The so-called "Wunderlich Act" of May 11, 1954, 68 Stat. 81,
provides, in substance, that a departmental decision on a question
of fact pursuant to a "disputes" clause in a government contract
shall be final and conclusive in accordance with the provisions of
the contract,
"unless the same is fraudulent or capricious or arbitrary or so
grossly erroneous as necessarily to imply bad faith, or is not
supported by substantial evidence."
Held: In a suit on a government contract, apart from
questions of fraud, determination of the finality to be attached to
a departmental decision on a question arising under a "disputes"
clause must rest solely on consideration of the record before the
department, and no new evidence may be received or considered. Pp.
373 U. S.
709-718.
157 Ct. Cl. ___, judgment vacated and cause remanded.
MR. JUSTICE HARLAN delivered the opinion of the Court.
This case involves the interpretation and application of the
"Wunderlich Act," 68 Stat. 81, 41 U.S.C. §§ 321-322,
[
Footnote 1]
Page 373 U. S. 710
an Act designed to permit judicial review of decisions made by
federal departments and agencies under standard "disputes" clauses
[
Footnote 2] in government
contracts. The issue before us is whether, in a suit governed by
this statute, the court is restricted to a review of the
administrative record on issues of fact submitted to administrative
determination, or is free to receive new evidence on such
issues.
In 1946, the respondent, Carlo Bianchi and Company, entered into
a contract with the Army Corps of Engineers for the construction of
a flood control dam. Included in the work to be performed was the
construction of a 710-foot tunnel, designed for the diversion of
water, to be lined with concrete and to have permanent steel
supports as protection for a 50-foot section at either end. The
specifications did not call for such permanent supports throughout
the remainder of the tunnel, but only for "[t]emporary tunnel
protection . . . where required for safety of the workmen." The
contract contained a standard "changed conditions" clause,
authorizing the contracting officer to provide for an increase in
cost if the contractor encountered subsurface conditions materially
different from those indicated in the contract or to be
reasonably
Page 373 U. S. 711
anticipated, and also contained the standard "disputes" clause
quoted,
supra, note
2
After the tunnel had been drilled by a subcontractor, but before
it was lined with concrete, the respondent took the position that
unforeseen conditions created extreme hazards for workmen,
requiring permanent protection throughout the tunnel, and that it
should be compensated for installing such protection. The
contracting officer decided that compensation would not be made,
and, pursuant to the "disputes" clause, a timely appeal from his
decision was taken to the Board of Claims and Appeals of the Corps
of Engineers. While the appeal was pending, respondent installed
the tunnel supports and completed work on the tunnel.
An adversary hearing was held before the Board at which a record
was made and each side offered its evidence and had an opportunity
for cross-examination. In December, 1948, the Board issued a
decision against the contractor, resolving certain conflicts in the
evidence in favor of the Government and holding, in substance, that
there were no unanticipated or unforeseen conditions requiring the
use of permanent steel protection throughout the tunnel.
Almost six years later, in December, 1954, respondent brought
the present action for breach of contract in the Court of Claims,
seeking substantial damages and alleging that the decisions of the
contracting officer and the Board were "capricious or arbitrary or
so grossly erroneous as necessarily to imply bad faith, or were not
supported by substantial evidence." At a hearing before a
Commissioner in 1956, the Government took the position that, on the
question whether the Board's decision was entitled to be considered
final, no evidence was admissible except the record before the
Board. But the Commissioner received evidence
de novo,
including, over government objection, a substantial amount of
evidence that had not
Page 373 U. S. 712
been before the Board. He subsequently made extensive findings
of fact, and concluded that the respondent was entitled to
recover.
In an opinion issued in January, 1959, the Court of Claims
accepted the Commissioner's findings and conclusions, ruling that,
"on consideration of all the evidence, the contracting officer's
decision (as affirmed by the Board) cannot be said to have
substantial support," and thus "does not have finality." 169 F.
Supp. 514, 517, 144 Ct.Cl. 500, 506. On the question whether it was
limited in its consideration to the evidence before the Board, the
court stated:
"In our opinion in
Volentine and Littleton v. United
States, 145 F. Supp. 952, 136 Ct.Cl. 638, holding that the
trial in this court should not be limited to the record made before
the contracting agency, but should be
de novo, we
recognized that there were logical weaknesses in our position. We
concluded, however, that the intent of Congress in enacting the
Wunderlich Act was in accord with our conclusion, and we adhere to
that conclusion in this case."
Ibid. After receiving additional evidence on damages,
the court entered judgment for respondent in the amount of
$149,617.36. We granted certiorari, 371 U.S. 939, to resolve a
conflict among the lower courts [
Footnote 3] on the important question of the kind of
judicial proceeding to be afforded in cases governed by the
Wunderlich Act.
Page 373 U. S. 713
I
The jurisdiction of the Court of Claims in the present case is
conferred by 28 U.S.C. § 1491, since this is a suit for
judgment against the United States "founded" upon an "express or
implied contract with the United States." Ordinarily, when
questions of fact arise in such suits, the function of the court is
to receive evidence and to make appropriate findings as to the
facts in dispute. But this Court long ago upheld the validity of
clauses in government contracts delegating to a government employee
the authority to make determinations of disputed questions of fact,
and required such determinations to be given conclusive effect in
any subsequent suit in the absence of fraud or gross mistake
implying fraud or bad faith.
See Kihlberg v. United
States, 97 U. S. 398;
Ripley v. United States, 223 U. S. 695.
Thus, the function of the Court of Claims in matters governed by
"disputes" clauses was, in effect, to give an extremely limited
review of the administrative decision, and although the scope of
review was somewhat expanded by that court over the years,
[
Footnote 4] it was expressly
restricted in
United States v. Wunderlich, 342 U. S.
98,
342 U. S. 100,
to determining whether or not the departmental decision had been
founded on fraud,
i.e., "conscious wrongdoing, an
intention to cheat or be dishonest."
The
Wunderlich decision, rendered over strong dissents,
evoked considerable effort to obtain legislation expanding the
scope of review beyond questions of fraud. A number of bills were
introduced in the Eighty-second and Eighty-third Congresses;
hearings were held in the Senate [
Footnote 5] and House of Representatives; [
Footnote 6] and the resulting
Page 373 U. S. 714
statute known as the "Wunderlich Act" was ultimately approved by
both Houses in 1954. This statute, quoted in full in
note 1 supra, is entitled an Act "To
permit review of decisions of the heads of departments . . .
involving questions arising under Government contracts," and
provides in substance that a departmental decision on a question of
fact rendered pursuant to a "disputes" clause shall be final and
conclusive in accordance with the provisions of the contract
"unless the same is fraudulent or capricious or arbitrary or so
grossly erroneous as necessarily to imply bad faith, or is not
supported by substantial evidence."
Respondent has not argued in this Court that the underlying
controversy in the present suit is beyond the scope of the
"disputes" clause in the contract, or that it is not governed by
the quoted language in the Wunderlich Act. Thus, the sole issue, as
stated
supra, p.
373 U. S. 710,
is whether the Court of Claims is limited to the administrative
record with respect to that controversy, or is free to take new
evidence. In considering this issue, we put to one side questions
of fraud, which are not involved in this case, which normally
require the receipt of evidence outside the administrative record
for their resolution, and which could be considered in judicial
proceedings even prior to the enactment of the statute.
It is our conclusion that, apart from questions of fraud,
determination of the finality to be attached to a departmental
decision on a question arising under a "disputes" clause must rest
solely on consideration of the record before the department. This
conclusion is based both on the language of the statute and on its
legislative history.
1. With respect to the language used, we note that the statute
is designated as an Act "[t]o permit review," and that the
reviewing function is one ordinarily limited to consideration of
the decision of the agency or court below
Page 373 U. S. 715
and of the evidence on which it was based. Indeed, in cases
where Congress has simply provided for review, without setting
forth the standards to be used or the procedures to be followed,
this Court has held that consideration is to be confined to the
administrative record, and that no
de novo proceeding may
be held.
Tagg Bros. & Moorhead v. United States,
280 U. S. 420;
National Broadcasting Co. v. United States, 319 U.
S. 190,
319 U. S. 227.
And, of course, as shown by the
Tagg Bros. and
NBC cases themselves, the function of reviewing an
administrative decision can be and frequently is performed by a
court of original jurisdiction, as well as by an appellate
tribunal.
Moreover, the standards of review adopted in the Wunderlich Act
-- "arbitrary," "capricious," and "not supported by substantial
evidence" -- have frequently been used by Congress, and have
consistently been associated with a review limited to the
administrative record. [
Footnote
7] The term "substantial evidence," in particular, has become a
term of art to describe the basis on which an administrative record
is to be judged by a reviewing court. This standard goes to the
reasonableness of what the agency did on the basis of the evidence
before it, for a decision may be supported by substantial evidence
even though it could be refuted by other evidence that was not
presented to the decisionmaking body.
2. The legislative history supports our conclusion that the
language used in the Act should be given its customary meaning. It
is true that several witnesses representing contractors explained
the purpose of the proposed legislation as restoring rights the
contractors had before
Wunderlich, [
Footnote 8] and that it had apparently been the
practice
Page 373 U. S. 716
of the Court of Claims to receive evidence on matters covered by
"disputes" clauses. [
Footnote
9] But is seems clear in context that these witnesses meant
only that the
standards of review should cover more than
conscious fraud, as the Court of Claims had assumed prior to
Wunderlich. Indeed with respect to the procedural
significance of the substantial evidence test, a leading
contractor's representative stated that it would
"result in these various departments and agencies feeling that
they will have to produce their witnesses at these hearings and
permit the contractor to examine them in order to have in the
record some substantial evidence to support their decisions when
they go up on appeal to the court. [
Footnote 10]"
The House Report recommending the bill ultimately enacted leaves
little doubt that the review intended was one confined to the
administrative record. H.R.Rep.No. 1380, 83d Cong., 2d Sess. The
explicit references to the Administrative Procedure Act, 60 Stat.
243, 5 U.S.C. § 1009, and to this Court's discussion of the
standards of review in
Consolidated Edison Co. of New York v.
Labor Board, 305 U. S. 197,
305 U. S. 229,
are only the least indications. Even more significant is the
Committee's view, echoing that of the witness quoted above, that
the standards proposed would remedy the practice in many
departments of failing to acquaint the contractor with the evidence
in support of the Government's position:
"It is believed that, if the standard of substantial evidence is
adopted, this condition will be corrected, and
Page 373 U. S. 717
that the records of hearing officers will hereafter contain all
of the testimony and evidence upon which they have relied in making
their decisions. It would not be possible to justify the retention
of the finality clauses in Government contracts unless the hearing
procedures were conducted in such a way as to require each party to
present openly its side of the controversy and afford an
opportunity of rebuttal."
H.R.Rep. No. 1380, 83d Cong., 2d Sess. 5.
This sound and clearly expressed purpose would be frustrated if
either side were free to withhold evidence at the administrative
level and then to introduce it in a judicial proceeding. Moreover,
the consequence of such a procedure would, in many instances, be a
needless duplication of evidentiary hearings, and a heavy
additional burden in the time and expense required to bring
litigation to an end. Thus, in the present case, judicial
proceedings began in 1954, almost six years after completion of the
departmental proceedings, and a final decision on the issue of
liability was not rendered until 1959. This is surely delay at its
worst, and we would be loath to condone any procedure under which
the need for expeditious resolution would be so ill served. Here
the procedure is clearly inconsistent with the legislative
directive.
It is contended that the Court of Claims has no power to remand
a case such as this to the department concerned,
cf. United
States v. Jones, 336 U. S. 641,
336 U. S.
670-671, and thus, if the administrative record is
defective or inadequate, or reveals the commission of some
prejudicial error, the court can only hold an evidentiary hearing
and proceed to judgment. There are, we believe, two answers to this
contention.
First, there would undoubtedly be situations
in which the court would be warranted, on the basis of the
administrative record, in granting judgment for the contractor
without the need for further administrative action.
Second, in situations where the court
Page 373 U. S. 718
believed that the existing record did not warrant such a course,
but that the departmental determination could not be sustained
under the standards laid down by Congress, we see no reason why the
court could not stay its own proceedings pending some further
action before the agency involved.
Cf. Pennsylvania R. Co. v.
United States, 363 U. S. 202.
Such a stay would certainly be justified where the department had
failed to make adequate provision for a record that could be
subjected to judicial scrutiny, for it was clearly part of the
legislative purpose to achieve uniformity in this respect. And, in
any case in which the department failed to remedy the particular
substantive or procedural defect or inadequacy, the sanction of
judgment for the contractor would always be available to the
court.
II
In its argument here, the Government has urged that, if judicial
review is confined to the administrative record, it must be
concluded that the Board's determination is supported by
substantial evidence, and thus is entitled to finality under the
Wunderlich Act. The respondent, on the other hand, contends that
there were several irregularities in the Board's procedures that
preclude giving its determination conclusive effect.
Neither of these matters is properly embraced within our grant
of certiorari, and we are therefore not called upon to pass on
them. We hold only that, in its consideration of matters within the
scope of the "disputes" clause in the present case, the Court of
Claims is confined to review of the administrative record under the
standards in the Wunderlich Act, and may not receive new evidence.
We therefore vacate the judgment below and remand the case for
further proceedings in conformity with this opinion.
It is so ordered.
Page 373 U. S. 719
[
Footnote 1]
41 U.S.C. § 321 provides:
"No provision of any contract entered into by the United States,
relating to the finality or conclusiveness of any decision of the
head of any department or agency or his duly authorized
representative or board in a dispute involving a question arising
under such contract, shall be pleaded in any suit now filed or to
be filed as limiting judicial review of any such decision to cases
where fraud by such official or his said representative or board is
alleged:
Provided, however, That any such decision shall
be final and conclusive unless the same is fraudulent or capricious
or arbitrary or so grossly erroneous as necessarily to imply bad
faith, or is not supported by substantial evidence."
41 U.S.C. § 322 provides:
"No Government contract shall contain a provision making final
on a question of law the decision of any administrative official,
representative, or board."
[
Footnote 2]
The standard "disputes" clause, as included in the contract
involved in this case, provides:
"Except as otherwise specifically provided in this contract, all
disputes concerning questions of fact arising under this contract
shall be decided by the contracting officer subject to written
appeal by the contractor within 30 days to the head of the
department concerned or his duly authorized representative, whose
decision shall be final and conclusive upon the parties thereto. In
the meantime, the contractor shall diligently proceed with the work
as directed."
[
Footnote 3]
With the decision below,
compare, e.g., Allied Paint &
Color Works, Inc. v. United States, 309 F.2d 133 (C.A.2d
Cir.);
Wells & Wells, Inc. v. United States, 269 F.2d
412 (C.A.8th Cir.).
See also Mann Chemical Laboratories, Inc.
v. United States, 174 F.
Supp. 563 (D.C.D.Mass.). In suits involving less than $10,000,
the District Courts have concurrent jurisdiction with the Court of
Claims over claims arising under government contracts, 28 U.S.C.
§ 1346(a)(2), and, in suits by the Government under such
contracts, have exclusive jurisdiction,
see 28 U.S.C.
§ 1345.
[
Footnote 4]
See, e.g., Southern Shipyard Corp. v. United States, 76
Ct.Cl. 468;
Needles v. United States, 101 Ct.Cl. 535.
[
Footnote 5]
Hearings before a Subcommittee of the Senate Judiciary Committee
on S. 2487, 82d Cong., 2d Sess.
[
Footnote 6]
Hearings before the House Judiciary Committee on H.R. 1839 et
al., 83d Cong., 1st Sess.
[
Footnote 7]
See, e.g., § 10 of the Administrative Procedure
Act, 60 Stat. 243, 5 U.S.C. § 1009; § 10 of the Fair
Labor Standards Act, 52 Stat. 1065, as amended, 29 U.S.C. §
210; § 10 of the National Labor Relations Act, 49 Stat. 453,
as amended, 29 U.S.C. § 160.
[
Footnote 8]
See, e.g., Senate Hearings,
supra, note 5 at 32-35 57-58.
[
Footnote 9]
The Government's citing
Needles v. United States, 101
Ct.Cl. 535, 606-607, suggests that, although the Court of Claims
did receive "live" evidence on such matters, it may not have
"consciously considered evidence not presented and not available to
the administrative officers making the final administrative
decision."
[
Footnote 10]
House Hearings,
supra, note 6 at 79-80
MR. JUSTICE DOUGLAS, with whom MR. JUSTICE STEWART concurs,
dissenting.
The petition to the Court of Claims alleged that changed
subsurface conditions required respondent to install permanent
tunnel protection by the use of steel arch ribs and steel liner
plates, that that work delayed completion of the project and
increased its cost, for which respondent should be reimbursed, and
that the decision of the Corps of Engineers in rejecting the claim
was "capricious" or "arbitrary."
The Wunderlich Act, 41 U.S.C. § 321, makes "final and
conclusive" any decision by a federal agency under customary
disputes clauses in government contracts with several exceptions
--
"unless the same is fraudulent or capricious or arbitrary or so
grossly erroneous as necessarily to imply bad faith, or is not
supported by substantial evidence."
I think the decision was "capricious or arbitrary" because
evidence was considered by the Appeals Board in making its decision
which the claimant did not see, and which he had no opportunity to
refute. I therefore think that a
de novo hearing was
permissible before the Court of Claims.
The Board found that respondent, at the start, should have used
temporary protection against fall-ins, and that, had it done so,
permanent tunnel protection would not have been required. In
February, 1948, before the hearing, a letter from the Acting
District Engineer to the Chief of Engineers reported a conversation
the Corps' resident engineer for this project had had with an
expert from New York's Bureau of Mines. The only inference that
could be drawn from that report was that the expert believed that
the tunnel was in safe condition shortly after it was bored, and
that its later unsafe condition was caused by the fact that
respondent
"had not had the foresight
Page 373 U. S. 720
to gunite the exposed tunnel roof with cement as the excavation
progressed to seal it against air slacking [
sic]. . .
."
Somehow, in a manner not disclosed by the record, this letter
came into the hands of the Appeal Board, and was considered by it
before a decision was rendered on the appeal.
*
After the decision, respondent learned of this expert's alleged
statements and called him as a witness at the hearing before the
Court of Claims, where he testified on the basis of his inspection
that permanent, not temporary, protection against fall-ins was
necessary from the beginning. As respects the guniting of the
tunnel, one of the Government's own witnesses testified at the
hearing before the Court of Claims that it would have served no
useful purpose.
This issue -- whether only temporary protection was needed --
was one of the main issues in the case. When the agency making the
decision relies on evidence that the claimant has no chance to
refute, the hearing becomes infected with a procedure that lacks
that fundamental fairness the citizen expects from his Government.
Cf. Willner v. Committee on Character & Fitness, ante,
p.
373 U. S. 96;
Gonzales v. United States, 348 U.
S. 407;
Morgan v. United States, 304 U. S.
1.
This irregularity points up what Judge Madden, writing for the
Court of Claims, said in
Volentine & Littleton v. United
States, 145 F. Supp. 952, 954, 136 Ct.Cl. 638, 641-642:
". . . the so-called 'administrative record' is, in many cases,
a mythical entity. There is no statutory provision for these
administrative decisions or for
Page 373 U. S. 721
any procedure in making them. The head of the department may
make the decision on appeal personally, or may entrust anyone else
to make it for him. Whoever makes it has no power to put witnesses
under oath or to compel the attendance of witnesses or the
production of documents. There may or may not be a transcript of
the oral testimony. The deciding officer may, and even in the
departments maintaining the most formal procedures, does, search
out and consult other documents which, it occurs to him, would be
enlightening, and without regard to the presence or absence of the
claimant."
We are dealing, in other words, with subnormal administrative
procedures. While the regulations governing hearings before the
Corps of Engineers are published and provide many protective
features (33 CFR § 210.4), they lack some of the safeguards
normally accorded claimants in administrative proceedings. Thus,
they are specifically exempt from § 5 and from § 7 of the
Administrative Procedure Act. 5 U.S.C. §§ 1004, 1006. The
exemption from § 7 is highlighted in this case. That section
provides in part:
"Every party shall have the right to present his case or defense
by oral or documentary evidence, to submit rebuttal evidence, and
to conduct such cross-examination as may be required for a full
and true disclosure of the facts."
(Emphasis supplied.)
That provision, if applicable, would have made reliance by the
Board on the
ex parte hearsay statement of this outside
expert reversible error. Lax procedural standards may at times do
no harm. But where, as here, opinion evidence on the vital issue in
the case was obtained
ex parte, and where that evidence is
shown to have been false, the conclusion that the decision was
"capricious" or "arbitrary" seems to me unavoidable.
Page 373 U. S. 722
A remand to the agency to determine whether the agency's
decision is "capricious" or "arbitrary" seems obviously
inappropriate, since it is the court, not the agency, that should
determine that question. Since these administrative proceedings are
exempt from the protective provisions of § 7 of the
Administrative Procedure Act, there is no procedure whereby a
contractor can determine whether the agency's decision rested on
the testimony of "faceless" or secret witnesses, as in this case.
Like the case where a contractor seeks reformation of his contract
(
cf. Blake Constr. Co. v. United States, 111 U.S.App.D.C.
271, 296 F.2d 393), the only place he can get the hearing Congress
intended him to have on whether the decision was "capricious" or
"arbitrary" is in the courts.
* The letter also contained a statement to the effect that only
$9,000 was involved in the appeal. This figure was used in the
Board's opinion, but it was nowhere mentioned in the hearing or
record before the Board. In fact, the figure was grossly
inaccurate.