The schedule of minimum wage rates included in a government
construction contract, as required by the Davis-Bacon Act, 40
U.S.C. (1946 ed.) § 276a, is not a representation or warranty
by the Government to the contractor as to the wage rates prevailing
in the contract area, and the Secretary of Labor's action in
prescribing minimum wage rates lower than those actually prevailing
in the area when bids were invited on a construction project does
not give the contractor a valid claim against the Government. Pp.
347 U. S.
172-178.
(a) The purpose of the Act was not to benefit contractors, but
to protect their employees from substandard earnings by fixing a
floor under wages on government projects. Pp.
347 U. S.
176-177.
(b) The requirement of the Act and the contract thereunder that
the contractors pay wages at rates "not less than" those specified
is no assurance that they will not have to pay more. Pp.
347 U. S.
177-178.
(c) That the Act requires the minimum wage rates specified in
government contracts to be "based upon . . . the wages . . .
determined by the Secretary of Labor to be prevailing" in the area
where the work is to be performed does not require a different
result. Pp.
347 U. S.
177-178.
123 Ct.Cl. 804, 107 F. Supp. 712, reversed in part.
The Court of Claims awarded respondent a recovery based on the
difference between the minimum wage rate specified under 40 U.S.C.
(1946 ed.) § 276a in respondent's contract with the Government
and higher rates specified in a determination by the Secretary of
Labor for the Federal Works Agency. 123 Ct.Cl. 804, 107 F. Supp.
712. This Court granted certiorari. 346 U.S. 809.
Reversed as
to this point, p.
347 U. S.
178.
Page 347 U. S. 172
MR. CHIEF JUSTICE WARREN delivered the opinion of the Court.
This case is before us on writ of certiorari to the Court of
Claims. The question presented is whether the schedule of minimum
wage rates included in a Government construction contract, as
required by the Davis-Bacon Act, [
Footnote 1] is a representation or warranty as to the
prevailing wage rates in the contract area. We hold that it is
not.
The Davis-Bacon Act requires that the wages of workmen on a
Government construction project shall be "not less" than the
"minimum wages" specified in a schedule furnished by the Secretary
of Labor. The schedule "shall be based upon the wages that will be
determined by the Secretary of Labor to be prevailing" for
corresponding work on similar projects in the area. [
Footnote 2] The Act also provides
Page 347 U. S. 173
for penalties, including termination of the contract, if it is
found that the contractor is paying less than the schedule rate.
[
Footnote 3]
The respondent, a construction company, was the successful
bidder for a Government flood control project on the Chemung River
at Elmira, New York. On January 31, 1941 at the request of the
Corps of Engineers, the Secretary of Labor submitted a schedule of
minimum wages for the project. This schedule set the minimum hourly
wage rate at $1.00 for carpenters and $.50 for laborers. On March
29, 1941, the Corps of Engineers issued an invitation for bids.
[
Footnote 4] Pursuant to the
Davis-Bacon Act,
supra, the Secretary's wage schedule was
included in the contract specifications furnished to respondent,
prior to the computation of its bid. [
Footnote 5] On May 14,
Page 347 U. S. 174
1941, respondent's bid of $232,669.30 was accepted and a written
contract was executed, incorporating the specifications and subject
only to formal approval by the Government. The contract provided
that respondent was to pay wages "not less than those stated in the
specifications . . . "; for breach of this provision, the
Government was authorized to terminate the contract. [
Footnote 6] On June 3, 1941, the contract was
formally approved, and on June 5, 1941, respondent received notice
to proceed with the work.
On October 22, 1940, the local carpenters' union had notified
the contracting officer that the hourly wage scale for carpenters
would be increased from $1.00 to $1.125 as of January 1, 1941. On
March 4, 1941, some three
Page 347 U. S. 175
weeks prior to the invitation for bids on the project involved
here, the Secretary of Labor had furnished another Government
agency, the Federal Works Agency, a schedule of minimum wages for
inclusion in the specifications for a federal housing project in
Elmira. This schedule set the minimum hourly wage rate at $1.125
for carpenters and $.55 for laborers. On April 1, 1941, the union
hourly rate for laborers was increased from $.55 to $.625.
In the performance of the contract, respondent paid the union
rates then in effect -- $1.125 for carpenters and $.625 for
laborers. On June 16, 1941, respondent protested to the contracting
officer that it was unable to obtain workmen at the rates specified
in the contract schedule, and demanded an adjustment of
compensation on the theory that the schedule was an affirmative
representation as to the prevailing wage rates in the area, and
that respondent was entitled to rely on this representation in the
computation of its bid. The contracting officer denied relief, and
the Chief of Engineers dismissed respondent's appeal. [
Footnote 7]
Respondent thereupon brought this action in the Court of Claims,
seeking damages for the alleged misrepresentation, as well as other
relief. The court specifically found that an investigation by
respondent would have revealed that the prevailing rates were
higher than the rates specified
Page 347 U. S. 176
in the schedule. [
Footnote
8] Nevertheless, it allowed respondent a recovery of $7,363.22,
consisting of the difference between the rates specified in the
contract schedule ($1.00 for carpenters and $.50 for laborers) and
the rates specified in the Secretary of Labor's determination for
the Federal Works Agency ($1.125 for carpenters and $.55 for
laborers). [
Footnote 9] The
court held that the contract schedule misrepresented -- although
inadvertently -- the prevailing wage rate in the Elmira area,
since, prior to the invitation to bid, the Secretary of Labor had
made a higher determination and the contracting officer could have
ascertained that fact. Respondent, the court held, was entitled to
rely on the schedule "as the Secretary's latest determination -- as
a representation of the wages it would have to pay when the work
was to be done." [
Footnote
10] We granted review [
Footnote 11] because of the obvious importance of the
decision in the administration of the Davis-Bacon Act.
The Act itself confers no litigable rights on a bidder for a
Government construction contract. [
Footnote 12] The language
Page 347 U. S. 177
of the Act and its legislative history plainly show that it was
not enacted to benefit contractors, but rather to protect their
employees from substandard earnings by fixing a floor under wages
on Government projects. [
Footnote 13] Congress sought to accomplish this result by
directing the Secretary of Labor to determine, on the basis of
prevailing rates in the locality, the appropriate minimum wages for
each project. The correctness of the Secretary's determination is
not open to attack on judicial review. [
Footnote 14]
The Court of Claims nevertheless awarded respondent damages on
the ground that the Government, through the Corps of Engineers, had
falsely represented the prevailing rates in the Elmira area. The
short answer to this is that the Government made no such
representation. Neither the contract nor the specifications refers
to "prevailing" rates. The contract speaks only of "wage rates not
less than those stated in the specifications." [
Footnote 15] The specifications, in turn,
speak only of "minimum wage rates applicable in the locality."
[
Footnote 16] The only
reference to "prevailing" rates appears in the statute itself,
which provides that the minimum wage rates are to be "based upon
the wages . . . determined by the Secretary of Labor to be
prevailing." But this provision in the Act cannot convert
Page 347 U. S. 178
the contractor's obligation to pay not less than the minimum
into a Government representation that the contractor will not have
to pay more. On its face, the Act is a minimum wage law designed
for the benefit of construction workers. The Act does not authorize
or contemplate any assurance to a successful bidder that the
specified minima will, in fact, be the prevailing rates. Indeed,
its requirement that the contractor pay "not less" than the
specified minima presupposes the possibility that the contractor
may have to pay higher rates. Under these circumstances, even
assuming a representation by the Government as to the prevailing
rate, respondent's reliance on the representation in computing its
bid cannot be said to have been justified.
The Government further contends that the Secretary of Labor was
justified in fixing different minimum rates for the housing and
flood control projects according to the degree of skill required by
each project, and that respondent is estopped to claim
misrepresentation because of its failure to make an investigation
of labor costs before submitting its bid. Because of our
disposition of the case, we find it unnecessary to reach these
issues. The portion of the judgment on which the Government sought
review is
Reversed.
[
Footnote 1]
Act of March 3, 1931, c. 411, § 1
et seq., 46
Stat. 1494, as amended by the Act of August 30, 1935, c. 825, 49
Stat. 1011, 40 U.S.C. §§ 276a-276a-5.
[
Footnote 2]
49 Stat. 1011, 40 U.S.C. § 276a:
". . . That the advertised specifications for every contract in
excess of $2,000, to which the United States or the District of
Columbia is a party, for construction, . . . of public buildings or
public works of the United States . . . which requires or involves
the employment of mechanics and/or laborers shall contain a
provision stating the minimum wages to be paid various classes of
laborers and mechanics which shall be based upon the wages that
will be determined by the Secretary of Labor to be prevailing for
the corresponding classes of laborers and mechanics employed on
projects of a character similar to the contract work in the city,
town, village, or other civil subdivision of the State . . . in
which the work is to be performed . . . ; and every contract based
upon these specifications shall contain a stipulation that the
contractor or his subcontractor shall pay all mechanics and
laborers employed directly upon the site of the work . . . the full
amounts accrued at time of payment, computed at wage rates not less
than those stated in the advertised specifications. . . ."
[
Footnote 3]
49 Stat. 1011, 40 U.S.C. § 276a-1.
[
Footnote 4]
The invitation provided in part:
"
Investigation of Conditions. -- Bidders are expected
to visit the locality of the work and to make their own estimates
of the facilities needed, the difficulties attending the execution
of the proposed contract, including local conditions, availability
of labor, uncertainties of weather, and other contingencies. In no
case will the Government assume any responsibility whatever for any
interpretation, deduction, or conclusion drawn from the examination
of the site. . . . Failure to acquaint himself with all available
information concerning these conditions will not relieve the
successful bidder of responsibility for estimating the difficulties
and costs of successfully performing the complete work."
[
Footnote 5]
The specifications contained the following provision:
"1-31.
Wage and Labor Provisions. (a) The Secretary of
Labor has determined the minimum wage rates applicable in the
locality for the labor classifications anticipated to be used on
the work. In accordance with Article 17 of the contract, employees
at the site shall be paid not less than these wages as listed
below:"
Designation Wage rate -- hourly
Carpenters, journeymen $1.00
* * * *
Laborers, unskilled 0.50
Laborers, concrete puddlers 0.50
[
Footnote 6]
Article 17 of the contract reads as follows:
"(
a) The contractor or his subcontractor shall pay all
mechanics and laborers employed directly upon the site of the work
. . . the full amounts accrued at time of payment, computed at wage
rates not less than those stated in the specifications. . . ."
"(
b) In the event it is found by the contracting
officer that any laborer or mechanic employed by the contractor or
any subcontractor directly on the site of the work covered by the
contract has been or is being paid a rate of wages less than the
rate of wages required by the contract to be paid as aforesaid, the
Government may, by written notice to the contractor, terminate his
right to proceed with the work or such part of the work as to which
there has been a failure to pay said required wages and prosecute
the work to completion by contract or otherwise, and the contractor
and his sureties shall be liable to the Government for any excess
costs occasioned the Government thereby."
[
Footnote 7]
The Chief of Engineers advised respondent:
"There is no authority in law for this office to question the
correctness of any determination made by the Secretary of Labor
pursuant to the provisions of the above cited act [the Davis-Bacon
Act]."
Later, in refusing to reconsider respondent's appeal, the Chief
of Engineers stated:
". . . The contract by Article 17 and by paragraph 1-31 of the
specifications provides that wages not less than those specified
shall be paid. The contract makes no representation as to the
availability of labor, nor as to the actual wage scales that would
be in effect. The alleged increased costs did not result from your
contract obligation, but from economic conditions which are
ordinary contingencies contemplated under the terms of the
contract."
[
Footnote 8]
123 Ct.Cl. 804, 810-811, 107 F. Supp. 712, 716:
"If plaintiff's president had investigated wage rates, he could
have ascertained that the prevailing rate for carpenters was $1.125
per hour, and that the prevailing rate for unskilled labor was $.55
per hour, with an advance to $.625 per hour, effective as of April
1, 1941. Also, before inviting bids on this project, the District
Engineer could have ascertained that the Secretary of Labor had
made a new determination of the prevailing wage rates for Elmira on
March 4, 1941."
[
Footnote 9]
On all other claims of respondent, the Court of Claims denied
recovery. That part of the court's judgment is the subject of
respondent's petition for writ of certiorari in No. 78, this Term.
[Certiorari denied,
post, p. 926.]
[
Footnote 10]
123 Ct.Cl. 804, 836-837, 107 F. Supp. 712, 731, relying on
Albert & Harrison, Inc. v. United States, 107 Ct.Cl.
292, 308-309, 68 F. Supp. 732,
cert. denied, 331 U.S.
810.
[
Footnote 11]
346 U.S. 809.
[
Footnote 12]
Compare 49 Stat. 1011, 40 U.S.C. § 276a-2(b),
conferring a right of action on employees to recover from the
contractor the amount due the employees under the minimum wage
schedule.
[
Footnote 13]
United States ex rel. Johnson v. Morley Const. Co., 98
F.2d 781, 788,
cert. denied, 305 U.S. 651;
Gillioz v.
Webb, 99 F.2d 585;
Winn-Senter Const. Co. v. United
States, 110 Ct.Cl. 34, 61, 75 F. Supp. 255;
cf. Perkins v.
Lukens Steel Co., 310 U. S. 113,
310 U. S. 128;
Endicott Johnson Corp. v. Perkins, 317 U.
S. 501,
317 U. S. 507.
See also H.R.Rep. No. 1756, 74th Cong., 1st Sess.;
S.Rep.No. 1155, 74th Cong., 1st Sess.; S.Rep.No. 1445, 71st Cong.,
3d Sess.
[
Footnote 14]
Alliance Const. Co. v. United States, 79 Ct.Cl. 730.
Cf., concerning the related Walsh-Healey Public Contracts
Act,
Perkins v. Lukens Steel Co., 310 U.
S. 113, and
Endicott Johnson Corp. v. Perkins,
317 U. S. 501.
[
Footnote 15]
See note 6
supra.
[
Footnote 16]
See note 5
supra.