraft's renegotiable contracts for 1966 and 1967; (2)
investigatory or other reports prepared by Board employees
"containing facts which are relevant to the Board's determination
as to Bannercraft's renegotiable contracts" for the two years; (3)
final opinions, and the like, and summaries on which determinations
were based for the years 1962 through 1968 for 11 named companies
engaged in similar manufacture; (4) facts upon which the Board
concluded that Bannercraft's pricing policy in 1966 was
unreasonable; (5) identification of those manufacturers with which
Bannercraft's production cost was compared, as stated in the
summary for 1966, with cross-reference to comparable data as to
each of the 11 named manufacturers; and (6) the "procurement
information," described in the summary for 1966, that the Board
contended indicated that there was a lack of effective price
competition.
[
Footnote 4]
"§ 552."
"
* * * *"
"(b) This section does not apply to matters that are --"
"
* * * *"
"(3) specifically exempted from disclosure by statute;"
"(4) trade secrets and commercial or financial information
obtained from a person and privileged or confidential;"
"(5) inter-agency or intra-agency memorandums or letters which
would not be available by law to a party other than an agency in
litigation with the agency;"
"
* * * *"
"(7) investigatory files compiled for law enforcement purposes
except to the extent available by law to a party other than an
agency. . . ."
[
Footnote 5]
The Board took the position (a) that the Board-agency
communications, the investigatory and other reports, and the
"procurement information" (to the extent it consisted of written
records), being the first, second, and sixth items specified in the
request of March 16, were exempt under 5 U.S.C. §§
552(b)(3), (4), (5), and (7); (b) that the facts relied upon by the
Board in concluding that Bannercraft's pricing policy was
unreasonable, that is, the fourth item in the request of March 16,
and the identification of manufacturers, the fifth item, were not
requests "for records"; and (c) that copies of clearance notices,
orders, and renegotiation agreements issued with respect to the 11
companies named in the third item of the March 16 request, and with
respect to manufacturers with whom Bannercraft's production cost
was compared, as called for by the fifth item, all with identifying
details deleted, were supplied therewith. Beyond this, documents
requested by Bannercraft were refused.
[
Footnote 6]
These were all documents that constituted the Astro
renegotiation report for the year; all documents in the file that
analyzed "or in any way [bore] upon" Astro's treatment of selling
expenses; all file documents that had to do with "Information
received," as referred to in a stated communication from the
Regional Board to Astro; all file documents that related to the
reasons for the Board's order denying Astro's request to file an
untimely application for commercial exemption; and all records that
had to do with Astro's renegotiation for the year "to the extent
that such documents have been generated by and are in the custody
of either" the Regional Board or the Board itself.
[
Footnote 7]
Delaware Fastener Corp. was merged into David B. Lilly Co.,
Inc., in 1970 after renegotiation proceedings as to each
corporation had begun, but before Lilly's suit was instituted.
[
Footnote 8]
The corporations requested all communications between the Board
and other governmental agencies concerning either corporation; all
sections of the Report of Renegotiation prepared by the Regional
Board; all analyses used in comparing either of the corporations
"with other contractors or subcontractors and reflecting the facts
relating to such comparisons"; all written communications between
the Board and firms holding renegotiable contracts or subcontracts
in any way concerning either of the corporations and their
performance; and all intra-agency memoranda and written
communications consisting of recommendations or analyses prepared
by the Board in connection with the renegotiation proceedings.
[
Footnote 9]
"§ 552. Public Information; agency rules, opinions, orders,
records, and proceedings."
"(a) Each agency shall make available to the public information
as follows:"
"
* * * *"
"(2) Each agency, in accordance with published rules, shall make
available for public inspection and copying --"
"(A) final opinions . . ."
"(B) . . . statements of policy and interpretations . . .
and"
"(C) administrative staff manuals and instructions to staff that
affect a member of the public;"
". . . A final order, opinion, statement of policy,
interpretation, or staff manual or instruction that affects a
member of the public may be relied on, used, or cited as precedent
by an agency against a party other than an agency only if -- "
"(i) it has been indexed and either made available or published
as provided by this paragraph; or"
"(ii) the party has actual and timely notice of the terms
thereof."
[
Footnote 10]
In pertinent part, § 552(a)(3) provides:
"On complaint, the district court . . . has jurisdiction to
enjoin the agency from withholding agency records and to order the
production of any agency records improperly withheld from the
complainant. In such a case the court shall determine the matter de
novo and the burden is on the agency to sustain its action. In the
event of noncompliance with the order of the court, the district
court may punish for contempt the responsible employee. . . .
Except as to causes the court considers of greater importance,
proceedings before the district court, as authorized by this
paragraph, take precedence on the docket over all other causes and
shall be assigned for hearing and trial at the earliest practicable
date and expedited in every way."
[
Footnote 11]
Predecessor renegotiation statutes are cited and described in
Lichter v. United States, 334 U.
S. 742,
334 U. S. 745
n. 1 (1948).
[
Footnote 12]
Section 105(c), 50 U.S.C.App. § 1215(c), provides that, in
the absence of fraud, malfeasance, or willful misrepresentation,
all liabilities of the contractor for excessive profits shall be
discharged if the "proceeding is not commenced prior to the
expiration of one year following the date upon which such statement
is so filed."
[
Footnote 13]
The respondents in the present litigation have agreed to suspend
their limitation periods pending resolution of the FOIA claims.
See 151 U.S.App.D.C. 174, 190 n. 12, 466 F.2d 345, 361 n.
12 (1972).
[
Footnote 14]
Until July, 1971, the proceeding was to be initiated in the Tax
Court. 65 Stat. 21.
[
Footnote 15]
The CFR citations throughout this section of this opinion are to
the 1972 version of Renegotiation Board procedures in effect at the
time of the Court of Appeals' decision. The regulations were
amended substantially in the fall of 1972.
See 32 CFR pts.
1400 1599 (1973).
[
Footnote 16]
The Court of Appeals in the present litigation and other federal
decisions have recognized the general applicability of the FOIA to
the Renegotiation Board.
See Fisher v. Renegotiation
Board, 153 U.S.App.D.C. 398, 473 F.2d 109 (1972);
Lykes
Bros. S.S. Co. v. United States, 198 Ct.Cl. 312, 327, 459 F.2d
1393, 1401 (1972);
Grumman Aircraft Engineering Corp. v.
Renegotiation Board, 138 U.S.App.D.C. 147, 425 F.2d 578
(1970).
[
Footnote 17]
Among other decisions emphasizing this general public purpose of
the Act are
Ethyl Corp. v. EPA, 478 F.2d 47, 48 (CA4
1973);
Sterling Drug, Inc. v. FTC, 146 U.S.App.D.C. 237,
242, 450 F.2d 698, 703 (1971);
Soucie v. David, 145
U.S.App.D.C. 144, 153, 448 F.2d 1067, 1076 (1971);
LaMorte v.
Mansfield, 438 F.2d 448, 451 (CA2 1971);
Bristol-Myers Co.
v. FTC, 138 U.S.App.D.C. 22, 25, 424 F.2d 935, 938,
cert.
denied, 400 U.S. 824 (1970).
[
Footnote 18]
S. 1666, 88th Cong., 2d Sess., was passed by the Senate on July
28, 1964, 110 Cong.Rec. 17086-17089, and reconsidered and passed
again on July 31, 1964, 110 Cong Rec. 17666-17668. There was
insufficient time, however, for full consideration by the House. S.
1160, 89th Cong., 1st Sess., then became the FOIA, and "is
substantially S. 1666." S.Rep. No. 813, 89th Cong., 1st Sess., 4
(1965). There was no change in the remedy provided.
The Senate report which accompanied S. 1666 explains,
"The provision for enjoining an agency from further withholding
is placed in the statute to make clear that the district courts
shall have this power."
S.Rep. No. 1219, 88th Cong., 2d Sess., 7 (1964). In discussing
the contempt provision, the Report states, "This is another
addition which has been made to avoid any possible misunderstanding
as to the courts' powers."
Ibid.
[
Footnote 19]
See Note, 1973 U.Ill.L.F.180, 191 (1973); Note, 51
Tex.L.Rev.757, 765 (1973).
[
Footnote 20]
The committee has provided that any contractor aggrieved by a
determination of excessive profits under the old law, whether he
was cooperative and signed a closing agreement or not, may have a
review of that determination in the Tax Court of the United States
and in the review have all issues, constitutional and otherwise,
decided by the court.
(Remarks of Cong. Disney.)
[
Footnote 21]
The Court of Claims has been described, "by virtue of its role
in the renegotiation process and its general expertise in the field
of government contracts," as being "uniquely qualified to supervise
discovery against the Renegotiation Board." Note, 41
Geo.Wash.L.Rev. 1072, 1084 (1973).
[
Footnote 22]
In this litigation, there is no allegation or evidence that the
Board was negotiating in bad faith or acting
ultra vires.
We therefore are not now concerned with the situation where
allegations or evidence of that kind is present
[
Footnote 23]
Since the institution of these suits, the Board has amended its
regulations to expand the discovery available to contractors.
See 32 CFR §§ 1470.3, 1472.3 to 1472.6, 1474.3
to 1474.5 (1973).
MR. JUSTICE DOUGLAS, with whom MR. JUSTICE STEWART, MR. JUSTICE
MARSHALL, and MR. JUSTICE POWELL concur, dissenting.
The Court reverses the Court of Appeals, saying that respondent
contractors had not exhausted their administrative remedies. At
issue is whether data in possession of the Renegotiation Board and
relevant to the controversy between respondents and that Board
should be disclosed to respondents. That raises a question under
the Freedom of Information Act. It is, I submit, clear that
respondents had exhausted every known way to obtain those data
through administrative channels. Nothing remained to be done at
that level. The District Court is the enforcement arm of the FOIA.
Today's decision, however, says that court cannot act. Hence,
respondents are without remedy. The end result is to make the FOIA
a dead letter in this area. Hence, my dissent.
The nature of the so-called administrative law aspects of the
problems under the Renegotiation Act is unique. The aim, of course,
is the elimination of excessive profits of contractors and
subcontractors in the national defense program, 50 U.S.C.App.
§ 1211. Detailed financial information must be filed with the
Renegotiation
Page 415 U. S. 27
Board,
id. § 1215(e)(1). If, on the basis of those
data, the Board decides to proceed, it refers the case to a
Regional Renegotiation Board, which determines tentatively the
amount of excessive profits, 32 CFR § 1472.3(e). [
Footnote 2/1] A conference with the
contractor is then arranged. It may agree with the Regional Board's
determination or contest it. If the latter, a second conference is
held with a panel of the Regional Board, which hears the arguments
of the contractor and submits its recommendations to the Regional
Board, which may be for a greater or lesser amount than the
original tentative determination,
id. §§
1472.3(f), (h), (i). Thereupon, the Regional Board makes its
recommendation,
id. § 1472.3(i). If the contractor is
still dissatisfied, it can appeal to the Renegotiation Board
itself. In that event, the case is assigned to a division of the
Board, which is not bound by or limited to any finding or
determination of the Regional Board,
id. § 1472.4(b).
The division studies the case
de novo, and makes a
recommendation to the Board which then makes a determination
greater than, equal to, or less than any of the prior
determinations,
id. § 1472.4(d). Even then, the
renegotiation process continues, the Board seeking to obtain the
contractor's voluntary agreement. Only if that effort fails is a
final order determining the amount of excessive profits made,
ibid.
That is the end of the administrative road, but the contractor
still has an appeal to the Court of Claims, which may redetermine
de novo what the excessive profits are, 50 U.S.C.App.
§ 1218 (1970 ed., Supp. II); and from the Court of Claims,
certiorari may be sought here,
id., § 1218a (1970
ed., Supp. II).
Page 415 U. S. 28
The history of the Act makes plain what can be inferred from the
nature of the administrative process just described -- that
Congress chose negotiation, not confrontation or traditional
adjudication, as the desirable route. The Act requires the Board to
"endeavor to make an agreement with the contractor or subcontractor
with respect to the elimination of excessive profits,"
id., § 1215(a). The pressure is on the contractor to
settle, as at each successive step in the procedure its liability
may be increased. The standards are rather vague and imprecise,
§§ 1213(e)(1)-(6), [
Footnote
2/2] the regulations stating that
"[r]easonable profits will be determined in every case by
over-all evaluation of the particular factors present, and not by
the application of any fixed formula with
Page 415 U. S. 29
respect to rate of profit, or otherwise,"
32 CFR § 1460.8. The vagueness of the standards and the
risk of an increase in liability at every level of the
administrative process have a powerful coercive influence.
Approximately 88% of the Board's cases are ended by voluntary
agreement, coercive orders being entered in only 12% of the cases.
See Fifteenth Annual Report, Renegotiation Board 13
(1970).
In the three cases involved in this litigation, the District
Court entered its stay orders before the contractors had run the
gauntlet of the administrative process in the limited sense that
each of them had another opportunity to negotiate a lower
settlement with the Board, not counting a
de novo hearing
before the Court of Claims.
The documents which the contractors want are in possession of
the Board. These documents, it is said, will reveal the strength or
weakness of the Board's case against the contractors and the facts
or assumptions on which the Board relies in assessing liability.
Without those documents, it is said, any meaningful negotiation,
envisioned by the Act, is difficult or impossible. Future
de
novo review is not meaningful, it is said, since the
contractors are completely in the dark as to the practical
considerations which could end the dispute, if the documents were
made available. Disclosure of the documents aids negotiation, which
is the aim of the Act, and disclosure is necessary and appropriate
to carry out the purposes of the Act.
The Court properly holds that the Renegotiation Board is an
"agency" within the meaning of the Freedom of Information Act, 5
U.S.C. § 552(a). The Court also properly holds that §
552(a)(3), which grants the district court jurisdiction "to enjoin
the agency from withholding agency records and to order the
production of any agency records improperly withheld from the
complainant," makes that court the enforcement
Page 415 U. S. 30
arm of the FOIA. But it denies relief here on the ground that
these contractors are obliged to pursue their "administrative
remedy" before going to court for an enforcement order.
The Court relies on
Aircraft & Diesel Equipment Corp. v.
Hirsch, 331 U. S. 752, and
other decisions of that vintage which established a judicial "hands
off" policy in renegotiation cases until the case had reached the
Tax Court (now the Court of Claims) stage. But those cases
antedated the FOIA. That Act, contrary to what the Court says, had
as one of its purposes "discovery for litigation purposes."
Congress was concerned not only with the press and the general
public when it lifted the veil of secrecy surrounding federal
agencies, but also with litigants. According to the Senate Report,
the new FOIA was designed in part to
"prevent a citizen from losing a controversy with an agency
because of some obscure and hidden order or opinion which the
agency knows about but which has been unavailable to the citizen
simply because he had no way in which to discover it,"
S.Rep. No. 813, 89th Cong., 1st Sess., 7.
The FOIA deals with problems of discovery, to use a lawyer's
term, and it does not leave the formulation of precise rules of
discovery exclusively to the agencies themselves, but, as noted,
makes the district court the enforcement arm of the Act.
Exhaustion of administrative remedies has skeins of various
colors,
McKart v. United States, 395 U.
S. 185,
395 U. S.
193-194. Ordinarily courts do not interfere until the
agency has completed its action,
id. at
395 U. S. 194,
"or else has clearly exceeded its jurisdiction,"
ibid. The
present case does not entail supplanting administrative expertise
on the merits. The issues tendered concern only administrative
procedure.
The court errs in saying that the contractors did not exhaust
their administrative remedies. They strenuously
Page 415 U. S. 31
sought the information mandated by the FOIA and exhausted all
administrative procedure for obtaining it. That right to full
disclosure, if not granted now, is forever lost. For as these
contractors seek relief at a higher tier of the administrative
process, the reviewing body will not consider whether the
contractors could have negotiated settlements of a lesser amount if
they had had access to the documents whose discovery is involved
here. As Judge J. Skelly Wright said below:
"[I]t should be apparent here that, if the contractors are to be
granted relief at all, they must have it now, before the
administrative momentum carries their cases beyond the point where
the harm can be undone. If we take Congress' declaration of purpose
seriously, then the parties are supposed to negotiate over excess
profits at the lower administrative levels. The seemingly endless
de novo reviews were intended to make the negotiating
process work, not to provide a substitute for negotiation. If the
negotiating process fails to occur, the opportunity is lost
forever. To say that compulsory awards imposed by the Board or the
Court of Claims at the end of the process provide an adequate
remedy is to ignore the difference between an agreement freely
arrived at, as preferred by Congress, and a judgment imposed by a
court of law."
151 U.S.App.D.C. 174, 186, 466 F.2d 345, 357.
The proceeding in the Court of Claims proscribes review of the
Board. Title 50 U.S.C.App. § 1218 (1970 ed., Supp. II)
states:
"A proceeding before the Court of Claims to finally determine
the amount, if any, of excessive profits
shall not be treated
as a proceeding to review the determination of the Board, but
shall be
Page 415 U. S. 32
treated as a proceeding
de novo."
(Emphasis added.) There is no power, as I see it, for the Court
of Claims to remand the case to the Board to cure any irregularity
in its procedures. If these contractors are to have the remedy of
full disclosure, it is now or never.
A procedure that accelerates settlements furthers the policy of
the Renegotiation Act. The Board judges the profits of the
contractors involved in the present case with the profits of other
contractors in determining whether their profits are excessive. The
relative prices, costs, and profits of those other companies are
germane to the ultimate issue to be resolved. One of these
contractors has a low "front office" overhead, as the executive
officer is the president, who has only a secretary. The rest of the
employees are engaged in production. The contractor who has a low
"front office" expense is penalized for efficiency if its profits
are reduced to the scale allowed contractors who have a high "front
office" expense. The Board, in its Regulations under the FOIA,
makes "available for public inspection and copying summaries of
facts and reasons issued by the Board," 32 CFR § 1480.5(a).
But an agency making decisions has no right to make secret the
basis of those decisions [
Footnote
2/3] if the FOIA is to have any real meaning in the
Page 415 U. S. 33
activities of the Renegotiation Board. If a contractor does not
know the reasons why the Board or any of its agencies cuts the
profits of a contractor 95%, it has no meaningful criteria to
determine whether it should settle with the Board or continue to
pursue its remedies up the escalator of the hierarchy. It is as if
a court could rule for the plaintiff or for the defendant without
ever having to disclose its reasons.
The result of today's decision is to put the citizen in a game
of "blind man's buff" with the Renegotiation Board. Enforcement of
the policy of full disclosure under the FOIA is no intrusion in the
determination of the merits of the controversy before the Board.
The expertise of the Board does not relate to the FOIA, but only to
the Renegotiation Act. The FOIA merely describes some of the
procedure to be followed by the Board. Aircraft concerned the
intrusion of the judiciary into the administrative process by a
suit to declare the whole renegotiating procedure unconstitutional
prior to any adjudication of the merits of the contractor's claim.
Granting the relief asked in that case would have gutted the
statutes. Granting the relief here would merely make the rules of
discovery, established by Congress, applicable to the Renegotiation
Board. Denial of the relief establishes a regime of secrecy when
Congress has demanded disclosure, and gives the Renegotiation Board
a degree of administrative absolution [
Footnote 2/4] at war with the philosophy of the
FOIA.
Page 415 U. S. 34
The trend at the federal level has been the evolution of
administrative agencies as principalities of power. The
Administrative Procedure Act, 60 Stat. 237, was passed as an
antidote to that development. It contained a provision in § 3,
5 U.S.C. § 1002 (1964 ed.), for disclosure of information by
the agencies. But it was soon criticized because it was
"full of loopholes which allow agencies to deny legitimate
information to the public. It has been shown innumerable times that
information is often withheld only to cover up embarrassing
mistakes or irregularities and justified by such phrases . . . as
-- 'requiring secrecy in the public interest,' 'required for good
cause to be held confidential,' and 'properly and directly
concerned.'"
S.Rep. No. 1219, 88th Cong., 2d Sess., 8. As the House Report
stated in support of supplanting § 3 of the Administrative
Procedure Act with the FOIA, "Government agencies whose mistakes
cannot bear public scrutiny have found
good cause' for
secrecy." [Footnote 2/5] H.R.Rep.
No. 1497, 89th Cong., 2d Sess., 6. As respects the role of the
courts, the House Report stated:
"The proceedings are to be
de novo so that the court
can consider the propriety of the withholding instead of being
restricted to judicial sanctioning of agency discretion. The Court
will have authority whenever it considers such action equitable and
appropriate to enjoin the agency from withholding its records and
to order the production of agency records improperly withheld. The
burden of proof is placed upon the agency which is the only party
able to justify the withholding. A private citizen
Page 415 U. S. 35
cannot be asked to prove that an agency has withheld information
improperly, because he will not know the reasons for the agency
action."
Id. at 9.
The reluctance of the Court to require this administrative
agency to live under the law calls to mind the admonition of Mr.
Justice Stone, speaking for the Court in
United States v.
Morgan, 307 U. S. 183,
307 U. S.
191:
"Court and agency are the means adopted to attain the prescribed
end, and so far as their duties are defined by the words of the
statute, those words should be construed so as to attain that end
through coordinated action. Neither body should repeat in this day
the mistake made by the courts of law when equity was struggling
for recognition as an ameliorating system of justice; neither can
rightly be regarded by the other as an alien intruder, to be
tolerated if must be, but never to be encouraged or aided by the
other in the attainment of the common aim."
I would affirm the judgment below.
[
Footnote 2/1]
The CFR citations throughout this opinion are to the regulations
which were in effect in 1970. The regulations were substantially
amended in the fall of 1972.
[
Footnote 2/2]
Section 1213(e) provides:
"In determining excessive profits, favorable recognition must be
given to the efficiency of the contractor or subcontractor, with
particular regard to attainment of quantity and quality production,
reduction of costs, and economy in the use of materials,
facilities, and manpower; and in addition, there shall be taken
into consideration the following factors:"
"(1) Reasonableness of costs and profits, with particular regard
to volume of production, normal earnings, and comparison of war and
peacetime products;"
"(2) The net worth, with particular regard to the amount and
source of public and private capital employed;"
"(3) Extent of risk assumed, including the risk incident to
reasonable pricing policies;"
"(4) Nature and extent of contribution to the defense effort,
including inventive and developmental contribution and cooperation
with the Government and other contractors in supplying technical
assistance;"
"(5) Character of business, including source and nature of
materials, complexity of manufacturing technique, character and
extent of subcontracting, and rate of turn-over;"
"(6) Such other factors the consideration of which the public
interest and fair and equitable dealing may require, which factors
shall be published in the regulations of the Board from time to
time as adopted."
[
Footnote 2/3]
The Board in its Regulations also provides:
"When a Regional Board has made . . . a final recommendation in
a Class A case, . . . and the contractor is unable to decide
whether to enter into an agreement for the refund of excessive
profits so determined or recommended, the Regional Board or the
Board, as the case may be, will furnish the contractor a written
summary of the facts and reasons upon which such final
determination or recommendation is based in order to assist the
contractor in determining whether or not it will enter into an
agreement:
Provided, That the contractor requests such a
statement within a reasonable time after it has been advised of
such final determination or recommendation,
and states that it
has submitted all the evidence which it believes to be relevant to
the renegotiation proceedings."
32 CFR § 1477.3. (Emphasis added.)
[
Footnote 2/4]
The hygienic effect of the Administrative Procedure Act is
absent here, because the Renegotiation Board is excluded from that
Act by reason of 50 U.S.C.App. § 1221, the only exception
being found in 5 U.S.C. § 552, at issue in this case.
[
Footnote 2/5]
For an account of the operation of the FOIA between 1967 and
1971,
see Archibald, Access to Government Information --
The Right Before First Amendment, in The First Amendment and the
News Media, Final Report, Annual Warren Conference on Advocacy in
the United States, June 9, 1973, p. 64.