Respondent oil company had contracts with three producers to
purchase gas for resale to a pipeline company which had applied to
the Federal Power Commission for a certificate of public
convenience and necessity under the Natural Gas Act. Each contract
provided for termination by the producer upon notice to the
respondent at any time after December 1, 1946, "but before the
issuance of such certificate." On November 30, 1946, the Commission
ordered that a certificate of public convenience and necessity be
issued to the pipeline company, upon specified terms and
conditions. The order was not made public until December 2, 1946,
on which day the producers severally notified respondent of the
termination of their contracts. Alleging that a certificate of
public convenience and necessity, "within the meaning of said
Natural Gas Act and said contracts," had been issued prior to the
attempt to terminate the contracts, respondent sued the three
producers in the Federal District Court under the Declaratory
Judgment Act for a declaration that the contracts were still "in
effect and binding upon the parties thereto." The decree of the
District Court that the contracts had not been effectively
terminated, and were still in full force and effect, was affirmed
by the Court of Appeals.
Held:
1. The matter in controversy as to which the respondent asked
for a declaratory judgment is not one that "arises under" the laws
of the United States, and since,.as to two of the defendant
producers, there was no diversity of citizenship, the proceedings
against them should have been dismissed for want of jurisdiction.
Pp.
339 U. S.
671-674.
(a) By the Declaratory Judgment Act, Congress enlarged the range
of remedies available in the federal courts, but did not extend
their jurisdiction. Pp.
339 U. S.
671-672.
(b) Where the existence of a federal question is the basis of
federal jurisdiction, such a federal question must be presented
Page 339 U. S. 668
by the plaintiff's claim itself, unaided by allegations in
anticipation of defenses which might be interposed. P.
339 U. S.
672.
2. There being diversity of citizenship in the case of the third
producer defendant, the District Court had jurisdiction of the suit
as to it. P.
339 U. S.
674.
(a) There being diversity of citizenship between respondent and
this defendant, and the venue being properly laid in the State
where the suit was brought, the case was properly in the District
Court. P.
339 U. S.
674.
(b) That the declaratory remedy which may be given by the
federal court may not be available in the state courts is
immaterial. P.
339 U. S.
674.
3. As to the third producer defendant, the judgment of the Court
of Appeals is vacated and the cause is remanded in order that the
Court of Appeals, either itself or by sending the case back to the
District Court, may further explore the issues through ways that
may be appropriate. Pp.
339 U. S.
674-679.
In a suit under the Federal Declaratory Judgment Act, the
District Court decreed that the contracts between respondent and
petitioners had not been terminated and remained in full force and
effect. The Court of Appeals affirmed. 174 F.2d 89. This Court
granted certiorari. 338 U.S. 846. As to one of the petitioners, the
judgment is vacated and the cause remanded; as to the other two
petitioners, the judgment is reversed with directions that the
cause be dismissed. P. 679.
Page 339 U. S. 669
MR. JUSTICE FRANKFURTER delivered the opinion of the Court.
In 1945, Michigan-Wisconsin Pipe Line Company sought from the
Federal Power Commission a certificate of public convenience and
necessity, required by § 7(c) of the Natural Gas Act, 52 Stat.
825, as amended, 15 U.S.C. § 717f(c), for the construction and
operation of a pipeline to carry natural gas from Texas to Michigan
and Wisconsin. A prerequisite for such a certificate is adequate
reserves of gas. To obtain these reserves, Michigan-Wisconsin
entered into an agreement with Phillips Petroleum Company on
December 11, 1945, whereby the latter undertook to make available
gas from the Hugoton Gas Field, sprawling over Kansas, Oklahoma,
and Texas, which it produced or purchased from others. Phillips had
contracted with petitioners, Skelly Oil Company, Stanolind Oil and
Gas Company, and Magnolia Petroleum Company, to purchase gas
produced by them in the Hugoton Field for resale to
Michigan-Wisconsin. Each contract provided that,
"in the event Michigan-Wisconsin Pipe Line Company shall fail to
secure from the Federal Power Commission on or before [October 1,
1946] a certificate of public convenience and necessity for the
construction and operation of its pipeline, Seller [a petitioner]
shall have the right to terminate this contract by written notice
to Buyer [Phillips] delivered to Buyer at any time after December
1, 1946, but before the issuance of such certificate."
The legal significance of this provision is at the core of this
litigation.
The Federal Power Commission, in response to the application of
Michigan-Wisconsin, on November 30, 1946, ordered that
"A certificate of public convenience and necessity be and it is
hereby issued to applicant [Michigan-Wisconsin], upon the terms and
conditions of this order,"
listing among the conditions that there be no transportation
Page 339 U. S. 670
or sale of natural gas by means of the sanctioned facilities
until all necessary authorizations were obtained from the State of
Wisconsin and the communities proposed to be served, that
Michigan-Wisconsin should have the approval of the Securities and
Exchange Commission for its plan of financing, that the applicant
should file for the approval of the Commission a schedule of
reasonable rates, and that the sanctioned facilities should not be
used for the transportation of gas to Detroit and Ann Arbor except
with due regard for the rights and duties of Panhandle Eastern Pipe
Line Company, which had intervened before the Federal Power
Commission, in its established service for resale in these areas,
such rights and duties to be set forth in a supplemental order. It
was also provided that Michigan-Wisconsin should have fifteen days
from the issue of the supplemental order to notify the Commission
whether the certificate "as herein issued is acceptable to it."
Finally, the Commission's order provided that, for purposes of
computing the time within which applications for rehearing could be
filed,
"the date of issuance of this order shall be deemed to be the
date of issuance of the opinions, or of the supplemental order
referred to herein, whichever may be later."
5 F.P.C. 953, 954, 956.
News of the Commission's action was released on November 30,
1946, but the actual content of the order was not made public until
December 2, 1946. Petitioners severally, on December 2, 1946, gave
notice to Phillips of termination of their contracts on the ground
that Michigan-Wisconsin had not received a certificate of public
convenience and necessity. Thereupon Michigan-Wisconsin and
Phillips brought suit against petitioners in the District Court for
the Northern District of Oklahoma. Alleging that a certificate of
public convenience and necessity "within the meaning of said
Natural Gas Act and said contracts" had been issued prior to
petitioners' attempt
Page 339 U. S. 671
at termination of the contracts, they invoked the Federal
Declaratory Judgment Act for a declaration that the contracts were
still "in effect and binding upon the parties thereto." Motions by
petitioners to have Michigan-Wisconsin dropped as a party plaintiff
were sustained, but motions to dismiss the complaint for want of
jurisdiction were denied. The case then went to the merits, and the
District Court decreed that the contracts between Phillips and
petitioners have not been "effectively terminated, and that each of
such contracts remain [
sic] in full force and effect." The
Court of Appeals for the Tenth Circuit affirmed, 174 F.2d 89, and
we brought the case here, 338 U.S. 846, because it raises in sharp
form the question whether a suit like this "arises under the
Constitution, laws or treaties of the United States," 28 U.S.C.
§ 1331, so as to enable District Courts to give declaratory
relief under the Declaratory Judgment Act. 48 Stat. 955, as
amended, now 28 U.S.C. § 2201.
"[T]he operation of the Declaratory Judgment Act is procedural
only."
Aetna Life Ins. Co. v. Haworth, 300 U.
S. 227,
300 U. S. 240.
Congress enlarged the range of remedies available in the federal
courts, but did not extend their jurisdiction. When concerned as we
are with the power of the inferior federal courts to entertain
litigation within the restricted area to which the Constitution and
Acts of Congress confine them, "jurisdiction" means the kinds of
issues which give right of entrance to federal courts. Jurisdiction
in this sense was not altered by the Declaratory Judgment Act.
Prior to that Act, a federal court would entertain a suit on a
contract only if the plaintiff asked for an immediately enforceable
remedy like money damages or an injunction, but such relief could
only be given if the requisites of jurisdiction, in the sense of a
federal right or diversity, provided foundation for resort to the
federal courts. The Declaratory Judgment Act allowed relief to be
given by way of recognizing the plaintiff's
Page 339 U. S. 672
right even though no immediate enforcement of it was asked. But
the requirements of jurisdiction -- the limited subject matters
which alone Congress had authorized the District Courts to
adjudicate -- were not impliedly repealed or modified.
See
Great Lakes Dredge & Dock Co. v. Huffman, 319 U.
S. 293,
319 U. S. 300;
Colegrove v. Green, 328 U. S. 549,
328 U. S.
551-552.
If Phillips sought damages from petitioners or specific
performance of their contracts, it could not bring suit in a United
States District Court on the theory that it was asserting a federal
right. And for the simple reason that such a suit would "arise"
under the State law governing the contracts. Whatever federal claim
Phillips may be able to urge would, in any event, be injected into
the case only in anticipation of a defense to be asserted by
petitioners. "Not every question of federal law emerging in a suit
is proof that a federal law is the basis of the suit."
Gully v.
First National Bank, 299 U. S. 109,
299 U. S. 115;
compare 28 U.S.C. § 1257,
with 28 U.S.C.
§ 1331. Ever since
Metcalf v. Watertown, 128 U.
S. 586,
128 U. S. 589,
it has been settled doctrine that, where a suit is brought in the
federal courts
"upon the sole ground that the determination of the suit depends
upon some question of a federal nature, it must appear at the
outset, from the declaration or the bill of the party suing, that
the suit is of that character."
But
"a suggestion of one party that the other will or may set up a
claim under the Constitution or laws of the United States does not
make the suit one arising under that Constitution or those
laws."
Tennessee v. Union & Planters' Bank, 152 U.
S. 454,
152 U. S. 464.
The plaintiff's claim itself must present a federal question
"unaided by anything alleged in anticipation of avoidance of
defenses which it is thought the defendant may interpose."
Taylor v. Anderson, 234 U. S. 74,
234 U. S. 75-76;
Louisville & Nashville R. Co. v. Mottley, 211 U.
S. 149,
211 U. S.
152.
Page 339 U. S. 673
These decisions reflect the current of jurisdictional
legislation since the Act of March 3, 1875, 18 Stat. 470, first
entrusted to the lower federal courts wide jurisdiction in cases
"arising under this Constitution, the Laws of the United States,
and Treaties." U.S.Const. Art. III, § 2.
"The change is in accordance with the general policy of these
acts, manifest upon their face, and often recognized by this court,
to contract the jurisdiction of the circuit courts [which became
the District Courts] of the United States."
Tennessee v. Union & Planters' Bank, supra, at
152 U. S. 462.
See also Arkansas v. Kansas & Texas Coal Co.,
183 U. S. 185,
183 U. S. 188,
and
Gully v. First National Bank, supra, at
299 U. S.
112-114. With exceptions not now relevant, Congress has
narrowed the opportunities for entrance into the federal courts,
and this Court has been more careful than in earlier days in
enforcing these jurisdictional limitations.
See Gully v. First
National Bank, supra, at
299 U. S.
113.
To be observant of these restrictions is not to indulge in
formalism or sterile technicality. It would turn into the federal
courts a vast current of litigation indubitably arising under State
law, in the sense that the right to be vindicated was
State-created, if a suit for a declaration of rights could be
brought into the federal courts merely because an anticipated
defense derived from federal law. Not only would this unduly swell
the volume of litigation in the District Courts, but it would also
embarrass those courts -- and this Court on potential review -- in
that matters of local law may often be involved, and the District
Courts may either have to decide doubtful questions of State law or
hold cases pending disposition of such State issues by State
courts. To sanction suits for declaratory relief as within the
jurisdiction of the District Courts merely because, as in this
case, artful pleading anticipates a defense based on federal law
would contravene the whole trend of jurisdictional legislation
Page 339 U. S. 674
by Congress, disregard the effective functioning of the federal
judicial system, and distort the limited procedural purpose of the
Declaratory Judgment Act.
See Developments in the Law --
Declaratory Judgments -- 1941-1949, 62 Harv.L.Rev. 787, 802-803
(1949). Since the matter in controversy as to which Phillips asked
for a declaratory judgment is not one that "arises under the . . .
laws . . . of the United States," and since, as to Skelly and
Stanolind, jurisdiction cannot be sustained on the score of
diversity of citizenship, the proceedings against them should have
been dismissed.
As to Magnolia, a Texas corporation, a different situation is
presented. Since Phillips was a Delaware corporation, there is
diversity of citizenship. Magnolia had qualified to do business in
Oklahoma and appointed an agent for service of process in
accordance with the prevailing Oklahoma statute. Okla.Stat.Ann.
tit. 18, § 452. Magnolia claimed that the subject matter of
this proceeding did not arise in Oklahoma within the meaning of its
consent to be sued. This contention was rejected below, and we do
not reexamine the local law as applied by the lower courts. Under
the doctrine of
Neirbo Co. v. Bethlehem Shipbuilding
Corp., 308 U. S. 165,
venue was properly laid in Oklahoma; that the declaratory remedy
which may be given by the federal courts may not be available in
the State courts is immaterial.
Therefore, in the case of Magnolia, we must reach the merits.
They relate to two matters: (1) the clause in the contract with
Phillips permitting its termination at any time after December 1,
1946, but before the "issuance" of "a certificate of public
convenience and necessity" by the Federal Power Commission, and (2)
whether this provision was satisfied by Magnolia's notice of
termination of December 2, 1946, despite the Commission's order of
November 30, 1946. The phraseology "certificate of
Page 339 U. S. 675
public convenience and necessity" in the contract is identic
with the phrase in § 7(c) of the Natural Gas Act. The Court of
Appeals equated the term of the contract with that in the statute,
and in effect deemed its problem to be the proper construction of
what constitutes the "issuance" of a "certificate of public
convenience and necessity" within the meaning of § 7(c). So
viewing the matter, the court held that the order of November 30,
1946, satisfied the requirement of the contract, and that therefore
a certificate of public convenience and necessity had been issued
within the terminal period of the contract, and that its
termination was not timely.
It will be recalled that the order of November 30, 1946, had
three parts: (A) it stated that "A certificate of public
convenience and necessity be and it is hereby issued to applicant
Michigan-Wisconsin;" (B) it imposed certain conditions upon the
grant, some of which were to be set forth in a supplemental order,
and (C) it said that,
"For the purpose of computing the time within which applications
for rehearing may be filed, the date of issuance of this order
shall be deemed to be the date of the issuance of the opinions, or
of the supplemental order referred to herein, whichever may be the
later."
5 F.P.C. at 954, 956. The course of reasoning by which the Court
of Appeals concluded that the order of November 30, 1946, satisfied
the statutory requirement for a certificate of public convenience
and necessity can be briefly summarized. It relied on the
grammatical argument that the Commission used the present tense in
its order and subsequently referred to it as an order "issuing a
certificate of public convenience and necessity,"
e.g., 6
F.P.C. 1, 37; the conditional nature of the order was not deemed to
impair its efficacy, since § 7(e) of the Natural Gas Act
authorized the Commission
"to attach to the issuance of the certificate and to the
exercise of the rights granted thereunder such reasonable terms and
conditions as the public
Page 339 U. S. 676
convenience and necessity may require;"
and the provision of the order connecting the date of the
order's issuance with the time defined for securing a rehearing was
thought relevant only to the supplemental order.
We are not persuaded now to rest decision on the analysis of the
Court of Appeals which led to its conclusion. We need not linger
long on the merely grammatical argument of that court; it is given
more weight than it can bear. Of course, the Commission has
considerable administrative discretion to decide when an order may
fairly be deemed to have been "issued." Section 16 of the Act
provides that "Orders of the Commission shall be effective on the
date and in the manner which the Commission shall prescribe." But
surely a certificate cannot be said to have been issued for
purposes of defining rights and the seeking of reconsideration by
an aggrieved person if its substance is merely in the bosom of the
Commission. Knowledge of the substance must to some extent be made
manifest. Here, the content of the order of November 30, 1946, was
not made public until December 2, 1946, the date of the termination
notice.
The Commission itself, in its rule for computing rehearing time,
distinguishes between "adoption" of an order and its "issuance."
[
Footnote 1] However, as a
matter of
Page 339 U. S. 677
usage, the Commission has referred to an order as having
"issued" a certificate on a particular date when, in fact, the date
was that of "adoption."
See, e.g., Arkansas Louisiana Gas
Co., 5 F.P.C. 813, 897;
cf. Pacific Gas & Elec.
Co., 5 F.P.C. 824, 901. Finally, the restriction of the Court
of Appeals of the rehearing provision of Part C to the supplemental
order finds no support on the face of the order of November 30,
1946. There is nothing to indicate that Part C was not to apply to
the entire order for purposes of § 19 of the Act, which allows
a rehearing by a party aggrieved "within thirty days after the
issuance of such order," and makes such rehearing a prerequisite to
judicial review.
See 6 F.P.C. 323.
Since the requirements of the Natural Gas Act for the issuance
of "a certificate of public convenience and necessity" may be
distributive in scope, varying with the different contexts in which
the question must be examined, this is not the occasion to decide
that these requirements have a single uniform content. Whether the
statutory requirement here was satisfied is not a question of fact,
the finding of which by the District Court is to be respected
unless clearly erroneous. The District Court merely found that the
content of the piece of paper dated November 30, 1946, was that day
agreed upon in executive session of the Commission, and that that
fact was made known. But this leaves untouched the legal
significance of this action of the Commission, and the Court ought
not now in darkness to pronounce on this question.
We are not restricted to disposition of the controversy on so
truncated a treatment of the issues that underlie the record.
Considering the fact that so to dispose of the case
Page 339 U. S. 678
would involve determination of an important problem concerning a
regulatory statute with implications of public importance that
private litigants naturally enough do not wholly represent and
that, on these matters neither the courts below nor this Court had
the benefit of the experience and illumination of the agency
entrusted with the enforcement of the Act, [
Footnote 2] the due administration of justice requires
that we should exercise our discretionary power in reviewing cases
to "require such further proceedings to be had as may be just under
the circumstances." 28 U.S.C. § 2106;
Honeyman v.
Hanan, 300 U. S. 14,
300 U. S. 25.
Accordingly, we think that the proper disposition requires that we
vacate the judgment as to Magnolia and remand the case in order
that the Court of Appeals either itself or by sending the case back
to the District Court can further explore, through ways that may be
appropriate, the issues which have been laid bare.
See Kennedy
v. Silas Mason Co., 334 U. S. 249.
The impact of the litigation both here and below was on the
proper construction of § 7(c). Even though the language of the
contract may be identic with that of § 7(c), this language in
the contract may have a scope independent of the proper
construction of § 7(c). The same words, in different settings,
may not mean the same thing.
Compare opinion of Mr.
Justice Holmes in
Towne v. Eisner, 245 U.
S. 418,
with his dissent in
Eisner v.
Macomber, 252 U. S. 189,
252 U. S. 219.
Parties do not necessarily endow statutory language in a contract
with the scope of the statute, particularly when the same term may
have variant meanings for different applications of the statute.
See Standard Oil Co. v.
Johnson, 316 U.S.
Page 339 U. S. 679
481,
316 U. S. 483.
Of course, the statutory meaning in the context of the entire
Natural Gas Act may not be irrelevant. In remanding the case, we do
not mean to foreclose this line of inquiry. [
Footnote 3]
In respect to Magnolia, the judgment of the Court of Appeals is
vacated and the cause remanded for further proceedings not
inconsistent with this opinion. As to Skelly and Stanolind, we
reverse the judgment with directions that the cause be
dismissed.
It is so ordered.
MR. JUSTICE BLACK agrees with the Court of Appeals, and would
affirm its judgment.
MR. JUSTICE DOUGLAS took no part in the consideration or
disposition of this case.
[
Footnote 1]
Rule 13(b) of the Commission's Rules of Practice and Procedure
provides:
"In computing any period of time involving the date of the
issuance of an order by the Commission, the day of issuance of an
order shall be the day the Office of the Secretary mails or
delivers copies of the order (full text) to the parties or their
attorneys of record, or makes such copies public, whichever be the
earlier. . . . The day of issuance of an order may or may not be
the day of its adoption by the Commission."
18 C.F.R. § 1.13(b). A deposition taken of the Secretary of
the Commission gave light on this point. The Commission's previous
rule on rehearing time is in 18 C.F.R. Cum.Supp. § 50.75.
Rule 13(c) provides: "Orders of the Commission shall be
effective as of the dates of issuance unless otherwise specifically
provided in the orders." 18 C.F.R. § 1.13(c). This provision
may be of significance if the effectiveness of a certificate is an
issue in proceedings under §§ 20 or 21 of the Act. The
Court of Appeals did not discuss the bearing of these rules upon
this case.
[
Footnote 2]
The significance of the conditions in qualifying what is
formally called a "certificate" in the order of November 30, 1946,
is precisely one of those matters upon which Commission practice
and experience may shed helpful light.
[
Footnote 3]
In its conclusions of law, the District Court stated:
"The certificate issued by the Commission to Michigan-Wisconsin
on November 30, 1946, although containing terms and conditions, was
and is a certificate issued under the requirements of the Natural
Gas Act, and one that is provided for by that act. A consideration
of the contracts between plaintiff and defendants, together with
the contract between plaintiff and Michigan-Wisconsin, compels a
conclusion that such certificate was one within the contemplation
of the parties, and satisfied the terms of the contracts."
The context suggests that, in the second sentence the District
Court may still have been focusing upon statutory meaning.
MR. CHIEF JUSTICE VINSON, with whom MR. JUSTICE BURTON joins,
dissenting in part.
I concur in that part of the Court's judgment that directs
dismissal of the cause as to Skelly and Stanolind. I have real
doubts as to whether there is a federal question here at all, even
though interpretation of the contract between private parties
requires an interpretation of a federal statute and the action of a
federal regulatory
Page 339 U. S. 680
body. But the Court finds it unnecessary to reach that question,
because it holds that the federal question, if any, is not a part
of the plaintiff's claim, and that jurisdiction does not therefore
attach. While this result is not a necessary one, I am not prepared
to dissent from it at this time.
But I am forced to dissent from the vacation and remand of the
cause in respect to Magnolia. I think that, as to this petitioner,
the judgment of the Court of Appeals should be affirmed. The Court
decides that the Court of Appeals erred in holding that the Federal
Power Commission had issued a certificate of public convenience and
necessity to Michigan-Wisconsin Pipe Line Company on November 30,
1946, despite the fact that, on that date, the Commission adopted
an order stating that
"A certificate of public convenience and necessity should be,
and it is hereby, issued to Applicant, upon the terms and
conditions of this order. . . ."
This disregard for what the District Court found to be the
Commission's express intention is based upon two alternative
grounds. First, it is suggested that, while the order issuing the
certificate was "adopted" on November 30, it was not "issued" until
December 2. Second, it is said that Part C of the November 30
order, which concerned the date of issuance of the order for
purposes of applications for rehearing, precludes a finding that a
certificate was issued on November 30. Neither of these grounds, in
my judgment, supports the Court's conclusion.
As to the first, which was not argued here nor in the Court of
Appeals, it is true that the Commission's rules provide that an
order is not to be deemed "issued" until the full text is
mimeographed and mailed to the parties to the proceeding. This
usually follows within two or three days after the order is
"adopted." The only purpose of the postponement of the date of
issuance of the
Page 339 U. S. 681
order, so far as we are informed, is to postpone the running of
the 30-day period for applications for rehearing until the full
text is available to the parties who have standing to ask for
rehearing.
But the Commission uniformly refers to the date of adoption of
the order as the date upon which the certificate of public
convenience and necessity was "issued." [
Footnote 2/1] It did so in this case when, on March 12,
1947, it issued a supplemental order referring to its "order of
November 30, 1946, issuing a certificate of public convenience and
necessity." Furthermore, the District Court found as a fact
that,
"On November 30, a Saturday, the Commission in executive session
made an order granting, with conditions, a certificate of public
convenience and necessity to the Michigan-Wisconsin Pipe Line
Company. During this session, as the members of the Commission came
to agreement as to the wording of the order, Mr. Fuquay, the
secretary of the Commission, prepared the order in full and exact
text. The secretary was directed by the Commission to release the
order immediately."
Following adjournment on that day, the secretary sent a telegram
to the parties to the proceeding, informing them that the
"Commission today . . . adopted Opinion and Order, in Docket No.
G.-669, issuing certificate, with conditions, to Michigan-Wisconsin
Pipe Line Company."
On the same day, releases to the press were made announcing the
action taken by the Commission.
Skelly, Stanolind, and Magnolia were not parties to this
proceeding. It may very well be that the date of issuance of the
order granting the certificate is December
Page 339 U. S. 682
2 or some later date -- for purposes of rehearing upon
application of the parties. But I think there is no question that
the certificate, as distinguished from the order, was issued on
November 30. That is the Commission's view, as indicated by its
supplemental order. The fact that it takes a few days to get its
orders mimeographed and the Commission has adopted a rule that, in
fairness to the parties, the time for rehearing shall not begin to
run until such orders, in full text, are available, does not mean
that the issuance of the certificate is also held in abeyance until
that time.
The second argument requires but short answer. Part C provides
that
"For the purposes of computing time within which applications
for rehearing may be filed, the date of issuance of this order
shall be deemed to be the date of issuance of the opinions, or of
the supplemental order referred to herein, whichever may be
later."
The paragraph means just what it says. I do not understand the
Court to hold that the Commission cannot thus postpone the running
of the time for rehearing. Computation of that time, as I have
indicated, has no necessary relation to the date of issuance of the
certificate.
I think that the Commission intended to and did issue a
certificate of public convenience and necessity to
Michigan-Wisconsin Pipe Line Company on November 30, 1946, whatever
the date of its order, for purposes of computation of time for
rehearing. The crucial clause of the contract refers to "the
issuance of such certificate (of public convenience and
necessity)." By their inclusion of a provision dependent upon the
action of a federal agency, it is obvious that the parties intended
that the contract should be construed with reference to the
effective
Page 339 U. S. 683
date of agency action under the statutes and the practices of
the Commission. The District Court so concluded. [
Footnote 2/2] I can see no reason, therefore to
remand the cause for further proceedings. In my view, effective
agency action was taken on November 30, 1946. As to Magnolia, I
would affirm the judgment of the Court of Appeals.
[
Footnote 2/1]
See, e.g., Arkansas Louisiana Gas Co., 5 F.P.C. 813,
897;
Pacific Gas and Elec. Co., 5 F.P.C. 824, 901.
[
Footnote 2/2]
The District Court stated as one of its conclusions of law:
"The certificate issued by the Commission to Michigan-Wisconsin
on November 30, 1946, although containing terms and conditions, was
and is a certificate issued under the requirements of the Natural
Gas Act and one that is provided for by that act. A consideration
of the contracts between plaintiff and defendants, together with
the contract between plaintiff and Michigan-Wisconsin, compels a
conclusion that such certificate was one within the contemplation
of the parties, and satisfied the terms of the contracts."