In a contract disputes procedure, the Atomic Energy Commission
(AEC) approved claims of its contractor for additional
compensation. In response to an AEC certifying officer's request
for advice as to one item, however, the General Accounting Office
(GAO) ruled that the claims could not be certified for payment.
When the AEC then refused to pay the compensation, the contractor
brought suit in the Court of Claims alleging that the GAO had no
authority to overturn the AEC approval. The Government, through the
Department of Justice, defended on the ground that the AEC
determination was not final, but was subject to judicial review
under the standards specified in § 321 of the Wunderlich
Act,
"[t]hat . . . the same is fraudulent or capricious or arbitrary
or so grossly erroneous as necessarily to imply bad faith, or is
not supported by substantial evidence."
The Court of Claims held that
"the Government has the right to the same extent as the
contractor to seek judicial review of an unfavorable administrative
decision on a contract claim."
Held:
1. The AEC, which, for the purpose of this contract, was the
United States, had exclusive administrative authority under the
disputes clause procedure to resolve the dispute here at issue, and
neither the contract between the parties nor the Wunderlich Act
permitted still further administrative review by the GAO. Pp.
406 U. S.
8-12.
Page 406 U. S. 2
2. The Wunderlich Act does not confer upon the Department of
Justice the right to appeal from a decision of an administrative
agency, nor is this a case involving a contractor's fraud,
concerning which the Department has broad powers to act under
several statutory provisions. Pp.
406 U. S.
12-19.
193 Ct.Cl. 335, 433 F.2d 1373, reversed.
DOUGLAS, J., delivered the opinion of the Court, in which
BURGER, C.J., and STEWART, BLACKMUN, and POWELL, JJ., joined.
BLACKMUN, J., filed a concurring opinion, in which BURGER, C.J.,
and STEWART and POWELL, JJ., joined,
post, p.
406 U. S. 19.
BRENNAN, J., filed a dissenting opinion, in which WHITE and
MARSHALL, JJ., joined,
post, p.
406 U. S. 23.
REHNQUIST, J., took no part in the consideration or decision of the
case.
MR. JUSTICE DOUGLAS delivered the opinion of the Court.
The question presented in this case is whether the Department of
Justice may challenge the finality of a contract disputes decision
made by the Atomic Energy Commission (AEC) in favor of its
contractor, where the contract provides that the decision of AEC
shall be "final
Page 406 U. S. 3
and conclusive." Section 1 of the Wunderlich Act leaves open for
contest a claim that "is fraudulent or capricious or arbitrary or
so grossly erroneous as necessarily to imply bad faith, or is not
supported by substantial evidence." [
Footnote 1]
Moreover, 41 U.S.C. § 322, provides that
"[n]o government contract shall contain a provision making final
on a question of law the decision of any administrative official,
representative, or board."
The Department of Justice challenged the settlement made by the
AEC on two grounds, (1) that the decision was "not supported by
substantial evidence" and (2) that it was "erroneous as a matter of
law."
But the disputes clause in the contract [
Footnote 2] says that the decision of the AEC is "final
and conclusive," unless
Page 406 U. S. 4
a court determines that the award is vulnerable under §
§ 1 and 2 of the Act. There is no federal statute which
submits disputes of this character to review by one or more
administrative agencies, where, as here, there is no charge of
fraud or bad faith. Nor is there a statute which enables another
federal agency to contest in court the validity of the decision of
the AEC, absent fraud or bad faith.
In plain lay language, the question then is whether, absent
fraud or bad faith, the contractor can rely on the ruling of the
federal agency with which it made the contract or can be forced to
go through still another tier of federal review. We hold that,
absent fraud or bad faith, the federal agency's settlement under
the disputes clause is binding on the Government; that there is not
another tier of administrative review; and that, save for fraud or
bad faith, the decision of AEC is "final and conclusive," it being,
for these purposes, the Federal Government. We reverse the judgment
of the Court of Claims.
Page 406 U. S. 5
I
On August 4, 1961, petitioner contracted with the AEC to build a
testing facility at the National Reactor Test Station in Idaho. The
work was completed and accepted by the AEC on June 29, 1962.
Because of various changes in contract specifications and
difficulties in meeting performance schedules, petitioner submitted
a series of claims to the contracting officer for resolution under
the standard disputes clause contained in the contract, asking for
equitable modifications of the contract and additional
compensation. On August 8 and November 8, 1962, the contracting
officer approved some of the claims and disapproved others, and the
petitioner sought review of the adverse decisions with the AEC.
Since it did not then have a contract appeals board, [
Footnote 3] the Commission referred
petitioner's appeal to a hearing examiner, before whom an adversary
hearing was held. On June 26, 1963, the examiner decided in favor
of eight of petitioner's claims and remanded the dispute to the
contracting officer for negotiations to determine the exact amount
due petitioner. 2 A.E.C. 631. The contracting officer then sought
review of this decision by the Commission.
See 10 CFR
§ 2.760 (Jan. 1, 1963).
The Commission declined to review four of the claims, 2 A.E.C.
738, which had the effect of sustaining the examiner's decision on
them. 10 CFR § 2.762(a) (Jan. 1, 1963). Included within this
group was the examiner's determination that amounts due petitioner
could not be retained to offset claims allegedly owed by petitioner
to other contractors and other agencies of government. The
Page 406 U. S. 6
Commission modified the examiner's decision on three of the
remaining claims and reversed him on the last, which petitioner has
since abandoned. It
"remanded to the contracting officer with instructions to
proceed to final settlement or decision in accordance with the
decision of the hearing examiner dated June 26, 1963, as modified
by [its] order of November 14, 1963, and by [that] decision."
2 A.E.C. 850, 856.
On March 6, 1964, prior to the AEC's final ruling but after it
had upheld the examiner's decision on the "retainage" claim, a
certifying officer of the Commission requested the opinion of the
General Accounting Office on whether a voucher for the retainage
claim could be certified for payment. Jurisdiction for the
Comptroller General's review was purportedly founded upon 31 U.S.C.
§ 82d. [
Footnote 4] After
some 33 months of what amounted to a plenary review of the
proceedings before the examiner, the Comptroller General concluded
that the voucher could not be certified for payment. 46 Comp.Gen.
441. On March 27, 1967, the AEC wrote petitioner, saying,
"The Atomic Energy Commission's view is that S&E
Contractors, Inc. has exhausted its administrative recourse to the
Commission. The Commission will take no action, in connection with
the claims, inconsistent with the views expressed by the
Comptroller General. . . ."
The petitioner then brought this action in the Court of Claims
seeking a judgment of $1.95 million and an order remanding the case
for negotiations on the time extension
Page 406 U. S. 7
to which it claimed it was entitled under the AEC's original
decision.
The defenses tendered raised no issue of any fraud or bad faith
of the contractor against the United States.
On cross-motions for summary judgment, a commissioner of the
Court of Claims ruled in favor of petitioner, holding that the
General Accounting Office lacked authority to review the decision
of the AEC, and that the AEC's refusal to follow its own decisions
favorable to petitioner was a breach of the disputes clause of the
contract. On review by the Court of Claims, however, that decision
was reversed by a four-to-three vote. While the majority
acknowledged "that the Comptroller General effectively stopped
payment of the claims," it did not pass upon the legality of that
action. 193 Ct.Cl. 335, 340, 433 F.2d 1373, 1375. Reasoning,
instead, that the Wunderlich Act allowed both the Department of
Justice and contractors an equal right to judicial review of
administrative decisions and that the AEC's refusal to abide by its
earlier decision was a permissible means of obtaining this review,
it remanded petitioner's claims "to the commissioner for his
consideration and report on the various claims under Wunderlich Act
standards."
Id. at 351, 433 F.2d at 1381.
The Commissioner did not base his opinion on any issue of fraud
or bad faith of the contractor against the United States, nor did
the Court of Claims. The case is now here on a petition for writ of
certiorari, which we granted. 402 U.S. 971.
Petitioner argues that neither the text nor the legislative
history of the Wunderlich Act supports the right of the United
States to seek judicial review of an administrative decision on a
contractual dispute, that the General Accounting Office was without
statutory or contractual authority to overturn the AEC's decision,
and that the
Page 406 U. S. 8
AEC should not be allowed to abandon after some 33 months its
own decision that had been made in petitioner's favor. In response,
the Solicitor General contends that the Wunderlich Act does give
the Department of Justice the right of judicial review of contract
decisions made by federal administrative agencies, and that the
Department of Justice is free to assert whatever defenses it
desires in the Court of Claims without regard to the earlier
actions of the federal contracting agency.
II
The disputes clause included in Government contracts is
intended, absent fraud or bad faith, to provide a quick and
efficient administrative remedy and to avoid "vexatious and
expensive and, to the contractor oftentimes, ruinous litigation."
Kihlberg v. United States, 97 U. S.
398,
97 U. S. 401
(1878). The contractor has ceded his right to seek immediate
judicial redress for his grievances, and has contractually bound
himself to "proceed diligently with the performance of the
contract" during the disputes process. The purpose of avoiding
"vexatious litigation" would not be served, however, by
substituting the action of officials acting in derogation of the
contract. [
Footnote 5]
The result in some cases might be sheer disaster. In the present
case, nearly a decade has passed since petitioner completed the
performance of a contract under which the only agency empowered to
act determined that it was entitled to payment. To postpone payment
for such a period is to sanction precisely the sort of "vexatious
litigation" which the disputes process was designed to avoid.
Page 406 U. S. 9
Here, petitioner contracted with the United States, acting
through the AEC, and it was exclusively with this Commission that
the administrative resolution of disputes rested. Disputes
initially were to be resolved between the contractor and the
contracting officer, and, if a settlement satisfactory to the
contractor could be reached at that level, no review would lie.
[
Footnote 6]
See United
States v. Mason Hanger Co., 260 U. S. 323;
United States v. Corliss Steam-Engine Co., 91 U. S.
321.
By the disputes clause, [
Footnote 7] the decision of the AEC is "final and
conclusive" unless "a court of competent jurisdiction" decides
otherwise for the enumerated reasons. Neither the Wunderlich Act
nor the disputes clause empowers any other administrative agency to
have a veto of the AEC's "final" decision or authority to review
it. Nor does any other Act of Congress, except where fraud or bad
faith is involved, give any other part of the Executive Branch
authority to submit the matter to any court for determination. In
other words, we cannot infer that, by some legerdemain the disputes
clause submitted the dispute to further administrative challenge or
approval, [
Footnote 8] and did
not mean what it says when it made
Page 406 U. S. 10
the AEC's decision "final and conclusive."
See United States
v. Mason & Hanger Co., supra, at
260 U. S. 326.
Kipps, The Right of the Government to Have Judicial Review of a
Board of Contract Appeals Decision Made Under the Disputes Clause,
2 Pub.Contract L.J. 286 (1969); Schultz, Wunderlich Revisited: New
Limits on Judicial Review of Administrative Determination of
Government Contract Disputes, 29 Law & Contemp.Prob. 115,
132-133 (1964).
A citizen has the right to expect fair dealing from his
government,
see Vitarelli v. Seaton, 359 U.
S. 535, and this entails in the present context treating
the government as a unit, rather than as an amalgam of separate
entities. Here, the AEC spoke for the United States and its
decision, absent fraud or bad faith, should be honored.
Cf.
NLRB v. Nash-Finch Co., 404 U. S. 138.
Since the AEC withheld payment solely because of the views of
the Comptroller General, and since he had been given no authority
to function as another tier of administrative review, there was no
valid reason for the AEC not to settle with petitioner according to
its earlier decision. For that purpose, the AEC was the United
States.
Cf. Small Business Administration v. McClellan,
364 U. S. 446,
364 U. S.
449.
The cases deny review by the Comptroller General of
administrative disputes clause decisions as "without legal
authority" absent fraud or overreaching.
E.g., McShain Co. v.
United States, 83 Ct.Cl. 405, 409 (1936). In
Page 406 U. S. 11
James Graham Mfg. Co. v. United States, 91 F. Supp.
715 (ND Cal.1950), for example, the contracting agency had
determined that the contractor was entitled to reimbursement for
certain expenditures under two cost-plus fee contracts, but the
Comptroller General refused payment. While the court noted the
"extensive and broad" powers of the Comptroller General, it held
that, absent instances of "fraud or overreaching," where the
Comptroller General's power was founded upon specific statutory
provisions such as 41 U.S.C. § 53, he had no "authority to
determine the propriety of contract payments" approved by the
contracting agency. 91 F. Supp. at 716. Accordingly, summary
judgment was entered by the court, which said, "Since the Navy
Department has determined that plaintiff contractor is entitled tax
the payment sought, this Court must adjudge accordingly."
Id. at 717.
Congress contemplated giving the General Accounting Office such
powers and, indeed, the Senate twice passed -- in the form of the
McCarran bill -- a provision which would have allowed the
Comptroller to review disputes decisions to determine if they were
"fraudulent, grossly erroneous, so mistaken as necessarily to imply
bad faith, or not supported by reliable, probative, and substantial
evidence." S. 24, 83d Cong., 1st Sess. (1953).
"If enacted, it would [have] invest[ed] the GAO with the power
-- which it has never had -- to upset an administrative decision
which it [found] 'grossly erroneous' or 'not supported by reliable,
probative, and substantial evidence.'"
Schultz, Proposed Changes in Government Contract Disputes
Settlement: The Legislative Battle over the Wunderlich Case, 67
Harv.L.Rev. 217, 243 (1953). The House of Representatives rejected
this provision, however, and the Wunderlich Act was ultimately
passed in its present form. We cannot, therefore, construe
Page 406 U. S. 12
it to give the Comptroller General powers which Congress has
plainly denied.
It is suggested, however, that the Comptroller General's power
is not one of review over the AEC decision, but is merely the power
"to force the contractor to bring suit, and thus to obtain judicial
review for the Government." The disputes clause, however, sets
forth the administrative means for resolving contractual disputes.
Under the present contract, the AEC is the final administrative
arbiter of such claims, and nowhere is there a provision for
oversight by the Comptroller General. The Comptroller General,
however, conducted a 33-month
de novo review of the AEC
proceedings, he blocked the payment to which the AEC determined
petitioner was entitled, and he placed upon petitioner the burden
of going to the Court of Claims to receive that payment. That
action by the Comptroller General was a form of additional
administrative oversight foreclosed by the disputes clause.
III
A majority of the Court of Claims held
"that the Government has the right to the same extent as the
contractor to seek judicial review of an unfavorable administrative
decision on a contract claim."
193 Ct.Cl. at 346, 433 F.2d at 1378. The Solicitor General
adopts this view, and sees in the Attorney General's obligation to
conduct litigation on behalf of the United States, 28 U.S.C.
§§ 516, 519, the power to overturn decisions of
coordinate offices of the Executive Department.
The Attorney General has the duty to "conduct . . . litigation
in which the United States, an agency, or officer thereof is a
party," 28 U.S.C. § 516, and to "supervise all [such]
litigation," 28 U.S.C. § 519. That power is pervasive, but it
does not appear how, under the Wunderlich Act, it gives the
Department of Justice the right to appeal from a decision of the
Atomic
Page 406 U. S. 13
Energy Commission. Normally, where the responsibility for
rendering a decision is vested in a coordinate branch of
Government, the duty of the Department of Justice is to implement
that decision, and not to repudiate it.
See 39
Op.Atty.Gen. 67, 68 (1937); 38 Op.Atty.Gen. 149, 150 (1934); 25
Op.Atty.Gen. 524, 529 (1905); 25 Op.Atty.Gen. 93, 96 (1903); 20
Op.Atty.Gen. 711, 713 (1894); 20 Op.Atty.Gen. 270, 272 (1891); 17
Op.Atty.Gen. 332, 333 (1882). Indeed, this view of the role of the
Department of Justice may be traced back to William Wirt, the first
of our Attorneys General to keep detailed records of his tenure in
office.
"Wirt it was who first recorded the proposition that the
Attorney General does not decide questions of fact, that the
Attorney General does not sit as an arbitrator in disputes between
the government departments and private individuals nor as a
reviewing officer to hear appeals from the decisions of public
officers. . . ."
H. Cummings & C. McFarland, Federal Justice 84 (1937)
(footnotes omitted).
The power to appeal to the Court of Claims a decision of the
federal agency under a disputes clause in a contract which the
agency is authorized to make is not to be found in the Wunderlich
Act and its underlying legislative history. [
Footnote 9] That Act was designed to overturn
our
Page 406 U. S. 14
decision in
United States v. Wunderlich, 342 U. S.
98 (1951), which had closed the courthouse doors to
certain citizens aggrieved by administrative action amounting to
something less than fraud.
See S.Rep. No. 32, 83d Cong.,
1st Sess.; H.R.Rep. No. 1380, 83d Cong., 2d Sess. It should not be
construed to require a citizen to perform the Herculean task of
beheading the Hydra in order to obtain justice from his
Government.
We are reluctant to construe a statute enacted to free citizens
from a form of administrative tyranny so as to subject them to
additional bureaucratic oversight, where there is no evidence of
fraud or overreaching. In this connection, it should be noted that
committee reports accompanying the Wunderlich Act indicate that
judicial review was provided so that contractors would not inflate
their bids to take into account the uncertainties of administrative
action. [
Footnote 10] This
objective would be ill served
Page 406 U. S. 15
if Government contractors -- having won a favorable decision
before the agencies with whom they contracted -- had also to run
the gauntlet of the General Accounting Office and the Department of
Justice.
IV
A contractor's fraud is, of course, a wholly different genus
than the case now before us. Even where the contractor has obtained
a judgment and the time for review of it has expired, fraud on an
administrative agency or on the court enforcing the agency action
is ground for setting aside the judgment.
"[S]etting aside the judgment to permit a new trial, altering
the terms of the judgment, or restraining the beneficiaries of the
judgment from taking any benefit whatever from it,"
Hazel-Atlas Co. v. Hartford Co., 322 U.
S. 238,
322 U. S. 245,
are the usual forms of relief which have been granted. Patents
obtained with unclean hands and contracts that are based on those
patents are similarly tainted, and will not be enforced.
Precision Co. v. Automotive Co., 324 U.
S. 806. Contracts with the United States -- like patents
-- are matters concerning far more than the interest of the adverse
parties; they entail the public interest:
"[W]here a suit in equity concerns the public interest as well
as the private interests of the litigants, this doctrine assumes
even wider and more significant proportions. For if an equity court
properly uses the maxim to withhold its assistance in such a case,
it not only prevents a wrongdoer from enjoying the fruits of his
transgression, but averts an injury to the public."
Id. at
324 U. S.
815.
Page 406 U. S. 16
Congress has made elaborate provisions for dealing with
fraudulent claims of contractors. Where the Comptroller General is
convinced "that any settlement was induced by fraud," he is
directed to "certify . . . all the facts . . . to the Department of
Justice, to the Administrator of General Services, and to the
contracting agency concerned." 58 Stat. 664, as amended, 41 U.S.C.
§ 116(b). The Administrator of General Services is also given
broad powers of investigation, and he is directed to give the
Department of Justice "any information received by him indicating
any fraudulent practices, for appropriate action." 41 U.S.C. §
118(d). Moreover, whenever "any contracting agency or the
Administrator of General Services believes that any settlement was
induced by fraud," the facts shall be reported to the Department of
Justice. 41 U.S.C. § 118(e). And the Department of Justice is
given broad powers to act.
Ibid. In addition, Congress has
imposed severe penalties on contractors who commit fraudulent acts,
and it has given the federal courts power to hear and determine
such cases. 41 U.S.C. § 119.
Broad, flexible civil remedies are also provided against those
who
"use or engage in . . . an agreement, combination, or conspiracy
to use or engage in or to cause to be used or engaged in, any
fraudulent trick, scheme, or device, for the purpose of securing or
obtaining, or aiding to secure or obtain, for any person any
payment, property, or other benefits from the United States or any
Federal agency in connection with the procurement, transfer, or
disposition of property. . . ."
63 Stat. 392, 40 U.S.C.§ 489(b).
As to the Court of Claims, 28 U.S.C. § 2514 provides
that:
"A claim against the United States shall be forfeited to the
United States by any person who corruptly practices or attempts to
practice any fraud against the United States in the proof,
statement, establishment, or allowance thereof. "
Page 406 U. S. 17
"In such cases, the Court of Claims shall specifically find such
fraud or attempt and render judgment of forfeiture. [
Footnote 11]"
These statutory provisions show that, apart from the inherent
power of courts to deal with fraud, the Department of Justice
indubitably has standing to appear or intervene at any time in any
appropriate court to restrain enforcement of contracts with the
United States based on fraud.
See, e.g., United States v.
Hougham, 364 U. S. 310
(1960);
Rex Trailer Co. v. United States, 350 U.
S. 148 (195);
United States v. Dinerstein, 362
F.2d 852 (CA2 1966).
So far as the Wunderlich Act is concerned, it is irrelevant
whether the administrative agency deciding this dispute is the AEC
or the AEC's board of contract appeals. It was common in the
beginning to give final authority over the resolution of disputes
under a Government contract to the designated contracting officer,
save for "fraud or such gross mistake as would necessarily imply
bad faith, or a failure to exercise an honest judgment."
Kihlberg v. United States, 97 U.S. at
97 U. S. 402.
Later came the present boards of contract appeals.
Boards of contract appeals within the respective agencies today
are common. They are not statutory creations, but are established
by administrative regulations. S.Doc. No. 99, 89th Cong., 2d Sess.,
Operation and Effectiveness of Government Boards of Contract
Appeals 20-21. Their decisions "constitute administrative
Page 406 U. S. 18
adjudication in its purest sense."
Id. at 21. As noted,
[
Footnote 12] the AEC has
had a board of contract appeals since 1964. Boards of contract
appeals were in effect long before the Wunderlich Act, and that
explains why the Act provides for review "of any decision of the
head of any department or agency or
his duly authorized
representative or board." 41 U.S.C. § 321 (emphasis
added).
We held in
United States v. Bianchi & Co.,
373 U. S. 709,
that, even where the decision on review in the Court of Claims is
that of a board of contract appeals, the review must be on the
administrative record, and that no trial
de novo may be
held. That decision led to proposals in Congress that, in effect,
rulings of contract appeals boards be denied finality. [
Footnote 13] S.Doc. No. 99,
supra, at 226 and n. 70. But Congress has not taken that
step. Some have urged that, where a decision of a board of contract
appeals is involved, the United States should have standing to
appeal to the Court of Claims.
Id. at 159. But our leading
authority on these problems, Professor Harold C. Petrowitz, who
wrote S.Doc. No. 99,
supra, observed,
"This has never been done, and the procedure may appear
anomalous in view of the relatively close relationship between
boards and the agencies they serve."
Ibid. However serious the problem may be, and whatever
its dimensions, it is obviously one for the Congress to resolve,
not for us to resolve within the limits of the Wunderlich Act.
This case does not involve the situation where an administrative
agency, upon timely petition for rehearing or prompt
sua
sponte reconsideration, determines that its earlier decision
was wrong, and, for that reason, refuses
Page 406 U. S. 19
to abide by it. The AEC has not, to this day, repudiated the
merits of its decisions in favor of petitioner. Nor, to repeat, is
this a case of a fraud of a contractor against the United States.
This is simply an instance where a contractor successfully resolved
its disputes with the agency with which it had contracted and to
whom that power had been delegated. The fruits of petitioner's
labors were frustrated, however, by the intermeddling of another
agency without power to act, and, when petitioner sought
enforcement of its rights in court, still another agency of the
Government entered and sought to disavow the decision made here by
the AEC.
If the General Accounting Office or the Department of Justice is
to be an ombudsman reviewing each and every decision rendered by
the coordinate branches of the Government, that mandate should come
from Congress, not from this Court.
The judgment of the Court of Claims is
Reversed.
MR. JUSTICE REHNQUIST took no part in the consideration or
decision of this case.
[
Footnote 1]
The Wunderlich Act, 68 Stat. 81, provides:
"No provision of any contract entered into by the United States,
relating to the finality or conclusiveness of any decision of the
head of any department or agency or his duly authorized
representative or board in a dispute involving a question arising
under such contract, shall be pleaded in any suit now filed or to
be filed as limiting judicial review of any such decision to cases
where fraud by such official or his said representative or board is
alleged:
Provided, however, That any such decision shall
be final and conclusive unless the same is fraudulent or capricious
or arbitrary or so grossly erroneous as necessarily to imply bad
faith, or is not supported by substantial evidence."
41 U.S.C. § 321.
"No Government contract shall contain a provision making final
on a question of law the decision of any administrative official,
representative, or board."
41 U.S.C. § 322.
[
Footnote 2]
The contract provided:
"6.
Disputes"
"(a) Except as otherwise provided in this contract, any dispute
concerning a question of fact arising under this contract which is
not disposed of by agreement shall be decided by the Contracting
Officer, who shall reduce his decision to writing and mail or
otherwise furnish a copy thereof to the Contractor. The decision of
the Contracting Officer shall be final and conclusive unless,
within 30 days from the date of receipt of such copy, the
Contractor mails or otherwise furnishes to the Contracting Officer
a written appeal addressed to the Commission. The decision of the
Commission or its duly authorized representative for the
determination of such appeals shall be final and conclusive unless
determined by a court of competent jurisdiction to have been
fraudulent, or capricious, or arbitrary, or so grossly erroneous as
necessarily to imply bad faith, or not supported by substantial
evidence. In connection with any appeal proceeding under this
clause, the Contractor shall be afforded an opportunity to be heard
and to offer evidence in support of its appeal. Pending final
decision of a dispute hereunder, the Contractor shall proceed
diligently with the performance of the contract and in accordance
with the Contracting Officer's decision."
"(b) This 'Disputes' Clause does not preclude consideration of
law questions in connection with decisions provided for in
paragraph (a) above; Provided, that nothing in this contract shall
be construed as making final the decision of any administrative
official; representative, or board on a question of law."
[
Footnote 3]
The Atomic Energy Commission Board of Contract Appeals was not
established until 1964.
See 10 CFR § 3.1
et
seq. (Jan. l, 1971).
[
Footnote 4]
Volume 55 Stat. 876, 31 U.S.C. § 82d provides:
"The liability of certifying officers or employees shall be
enforced in the same manner and to the same extent as now provided
by law with respect to enforcement of the liability of disbursing
and other accountable officers, and they shall have the right to
apply for and obtain a decision by the Comptroller General on any
question of law involved in a payment on any vouchers presented to
them for certification ."
[
Footnote 5]
The American Bar Association, as
amicus curiae,
notes
"that the contractor's consent to permit a specific
representative of the Government to decide disputes -- the
Commission -- should not be read as permitting any different
representative of the Government to 'veto' decisions rendered by
the Commission which are in favor of the contractor."
[
Footnote 6]
While the quoted language from paragraph 6(a) of the contract
concerns factual disputes and while questions of law are dealt with
in paragraph 6(b) (
see n 2,
supra), there is no reason to believe that
the two clauses should not be considered
in pari materia,
or that a different avenue for review should apply to legal
questions than to those of fact. Indeed, paragraph 6(b) speaks of
"consideration of law questions
in connection with decisions
provided for in paragraph (a)." (Emphasis added.) The
difference between the two clauses relates only to the standard of
reviewability, and does not establish separate avenues of
review.
[
Footnote 7]
See n 2,
supra.
[
Footnote 8]
For certain types of fraud against the Government, Congress has
vested the General Accounting Office with investigative powers. In
the case of kickbacks by Government contractors, for example,
"the General Accounting Office shall have the power to inspect
the plants and to audit the books and records of any prime
contractor or subcontractor engaged in the performance of a
negotiated contract,"
74 Stat. 741, 41 U.S.C. § 53, and criminal penalties are
provided if a violation is established. 41 U.S.C. § 54.
If the Comptroller General has the broad, roving, investigatory
powers that are asserted, specific statutory grants of authority
such as this provision relating to kickbacks would be
superfluous.
[
Footnote 9]
It has been said that the Act's legislative history "has
something for everyone." Kipps, The Right of the Government to Have
Judicial Review of a Board of Contract Appeals Decision Made Under
the Disputes Clause, 2 Pub.Contract L.J. 286, 295 (1969). Suffice
it to say we find the Act's history, at best, ambiguous. In
construing laws, we have been extremely wary of testimony before
committee hearings and of debates on the floor of Congress save for
precise analyses of statutory phrases by the sponsors of the
proposed laws.
See generally NLRB v. Fruit Packers,
377 U. S. 58,
377 U. S. 66
(1964);
Mastro Plastics Corp. v. NLRB, 350 U.
S. 270,
350 U. S. 288
(1956);
Schwegmann Bros. v. Calvert Corp., 341 U.
S. 384,
341 U. S.
394-395 (1951);
United States v. St. Paul, M. &
M. R. Co., 247 U. S. 310,
247 U. S. 318
(1918);
Omaha & Council Bluffs Street R. Co. v. ICC,
230 U. S. 324,
230 U. S. 333
(1913);
United States v. Trans-Missouri Freight Assn.,
166 U. S. 290,
166 U. S. 318
(1897).
The reason is the caveat of Mr. Justice Holmes, "We do not
inquire what the legislature meant; we ask only what the statute
means." The Theory of Legal Interpretation, 12 Harv.L.Rev. 417,
419.
[
Footnote 10]
The House Report stated,
"A continuation of this situation [created by the
Wunderlich decision] will render the performance of
Government work less attractive to the responsible industries upon
whom the Government must rely for the performance of such work, and
will adversely affect the free and competitive nature of such work.
It will discourage the more responsible element of every industry
from engaging in Government work, and will attract more speculative
elements whose bids will contain contingent allowances intended to
protect them from unconscionable decisions of Government officials
rendered during the performance of their contracts."
H.R.Rep. No. 1380, 83d Cong., 2d Sess., 4.
In a similar vein, the Senate Report on the Senate version of
the Wunderlich Act stated,
"The impact of this decision on the many business firms who, in
a condition of expanding production with respect to the defense of
the United States, must deal with many of the Government
departments in Government construction and defense materials, was
one that could only cause great expense to the United States in
that the contractors would be forced to puff up their bids so as to
be sure of sufficient funds to provide for unforeseen
contingencies."
S.Rep. No. 32, 83d Cong., 1st Sess., 2.
[
Footnote 11]
Where the Department of Justice has successfully asserted this
defense of fraud, the Court of Claims has disallowed contractors'
claims.
See, e.g., Kamen Soap Products Co. v. United
States, 129 Ct.Cl. 619, 124 F. Supp. 608 (1954) (fraudulent
preparation of evidence);
Morris Demolition Corp. v. United
States, 99 Ct.Cl. 3313 (1943);
Jerman v. United
States, 96 Ct.Cl. 540 (1942) (fraudulent invoices);
Mervin
Contracting Corp. v. United States, 94 Ct.Cl. 81 (1941) (false
payroll vouchers);
Atlantic Contracting Co. v. United
States, 57 Ct.Cl. 185 (1922) (embezzlement).
[
Footnote 12]
See n 3,
supra. And see 29 Fed.Reg. 12829
et
seq.
[
Footnote 13]
For other aspects of exhaustion of administrative review of
decisions from boards of contract appeals,
see United States v.
Moorman, 338 U. S. 457;
United States v. Grace & Sons, 384 U.
S. 424;
United States v. Utah Construction Co.,
384 U. S. 394.
MR. JUSTICE BLACKMUN, with whom THE CHIEF JUSTICE, MR. JUSTICE
STEWART, and MR. JUSTICE POWELL join, concurring.
Because I agree that, in this case, where neither fraud nor bad
faith is charged, the Wunderlich Act, 41 U.S.C. §§
321-322, does not operate to give the United States the power to
challenge a contract disputes clause finding of fact in favor of
the contractor by the Government's own contracting agency, I join
the Court's opinion and its judgment. I venture some supportive
comments:
1. The contracting officer and the Atomic Energy Commission
acted here in an executive capacity for the United
Page 406 U. S. 20
States.
See Small Business Administration v. McClellan,
364 U. S. 446,
364 U. S.
448-450 (1960). The Commission is the party to the
contract with the contractor. Its exercise of executive judgment is
necessarily that of the United States. Yet the Government, by its
position here, would grant itself the right to challenge its own
executive determination whenever the General Accounting Office, by
interposition, thinks this should be done. This, for me, does not
make good sense, and, in the absence of clear congressional
authorization, I doubt that it would make good law.
2. The disputes clause in Government contracts has been employed
for over four decades. The clause is one drawn and prescribed by
the United States. It is not one drawn by the contractor, or by any
group of contractors with whom the United States deals. And for
years, with the specified exceptions, that clause itself has been
regarded as conferring no right of judicial review on the part of
the Government.
3. By accepting the disputes clause in his contract, the
contractor bears the interim financial burden and gives up the
right of rescission and the right to sue for damages. What he
receives in return is the Government's assurances of speedy
settlement and of prompt payment, not payment delayed for months
or, as here, for years.
4. To compel a contractor to go through the administrative
process and to proceed and to perform with less than his usual
arsenal of defenses against administrative arbitrariness or
unfairness, and then to have that determination submitted to
judicial review at the behest of still another agency of
Government, subjects the contractor to untoward delay in payment,
and to a financial hazard that may well prove to be ruinous.
5. The result would be a strange one if, as even the GAO here
concedes, a contracting officer's decision favorable to a
contractor possesses finality,
United States v.
Corliss
Page 406 U. S. 21
Steam-Engine Co., 91 U. S. 321
(1876);
United States v. Mason & Hanger Co.,
260 U. S. 323
(1922), while a decision at the higher level of the agency itself
does not. When the officer and the contractor agree to the
disposition of a dispute, there is no occasion for the issuance of
a decision by the contracting officer, and the Wunderlich Act, by
its terms, does not apply. And if the contractor accepts a decision
of the contracting officer, and does not appeal to the Commission,
that decision, by the specific provisions of the disputes clause,
is final and conclusive as to questions of fact. Under the
Government's position, however, the decision at the agency head
would enjoy no such preferred and conclusive status.
*
6. Lurking in the background of the Court's decision is
advantage to the Government resulting from what strikes me as a
possible breach of contract. The contractor here, according to the
long-term understanding of the disputes clause, consented to the
disposition of disputes by the contracting officer and by the AEC
on appeal, and to the finality of decision at those points. It did
not
Page 406 U. S. 22
consent to its review or to the exercise of veto power by any
other agency of Government. When the United States then disavows
the Commission's decision -- a decision that, as the Court notes,
to this day has never been withdrawn or repudiated by the AEC -- it
seems to me that the Government imposes something to which the
contractor has not agreed.
7. The legislative history, which the dissent finds so clearly
supportive of its conclusion, is not at all that clear for me. I
doubt if anyone who reads and absorbs the Appendix to the dissent's
opinion will find it clear and indicative. I regard it, as does the
Court and as did the dissenters in the Court of Claims, as
decidedly ambiguous, at best. Even the Court of Claims majority
struggled with the history and conceded that it did not
"explicitly" provide for Government-instituted judicial review. 193
Ct.Cl. 335, 342, 433 F.2d 1373, 1376. This is not surprising, for
the Wunderlich Act was intended to relieve contractors from the
holding in
United States v. Wunderlich, 342 U. S.
98 (1951), where the Court restricted
contractor-instigated judicial review to the situation of alleged
and proved fraud. In
Wunderlich, the Government sought to
reinstate an Interior Secretary's fact decision, favorable to the
Government and adverse to the contractor, which the Court of Claims
had set aside as "arbitrary," "capricious," and "grossly
erroneous." The Government there urged -- and prevailed over three
dissenting votes -- a narrow judicial review standard for the
contractor. Congress reacted, and the Wunderlich Act overrode this
restrictive measure of review and opened the door to the contractor
to the extent permitted by the proviso clause of § 321.
I am not able to read into this legislative change a
corresponding nod in the direction of the Government. The flat
rejection by Congress of the proposed provision for GAO review is
significant. There would be no point
Page 406 U. S. 23
in that rejection if GAO has the power to defeat the finality of
the disputes decision anyway. And the differing approaches taken on
this appeal by the Department of Justice and the GAO themselves
indicate the inconclusiveness of the legislative history.
8. The issue is not whether advantage is or is not to be taken
of the Government. Of course, the Government's rights are to be
protected. That protection, however, is afforded by the nature and
workings of the contract disputes system, by its emphasis on
expeditious performance and getting the job done, and by the
presence of the contracting officer and the agency, but not of the
GAO. This results in fulfillment of the contract and, at the same
time, gives the contractor the protection he needs against fraud,
capriciousness, arbitrariness, bad faith, and absence of evidence.
In the exercise of its legislative judgment, Congress has
determined that, in this area, the Government needs no more.
I therefore join in reversing the judgment of the Court of
Claims and in giving this contractor the benefit of the decision
made by the Atomic Energy Commission itself, the very agency that
was the contractor's opposite party to the contract.
* Judge Collins, dissenting in the Court of Claims, says it
well:
"When a dispute arises between a contractor and the Government,
the 'disputes' clause sets out clearly the procedure to be
followed. First, the parties may voluntarily settle the dispute. If
they do, that is the end of the matter. If no settlement is
reached, the disputed matters are decided by the agency's
contracting officer. If the contractor does not appeal to the
agency from the contracting officer's decision within the
prescribed time, that, again, is the end of the matter. If,
however, the contractor does appeal to the agency, then, according
to the court, a decision rendered by the agency or its board
favorable to the contractor is not the end of the matter; the
agency is free at any time to disavow or repudiate its own
decision, thereby forcing the contractor to sue. The anomaly
created by the court's decision is too obvious to need elaboration.
While an agency will still be bound by the decisions of its
contracting officers, it will not be bound by decisions made at the
highest level."
193 Ct.Cl. 335, 379-380, 433 F.2d 1373, 1397-1398. (Footnotes
omitted.)
MR. JUSTICE BRENNAN, with whom MR. JUSTICE WHITE and MR. JUSTICE
MARSHALL join, dissenting.
This is a suit by petitioner against the United States to
recover on a contract between petitioner and the Atomic Energy
Commission. The contract included a "disputes clause," which
provided that the Commission would decide any factual disputes that
arose under the contract, and that its decision would
"be final and conclusive unless determined by a court of
competent jurisdiction to have been fraudulent, or capricious, or
arbitrary, or so grossly erroneous as necessarily to imply bad
faith, or not supported by substantial evidence.
Page 406 U. S. 24
The disputes clause also provided that, while it did 'not
preclude consideration of law questions in connection with
[disputes] decisions,' it was not to 'be construed as making final
the [Commission's] decision . . . on a question of law.' Disputes
arose during performance of the contract, and the Commission
decided them in petitioner's favor. The General Accounting Office,
however, when rendering an advisory opinion requested on behalf of
the Commission as to one of the disputed items, disagreed with the
Commission's decision, and, for that reason, the Commission refused
to pay. In petitioner's subsequent suit in the Court of Claims,
petitioner relied upon the Commission's decision as a 'final and
conclusive' resolution of the disputes, entitling petitioner to
summary judgment. The Department of Justice defended the suit on
the grounds that the Commission's decision was not supported by
substantial evidence, and was erroneous on questions of law. The
issue before us is whether the Government, through the Department
of Justice, may assert those defenses."
It may be helpful at the outset to put this case in perspective
by reviewing briefly the law developed over the past century to
regulate the enforcement of disputes clauses in Government
procurement contracts. Until 1954, with the passage of the
Wunderlich Act, disputes clauses provided that the decision of a
designated Government official upon a matter in dispute under the
contract would be final and binding upon both parties. Although, in
terms, the disputes clauses precluded judicial review of disputes
decisions, this Court, beginning in 1878, consistently held that
the finality of a disputes decision could be challenged in court by
either party on the ground of fraud or bad faith by the deciding
Government official. Thus, the "fraud" exception to the finality of
disputes decisions was not written into disputes clauses, but was
judicially fashioned.
Page 406 U. S. 25
Under this system, then, a contractor dissatisfied with an
adverse disputes decision could contest the finality of that
decision only by proving in court that it was fraudulent. The
Government, of course, bore an identical burden when it contested
the finality of a disputes decision in favor of the contractor.
That situation arose when GAO, congressional watchdog of Government
expenditures, refused to sanction payment to a contractor of the
amount found due under a disputes decision in his favor, and
thereby forced him to bring suit. GAO's view of the disputes
decision, however, was of no consequence in court; indeed, whether
or not the Government defended the contractor's suit was a matter
solely for the judgment of the Government's lawyer, the Department
of Justice. Once in court, the contractor relied upon the finality
of the disputes decision and recovered on that basis unless the
Government proved that the decision was fraudulent.
Over the years, the Court of Claims gradually broadened the
fraud exception to the finality of disputes decisions. In 1951,
however, this Court stopped the trend by holding that a disputes
decision, rendered pursuant to a disputes clause purporting to make
that decision final, was conclusive upon both parties unless the
challenger proved in court that the deciding Government official
was guilty of "conscious wrongdoing, an intention to cheat or be
dishonest."
United States v. Wunderlich, 342 U. S.
98,
342 U. S. 100
(1951).
Wunderlich's narrow definition of the fraud
exception alarmed the Government as well as contractors, for, in
practical effect, it meant that disputes decisions were virtually
invulnerable to challenge.
The result of this concern was the so-called Wunderlich Act,
drafted by GAO and supported by GAO, Government procurement
agencies, and contractors. The Act overruled
Wunderlich by
directing that no disputes clause, purporting to make disputes
decisions final,
"shall
Page 406 U. S. 26
be pleaded in any suit . . . as limiting judicial review of any
[disputes] decision to cases where fraud by [the Government]
official . . . is alleged."
The Act did more than simply overrule
Wunderlich,
however, for it also explicitly stated the grounds upon which
courts could set aside disputes decisions:
"any [disputes] decision shall be final and conclusive unless
the same is fraudulent or capricious or arbitrary or so grossly
erroneous as necessarily to imply bad faith, or is not supported by
substantial evidence."
Finally, the Act provided that "[n]o Government contract shall
contain a provision making final on a question of law the decision
of any [Government] official. . . ."
The Wunderlich Act, then, rendered the old forms of disputes
clauses unserviceable, for no longer could the parties bind
themselves to the finality of a disputes decision, judicially
reviewable only if the challenger proved that it was fraudulent.
Consequently, the disputes clause in the contract before us did not
even attempt to provide for the finality of the Commission's
disputes decisions, but instead expressly tracked the language of
the Act. Under this disputes clause and the Act, the party
dissatisfied with a disputes decision is no longer limited to
challenging the finality of that decision only on the ground that
it was "fraudulent," for the dissatisfied party is now entitled
also to prove in court that the decision was "capricious,"
"arbitrary," "so grossly erroneous as necessarily to imply bad
faith," "not supported by substantial evidence," or incorrect "on a
question of law." In this case, the Government relied upon the last
two grounds to challenge the finality of the Commission's disputes
decision in favor of petitioner. [
Footnote 2/1]
Page 406 U. S. 27
As noted above, under pre-Wunderlich Act disputes clauses, which
purported to make disputes decisions final, the Government, like
the contractor, could avail itself of the judicially created fraud
exception to the finality of disputes decisions. The Government
obtained judicial review when GAO refused to sanction payment after
a disputes decision in favor of the contractor, thus forcing him to
bring a suit in which the Department of Justice represented the
Government. That was precisely the path followed in this case, for
GAO, in response to a request for an advisory opinion, informed the
Commission that payment would be improper because the disputes
decision did not meet the standards of the Wunderlich Act, and, in
petitioner's subsequent suit, the Department of Justice represented
the Government. Had this case arisen under earlier forms of
disputes clauses, which purported to make disputes decisions final,
and before the Wunderlich Act, the Government could have defended
the suit only on the judicially created ground that the disputes
decision was fraudulent. Under the current clause and the Act,
Page 406 U. S. 28
however, the Government is not limited to that narrow ground.
Like the contractor, the Government may now also rely upon any or
all of the other grounds enumerated in the clause and the Act. The
Commission's disputes decision is not "final and conclusive," under
the clause and the Act, if the Court of Claims determines, as the
Government asserted here, that the decision was "not supported by
substantial evidence" or was incorrect "on a question of law."
[
Footnote 2/2]
Yet the Court today holds that the Government has no right to
defend petitioner's suit. Had the Commission's disputes decision
been adverse to petitioner, of course, petitioner would have been
free to challenge its finality in court, under the disputes clause
and the Act, on the grounds that it was "not supported by
substantial evidence" and was incorrect "on a question of law." The
Court holds, however, that the Government may not challenge the
finality of the disputes decision in favor of petitioner because
the Government, under the disputes clause and the Act, has no right
to judicial review of disputes decisions. [
Footnote 2/3] The Court reaches this
Page 406 U. S. 29
conclusion on the strength of its assertions that GAO had no
business exercising its statutory authority and advising the
Commission that the disputes decision was erroneous, that the
Department of Justice had no business exercising its statutory
authority and appearing in the Court of Claims to defend
petitioner's suit, and that the Government is always entitled to
relief if the contractor perpetrates a fraud. Noticeably absent
from the Court's opinion is any justification for interpreting the
disputes clause and the Act to apply only when a disputes decision
is adverse to the contractor. Somehow the Court construes a
contract and a statute that bar finality for
all disputes
decisions to require finality for disputes decisions in favor of
contractors.
Today's decision is demonstrably wrong. The Court holds that
Congress enacted the Wunderlich Act for the benefit of contractors,
to arm them with grounds in addition to fraud to challenge in court
the finality of disputes decisions unfavorable to them. Yet,
without an iota of support in the language of the Act, which
expressly governs "any" disputes decision in "any suit," or in the
Act's legislative history, which confirms that the expanded grounds
of judicial review were to be available to both the Government and
contractors, the Court holds that the Government, unlike
contractors, may not rely upon the Act to challenge in court the
finality of disputes decisions. Indeed, the Court goes further,
for, as noted, the disputes clause before us did not purport to
make the Commission's disputes decisions final. The Court thus
holds that the Act denies the Government the privilege of entering
into a contract that affords it as well as the contractor the right
to judicial review of disputes decisions. Hence, while the
Page 406 U. S. 30
Act ensures that contractors are entitled to judicial review
even when the disputes clause provides for finality, the Act also,
according to the Court, ensures that the Government is denied
judicial review even when the disputes clause does not provide for
finality. Today's decision produces the absurd result that, when
the Government agreed to a disputes clause with no provision for
judicial review, it could nevertheless challenge the finality of a
disputes decision at least for fraud, but now that the Government
has agreed to a disputes clause specifying five grounds of judicial
review, including fraud, it is entitled, holds the Court, to none
at all. [
Footnote 2/4] The
Government's position is thus worse than it was before the Act, for
it is deprived of even the limited review for fraud to which it was
entitled under
Wunderlich. Finally, the Act flatly
prohibits disputes clauses that make disputes decisions final on
questions of law. The clause before us, following the Act,
expressly provided
Page 406 U. S. 31
that the Commission's disputes decisions could not be final on
questions of law. Yet, in the face of the Act and the disputes
clause, the Court holds that the Commission's decision is final on
questions of law.
Analysis of the judicial history of disputes clauses, both in
this Court and in the Court of Claims, will unfortunately unduly
extend the length of this opinion. But the devastation today's
decision wreaks upon Government procurement practices is sufficient
justification, and Congress should be alert to the urgent need for
immediate remedial legislation. Congress alone can restore the
former balance between Government and contractor, for today's
decision not only holds that the Act's expanded scope of judicial
review is available solely for contractors, but also holds that the
Act, in some unspecified way, prohibits the contracting parties
from agreeing to a disputes clause that affords the Government that
same scope of review. Congress must therefore make more explicit
what is already explicit in the Wunderlich Act, but this time in
terms so plain that even this Court will be unable to thwart the
congressional will.
I
A The contract in
Kihlberg v. United States,
97 U. S. 398
(1878), as the Court construed it, provided that the decision of a
designated Government official would be "conclusive." The official
rendered a decision adverse to the contractor, and the contractor
brought suit. Because there was "neither allegation nor proof of
fraud or bad faith" by the official, the Court held that his
decision could not "be subjected to the revisory power of the
courts without doing violence to the plain words of the contract."
Id. at
97 U. S. 401.
The Court then enunciated the standard of judicial review that has
been the
Page 406 U. S. 32
basis for the decision of every subsequent disputes clause case,
both in this Court and in the Court of Claims:
"in the absence of fraud or such gross mistake as would
necessarily imply bad faith, or a failure to exercise an honest
judgment, his action in the premises is conclusive upon the
[contractor] as well as upon the government."
Id. at
97 U. S. 402
(emphasis added).
The very first case in this Court, then, laid down the rule that
a decision rendered pursuant to a disputes clause was equally
binding upon both parties; the contractor and the Government could
impeach a disputes decision that the contract purported to make
final, but only by proving that the decision was fraudulent. Until
today, this Court never departed from the
Kihlberg view
that the same standard of judicial review is available to both
parties.
Sweeney v. United States, 109 U.
S. 618 (1883), reiterated the
Kihlberg rule in
another suit by a contractor dissatisfied with a disputes decision
rendered by a Government official. Because
"there was neither fraud, nor such gross mistake as would
necessarily imply bad faith, nor any failure to exercise an honest
judgment on the part of the officer,"
the Court held, "on the authority of
Kihlberg v. United
States," that the official's decision was conclusive.
Id. at
109 U. S.
620.
The Court next decided three cases involving contracts between
private parties. In
Martinsburg & Potomac R. Co. v.
March, 114 U. S. 549
(1885), a contractor agreed to do certain work for a railroad
company, and the contract provided that disputes would be decided
by a company official whose decision would be "final and
conclusive."
Id. at
114 U. S. 553.
The official's decision was in favor of the company, and the
contractor brought suit. The Court, stating that the "case is
within the principles announced in
Kihlberg v. United
States and
Page 406 U. S. 33
Sweeney v. United States,"
id. at
114 U. S. 550
(here, and in subsequent similar quotations, citations not
repeated), held that the official's decision was conclusive because
there was no proof that he
"had been guilty of fraud, or had made such gross mistake in his
estimates as necessarily implied bad faith, or had failed to
exercise an honest judgment in discharging the duty imposed upon
him,"
id. at
114 U. S.
553.
The contract in
Chicago, S. F. & C. R. Co. v.
Price, 138 U. S. 185
(1891), was essentially the same as the contract in
March.
In
Price, however, the official's disputes decision was in
favor of the contractor. The company refused to pay in accordance
with the decision, and the contractor brought suit. The Court first
reviewed
March and stressed that
March had
applied "the principles announced in
Kihlberg v. United
States and
Sweeney v. United States."
Id. at
138 U. S. 193.
The Court then pointed out that
"[t]he only difference between that case [
March] and
the present one is that the alleged mistakes of the engineer in the
former were favorable to the railroad company, while, in this case,
they are favorable to the contractors."
Id. at
138 U. S. 194.
"[T]hat difference," said the Court, "cannot affect the
interpretation of the contract."
Ibid. Because there was
no proof of "fraud upon the part of the company's engineers, or
such gross mistakes by them as imply bad faith," the Court held
that the disputes decision was binding upon the company.
Id. at
138 U. S.
195.
Price thus established that the party whose employee
was delegated authority to make the disputes decision could also
challenge the finality of that decision, although, like the
contractor, only under the
Kihlberg test of fraud. The
Court reaffirmed this application of the
Kihlberg rule in
Sheffield & Birmingham Coal, Iron & R. Co. v.
Gordon, 151 U. S. 285
(1894), holding that,
Page 406 U. S. 34
"in the absence of fraud or mistake" by the company official,
his decision in favor of the contractor "was conclusive upon the
company."
Id. at
151 U. S.
292.
United States v. Gleason, 175 U.
S. 588 (1900), involved a Government official's disputes
decision adverse to the contractor. The Court again affirmed the
rule of
Kihlberg and the intervening cases
"that it is competent for parties to a contract, of the nature
of the present one, to make it a term of the contract that the
decision of an engineer, or other officer, of all or specified
matters of dispute that may arise during the execution of the work
shall be final and conclusive, and that, in the absence of fraud or
of mistake so gross as to necessarily imply bad faith, such
decision will not be subjected to the revisory power of the courts.
Martinsburg & Potomac Railroad v. March; Chicago, Sante Fe
&c. Railroad v. Price."
Id. at
175 U. S. 602.
The Court also followed the
Kihlberg rule in
Ripley v.
United States, 223 U. S. 695,
223 U. S.
701-702, 704 (1912), and
Merrill-Ruckgaber Co. v.
United States, 241 U. S. 387
(1916).
In
United States v. Mason & Hanger Co.,
260 U. S. 323
(1922), the contractor was paid in accordance with a disputes
decision in his favor, but the Comptroller of the Treasury
disagreed with the decision, and subsequently deducted the amount
paid from other sums due the contractor.
Id. at
260 U. S. 325.
The contractor brought suit, relying upon the finality of the
disputes decision. The Court's holding was direct and simple:
"We have decided that the parties to the contract can so provide
and that the decision of the officer is conclusive upon the
parties.
Kihlberg v. United States; Martinsburg & Potomac
R. R. Co. v. March;
Page 406 U. S. 35
United States v. Gleason; Ripley v. United States. This
is extending the rule between private parties to the
Government."
Id. at
260 U. S. 326.
Mason & Hanger, then, applied the
Kihlberg
rule when the contractor in a Government contract relied upon the
disputes decision by a Government official and the Government
challenged it. Hence, both parties to a Government contract, like
both parties to a private contract, as in
Price and
Gordon, were free to challenge the finality of a disputes
decision, although only upon the limited grounds permissible under
Kihlberg.
Mason & Hanger also held that "the Comptroller of
the Treasury has no power" over a disputes decision, 260 U.S. at
260 U. S. 326,
meaning that his disagreement with the decision was irrelevant, and
had no effect in court, where the parties' rights under the
contract were determined. The Government, like the contractor,
could prevail only by proving that the disputes decision was
fraudulent. The Comptroller's authority was limited to his power to
refuse to sanction payment to the contractor, thereby forcing the
contractor to bring suit for a judicial determination of his right
to payment in accordance with the disputes decision in his favor.
[
Footnote 2/5]
In sum, the rule first announced in
Kihlberg in 1878
had, with
Mason & Hanger in 1922, been held to apply
to any disputes decision, whether, in a Government or in a private
contract, and to apply no matter which party relied upon the
finality of the decision. If the Government (or, in a private
contract, the party whose official decided the dispute) relied upon
the finality of the decision, the contractor had to prove that it
was fraudulent.
Kihlberg; Sweeney; March; Gleason. If
Page 406 U. S. 36
the contractor relied upon the finality of the decision, the
Government (or, in a private contract, the party whose official
decided the dispute) had to prove that it was fraudulent.
Price; Gordon; Mason & Hanger. [
Footnote 2/6]
In
United States v. Moorman, 338 U.
S. 457 (1950), the Court once again gave extended
consideration to the proper judicial interpretation of disputes
clauses. The Court pointed out that
"[c]ontractual provisions such as these have long been used by
the Government. No congressional enactment condemns their creation
or enforcement."
Id. at
338 U. S. 460.
The Court then reviewed
Kihlberg, Sweeney, and
March, and said that
"[t]he holdings of the foregoing cases have never been departed
from by this Court. They stand for the principle that parties
competent to make contracts are also competent to make such
agreements."
Id. at
338 U. S. 461.
The Court added that
"[i]f parties competent to decide for themselves are to be
deprived of the privilege of making such anticipatory provisions
for settlement of disputes, this deprivation should come from the
legislative branch of government."
Id. at
338 U. S.
462.
Finally came
United States v. Wunderlich, 342 U. S.
98 (1951). The contract contained the usual disputes
clause providing that the disputes decision was "final and
conclusive."
Id. at
342 U. S. 99.
After noting that the
Page 406 U. S. 37
same disputes clause had been upheld in
Moorman, the
Court stated:
"Contracts, both governmental and private, have been before this
Court in several cases in which provisions equivalent to [this
disputes clause] have been approved and enforced 'in the absence of
fraud or such gross mistake as would necessarily imply bad faith,
or a failure to exercise an honest judgment. . . .'
Kihlberg v.
United States; Sweeney v. United States; Martinsburg & P. R.
Co. v. March; Chicago, S. F. & C. R. Co. v. Price."
Id. at
342 U. S.
99-100.
We thus have an unbroken line of cases in this Court, from 1878
to 1951, applying a simple, straightforward rule of judicial
review. A contractual disputes clause making final a decision by an
agent of one of the parties was given full effect in court, subject
to the judicially created exception that allowed relief to the
party challenging the decision if he was able to prove that it was
fraudulent. This rule applied whether the contract was Government
or private, and no matter which party challenged the finality of
the decision. In short, a disputes clause was equally binding upon
both parties.
B
Most disputes clause cases, of course, have been decided not by
this Court, but by the Court of Claims. That court followed the
Kihlberg rule when a contractor challenged a disputes
decision against him,
see, e.g., Kennedy v. United States,
24 Ct.Cl. 122 (1889);
P. H. McLaughlin & Co. v. United
States, 37 Ct.Cl. 150 (1902);
Pacific Hardware Co. v.
United States, 49 Ct.Cl. 327 (1914);
Brinck v. United
States, 53 Ct.Cl. 170 (1918);
Southern Shipyard Corp. v.
United States, 76 Ct.Cl. 468 (1932), as well as when the
Government challenged a disputes decision in the contractor's
favor.
Page 406 U. S. 38
In
Pacific Hardware, supra, the contract provided that
a Government official would deduct specified amounts from the
contract price if the contractor delayed in performing the
contract. Deductions were made, and the contractor brought suit.
The court applied the
Kihlberg rule, and upheld the
deductions. 49 Ct.Cl. at 336. The contract also provided that the
official could waive deductions under certain circumstances. The
contractor argued that this power violated public policy, and
therefore vitiated the contract. The court rejected the argument,
but added that the power to decide in favor of the contractor by
waving deductions, like the power to decide against the contractor
by making deductions, was subject to the
Kihlberg
rule:
"Of course, if there were fraud or such gross error as implies
bad faith or a failure to exercise an honest judgment in deciding
that the deductions be not made, the Government would not be bound
and the contractor would remain liable."
Id. at 337.
In
Yale & Towne Mfg. Co. v. United States, 58
Ct.Cl. 633 (1923), the disputes decision was in favor of the
contractor, but the Government refused to pay because the
Comptroller of the Treasury disagreed with the decision. The
contractor argued
"that the contract reposed in the contracting officer . . . the
right to determine whether or not and the extent to which the
contractor was entitled to extension of time, and that the finding
of that officer was conclusive upon the parties in the absence of
fraud or mistakes so gross as to imply bad faith."
Id. at 637.
The court, noting "that a long line of decisions not only by
this court but by the Supreme Court require the sustaining of the
[contractor's] contention," stated:
"Provisions in Government contract reposing in some designated
official the right to determine certain
Page 406 U. S. 39
questions and making his determination thereof conclusive are of
frequent occurrence. Such provisions are inserted largely for the
protection of the Government, and the cases in which such a
determination by the designated official has been upheld by the
courts have been largely cases in which the rule has been invoked
in favor of the United States and against the [contractor],
but
the rule is nonetheless effective if perchance it occasionally may
operate the other way."
Id. at 638 (emphasis added).
In
Penn Bridge Co. v. United States, 59 Ct.Cl. 892
(1924), the disputes decision was in favor of the contractor, but
the Comptroller General disagreed with the decision and deducted
the amount from other sums due the contractor. The Court, referring
to the Comptroller's attempt to
"substitute his judgment for that of the contracting officer,
and thereby eliminate from the case the finding of the contracting
officer when the rights of the parties are in this court for
adjudication,"
id. at 898, stated that "action by the comptroller
could [not] in any way conclude this court in the determination of
the rights of the parties under the contract,"
id. at 896.
The court then applied the
Kihlberg rule.
Id. at
897.
Penn Bridge, then, aside from reaffirming that the same
rule of judicial review applied whether the Government or the
contractor challenged the finality of a disputes decision, also
demonstrates that GAO's view of the correctness of a disputes
decision was of no effect in court. GAO's only power -- the power
of the purse -- was to force the contractor to bring suit, and thus
to obtain judicial review for the Government. But once the case
reached court, review was the same for both parties.
GAO's opinion of a disputes decision was irrelevant in court
even when GAO favored the contractor. In
Page 406 U. S. 40
Eaton, Brown & Simpson, Inc. v. United States, 62
Ct.Cl. 668 (1926), the disputes decision was in favor of the
Government, but the Comptroller General disagreed, and paid the
contractor. I n the contractor's suit to recover on other claims,
the court held that the disputes decision controlled, and deducted
the amount GAO had paid from other sums due the contractor. "The
action of the comptroller is not conclusive upon this court in
determining the rights of the parties.
See Penn Bridge Co. v.
United States."
Id. at 685.
In
Carroll v. United States, 76 Ct.Cl. 103 (1932), the
Comptroller General disagreed with a disputes decision in favor of
the contractor, and assessed damages in a sum greater than the
amount due under the contract. The contractor brought suit, and the
Government argued that it was entitled to the excess. The court
replied:
"The issue is not a new or novel one insofar as judicial
precedents are concerned. At least beginning with the case of
Kihlberg v. United States to the present time, the Supreme
Court has uniformly held that, in Government contracts containing
provisions similar to the one in suit, the parties are competent to
bind themselves to the conclusiveness and finality of the action
and findings of the department with which the contract is made, and
that such action is not open to the supervisory power of the courts
unless overturned by proof of fraud or such gross error as to
warrant the implication of fraud."
Id. at 124-125.
In
Albina Marine Iron Works v. United States, 79 Ct.Cl.
714 (1934), the disputes decision was in the contractor's favor,
but the Comptroller General disagreed, and assessed damages. The
court held that the disputes decision
"was a final disposition of the matter. Neither
Page 406 U. S. 41
fraud nor bad faith is alleged or proven. The court cannot go
behind the decision of the contracting officer where the contract
makes him the final arbiter of the facts of the case unless there
has been fraud or such gross error which, in effect, would imply
bad faith. The cases in this court and the Supreme Court so holding
are numerous."
Id. at 720. After repeating that it could not review
the disputes decision "without the establishment of fraud or such
gross error which would imply bad faith," the court concluded:
"It is seldom that a case arises like the instant case, where
the contractor is upholding the decision of the contracting officer
and the Government is attempting to overthrow the decision of the
officer appointed and designated by it to contract and carry out
the terms of the undertaking. Unless proven to the contrary, full
faith and credit should be accorded an officer of the Government in
arriving at a decision which requires fair and impartial action on
his part."
Id. at 721.
In
McShain Co. v. United States, 83 Ct.Cl. 405 (1936),
the designated Government official decided that the contractor's
delay in completing the contract was unavoidable. The Comptroller
General later decided that part of the delay was the contractor's
fault, and deducted damages from the amount due under the contract.
The contractor brought suit, relying upon the finality of the
disputes decision. The court said:
"Neither fraud nor bad faith is alleged or proven. This court
and the Supreme Court, by numerous decisions, have held there is no
going behind the decision of the contracting officer when the
contract provides that 'his finding of facts therein shall be final
and conclusive on the parties thereto.' The action of the
Comptroller General was without
Page 406 U. S. 42
legal authority.
Kihlberg v. United States; United States v.
Gleason."
Id. at 409. [
Footnote
2/7]
In
B-W Construction Co. v. United States, 97 Ct.Cl. 92
(1942), the Comptroller General deducted damages for delay after a
disputes decision in the contractor's favor. The court held that,
because of the disputes clause,
"[i]t is . . . the action of the head of the department that is
before us for review. On the question now before us, that action is
binding on us unless we find that it was arbitrary or grossly
erroneous. In no event are we bound under this contract by the
action of the Comptroller General."
Id. at 123.
In
Mitchell Canneries v. United States, 111 Ct.Cl. 228,
77 F. Supp. 498 (1948), the Comptroller General disagreed with a
disputes decision in favor of the contractor and set off that
amount against other sums due the contractor on other contracts.
The court applied
"[t]he established principle of law that the findings of fact of
a contracting officer are binding upon both the Government and the
contractor if there is no fraud, gross error or arbitrariness by
the contracting officer amounting to bad faith."
Id. at 247, 77 F. Supp. at 502.
These Court of Claims cases are further cogent authority that
the Government was, until today, entitled to exactly the same
judicial review as contractors. A disputes clause providing for a
final decision by a Government
Page 406 U. S. 43
official was equally binding upon both parties. GAO's opinion of
that decision was irrelevant in court. GAO's only power was to
refuse to sanction payment under a disputes decision favorable to a
contractor, and thereby compel the contractor to bring suit. Once
in court, the standard of review applicable to contractor
challenges likewise controlled the Government's challenge.
The district courts reached the identical result. In
James
Graham Mfg. Co. v. United States, 91 F.
Supp. 715 (ND Cal.1950), the Comptroller General refused to
accept a disputes decision in favor of the contractor. Although the
agency adhered to the merits of its decision, it refused to pay
because of the Comptroller's contrary view. The court said:
"Another officer of the United States government, the
Comptroller General, who has general control of the government's
purse strings, has refused to sanction payment of the account which
the Navy Department has approved. The question . . . is: has he
power to determine that payment shall not be made?"
"The powers of the Comptroller General are extensive and broad.
But he does not, absent fraud or overreaching, have authority to
determine the propriety of contract payments when the contracts
themselves vest the final power of determination in the contracting
executive department.
United States v. Mason & Hanger Co.;
United States v. Moorman."
Id. at 716. [
Footnote
2/8]
Page 406 U. S. 44
In
Consolidated Vultee Aircraft Corp. v. United
States, 97 F. Supp.
948 (Del.1951), the contractor received an adverse disputes
decision from the contracting officer, but won reversal on appeal
to the agency. GAO disagreed with the agency's decision, and
refused to pay, forcing the contractor to bring suit. The court
held for the contractor on the authority of
Mason & Hanger,
Penn Bridge, and
James Graham. Id. at
951.
C
The law was thus crystal clear. The district courts, the Court
of Claims, and this Court consistently applied the rule, originally
announced almost a century ago in
Kihlberg, that
contractual clauses providing for the finality of disputes
decisions rendered by an employee of one of the parties were
enforceable in court, with the judicially created exception for
fraudulent decisions. No court, nor even any contractor, ever
questioned that GAO could obtain judicial review for the Government
simply by refusing to approve payment on a disputes
Page 406 U. S. 45
decision favorable to a contractor. It was accepted by all that
the Government and the contractor both were entitled to judicial
review. [
Footnote 2/9] The problem
that gave rise to the Wunderlich Act was not
who was
entitled to judicial review, nor
how judicial review was
to be attained. The problem was the scope of judicial review.
As the Court noted in
United States v. Bianchi &
Co., 373 U. S. 709,
373 U. S. 713
(1963), under the
Kihlberg rule, a court's function "in
matters governed by
disputes' clauses was, in effect, to give
an extremely limited review of the administrative decision"; the
Court of Claims, however, had "somewhat expanded" the scope of
judicial review "over the years." See, e.g., Needles v. United
States, 101 Ct.Cl. 535, 601-607 (1944). It was this expansion
of the scope of judicial review that Wunderlich
addressed.
Certiorari was granted in
Wunderlich "to clarify the
rule of this Court which created an exception to the conclusiveness
of such administrative decision[s]." 342 U.S. at
342 U. S. 99.
The Court gave a restrictive interpretation to this exception.
"Despite the fact that other words such as 'negligence,'
'incompetence,' 'capriciousness,' and 'arbitrary'
Page 406 U. S. 46
have been used in the course of the opinions, this Court has
consistently upheld the finality of the department head's decision
unless it was founded on fraud, alleged and proved. So fraud is, in
essence, the exception. By fraud, we mean conscious wrongdoing, an
intention to cheat or be dishonest. The decision of the department
head, absent fraudulent conduct, must stand under the plain meaning
of the contract."
Id. at
342 U. S.
100.
Within a month after
Wunderlich was decided, its
restrictive scope of judicial review was applied against the
Government. In
Leeds & Northrup Co. v. United
States, 101 F.
Supp. 999, (ED Pa.1951), the contractor, after a favorable
disputes decision, was reimbursed for certain costs. Several years
later, GAO reviewed that decision, disagreed with it, and set off
the amount already paid from sums due the contractor on another
contract. The contractor was therefore compelled to bring suit. The
court first pointed out that GAO's power
"is subject to the rights of parties to a contract, including
the Government, to provide for some designated person or persons,
even if in the employ of one of the parties, to make a final
determination of any question which may arise between them. This
principle has been unequivocally declared by the courts, including
the Supreme Court of the United States in many cases."
Id. at 1002. After quoting extensively from James
Graham, the court stated the rule of judicial review as
follows:
"The Bureau' determinations of questions of fact under [the
disputes clause] are final and conclusive in the absence of fraud.
United States v. Wunderlich. For a court to set aside such
determinations under [the disputes clause], fraud, meaning
conscious wrongdoing or an intention to cheat or be
Page 406 U. S. 47
dishonest, must be alleged and proved.
United States v.
Wunderlich."
Id. at 1003.
See also Sunroc Refrigeration Co. v.
United States, 104 F.
Supp. 131 (ED Pa.1952), which, following
Leeds &
Northrup, also applied the
Wunderlich scope of review
against the Government.
II
The
Wunderlich opinion concluded, "If the standard of
fraud that we adhere to is too limited, that is a matter for
Congress." 342 U.S. at
342 U. S. 100.
Almost immediately after the decision was issued, congressional
legislation was sought to expand the scope of judicial review
limited by
Wunderlich to "fraud" in a narrow sense. I have
attached an Appendix detailing the legislative history, and shall
only summarize that history here.
Although several bills were introduced in the 82d Congress,
congressional attention focused upon S. 2487. In its original form,
S. 2487 provided:
"That no provision of any [Government] contract . . . relating
to the finality or conclusiveness of any decision of the Government
[official], in a dispute involving a question of fact arising under
such contract, shall be construed to limit judicial review of any
such decision only to cases in which fraud by such Government
[official] is alleged."
Wunderlich, of course, construed the standard disputes
clause, which purported to make disputes decisions final, to limit
judicial review to instances of fraudulent decisions. S. 2487,
then, was simply an acceptance of the invitation extended in
Wunderlich itself. S. 2487, however, did not specify what
the scope of judicial review would be, but merely directed that
judicial review could not be limited to fraud. Moreover, there was
no indication in the language of S. 2487 that it was overruling
Page 406 U. S. 148
Wunderlich only as to disputes decisions unfavorable to
contractors. It obviously applied to the judicial review of
"
any such decision." (Emphasis added.)
The Comptroller General's initial report of GAO's views on S.
2487 made that abundantly clear. The report criticized
Wunderlich as contrary to the interests of both the
Government and contractors. Indeed, as a representative of the
Government, the Comptroller General stressed
Wunderlich's
undesirable impact upon the Government's interest, for
administrative "officials can make just as arbitrary determinations
in favor of contractors, at the expense of the taxpayers."
[
Footnote 2/10] And, as the
Assistant Comptroller General put it in his testimony at the Senate
hearings,
Wunderlich "means that the decision of the
administrative officials nearly always will be final because of the
extreme difficulty of proving fraud." [
Footnote 2/11] Because the restricted scope of judicial
review prescribed in
Wunderlich applied to the Government
no less than to contractors, GAO had good reason for its concern.
[
Footnote 2/12]
GAO then offered a substitute bill that it believed would
protect the Government's interests. The bill provided that a
disputes clause decision
"shall not be treated as binding if the General Accounting
Office or a court finds that the action of [the Government
official] is fraudulent, arbitrary,
Page 406 U. S. 49
capricious, grossly erroneous, or that it is not supported by
substantial evidence."
GAO's substitute bill thus differed from S. 2487 in two
respects.
First, rather than merely reversing
Wunderlich, it explicitly defined the expanded scope of
review by specifying five grounds upon which a disputes decision
could be set aside. Clearly this expanded review was to operate for
both contractors and the Government, just as the "fraud" standard
of review always had. It would be absurd to suppose that GAO
defined the expanded scope of review only for contractors.
Second, GAO's substitute bill authorized GAO review in
addition to judicial review. More precisely, it empowered GAO as
well as the courts to set aside any disputes decision, whether
favorable to the contractor or favorable to the Government. That
was a significant expansion of S. 2487. GAO never previously was
empowered to upset a disputes decision. Rather, GAO authority was
always limited to refusing to sanction payment on a decision
favorable to a contractor, thereby forcing him into court. At that
point, of course, GAO's view of the merits of the disputes decision
was irrelevant. Consequently, GAO's substitute bill, if enacted,
would have increased GAO's power enormously, for it effectively
authorized GAO to oust the courts of all jurisdiction to review
disputes decisions that GAO considered unacceptable. Not
surprisingly, this part of GAO's proposal became highly
controversial.
Extended hearings on S. 2487 were held in the Senate. Although
most of the witnesses and statements concerned themselves solely
with urging expanded judicial review for contractors, without
adverting to such review for the Government, there were notable
exceptions. The Associated General Contractors took the position
that judicial review must be available to both parties, as did
Page 406 U. S. 50
several attorneys who specialized in the representation of
contractors. [
Footnote 2/13]
Opponents of that view proposed bills that would have expressly
limited he right of judicial review to contractors. [
Footnote 2/14] The Comptroller General
subsequently submitted another report objecting to these bills
because their adoption would deprive the Government of the defense
of administrative finality while permitting contractors "to utilize
such defense should the accounting officers of the Government
attempt to question the validity of a payment." [
Footnote 2/15] It is significant that no one ever
suggested during the Senate hearings that the expanded scope of
review provided in S. 2487 and GAO's substitute bill was to be
available only for contractors, and not also for the
Government.
An amended S. 2487 was reported out of Committee following the
hearings. [
Footnote 2/16] It
provided that no disputes clause
"shall be pleaded as limiting judicial review of any [disputes]
decision to cases in which fraud by [the Government] official . . .
is alleged."
Thus, amended S. 2487, like the bill in its original form,
contained an explicit reversal of the
Wunderlich standard
of judicial review. Like the original bill, moreover, amended S.
2487 gave not the slightest indication that it was a command solely
to the Government not to "plead" the disputes clause as limiting
the contractor's right to judicial review. Amended S. 2487 plainly
directed
Page 406 U. S. 51
that no disputes clause could be pleaded to limit judicial
review of
any disputes decisions. Neither party, under
amended S. 2487, could rely upon a disputes clause to limit the
other party's right to judicial review to instances of fraudulent
disputes decisions.
Amended S. 2487, however, went beyond the original bill by
incorporating GAO's substitute bill:
"[A]nd any such provision shall be void with respect to any such
decision which the General Accounting Office or a court, having
jurisdiction, finds fraudulent, grossly erroneous, so mistaken as
necessarily to imply bad faith, or not supported by reliable,
probative, and substantial evidence."
Thus, amended S. 2487 reversed
Wunderlich, adopted
GAO's definition of the expanded scope of review, and authorized
GAO as well as the courts to apply that expanded review and set
aside
any disputes decisions.
The Committee Report on amended S. 2487 expressly noted
"that to the same extent [the
Wunderlich] decision
would operate to the disadvantage of an aggrieved contractor, it
would also operate to the disadvantage of the Government in those
cases, as sometimes happens, when the contracting officer makes a
decision detrimental to the Government interest in the claim.
[
Footnote 2/17]"
The reversal of
Wunderlich, then, was clearly seen as
an expansion of judicial review that would apply no matter which
party, the Government or the contractor, challenged the disputes
decision.
The report then explained that the addition of GAO's proposal
meant that amended S. 2487 would
"have the effect of permitting review in the General Accounting
Office or a court with respect to any decision of a contracting
officer or a head of an agency which is found to be fraudulent,
grossly erroneous,
Page 406 U. S. 52
so mistaken as necessarily to imply bad faith, or not supported
by reliable, probative, and substantial evidence. In other words,
in those instances where a contracting officer has made a mistaken
decision, either wittingly or unwittingly, it will not be necessary
for the aggrieved party to, in effect, charge him with being a
fraud or a cheat in order to affect [
sic] collection of
what is rightfully due. [
Footnote
2/18]"
Thus, the expanded scope of review, explicitly defined, would be
available to both parties before either GAO or a court. In short,
amended S. 2487 empowered a court to set aside a disputes decision
at the behest of either the Government or the contractor, and,
likewise, it empowered GAO to set aside a decision challenged by
either party. Although the report asserted that amended S. 2487 was
intended "simply to recognize the jurisdiction which the General
Accounting Office already has," [
Footnote 2/19] in fact, amended S. 2487 would have
given GAO the entirely new power to make a binding review of
disputes decisions. It would have made GAO, as was later charged,
into a second court of claims.
Although the Senate passed amended S. 2487, the 82d Congress
expired without House action. When it was reintroduced in the
Senate of the 83d Congress, [
Footnote
2/20] Senator McCarran, the bill's sponsor, observed that the
Wunderlich decision "cuts two ways," and, as an example,
cited a case I have already discussed,
Leeds & Northrup Co.
v. United States, 101 F.
Supp. 999 (ED Pa.1951), in which
"[t]he Comptroller General . . . attempted to recover on behalf
of the Government, because the mistake was against the Government.
The contractor interposed a
Page 406 U. S. 53
defense based on . . . the
Wunderlich case. . . . [T]he
result was a failure of recovery on behalf of the Government.
[
Footnote 2/21]"
Thus, Senator McCarran, like GAO, recognized that the narrow
review permissible under
Wunderlich bound both the
Government and the contractor, and, like GAO, he considered that
reversal of
Wunderlich would also apply equally to both
parties. A month later, during floor debate, Senator McCarran again
emphasized that, while
Wunderlich could "operate greatly
to the disadvantage of contractors," it could also "operate to the
disadvantage of the Government." [
Footnote 2/22] The Senate then passed the bill,
obviously with the understanding that the expanded scope of
judicial review provided would be available to both the Government
and contractors.
Amended S. 2487 was also introduced in the House of the 83d
Congress. [
Footnote 2/23] At the
initial House hearing in July, 1953, several witnesses asserted
that enactment of the bill was essential to enable both the
Government and contractors to obtain effective judicial review of
disputes decisions. [
Footnote
2/24] Opposition then developed to the provision empowering GAO
to invalidate such decisions. The objection was, quite predictably,
that
"[t]he effect of the provision is to set up the General
Accounting Office as a 'court of claims.' . . . [A]n agency of the
legislative branch . . . should not be used to perform functions
intended for the judicial branch. [
Footnote 2/25]"
Understanding the precise nature of this objection is important.
No one suggested that amended S. 2487
Page 406 U. S. 54
did not grant the Government the same scope of judicial review
that it granted contractors. Obviously, since amended S. 2487
authorized both GAO and the courts to exercise the same review, and
since the objection was that GAO should not be able to set aside
disputes decisions favorable to contractors, it would have been
absurd to suggest that amended S. 2487 did not likewise authorize
the courts to set aside such decisions. Nor did anyone question the
ability of GAO to obtain judicial review for the Government through
its power to refuse to approve payment on disputes decisions. All
agreed that the purpose of the proposed legislation was to overturn
the standard of review set by
Wunderlich; the narrow scope
of judicial review permissible under that case was to be done away
with in favor of a broader, specifically defined review. The
purpose was to expand judicial review, not to insert further
administrative review into the disputes process. Thus, the
opposition urged, not unreasonably, that the avowed purpose of
overruling
Wunderlich would not be served by expanding
GAO's power to transform it into another court. Hence, deletion of
GAO from amended S. 2487 would leave the power of binding review
exclusively with the courts.
The Comptroller General bowed to this opposition. Stating
(erroneously, I think) that GAO "has not asked for authority which
it did not have before the decision in the
Wunderlich
case," he offered another substitute bill deleting the
objectionable provision. He asserted that
"this substitute language will accomplish what we have been
striving for all along, and will place the General Accounting
Office in precisely the same situation it was in before"
Wunderlich. [
Footnote
2/26] This bill, in the form submitted by GAO with one minor
addition, was enacted as the Wunderlich Act.
Page 406 U. S. 55
Thus, the result of GAO's attempt to obtain the power of binding
review over disputes decisions was failure. That power was left
where it was before the Act, solely with the courts. GAO simply
retained the power it had always had, the power to force the
contractor into court where the Government would get judicial
review of the disputes decision in his favor.
The hearings resumed in January, 1954. In urging passage of
GAO's revised substitute bill, GAO's General Counsel stated that,
despite deletion of the provision for binding GAO review, the bill
would not only protect contractors, but would also protect the
Government
"against decisions adverse to the interests of the United
States. Certainly the rights of contract[ors] and the Government to
review or appeal should be coextensive. [
Footnote 2/27]"
Similarly, the Associate General Counsel of the General Services
Administration asserted that GAO's revised substitute bill was
adequate to "insure an opportunity to protect the Government
against excessive generosity," since GAO, under the bill,
"could seek a court review by a setoff or by applying to the
Department of Justice for recovery in a case where they felt that
the action of the contracting officer was grossly erroneous as
against the Government. [
Footnote
2/28]"
Many witnesses who opposed GAO's original substitute bill, and
thus opposed amended S. 2487, now supported GAO's revised
substitute bill because it made clear that the power to set aside
disputes decisions was vested exclusively in the courts, and not
shared by the courts with GAO. There was no suggestion from anyone
that deletion of GAO from amended S. 2487 also had the effect of
precluding the Government from obtaining judicial review under the
standards available to contractors. Any
Page 406 U. S. 56
such suggestion would have been absurd, for, as noted above,
amended S. 2487 granted the courts and GAO exactly the same power.
In fact, at one point in the hearings, a witness objected that
GAO's revised substitute bill did "not say specifically that an
appeal can be taken by an aggrieved contractor." The ensuing
colloquy with Committee members made plain that the language of the
bill "necessarily include[d] both parties." [
Footnote 2/29] Moreover, as in the case of the Senate
Committee, the House Committee was presented with a proposed bill
that would have expressly limited the right of judicial review to
contractors. [
Footnote 2/30] As
with the Senate, that suggestion was not adopted. Instead, the
Committee reported out the bill, submitted by GAO, that is now the
Wunderlich Act. The Act expanded the scope of judicial review, and
that was all it did. The Committee report made that plain.
"The committee foresees no possibility of the proposed
legislation creating any new rights that a contractor may not have
had prior to its enactment, with the exception of the standards of
review therein prescribed. [
Footnote
2/31]"
Nor did the Act grant GAO new power, for, as the report said,
"there is no intention of setting up the General Accounting Office
as a
court of claims.'" On the other hand, the Act did not
diminish GAO's existing authority to hold up payment and force the
contractor to bring suit, as the report also stressed.
"The elimination of the specific mention of the General
Accounting Office from the provisions of the bill as amended should
not be construed as taking away any of the jurisdiction of that
Office. [
Footnote 2/32]"
Thus, GAO authority was left exactly where it was.
Page 406 U. S. 57
A point I have already made about deletion of the reference to
GAO bears repeating. Amended S. 2487, by incorporating GAO's
original substitute bill, granted GAO precisely the same binding
power of review that it granted the courts. Contractors did not
object to that provision because it authorized GAO to set aside
disputes decisions unfavorable to contractors. They objected
because amended S. 2487 authorized GAO to set aside disputes
decisions favorable to contractors. That power, opponents of
amended S. 2487 urged, must be vested solely in the courts. They
prevailed, and the reference to GAO was deleted. Deletion of the
authority granted to GAO obviously could have no effect whatever on
the identical authority granted to the courts. [
Footnote 2/33]
The Senate originally passed amended S. 2487 upon the clear
understanding that the expanded scope of judicial review it
contained would be available to both the
Page 406 U. S. 58
Government and contractors. When the House bill came to the
Senate after deletion of the GAO provision, Senator McCarran, who
had previously stressed that
Wunderlich hurt both the
Government and contractors, explained that, while the House bill
differed from the bill passed by the Senate, since it deleted the
authority to GAO, it was "designed to accomplish the same purpose."
[
Footnote 2/34] That purpose, of
course, was to overturn
Wunderlich and to provide the
courts with grounds of review in addition to fraud. The two bills
could not, of course, "accomplish the same purpose" if the House
bill authorized expanded judicial review only for contractors,
leaving the Government either with the
Wunderlich standard
or with no review at all. After Senator McCarran responded
affirmatively to the statement that the difference was only "a
modification of the language in the Senate bill, and the two bills
agree in their effect," [
Footnote
2/35] the Senate passed the House bill.
The text of the Act is its own witness to the congressional
purpose. It provides that no clause in a Government contract
purporting to make final an administrative determination of a
dispute arising under the contract "shall be pleaded in any suit .
. . as limiting judicial review." The proviso then defines the
applicable scope of review.
It is impossible to read the plain words of this statute as
directing that judicial review is available only for disputes
decisions unfavorable to contractors. Indeed, the language is so
clear that there should be no need to search through the
legislative history for a contrary meaning. [
Footnote 2/36] That history, in any event, demonstrates
that the Act means exactly what it says.
Page 406 U. S. 59
Two significant considerations buttress my conclusion that the
Court's construction of the Act is patently and grievously
erroneous.
First. The bill that became the Wunderlich Act was a
Government bill. As the Committee report said, the Act,
with a minor exception, "is exactly the same legislation suggested
by the Comptroller General." [
Footnote 2/37] GAO offered it as a substitute for the
original S. 2487 because of
Government concern that
administrative "officials can make just as arbitrary determinations
in favor of contractors, at the expense of the taxpayers."
[
Footnote 2/38] The bill
explicitly stated that the expanded scope of review would add to
"fraudulent" the grounds that the disputes decision was
"arbitrary," "capricious," "grossly erroneous," or "not supported
by substantial evidence." After GAO modified the bill to delete the
provision authorizing GAO review, in addition to court review, on
those grounds,
Government procurement agencies joined
forces with GAO in strong support of passage. It is absurd to
suppose that the
Government pressed for a bill that
granted contractors an expanded scope of judicial review, inserted
in the bill by the
Government, yet denied the Government
judicial review on those same grounds.
Second. That absurdity is compounded by the
consequences that result from interpreting the Act to deny
Page 406 U. S. 60
the Government judicial review of disputes decisions. Before
Wunderlich, the Government could challenge the finality of
those decisions at least on the ground of fraud. If the Act affords
only contractors judicial review, and denies review to the
Government, it follows that the Government has been deprived even
of the right it had under
Wunderlich to challenge
"fraudulent" disputes decisions. The principal Government
procurement agencies, now including the Atomic Energy Commission,
have created contract appeals boards as the final level of agency
review of disputes decisions. Because the Act expressly provides
for judicial review of such "board" decisions, interpreting it to
deny the Government review means that, however "fraudulent,"
however "arbitrary," however "capricious," however "grossly
erroneous," however clearly "not supported by substantial evidence"
the board's determination, the procurement agency and the
Government itself are helpless to redress the wrong. In this case,
that might mean the loss of more than one million dollars to
American taxpayers. But at stake are countless millions. To say
that Government wrote and secured passage of a bill to work that
result is preposterous. [
Footnote
2/39]
III
So far as I can penetrate the Court's opinion, its primary
premise is exposed by such sentences as these:
"The purpose of avoiding 'vexatious litigation' would
Page 406 U. S. 61
not be served, however, by substituting the action of officials
acting in derogation of the contract."
Ante at
406 U. S. 8.
[
Footnote 2/40]
"Neither the Wunderlich Act nor the disputes clause empowers any
other administrative agency to have a veto of AEC's 'final'
decision or authority to review it."
Id. at
406 U. S. 9.
"In other words, we cannot infer that, by some legerdemain, the
disputes clause submitted the dispute to further administrative
challenge or approval. . . ."
Ibid. "Here, the AEC spoke for the United States and
its decision, absent fraud or bad faith, should be honored."
Id. at
406 U. S. 10.
[
Footnote 2/41]
"Since the AEC withheld payment solely because of the views of
the Comptroller General, and since he had been given no authority
to function as another tier of administrative review, there was no
valid reason for AEC not to settle with petitioner according to its
earlier decision."
Ibid. [
Footnote 2/42]
"That action by the
Page 406 U. S. 62
Comptroller General was a form of additional administrative
oversight foreclosed by the disputes clause."
Id. at
406 U. S. 12.
"[The Act] should not be construed to require a citizen to
perform the Herculean task of beheading the Hydra in order to
obtain justice from his Government."
Id. at
406 U. S. 14.
"We are reluctant to construe a statute enacted to free citizens
from a form of administrative tyranny so as to subject them to
additional bureaucratic oversight, where there is no evidence of
fraud or overreaching."
Id. at
406 U. S. 14.
[
Footnote 2/43]
"This objective [preventing the inflating of bids] would be
ill-served if Government contractors -- having won a favorable
decision before the agencies with whom they contracted -- had also
to run the gauntlet of the General Accounting Office and the
Department of Justice."
Id. at
406 U. S.
14-15.
The Court's
bete noire, then, is primarily the General
Accounting Office, with a sideswipe at the Department of Justice.
We are left to infer, I gather, that Congress shared the Court's
distaste for the activities of those agencies in these cases, and
enacted the Wunderlich Act not only to arm contractors with
expanded grounds of judicial review of disputes decisions favorable
to the Government, but also, by the device of denying judicial
review to the Government, to abolish the authority of GAO to
disapprove payments to contractors under disputes decisions, thus
forcing contractors to sue, and, by that device, to relieve the
Department of Justice of any suits
Page 406 U. S. 63
to defend on behalf of the United States. There are three
dispositive answers to the Court's supposition.
First. The notion that Congress enacted the Wunderlich
Act to abolish the authority of GAO and the Department of Justice
is completely a figment of the Court's own imagination. As the
judicial history shows, both agencies have exercised for decades
powers identical to those exercised in this case, with no prior
complaints that I can discover and with complete congressional
approval. I need only quote from the Committee report that
accompanied the bill that is now the Wunderlich Act.
"The proposed legislation, as amended, will not add to, narrow,
restrict, or change in any way the present jurisdiction of the
General Accounting Office either in the course of a settlement or
upon audit, and the language used is not intended either to change
the jurisdiction of the General Accounting Office or to grant any
new jurisdiction, but simply to recognize the jurisdiction which
the General Accounting Office already has."
"The elimination of the specific mention of the General
Accounting Office from the provisions of the bill as amended should
not be construed as taking away any of the jurisdiction of that
Office.
It is intended that the General Accounting Office, as
was its practice, in reviewing a contract and change orders for the
purpose of payment, shall apply the standards of review that are
granted to the courts under this bill. At the same time, there is
no intention of setting up the General Accounting Office as a
'court of claims.' Nor should the elimination of the specific
mention of the General Accounting Office in the bill be construed
as limiting its review to the fraudulent intent standard prescribed
by the
Wunderlich decision. "
Page 406 U. S. 64
The specific intent of this legislation, insofar as it
affects the General Accounting Office, is explicitly stated in the
letter . . . from the Comptroller General himself. . . .
The report then quoted from the Comptroller General's letter, in
which he said that GAO "has not asked for authority which it did
not have before the decision in the
Wunderlich case," and
in which he quoted from the Senate Committee's report on amended S.
2487:
"[I]t is not intended to narrow or restrict or change in any way
the present jurisdiction of the General Accounting Office, either
in the course of a settlement or upon audit; [it] is not intended
either to change the jurisdiction of the General Accounting Office
or to grant any new jurisdiction, but simply to recognize the
jurisdiction which the General Accounting Office already has.
[
Footnote 2/44]"
Second. The case law detailed earlier in this opinion,
including
Eaton, Brown & Simpson, Inc. v. United
States, 62 Ct.Cl. 668 (1926), in which GAO disagreed with a
disputes decision in favor of the Government and paid the
contractor, establishes without question that GAO has no power to
overturn a disputes decision. The limit of its authority is to
refuse to sanction payment to the contractor, and thus force him to
bring suit. The judicial precedents in this Court, the Court of
Claims, and the district
Page 406 U. S. 65
courts are explicit that only a court can determine the merits
of the dispute within the grounds of review specified by the
Wunderlich Act. It is therefore completely irrelevant that "the AEC
withheld payment sorely because of the views of the Comptroller
General."
Ante at
406 U. S. 10. Indeed, the Court exposes the fallacy of
its own position when it states that
"the disputes clause in the contract says that the decision of
the AEC is 'final and conclusive' unless a
court
determines that the award is vulnerable under §§ 1 and 2
of the Act."
Id. at
406 U. S. 3
(emphasis added).
See also id. at
406 U. S. 3-4:
"By the disputes clause, the decision of AEC is 'final and
conclusive' unless 'a
court of competent jurisdiction'
decides otherwise for the enumerated reasons."
(Emphasis added.)
Third. Similarly, the Court states, in response to the
Government's nonexistent contention that the Department of Justice
has "the power to overturn decisions of coordinate offices of the
Executive Department,"
id. at
406 U. S. 12,
"That power [of the Department of Justice to defend suits
against the United States] is pervasive but it does not appear how,
under the Wunderlich Act, it gives the Department of Justice the
right to appeal from a decision of the Atomic Energy
Commission,"
id. at
406 U. S. 12-13
(emphasis added).
See also id. at
406 U. S. 13:
"The
power to appeal to the Court of Claims a decision
of the federal agency under a disputes clause in a contract which
the agency is authorized to make is not to be found in the
Wunderlich Act and its underlying legislative history."
(Emphasis added.) No one suggests that the Department of Justice
has a "right to appeal." It is involved in this case only because
GAO's refusal to sanction payment forced petitioner to sue the
United States, thus creating a lawsuit that the Department of
Justice, as the Government's lawyer, had a duty to defend. It would
be strange if the Department had a duty to confess judgment.
In support of its construction of the Act, the Court
Page 406 U. S. 66
makes a statement, which I have already quoted, that invites a
further comment:
"[J]udicial review was provided so that contractors would not
inflate their bids to take into account the uncertainties of
administrative action. This objective would be ill-served if
Government contractors -- having won a favorable decision before
the agencies with whom they contracted -- had also to run the
gauntlet of the General Accounting Office and the Department of
Justice."
Id. at
406 U. S.
14-15.
Contractor witnesses at the committee hearings asserted that
contractors would have to inflate their bids if they could attack a
disputes decision only on the ground that it was fraudulent. As the
Court says, the Act resolved this problem by expanding the scope of
judicial review, so that contractors can attack a disputes decision
on grounds in addition to fraud.
That was the protection
Congress gave contractors so that they would not have to inflate
their bids.
After recognizing this, the Court says that, because contractors
got expanded judicial review to prevent the necessity of inflating
bids, they
also got the benefit of not having decisions in
their favor subject to judicial review
at all, since
otherwise the objective of preventing inflated bids "would be
ill-served." It would be difficult to imagine a more obvious
non sequitur. The Court could as easily say that "[t]his
objective would be ill-served" if the contractors ever lost a
disputes decision.
I might add that the Court does not say that the "objective
would be ill-served" if favorable contractor decisions were subject
to
judicial review; it says that the "objective would be
ill-served" if contractors "had also to run the gauntlet of the
General Accounting Office and the Department of Justice." Yet what
the Court means, of course, is judicial review, for neither GAO
nor
Page 406 U. S. 67
the Department of Justice can take a favorable decision away
from a contractor. Only a
court can do that.
The Court is forced to go to extreme lengths to assert that the
Government still may have relief for fraud. That is because the
Court concedes, as it must, that its construction of the Act
denying the Government judicial review forecloses review of
disputes decisions that are "fraudulent," just as it forecloses
judicial review of decisions that are "arbitrary," "capricious,"
"grossly erroneous," or "not supported by substantial evidence."
The Court's attempted escape is to suggest that the Government may
have relief for fraud under the statutes in which "Congress has
made elaborate provisions for dealing with fraudulent claims of
contractors."
Id. at
406 U. S. 16.
Apart from the absence of any explanation why, if statutory
remedies were always available, this Court found it necessary to
fashion, for Government and contractor alike, a judicial exception
to the finality of disputes decisions, the point is frivolous.
[
Footnote 2/45] Obviously the
fraud statutes the Court mentions have no application whatever to
the fraud we are discussing in this case.
The "fraud" that is an issue in a disputes clause case is not
contractor fraud. Not one case construing a disputes clause, from
1878 to the present day, ever mentions "fraud" by the
contractor. Nor has anyone ever suggested
Page 406 U. S. 68
that the Government needs judicial review of disputes decisions
to guard against fraud by the
contractor. The "fraud" that
is involved is a
fraudulent decision. The disputes clause
and the Act itself provide judicial review to determine whether the
"
decision . . . is fraudulent." (Emphasis added.) When a
disputes decision is challenged, the only questions concern that
decision: was it "fraudulent"? was it "capricious"? was it
"arbitrary"? was it "grossly erroneous"? was it "not supported by
substantial evidence"? [
Footnote
2/46] The Court is absolutely right that "[a] contractor's
fraud is, of course, a wholly different genus than the case now
before us."
Id. at
406 U. S. 15.
IV
The time-tested standards of statutory construction require
interpretation of the statutory wording to effect the congressional
purpose as revealed by legislative history. The Court totally
discards those standards in construing the Wunderlich Act. Instead,
the Court purports to discover a nonexistent hostility of Congress
toward the "intermeddling,"
id. at
406 U. S. 19, of
GAO and the Department of Justice in the disputes process, and, for
that reason, a congressional purpose to prevent the subjection of
"citizens . . . to additional bureaucratic oversight,"
id.
at
406 U. S. 14. The
virtually century-long judicial history that forms the background
of the Act, its explicit language, and its clear legislative
history completely refute the proposition. I dissent, and would
affirm the judgment of the Court of Claims.
Page 406 U. S. 69
[
Footnote 2/1]
The concurring opinion seems to read the judicial review
provision out of the disputes clause:
"And if the contractor accept a decision of the contracting
officer, and does not appeal to the Commission, that decision, by
the
specific provisions of the disputes clause, is final
and conclusive as to questions of fact. Under the Government's
position, however, the decision at the agency head would enjoy no
such preferred and conclusive status."
Ante at
406 U. S. 21
(emphasis added). The Commission's disputes decision does not have
"conclusive status" under the disputes clause, of course, because
of a "specific provision" of the clause. That provision directs
that the Commission's decision is "final and conclusive
unless" (emphasis added) a court determines that it was
"fraudulent," etc. It does not direct that the Commission's
decision is final and conclusive unless the
contractor
appeals to the courts. That is the language of the earlier
provision, referred to by the concurring opinion, under which the
contracting officer's decision is final and conclusive unless the
contractor appeals to the Commission. If "the specific
provisions of the disputes clause" apply after the contracting
officer's decision, surely they also apply after the Commission's
decision.
[
Footnote 2/2]
The Court's opening sentence appears to say that we are dealing
with a pre-Wunderlich Act disputes clause that "provides that the
decision of AEC shall be
final and conclusive.'" Ante
406 U. S. The
Court later recognizes the obvious: "By the Disputes Clause, the
decision of AEC is `final and conclusive' unless `a court of
competent jurisdiction' decides otherwise for the enumerated
reasons." Id. at 406 U. S.
9
[
Footnote 2/3]
It was suggested at oral argument that the procurement agency
might pay the contractor in accordance with a disputes decision in
his favor, and that, subsequently, prompted by GAO's post-audit,
the Department of Justice might sue the contractor to recoup the
payment on the ground that the agency's decision was improper under
the disputes clause and the Wunderlich Act. The Court's holding
today, of course, prohibits the Government from obtaining judicial
review of disputes decisions by that method. Indeed, that would be
an
a fortiori case, for the agency not only would have
decided in favor of the contractor, but also would have paid him in
accordance with its decision. If a disputes decision is final when
the agency refuses to implement it by payment, certainly it is
final when the agency pays.
[
Footnote 2/4]
The Court's constant repetition of the phrase "fraud or bad
faith" might suggest to the casual reader that the Court is holding
that the Government may challenge the finality of disputes
decisions on those grounds. That, however, is not true, for fraud
and bad faith are two of the grounds specified in the disputes
clause and the Wunderlich Act: a disputes decision may be set aside
if it is "fraudulent" or if it is "so grossly erroneous as
necessarily to imply bad faith." In contrast to the disputes clause
and the Act, the Court is not referring to disputes decisions
resulting from the fraud or bad faith of the
disputes
decisionmaker. Rather the Court is referring to fraud or bad
faith on the part of the
contractor, as the Court's
statement of facts makes clear: "The defenses tendered raised no
issue of any fraud or bad faith of the contractor against the
United States."
Ante at
406 U. S. 7. "The
Commissioner did not base his opinion on any issue of fraud or bad
faith of the contractor against the United States, nor did the
Court of Claims."
Ibid. See also id. at
406 U. S. 9-10 n.
8 and
406 U. S. The
concurring opinion also refers to "fraud" and "bad faith."
Ante at 19. Again, however, the reference is not to fraud
and bad faith as used in the disputes clause and the Act.
[
Footnote 2/5]
The Court's citation of
Mason & Hanger, ante at
406 U. S. 10, is,
to say the least, perplexing.
[
Footnote 2/6]
Goltra v. Weeks, 271 U. S. 536
(1926), which involved a contractor's challenge to the finality of
a disputes decision by a Government official, also demonstrate that
the rule was the same no matter which party challenged the
decision. The Court there held that the official's decision was
binding "unless there is an absence of good faith in the exercise
of the judgment."
Id. at
271 U. S. 548.
Significantly, the Court cited as authority not only
Kihlberg,
Sweeney, March, and
Gleason, all cases in which the
contractor challenged and the Government (in
March, the
party whose official decided the dispute) relied upon the disputes
decision, but also
Mason & Hanger, in which the
Government challenged the finality of a disputes decision upon
which the contractor relied.
[
Footnote 2/7]
The Court cites
McShain Co. for the proposition that
"[t]he cases deny review" by GAO "absent fraud or overreaching."
Ante at
406 U. S. 10.
Since
McShain Co. is simply another example of the
application of the
Kihlberg rule against the Government, I
am at a loss to understand the Court's statement. As the excerpt I
have quoted in the text demonstrates,
McShain Co. did not
"deny review" by GAO; rather, like the other cases, it held that
GAO's view of the merits of the disputes decision was irrelevant in
court, and that the Government could upset the finality of that
decision only by proving in court that it was fraudulent.
[
Footnote 2/8]
The Court states,
ante at
406 U. S. 11,
that the District Court, in
James Graham, by referring to
"fraud or overreaching," referred to instances "where the
Comptroller General's power was founded upon specific statutory
provisions such as 41 U.S.C. § 53," a statute relating to
"kickbacks by Government contractors,"
id. at
406 U. S. 9 n. 8.
In fact, however, the District Court not only did not refer to that
statute, it did not refer to any statute, nor even intimate that a
statute might be relevant. What the District Court did was use the
phrase "fraud or overreaching" as shorthand for the
Kihlberg rule, the judicially created fraud exception to
the finality of disputes decisions. That usage is readily apparent
from a glance at the District Court's citations:
Mason &
Hanger and
Moorman from this Court, and
Penn
Bridge, Carroll, and
McShain Co. from the Court of
Claims.
The Court also says,
id. at
406 U. S. 11,
that, in
James Graham,
"summary judgment was entered by the court, which said, 'since
the Navy Department has determined that plaintiff contractor is
entitled to the payment sought, this Court must adjudge
accordingly.'"
The Court omits to quote the immediately preceding sentence in
the
James Graham opinion: "And the Navy Department's
decision that these particular dues and contributions are
reimbursable is
not arbitrary or unconscionable." 91 F.
Supp. at 717 (emphasis added). Thus, again, the District Court was
referring to the
disputes decision, and not, as the Court
today would have it, to "fraud or overreaching" by the
contractor.
[
Footnote 2/9]
The concurring opinion asserts that
"[t]he contractor here, according to the long-term understanding
of the disputes clause, consented to the disposition of disputes by
the contracting officer and by the AEC on appeal, and to the
finality of decision at those points."
Ante at
406 U. S. 21. If
the concurring opinion is speaking of pre-Wunderlich Act disputes
clauses, the authorities I have cited establish the utter
inaccuracy of the assertion. Indeed; the concurring opinion also
asserts that,
"for years,
with the specified exception, [the
disputes] clause itself has been regarded as conferring no right of
judicial review on the part of the Government."
Id. at
406 U. S. 20
(emphasis added). The italicized words can only refer to the
judicially created exception for fraudulent decisions. The
concurring opinion gives no indication that, in either of the
assertions, it is referring to the current disputes clause.
[
Footnote 2/10]
Hearings on S. 2487 before a Subcommittee of the Senate
Committee on the Judiciary, 82d Cong., 2d Sess., 6.
[
Footnote 2/11]
Id. at 8
[
Footnote 2/12]
It is misleading to assert, as does the Court, that
Wunderlich "closed the courthouse doors to
certain
citizens."
Ante at
406 U. S. 14
(emphasis added). Similarly, the concurring opinion asserts that
Wunderlich "restricted
contractor-instigated
judicial review," and that the Government "prevailed" in
Wunderlich with "a narrow judicial review standard for the
contractor."
Ante at
406 U. S. 22
(emphasis added). The concurring opinion's assertions are the more
surprising in view of its apparent recognition that the Government
was subject to the same standard of judicial review as contractors.
See 406 U.S.
1fn2/9|>n. 9,
supra.
[
Footnote 2/13]
Hearings on S. 2487,
supra, 406 U.S.
1fn2/10|>n. 10, at 29-32, 68, 83-84, 107, 114.
[
Footnote 2/14]
Id. at 59, 107. Moreover, H; R. 6301, also introduced
in the 82d Congress, provided for judicial review only in those
instances
"in which the contractor shall seek to set aside a decision on a
disputed question between the United States and such contractor,
made by an officer, board, or other representative of the United
States. . . ."
Neither House supported this bill.
[
Footnote 2/15]
Hearings on S. 2487,
supra, 406 U.S.
1fn2/10|>n. 10, at 119.
[
Footnote 2/16]
See S.Rep. No. 1670, 82d Cong., 2d Sess.
[
Footnote 2/17]
Id. at 2.
[
Footnote 2/18]
Ibid.
[
Footnote 2/19]
Id. at 3
[
Footnote 2/20]
Amended S. 2487 was reintroduced as S. 24, but, for ease of
reference, I will continue to refer to it as amended S. 2487.
[
Footnote 2/21]
99 Cong Rec. 4573.
[
Footnote 2/22]
99 Cong.Rec. 6170.
[
Footnote 2/23]
Amended S. 2487 was introduced as H.R. 1839, but, for ease of
reference, I will continue to refer to it as amended S. 2487.
[
Footnote 2/24]
Hearings on H.R. 1839
et al. before Subcommittee No. 1
of the House Committee on the Judiciary, 83d Cong., 1st and 2d
Sess., ser. 12, at 3-20.
[
Footnote 2/25]
Id. at 26.
[
Footnote 2/26]
Id. at 136.
[
Footnote 2/27]
Id. at 39.
[
Footnote 2/28]
Id. at 59
[
Footnote 2/29]
Id. at 110
[
Footnote 2/30]
Id. at 89.
[
Footnote 2/31]
R. Rep. No. 1380, 83d Cong., 2d Sess., 6.
[
Footnote 2/32]
Id. at 7.
[
Footnote 2/33]
The Court's only foray into the legislative history is its
assertion that
"Congress contemplated giving the General Accounting Office such
powers and, indeed, the Senate twice passed -- in the form of the
McCarran bill -- a provision which would have allowed the
Comptroller to review disputes decisions to determine if they"
satisfied the standards of the Act.
Ante at
406 U. S. 11. The
Court therefore concludes that the Act cannot be construed "to give
the Comptroller General powers which Congress has plainly denied."
Id. at
406 U. S. 12.
Similarly, the concurring opinion asserts that
"[t]he flat rejection by Congress of the proposed provision for
GAO review is significant. There would be no point in that
rejection if GAO has the power to defeat the finality of the
disputes decision anyway."
Ante at
406 U. S. 22-23.
Unfortunately, the Court and the concurring opinion overlook that
the proposed provision was not simply "for GAO review." It was for
binding GAO review. Because it was not enacted, GAO does
not "have a veto of AEC's 'final' decision,"
ante
at
406 U. S. 9
(opinion of the Court); GAO does not have "power to defeat the
finality of the disputes decision,"
ante at
406 U. S. 23
(concurring opinion). Both the Act and the disputes clause
specifically provide that only a
court can set aside a
disputes decision. And that is precisely the point the legislative
history makes clear.
[
Footnote 2/34]
100 Cong.Rec. 5717
[
Footnote 2/35]
100 Cong.Rec. 5718.
[
Footnote 2/36]
The need arises in this case only because petitioner argues
that, despite the clear language of the Act, the legislative
history reveals that Congress meant to reserve the right of
judicial review solely to contractors. It is thus somewhat odd that
the Court considers it worthwhile to assert "that the Act's
legislative history
has something for everyone,'" and that the
Court "find[s] the Act's history, at best, ambiguous."
Ante at 406 U. S. 13 n.
9. The concurring opinion likewise professes to find the
legislative history "decidedly ambiguous, at best," ante
at 406 U. S. 22, yet
nevertheless goes on to assert that Congress "intended to
relieve contractors" and "opened the door to the
contractor," ibid. (emphasis added). These
comments are all the more inexplicable because neither the Court
nor the concurring opinion attempts even the most cursory analysis
of the text of the Act itself.
[
Footnote 2/37]
H.R. Rep. No. 1380,
supra, 406 U.S.
1fn2/31|>n. 31, at 6.
[
Footnote 2/38]
See 406 U.S.
1fn2/10|>n. 10,
supra.
[
Footnote 2/39]
The concurring opinion asserts that, "[i]n the exercise of its
legislative judgment, Congress has determined that in this area the
Government," unlike contractors, does not need the Act's protection
"against fraud, capriciousness, arbitrariness, bad faith, and
absence of evidence."
Ante at
406 U. S. 23. As
the concurring opinion never refers to the language of the Act, and
finds the legislative history "not at all that clear," "decidedly
ambiguous, at best,"
id. at
406 U. S. 22, and
"inconclusive,"
id. at
406 U. S. 23, it
is difficult to understand the basis for this statement.
[
Footnote 2/40]
This statement, albeit obscurely, may mean that the purpose of
avoiding litigation would not be served by subjecting a disputes
decision in
favor of the contractor to judicial review,
for that would be litigation. Yet, just as obviously, the purpose
of avoiding litigation would not be served by subjecting a disputes
decision against the contractor to judicial review.
[
Footnote 2/41]
See 406 U.S.
1fn2/4|>n. 4,
supra, 406 U.S.
1fn2/43|>n. 43,
infra.
[
Footnote 2/42]
This is a difficult statement to understand. Assume that the
Commission had "no valid reason" not to pay petitioner. Was the
Commission's nonpayment in violation of the contract? Was it in
violation of the Wunderlich Act? The Court does not say
If nonpayment violated neither the contract nor the Act, it seem
rather strange that this Court should order the Commission to pay.
The Court's statement appears to be connected with its later
statement that "[t]he AEC has not, to this day, repudiated the
merits of its decisions in favor of petitioner."
Ante at
406 U. S. 19.
Again, however, the Court does not say how or even whether the
Commission's "nonrepudiation" violated the contract or the Act.
In the same vein, the concurring opinion asserts that there is
"a possible breach of contract" in this case:
"When the United States then disavows the Commission's decision
-- a decision which, as the Court notes, to this day has never been
withdrawn or repudiated by the AEC -- it seems to me that the
Government imposes something to which the contractor has not
agreed."
Ante at
406 U. S. 21,
406 U. S. 22. The
concurring opinion, however, does not say how the Government's
"disavowal" violated the contract.
[
Footnote 2/43]
If this statement implies that a contractor
is "subject
. . . to additional bureaucratic oversight, where there is . . .
evidence of fraud or overreaching" (emphasis added), one might well
ask why that is so. Fraud is only one of the five grounds of
judicial review specified in the Act and the disputes clause.
Obviously either all or none are available.
See 406 U.S.
1fn2/4|>n. 4,
supra.
[
Footnote 2/44]
H.R.Rep. No. 1380,
supra, 406 U.S.
1fn2/31|>n. 31, at 6-7 (emphasis added). This detailed
refutation that GAO authority was being curtailed was necessary to
allay the fears expressed by the attorney who argued
Wunderlich for the contractor. He testified during the
House hearings that deletion of GAO from amended S. 2487, passed by
the Senate, might be misconstrued as depriving GAO of its prior
authority to refuse tax sanction payment, and thereby "throw the
matter into court."
See Appendix,
infra at 78-80.
Today's decision fulfills his prophecy.
[
Footnote 2/45]
The Court asserts that,
"[i]f the Comptroller General has the broad, roving,
investigatory powers that are asserted, specific statutory grants
of authority such as this provision [41 U.S.C. § 53] relating
to kickbacks would be superfluous."
Ante at
406 U. S. 10 n.
8. The GAO authority asserted here, however, is simply the
authority to refuse to sanction payment under a disputes decision
on the ground that the decision does not satisfy the standards of
the Wunderlich Act. The Act, of course, has nothing whatever to do
with illegal activities of contractors. It concerns only the
finality of administrative
disputes decisions. Enforcement
of the Act obviously would not make the statutory prohibition of
kickbacks "superfluous."
[
Footnote 2/46]
Even my Brother DOUGLAS once recognized this:
"We should allow the Court of Claims, the agency close to these
disputes, to reverse
an official whose conduct is plainly
out of bounds whether
he is fraudulent, perverse,
captious, incompetent, or just palpably wrong."
United States v. Wunderlich, supra, at
342 U. S. 102
(dissenting opinion) (emphasis added).
|
406 U.S.
1app|
APPENDIX TO OPINION OF BRENNAN, J., DISSENTING
Within two months after the decision in
United States v.
Wunderlich, 342 U. S. 98
(1951), six bills to expand the scope of judicial review of agency
disputes decisions were introduced. S. 2432 (Sen. Chavez); S. 2487
(Sen. McCarran); H.R. 6214 (Rep. Celler); H.R. 6301 (Rep.
Springer); H.R. 6338 (Rep. Wilson); H.R. 6404 (Rep. Walter).
Hearings were held in the Senate on S. 2487. Hearings on S. 2487
before a Subcommittee of the Senate Committee on the Judiciary, 82d
Cong., 2d Sess. (1952). S. 2487 provided:
"That no provision of any contract entered into by the United
States, relating to the finality or conclusiveness of any decision
of the Government contracting officer, or of the head of the
department or agency of the United States concerned or his
representative, in a dispute involving a question of fact arising
under such contract, shall be construed to limit judicial review of
any such decision only to cases in which fraud by such Government
contracting officer or such head of department or agency or his
representative is alleged."
Id. at 1.
The Comptroller General's report to the Judiciary Committee,
setting forth GAO's views on S. 2487, stated that GAO felt that the
result of the
Wunderlich decision was "undesirable both as
to the contractor's interests and the interests of the Government."
Id. at 5-6. The Comptroller General stressed the latter
interest.
"I am as deeply concerned, however, that the rule allows the
contracting officials uncontrolled discretion over the Government's
contractual affairs, as well and places them in a position to make
as arbitrary and reckless use of their power against the
Page 406 U. S. 70
interests of the Government as against the interests of the
contractor. In other words, deciding officials can make just as
arbitrary determinations in favor of contractors, at the expense of
the taxpayers."
Id. at 6. The report concluded that GAO considered S.
2487
"inadequate and . . . objectionable because no provision is made
therein for a review of decisions of administrative officers by the
General Accounting Office. Without a provision to that effect. the
General Accounting Office. in performing its statutory functions.
would be precluded from questioning the propriety or legality of
payments made to a contractor as the result of an arbitrary or
grossly erroneous decision on the part of the contracting
officer."
Id. at 7. The report recommended a substitute bill,
which provided that
"Any stipulation in a Government contract to the effect that
disputed questions shall be finally determined by an administrative
official, representative or board shall not be treated as binding
if the General Accounting Office or a court finds that the action
of such officer, representative or board is fraudulent, arbitrary,
capricious, grossly erroneous, or that it is not supported by
substantial evidence."
"
Ibid."
Frank L. Yates, the Assistant Comptroller General, expanded on
the report in his testimony before the Subcommittee. He asserted
that, prior to
Wunderlich, disputes clause decisions on
questions of fact arising under Government contracts
"were not disturbed by the General Accounting Office or the
courts unless the action of the administrative officer was
fraudulent, arbitrary, capricious, grossly erroneous, or without
foundation in fact.
Page 406 U. S. 71
Wunderlich, Mr. Yates said, 'means that the decision of
the administrative officials nearly always will be final because of
the extreme difficulty of proving fraud.'
Id. at 8. And,
he continued, 'the rule works both ways,' for"
"[a] deciding administrative official can make decisions adverse
to the Government as well as to contractors, in which event an
improper decision results in a burden, an improper burden, to the
taxpayers of the country."
Id. at 9. Thus, he said,
"it appears that the executive contracting agencies, without
specific legislation authorizing them to do so, may, by agreement
with the contractor, circumvent the operations of courts and the
General Accounting Office to the serious detriment of both private
business and the Government."
Id. at 9-10. Mr. Yates explained that GAO's substitute
bill would restore "to the courts and to the General Accounting
Office . . . their normal and proper jurisdiction," for:
"[I]t would permit [administrative officers] to make
determinations on questions of fact which would have final effect
if the decisions were not found by the General Accounting Office or
the courts to be fraudulent, arbitrary, capricious,
et
cetera. Such a law not only would protect a contractor from
fraudulent, arbitrary or capricious action by giving him, in
addition to resort to the courts, a further administrative remedy
before the General Accounting Office . . . , but it would also
provide a protection, through the General Accounting Office,
against decisions adverse to the interests of the United States.
Certainly the rights of contractors and the Government to review or
appeal should be coextensive."
Id. at 11.
The managing director of the Associated General Contractors, H.
E. Foreman, testified that the construction industry had for many
years attempted without success to secure changes in the standard
disputes clause. The
Page 406 U. S. 72
industry's latest proposed disputes clause, which Mr. Foreman
read at the hearing, provided
"[t]hat nothing in this contract . . . shall void the right of
either party to this contract carrying the dispute before a court
of competent jurisdiction."
Id. at 24. The association's general counsel, John C.
Hayes, stated that its position was
"that any decision made by a contracting officer or head of a
department, agency, or bureau, should be subject to judicial
review, in order to guarantee that such decision is reasonable,
made with due regard to the rights of both the contracting parties,
and supported by the evidence upon which such decision was
based."
Id. at 29. In amplifying on this position, Mr. Hayes
testified that only "by permitting judicial review of the
contracting officer's decision . . . can the rights of both the
contracting parties be protected." Although he then referred to the
need for legislation that would authorize the courts to "enter
judgment against the United States on any claim in which the
contractor shall seek a review" of a disputes decision, he
immediately added that the legislation should provide "that any
provision in any contract with the United States abridging the
right of the parties to court review shall be null and void."
Id. at 30. Finally, in commenting on GAO's proposed
substitute bill, Mr. Hayes said that the association "would welcome
further administrative review," but that contractors also
"should be permitted our judicial review, whether it be the
government or whether it be the contractor, it doesn't make any
difference. It has to cut both ways. . . ."
Id. at 31. Replying to a specific question, Mr. Hayes
denied that judicial review "was a one-way street in favor of the
contractor," repeating that "it cuts both ways." He concluded that
the association wished "to take the position of being absolutely
fair in urging legislation that will protect the rights of both
Government and contractor."
Id. at 32.
Page 406 U. S. 73
There was much discussion of GAO's substitute bill and GAO's
role in the review of agency disputes decisions. A former counsel
to the Comptroller General, O. R. McGuire, testified that GAO's
review should be limited to questions of law, and that GAO should
"accept the facts, unless, of course, there is fraud, or just gross
mistake."
Id. at 41. John W. Gaskins, who was on the brief
for Wunderlich in the Supreme Court, proposed a revision of GAO's
substitute bill specifically granting both GAO and the courts
"jurisdiction to set aside any [administrative] decision" that did
not comport with the standards set out in GAO's bill.
Id.
at 68. Gardiner Johnson, an attorney who specialized in the
representation of contractors, testified that, as he understood
GAO's position, GAO
"simply wanted practically the same right that the contractors
are requesting to take an appeal from what they consider to be an
unfair and unreasonable decision."
Id. at 84. As so understood, he said,
"our people have no basic quarrel with that. We are against all
forms of unfair, unreasonable decisions either against the
Government and the taxpayer or against the contractor."
Id. at 83.
Most of the witnesses and most of the submitted statements,
however, were concerned only with protecting contractors.
E.g.,
id. at 2-3, 62, 775, 85-87, 119-136. A few witnesses went even
further. Robert E. Kline, Jr., an attorney representing the
National Association of River and Harbors Contractors, proposed
amendments to S. 2487 designed
"to assure full restoration to Government contractors of their
inherent right to judicial review of unjust decisions by Government
contracting officers and department heads."
Id. at 58. These amendments specifically limited the
legislation to contractors' suits in which a court would "enter
judgment against the United States."
Id. at 59. Alan
Johnstone, an attorney representing a contractor, initially
suggested that the legislation
Page 406 U. S. 74
"should provide . . . simply that all administrative
determinations in the performance of a contract with the United
States shall be subject to review by the Comptroller General and by
the courts, according to law, the provisions of any such contract
to the contrary notwithstanding."
Id. at 61-62. Mr. Johnstone returned to testify later,
and, although expressing a preference for a "bill mak[ing]
justiciable any grievance which either of the parties to the
contract would have," submitted two proposed bills on behalf of
himself, Mr. McGuire, and Mr. Gaskins, both of whom had already
testified, and Harry D. Ruddiman, who subsequently testified at the
House hearings. These proposals made judicial review available only
to contractors, one providing that "the United States shall not
employ as a defense the finality of" agency decisions, the other
that "the United States shall not avail itself of the defense of
the finality of such decision[s]."
Id. at 107.
In contrast, the Associated General Contractors, adhering to the
position its representatives had taken at the hearings, submitted a
resolution adopted at its annual convention stating that any
disputes decision
"should be subject to judicial review in order to guarantee that
such decision is reasonable, made with due regard to the rights of
both the contracting parties, and supported by the evidence upon
which such decision was based,"
and urging legislation that would provide "that any provision in
any contract with the United States abridging the rights of the
parties thereto to court review shall be null and void."
Id. at 114.
After the hearings concluded, the Comptroller General sent the
Committee a copy of his report to the Chairman of the House
Judiciary Committee dealing with the House bills.
Id. at
116-119. This report reiterated many of the comments made in the
Comptroller General's earlier report to the Senate Committee. The
report
Page 406 U. S. 75
also objected to the two proposed bills, submitted by Mr.
Johnstone, limiting judicial review to contractors on the ground
that
"the Government would be precluded from employing the finality
of the administrative decision as a defense to a suit, [while] the
contractors would be free to utilize such defense should the
accounting officers of the Government attempt to question the
validity of a payment made to a contractor."
The report, as did the prior one, recommended adoption of GAO's
substitute bill.
Id. at 119.
S. 2487 was reported out in amended form, incorporating the
substance of GAO's proposal. As amended, S. 2487 provided
"That no provision of any contract entered into by the United
States, relating to the finality or conclusiveness, in a dispute
involving a question arising under such contract, of any decision
of an administrative official, representative, or board, shall be
pleaded as limiting judicial review of any such decision to cases
in which fraud by such official, representative, or board is
alleged; and any such provision shall be void with respect to any
such decision which the General Accounting Office or a court,
having jurisdiction, finds fraudulent, grossly erroneous, so
mistaken as necessarily to imply bad faith, or not supported by
reliable, probative, and substantial evidence. . . ."
S.Rep. No. 1670, 82d Cong., 2d Sess., 1 (1952). The Committee
report stated that
"[t]he purpose of the proposed legislation is to overcome the
inequitable effect, under a recent Supreme Court decision, of
language in Government contracts which makes the decision of the
contracting officer or the head of the agency final with respect to
questions of fact."
Ibid. The report pointed out
"that, to the same extent [the
Wunderlich] decision
Page 406 U. S. 76
would operate to the disadvantage of an aggrieved contractor, it
would also operate to the disadvantage of the Government in those
cases, as sometimes happens, when the contracting officer makes a
decision detrimental to the Government interest in the claim."
Id. at 2. The report further explained that:
"S. 2487 will have the effect of permitting review in the
General Accounting Office or a court with respect to any decision
of a contracting officer or a head of an agency which is found to
be fraudulent, grossly erroneous, so mistaken as necessarily to
imply bad faith, or not supported by reliable, probative, and
substantial evidence. In other words, in those instances where a
contracting officer has made a mistaken decision, either wittingly
or unwittingly, it will not be necessary for the aggrieved party
to, in effect, charge him with being a fraud or a cheat in order to
affect [
sic] collection of what is rightfully due."
Ibid. Finally, the report stressed that amended S. 2487
was
"not intended to narrow or restrict or change in any way the
present jurisdiction of the General Accounting Office . . . , but
simply to recognize the jurisdiction which the General Accounting
Office already has."
Id. at 2-3. Although the Senate, without debate, passed
amended S. 2487, 98 Cong.Rec. 7783-7784;
id. at 9059, the
House did not act upon it during the 82d Congress. It was
reintroduced in the Senate of the 83d Congress as S. 24. The
Committee report was, with formal changes, identical to the report
on amended S. 2487. S.Rep. No. 32, 83d Cong., 1st Sess. (1953).
Senator McCarran, the bill's sponsor, explained on the floor that
the effect of the
Wunderlich decision was to require
"that the aggrieved party allege and prove that some Government
employee deliberately cheated, or intended to defraud
Page 406 U. S. 77
him, in order to get a court review of the question."
99 Cong.Rec. 4572. He also noted that:
"Senators who have looked into this matter know that this
decision of the Supreme Court cuts two ways. It can hurt the
Government badly, as well as doing an injustice to contractors. In
a recent case . . . , [t]he Comptroller General . . . attempted to
recover on behalf of the Government, because the mistake was
against the Government. The contractor interposed a defense based
on . . . the
Wunderlich case. . . . [T]he result was a
failure of recovery on behalf of the Government."
"It was because of this case . . . that the Comptroller General
. . . testified before the Judiciary Committee in behalf of this
bill."
Id. at 4573. Later the same day, however, Senator
McCarran stated that the Air Force
"objected to the fact that the bill gave the Comptroller General
the same right that was given to a contractor to question a
decision of a contracting officer."
Id. at 4598. He also stated that
"the Comptroller General feels that, in order to protect the
interests of the Government, it is necessary that he shall have as
much right to question the decision of a contracting officer . . .
as may be given to the private party to the contract."
Id. at 4599. When S. 24 reached the floor a month
later, Senator McCarran again emphasized that, while the
Wunderlich decision could "operate greatly to the
disadvantage of contractors," it could also "operate to the
disadvantage of the Government."
Id. at 6170. The Senate
then passed the bill.
Id. at 6201.
Representative Reed introduced amended S. 2487 in the House as
H.R. 1839, and hearings were held on it and two related bills, H.R.
3634 (Rep. Celler) and H.R. 6946 (Rep. Willis). Hearings on H.R.
1839
et al. before Subcommittee No. 1 of the House
Committee on
Page 406 U. S. 78
the Judiciary, 83d Cong., 1st and 2d Sess., ser. 12 (1953,
1954).
At the initial hearing in July, 1953, all witnesses supported
the bill. Elwyn L. Simmons, a contractor, asserted that, because of
"incompetent or negligent or capricious agency representative[s],"
the
Wunderlich decision could "work as readily against the
Government's interests as against that of the contractor," and
that
"only your immediate legislative action through enactment of
H.R. 1839 or S. 24 can now protect both the Government and the
contractor from this . . . unprecedented situation."
Id. at 4. Referring to the Senate debates on S. 24, Mr.
Simmons noted
"that there was some objection by contractors doing business
with the Air Force to the inclusion of the GAO under the provisions
of this bill. I do not know what basis these Air Force contractors
have for their objection, but we, as general contractors, are used
to the GAO in our business and their auditing staff and forms no
basis for our objection."
Id. at 5.
George P. Leonard, an officer of the Wunderlich Contracting Co.,
testified that, because of
Wunderlich,
"neither the Government through the GAO, nor the contractors
through the courts, have any right to appeal from contracting
officers' decisions even though they may be grossly erroneous."
Id. at 7. He added that he saw
"no reason why anybody should object to either the General
Accounting Office or the courts passing on these decisions of the
contracting officers."
Id. at 8.
Harry D. Ruddiman, who argued for Wunderlich before the Supreme
Court, submitted a prepared statement asserting that, unless H.R.
1839 was enacted, "not only the contractor, but also the
Government, will be unable to obtain effective judicial review of
contracting officers' decisions." In his view, H.R. 1839 "would
restore to
Page 406 U. S. 79
the courts an effective review of determinations made by
contracting officers."
Id. at 12. Although, in light of
the Senate reports on amended S. 2487 and S. 24, Mr. Ruddiman
discounted "[f]ears . . . that the reference to the General
Accounting Office in S. 24 would give it powers with respect to the
review of payments under Government contracts beyond those which it
already possesses," he suggested in his statement that "any doubt
on the matter . . . can very easily be removed by striking out the
words
the General Accounting Office or'" in H.R. 1839.
Id. at 13. In his testimony, however, Mr. Ruddiman
expressed reservations about removing GAO from the bill.
"Lastly, I would like to deal with an objection which has been
raised to including the General Accounting Office in the provisions
of this bill. I don't know just exactly what the basis of the
objection is, but, in my opinion, any fears along that line are
groundless. As I see it, the General Accounting Office, as a matter
of practice, in reviewing contracts and change orders for purposes
of payment, is always going to apply the standards of review that
are granted to the courts. That has been their practice before the
Wunderlich decision. They figured if there was good reason
to doubt the finality of the decision, the matter ought to be
referred to the courts. I think that is all that would be done by
the language of this bill."
"At one time, I thought there would probably be no objection to
striking out the reference to the General Accounting Office as
mentioned in S. 24 or H.R. 1839. I felt that, even if you had no
reference, the General Accounting Office would still exercise that
same jurisdiction. However, in view of the fact that the Senate has
already passed a bill which has included a reference to the General
Accounting
Page 406 U. S. 80
Office, I think it would be dangerous now to eliminate the
General Accounting Office from the provisions of this bill. It
might be misconstrued as taking away this jurisdiction from the
General Accounting Office."
Id. at 16. Representative Graham, a committee member,
replied that it was "needless to refer to" GAO anyway.
Ibid. Mr. Ruddiman, however, adhered to his view in a
letter to the Subcommittee the following day.
"I feel that, if the bill, as passed by the Senate, had
contained no reference to the General Accounting Office, and the
House of Representatives had passed such a bill without amendment,
the General Accounting Office, as a practical matter, would, in
reviewing payments under Government contracts and change orders,
employ these same standards of review that are granted by the bill
to the courts. Thus, if the General Accounting Office was
confronted with an administrative decision which it thought would
be set aside by the courts, it would refuse to make payment, and
throw the matter into court. However, since the Senate, in passing
S. 24, has expressly included the General Accounting Office in the
bill, some doubt as to the General Accounting Office jurisdiction
might arise if the House of Representatives should then strike out
all reference to the General Accounting Office. There would then be
the possibility that this action would be construed as limiting
review by the General Accounting Office to the ineffective ground
of fraudulent intent prescribed by the
Wunderlich
decision. It is therefore my suggestion that the bill be passed
without change in the language employed by the Senate."
Id. at 17.
Alan Johnstone, the final witness of the day, likewise
Page 406 U. S. 81
urged that GAO be left in H.R. 1839.
Id. at 18. He said
that "this bill would throw wide the portals of the courts of
justice to anyone, including the Government, which has a
grievance," and, referring, as had Senator McCarran, to
Leeds
& Northrup Co. v. United States, 101 F.
Supp. 999 (ED Pa.1951), in which a contractor successfully
asserted a
Wunderlich defense, he said "that what is sauce
for the goose is sauce for the gander."
Id. at 19.
Opposition to H.R. 1839 was also becoming apparent. Among the
letters sent to the Committee,
id. at 22-30, all calling
for legislation to protect the rights of contractors, was one
urging deletion of the reference to GAO because
"[t]he effect of the provision is to set up the General
Accounting Office as a 'court of claims.' . . . [A]n agency of the
legislative branch . . . should not be used to perform functions
intended for the judicial branch."
Id. at 26.
Shortly before the hearings resumed in January, 1954, the
Comptroller General wrote the Chairman of the Committee about H.R.
1839. He noted that
"there was considerable opposition to the bill from some
quarters . . . on the basis . . . that the General Accounting
Office should not be given express authority by statute to review
and overrule the determinations of administrative officials."
Id. at 135. He responded that GAO "has not asked for
authority which it did not have before the decision in the
Wunderlich case," and he referred to the statement in the
Senate reports that the bill would not affect GAO's jurisdiction.
Nevertheless, he then presented a substitute bill, to which he said
there would be little or no opposition by industry groups and
administrative agencies. He stated that
"this substitute language will accomplish what we have been
striving for all along, and will place the General Accounting
Office in
Page 406 U. S. 82
precisely the same situation it was in before"
Wunderlich. Id. at 136. GAO's proposed bill
provided:
"That no provision of any contract entered into by the United
States, relating to the finality or conclusiveness of any decision
of the head of any department or agency or his duly authorized
representative or board in a dispute involving a question arising
under such contract, shall be pleaded as limiting judicial review
of any such decision to cases where fraud by such official or his
said representative or board is alleged: Provided, however, that
any such decision shall be final and conclusive unless the same is
fraudulent or capricious or arbitrary or so grossly erroneous as
necessarily to imply bad faith, or is not supported by substantial
evidence. . . ."
Ibid. With the addition of the words "in any suit now
filed or to be filed," added to deal with retroactivity problems,
see, e.g., id. at 48, 82, GAO's bill eventually was
enacted as the Wunderlich Act.
In commenting upon GAO's bill, E. L. Fisher, GAO's general
counsel, reiterated much of the testimony of the Assistant
Comptroller General, Mr. Yates, at the Senate hearing. Mr. Fisher,
as had Mr. Yates, stressed that the
Wunderlich "rule works
both ways. A deciding administrative official can make decisions
adverse to the Government, as well as to contractors."
Id.
at 38. Mr. Fisher, in language virtually identical to that earlier
used by Mr. Yates, urged passage of either H.R. 1839 or GAO's
proposed substitute because they
"would permit [administrative officers] to make determinations
on questions of fact which would have final effect if the decisions
were not found by the General Accounting Office or the courts to be
fraudulent, arbitrary, capricious, and so forth. Such a law not
only would protect a contractor from fraudulent,
Page 406 U. S. 83
arbitrary or capricious action by giving him, in addition to
resort to the courts, a further administrative remedy before the
General Accounting Office, and would also provide a protection,
through the General Accounting Office, against decisions adverse to
the interests of the United States. Certainly the rights of
contract[ors] and the Government to review or appeal should be
coextensive."
Id. at 39.
The associate general counsel of the General Services
Administration, J. H. Macomber, Jr., similarly emphasized the need
to protect the Government's interests, stating
"that there should be some provision in the legislation, if not
an explicit provision, at least by appropriate wording with respect
to the judicial review portion, that will insure an opportunity to
protect the Government against excessive generosity, against
decisions of the contracting officer adverse to the
Government."
Id. at 59. Mr. Macomber suggested that
"there might be some doubt under the wording of H.R. 6946 . . .
where specific reference is made to a finding by the court[,] as to
whether the General Accounting Office could seek a court review by
a setoff or by applying to the Department of Justice for recovery
in a case where they felt that the action of the contracting
officer was grossly erroneous as against the Government. I think
that the language suggested by the Comptroller General's revision
gets away from that difficulty."
Ibid.
Mr. Simmons, a contractor who had supported H.R. 1839 at the
initial hearing, appeared again to support GAO's substitute bill on
the ground that it
"was prepared to meet objections of certain industries against
giving the General Accounting Office express statutory authority to
review administrative decisions under the disputes
Page 406 U. S. 84
clause, and is designed to give the General Accounting Office no
more authority in this connection than it had before the
Wunderlich decision."
Id. at 76.
Many other witnesses supported GAO's substitute bill on
essentially the same grounds.
E.g., id. at 52-56, 77-88,
91-95, 101-104, 123-124. Louis F. Dahling, associate counsel for
the Automobile Manufacturers Association, asserted that H.R. 1839
would "make the General Accounting Office another Court of Claims,"
and thus deprive contractors of their day in court.
"Now, it does not appear from the language in that bill that
there would be any appeal from a decision of the General Accounting
Office, and that office will in all probability make the first
review of any disputes clause decision. If that agency should
decide that the decision was not supported by substantial evidence,
it would appear that the contractor would have no redress.
Furthermore, the General Accounting Office is a part of the
legislative department of the Government. . . . If this agency is
made another Court of Claims, in a sense, it becomes a judge and
jury and a prosecutor."
Id. at 97. Mr. Dahling therefore supported GAO's bill
because it did "not grant judicial power to the General Accounting
Office."
Id. at 98. Charles Maechling, Jr., a
representative of the Radio-Electronics-Television Manufacturers
Association, echoed this view.
"Under S. 24, however, the scope and powers of the General
Accounting Office are vastly enlarged, and this agency of the
Government, which has heretofore exercised principally
investigatory and audit functions, becomes clothed with powers of a
judicial nature. S. 24 appears to set up the General Accounting
Office as a third administrative tier of review in Government
contract disputes."
Id. at 105.
Page 406 U. S. 85
Similarly, the American Merchant Marine Institute submitted a
statement objecting to H.R. 1839
"insofar as it establishes the General Accounting Office as a
sort of intermediate or 'floating' court, and vests it with express
statutory authority to set aside [an administrative] decision
merely because its administrative officers, in their opinion,
consider the decision not to be supported by substantial evidence.
On the other hand, we fully agree that a decision of a contracting
officer or, upon appeal, of the head of the contracting agency,
should be subject to judicial review and reversal by the courts. .
. . This judicial function, however, should not be shared with or
otherwise vested in the General Accounting Office. . . . The
literal effect of S. 24 appears to be that, once the General
Accounting Office may have found the decision to be not supported
by substantial evidence, it may not thereafter be pleaded in court
either by the contracting party or the Government as limiting the
scope of judicial review to that provided for by the disputes
clause."
Id. at 122. Opposition to H.R. 1839, then, was premised
on the fear that its reference to GAO might deprive contractors of
any recourse to the courts. That judicial review was the
contractors' sole concern is also clear from the position taken by
the Associated General Contractors,
id. at 61-75, which
supported H.R. 1839 on the ground that it would restore to
contractors "the fundamental right of judicial review of disputes
arising under Government contracts."
Id. at 62.
That deletion of the reference to GAO was not understood as
denying judicial review to the Government becomes evident from an
examination of Representative Willis' testimony about his bill,
H.R. 6946, which was identical to H.R. 1839 except that it omitted
the words "the General Accounting Office or."
Id. at 31.
He testified
Page 406 U. S. 86
that the "
Wunderlich decision could react, and has
reacted, unfavorably to the Government where the Government felt it
was the aggrieved party."
Id. at 32. The following
colloquy then occurred:
"Mr. HYDE. The only question that occurred to me was that you
mentioned there might be a time when the Government was the
aggrieved party. With the present procedure, the Government is not
likely to be the aggrieved party?"
"Mr. WILLIS. It could be. It could very well be, because here
you are dealing with fraud, and the court says that, in order to
have relief, one must be guilty of fraud. Now a contracting officer
who hands down a decision against the Government can very adversely
affect the Government itself, and the Government, some of these
days, might find a decision very much against itself. The decision
works both ways, in that there is no appeal either way from the
holding of the contracting officer unless a showing of fraud is
made, and the Government itself might be caught some of these days
under this
Wunderlich decision. I know of one case when
the court so ruled."
"
* * * *"
"Mr. HYDE. If the contracting officer makes a finding, under
what circumstances would the Government be the one to take an
appeal or want to take an appeal? Who would be the one in the
Government to say, 'We are going to take an appeal'?"
"Mr. WILLIS. I imagine the General Accounting Office would be
interested, and the Department of Justice and the Department of
Defense. Suppose a dispute arises . . . , [a]nd then, on matters of
fact, the contracting officer holds one way. Then neither side has
recourse unless there is a showing that the
Page 406 U. S. 87
contracting officer was dishonest, was guilty of fraud, or
intended to cheat someone."
Id. at 33-34.
This testimony is significant also in light of the later
testimony of Franklin M. Schultz, a former law professor who had
written about the problems created by the
Wunderlich
decision. Mr. Schultz expressed concern that GAO's substitute bill
did "not say specifically that an appeal can be taken by an
aggrieved contractor." A committee member then asked whether the
language of GAO's bill did "not necessarily include both parties."
Id. at 110. The following colloquy ensued:
"Mr. SCHULTZ. Yes, and that is exactly my point. . . . [S]everal
years from now, if the Comptroller General decides . . . that a
contracting officer's decision is not supported by substantial
evidence, he could refuse payment, and, in a court action, he could
say that this bill means that it is a two-way street, not only may
the contractor upset the contracting officer for not having
substantial evidence behind the decision, but in the case where the
contracting officer makes a decision favorable to the contractor,
the GAO has similar upsetting power. . . ."
"
* * * *"
"Mr. WILLIS. This judicial review referred to in that passage
there referring to a review by GAO, when GAO has been left out
deliberately as compared to S. 24?"
"Mr. SCHULTZ. Well, that is persuasive, sir, but you do have the
testimony of Mr. Fisher, sponsoring [GAO's] bill . . . saying that
the rights of contractors and the Government to appeal should be
coextensive. . . ."
Id. at 110-111. Mr. Schultz went on to say what was
implicit in the above colloquy, that his objection was not to
judicial
Page 406 U. S. 88
review for the Government, which he recognized would be
available, but to judicial review for either the Government or
contractors on the basis of the "substantial evidence" test. He
indicated that his "own preference would be for the language of
[GAO's] bill without the phrase
substantial evidence,'"
id. at 113, and, in a subsequent letter to the
Subcommittee, he again suggested that neither the Government nor
contractors should be permitted to rely upon that standard to upset
an administrative decision, id. at 118-119.
The Subcommittee was presented with, but took no action upon, a
bill proposed by the American Bar Association that would have
expressly limited the right of judicial review to contractors.
Id. at 89. Instead, the Committee reported out the bill
that is now the Wunderlich Act. H.R.Rep. No. 1380, 83d Cong., 2d
Sess. (1954). The report stated:
"The purpose of the proposed legislation . . . is to overcome
the effect of the Supreme Court decision . . . under which the
decisions of Government officers rendered pursuant to the standard
disputes clauses in Government contracts are held to be final
absent fraud on the part of such Government officers."
". . . The proposed legislation also prescribes fair and uniform
standards for the judicial review of such administrative decisions
in the light of the reasonable requirements of the various
Government departments and agencies, of the General Accounting
Office, and of Government contractors."
Id. at 1-2. The report also discussed the effect of the
legislation on GAO, in much the same terms as had the prior Senate
reports.
"The proposed legislation, as amended, will not add to, narrow,
restrict, or change in any way the present
Page 406 U. S. 89
jurisdiction of the General Accounting Office either in the
course of a settlement or upon audit, and the language used is not
intended either to change the jurisdiction of the General
Accounting Office or to grant any new jurisdiction, but simply to
recognize the jurisdiction which the General Accounting Office
already has."
"The elimination of the specific mention of the General
Accounting Office from the provisions of the bill as amended should
not be construed as taking away any of the jurisdiction of that
Office. It is intended that the General Accounting Office, as was
it practice, in reviewing a contract and change orders for the
purpose of payment, shall apply the standards of review that are
granted to the courts under this bill. At the same time, there is
no intention of setting up the General Accounting Office as a
'court of claims.' Nor should the elimination of the specific
mention of the General Accounting Office in the bill be construed
as limiting its review to the fraudulent intent standard prescribed
by the
Wunderlich decision."
Id. at 7.
Representative Graham stated on the floor of the House that the
Comptroller General had approved the bill, and the House passed it
without debate. 100 Cong.Rec. 5510. When the bill came to the
Senate, Senator McCarran explained that
"The purpose of the proposed legislation is to overcome the
inequitable effect, under the decision of the Supreme Court in the
Wunderlich case, of language in Government contracts which
makes the decision of the contracting officer or the head of the
agency final, with respect to questions of fact. To put it another
way, the objective of this bill is to preserve the right of review
by the courts in cases
Page 406 U. S. 90
involving action by a contracting officer which is arbitrary,
capricious, fraudulent, or so grossly erroneous as necessarily to
imply bad faith."
"The language of the House bill, while quite different from the
language approved in the Senate, is designed to accomplish the same
purpose. It is my understanding the Department of Justice takes the
view that the House language will accomplish the same purpose as
the Senate language. It is my further understanding that the
Comptroller General of the United States has expressed complete
satisfaction with the House language, and has declared that, in his
opinion, it will accomplish the purposes sought to be served by the
Senate language."
Id. at 5717. After Senator McCarran further assured the
Senate that GAO was "satisfied with the language in the House bill"
and that "otherwise [he] would not care to go along,"
ibid., a final colloquy occurred:
"Mr. THYE. As I understand, the bill was passed by the Senate,
and a similar bill was passed by the House. The only question
involved is a modification of the language in the Senate bill, and
the two bills agree in their effect, so to speak?"
"Mr. McCARRAN. That is correct."
"Mr. THYE. There is nothing else of a legislative nature
involved. Is that correct?"
"Mr. McCARRAN. That is correct."
Id. at 5718. The Senate then passed the bill.
Ibid.