The Fair Labor Standards Act applies to employees of a private
contractor operating a Government-owned munitions plant under a
cost plus a fixed fee contract with the Government. Pp.
339 U. S.
498-522.
1. Such employees are not employees of the United States within
the meaning of the Act. Pp.
339 U. S.
504-508.
2. Such employees are engaged in the production of goods for
commerce within the meaning of the Act. Pp.
339 U. S.
509-515.
(a) The "transportation" of munitions of the United States to
destinations outside of the state of their production is "commerce"
within the meaning of the Act, even though the munitions were
transported for use or consumption, and not for sale or exchange.
Pp.
339 U. S.
511-512.
(b) The munitions produced were "goods" within the meaning of
the Act, even though they were produced for delivery into the
actual physical possession of the United States as their ultimate
consumer. Pp.
339 U. S.
512-515.
3. The Fair Labor Standards Act and the Walsh-Healey Act of June
30, 1936, 41 U.S.C. §§ 35
et seq., are not
mutually exclusive, but are mutually supplementary. Pp.
339 U. S.
515-520.
4. Neither the Act of July 2, 1940, 50 U.S.C.App. §§
1171, 1172, nor the action of the Secretary of War taken pursuant
thereto excludes the applicability of the Fair Labor Standards Act
to such employees. Pp.
339 U. S.
520-522.
174 F.2d 718; 174 F.2d 730; 171 F.2d 964, reversed.
The facts and proceedings below are stated in the opinion at pp.
339 U. S.
499-504. The judgments below are
reversed, and the
causes remanded, p.
339 U. S.
522.
Page 339 U. S. 498
MR. JUSTICE BURTON delivered the opinion of the Court.
The question in each of these cases is whether the Fair Labor
Standards Act of 1938, as amended, [
Footnote 1] applies to a person employed, by a private
contractor at a Government-owned munitions plant operated by the
contractor under a cost plus a fixed fee contract made with the
United
Page 339 U. S. 499
States. We hold that the Act does apply, but we do not reach the
question of the validity of the individual claims based upon
it.
This issue was argued here in
Kennedy v. Silas Mason
Co., 334 U. S. 249. We,
however, remanded that case and withheld decision of the issue,
awaiting a more solid basis of findings. 334 U.S. at
334 U. S. 257.
Each of the instant cases presents such a basis.
No. 96 (The Powell Case).
In December, 1940, the United States contracted with The United
States Cartridge Company, respondent herein, as "an independent
contractor and in no wise an agent of the Government" on a cost
plus a fixed fee basis to operate the Government's St. Louis
Ordnance Plant in Missouri. [
Footnote 2] The contract stated that it was authorized by
the Act of July 2, 1940. [
Footnote
3] It provided that the respondent would operate the
Government's plant for the manufacture of certain types and
quantities of small arms ammunition, that the Government would
reimburse the
Page 339 U. S. 500
respondent for its expenditures in such operation and, in
addition, pay the respondent a fixed fee based upon the types and
quantities of ammunition it supplied. The title to the site, plant,
equipment and, in general, to the raw material, work in progress,
and finished munitions was to be in the Government. [
Footnote 4] Most of the materials were to be
supplied by the Government. The contract provided expressly for the
reimbursement of the respondent's expenses for labor. The
respondent, in turn, agreed to supply practically all services
incident to the setting up of an efficient operating force and to
the operation of the plant until the required ammunition had been
produced. The respondent was made responsible for storing the
materials, supplies, and finished ammunition, and for loading the
ammunition on cars or other carriers in accordance with the
Government's instructions. The ammunition generally was shipped by
common carrier on Government bills of lading to military
destinations outside of Missouri. The Government reserved large
rights of supervision, auditing, and inspection, to be exercised
through its "Contracting Officer." The employees, including the
petitioners, were to be hired, assigned, directed, supervised,
paid, and discharged by the respondent.
Page 339 U. S. 501
The contract stated expressly that all persons engaged in the
work "shall be subject to the control and constitute employees of
the Contractor. . . ." It quoted all of the "representations and
stipulations" relating to employment directed by the Walsh-Healey
Act. [
Footnote 5] Under it, the
contracting officer (subject to a right of appeal) could require
the respondent to dismiss any employee whom he deemed incompetent
or whose retention "is deemed" not to be in the public interest.
The contract made no express reference to the Fair Labor Standards
Act. However, in a booklet which was distributed by the respondent,
each employee at the St. Louis Ordnance Plant was informed, among
other things, that
"There will be eight hours in any working day, and forty hours
will constitute a working week. . . . When production demands
require a longer work day, or longer work week, the Company will
pay the legal overtime rate
as provided under the Walsh-Healey
Act and the Fair Labor Standards Act."
(Emphasis supplied.)
The 59 individual petitioners were employed in the safety
department of the plant. They alleged that, under the Fair Labor
Standards Act, they were entitled to overtime pay which they had
not received. They sued in the United States District Court for the
Eastern District of Missouri to recover that pay, plus liquidated
damages and an attorney's fee. The respondent denied liability on
many grounds, including those that the Fair Labor Standards Act did
not apply to employees at the St. Louis Ordnance Plant and that, in
any event, these petitioners were not entitled to any recovery
under that Act. After trial, the District Court entered judgment in
favor of the petitioners for the total sum of $246,251.44 (twice
the amount of the overtime pay claimed), plus $24,625 as an
attorney's
Page 339 U. S. 502
fee and costs. The respondent moved for a new trial so that the
Portal-to-Portal Act of 1947, [
Footnote 6] which had been adopted five days before the
District Court's judgment, might be applied to the issues. The
motion was denied, and the case was appealed. While the appeal was
pending in the United States Court of Appeals for the Eighth
Circuit, the decision of this Court in
Kennedy v. Silas Mason
Co., supra, was announced. The Court of Appeals thereupon
heard a reargument of this case with special reference to the
issues raised in the
Silas Mason case. Sitting en banc, it
reversed the District Court and held that the Fair Labor Standards
Act did not apply to employment at the St. Louis Ordnance Plant.
174 F.2d 718. All seven judges held that the Walsh-Healey Act
applied to such employment to the exclusion of the Fair Labor
Standards Act. Four of those judges also joined in an opinion (p.
726) stating that the Act of July 2, 1940, had given discretion to
the Secretary of War to determine what overtime regulations should
be applicable to Government-owned privately operated plants, and
that, through his adoption of the Walsh-Healey Act, he had rendered
the Fair Labor Standards Act inapplicable under this contract. The
Court of Appeals did not reach the merits of the individual claims
of the petitioners under the Fair Labor Standards Act. We granted
certiorari. 338 U.S. 810.
No. 79 (The Aaron Case)
This case presents substantially the same issue as that in the
Powell case, but it relates to employees at the Arkansas Ordnance
Plant. The issue arises on a summary judgment of the United States
District Court for the Eastern District of Arkansas in favor of the
respondent, rendered on pleadings, supporting affidavits,
admissions
Page 339 U. S. 503
of fact, and answers to interrogatories. The plant was operated
by the respondent under a cost plus a fixed fee contract entered
into with the United States in July, 1941, and generally
comparable, for present purposes, with that, in the
Powell
case. The petitioners, 1,278 in number, were handlers, carriers,
and processors of explosives, who claimed additional compensation
under the Fair Labor Standards Act for approximately 35 minutes
before, and 30 minutes after, their scheduled work in the plant.
The respondent answered and moved for summary judgment on three
grounds -- that the petitioners were not engaged in the kind of
work that is covered by the Fair Labor Standards Act, that they are
not within the coverage of the Act because they were employees of
the United States, and that, by virtue of the Portal-to-Portal Act
of 1947, they are not entitled to recover in any event.
In rendering judgment for the respondent, the District Court
adopted its opinion in
Barksdale v. Ford, Bacon &
Davis, 70 F. Supp.
690. Without passing on other contentions, it there held that
the Fair Labor Standards Act was not applicable because, in
processing and assembling munitions under like conditions, the
respondent had not been engaged "in the production of goods for
commerce" within the meaning of that Act. The Court of Appeals for
the Eighth Circuit affirmed, 174 F.2d 730, on authority of its
decision in the
Powell case,
supra. We granted
certiorari. 337 U.S. 955.
No. 58 (The Creel Case)
This case, from the Fifth Circuit, presents substantially the
same issue as do the
Powell and
Aaron cases. The
issue arises on a summary judgment in favor of the respondent,
rendered by the United States District Court for the Eastern
District of Texas on pleadings and supporting affidavits. Here, the
Lone Star Ordnance Plant,
Page 339 U. S. 504
near Texarkana, Texas, was owned by the Government and operated
by the respondent under a cost plus a fixed fee contract entered
into with the United States in July, 1941, comparable in its
material features to those in the
Powell and
Aaron cases. The petitioners, several hundred in number,
were employed at the plant in capacities such as those of truck
drivers, lift-fork operators, loaders, and unloaders. Their
services were used in the production of munitions, such as shells,
bombs, detonators, and other ordnance items. The title to
substantially all of the raw material, work in progress, and
finished products was in the Government. Most of the materials were
furnished by the Government, and the finished products were shipped
in accordance with Government instructions on Government bills of
lading to military destinations, usually outside of Texas. The
petitioners sued for overtime pay claimed to be due them under the
Fair Labor Standards Act. Quoting from the opinion of the District
Court in the
Barksdale case,
supra, the trial
court gave judgment for the respondent. The Court of Appeals for
the Fifth Circuit affirmed. 171 F.2d 964. It stated that the
respondent, on the record before it, was an agency of the
Government, was not an independent contractor, and was not engaged
in commerce within the meaning of the Fair Labor Standards Act. We
granted certiorari. 337 U.S. 923. We heard this case with the
Powell and
Aaron cases.
The United States filed a brief and argued here, as
amicus
curiae, in support of the petitioners on the limited issue now
before us.
I
. THE PETITIONERS WERE NOT EMPLOYEES OF THE UNITED STATES
WITHIN THE MEANING OF THE FAIR LABOR STANDARDS ACT
If the petitioners were employees of the United States, the Fair
Labor Standards Act excludes them from its
Page 339 U. S. 505
coverage. [
Footnote 7] A
similar defense is presented through the claim that the respondents
were not independent contractors, but were agencies of the United
States, representing and binding the United States as their
principal in the employment of petitioners.
In each contract, there was a provision comparable to the
following quoted from the contract in the
Powell case:
"Article I-E-Authority of the Contractor."
"In carrying out the work under this Title I, the Contractor is
authorized to do all things necessary or convenient in and about
the operating and closing down of the Plant, or any part thereof,
including (but not limited to)
the employment of all persons
engaged in the work hereunder (who shall be subject to the control
and constitute employees of the Contractor). . . ."
(Emphasis supplied.)
Each contract is replete with references to the persons employed
as the "employees of the Contractor" or "persons employed by the
Contractor."
The contract in the
Powell case contained the following
additional clause:
"Article III-A -- Status of Contractor."
"It is expressly understood and agreed by the Contractor and the
Government that, in the performance of the work provided for in
this contract,
the Contractor is an independent contractor, and
in no wise an agent of the Government."
(Emphasis supplied.)
Page 339 U. S. 506
Such provisions are persuasive that the petitioners should be
recognized here as employees of the respective respondents, and the
respondents as independent contractors. The respondents argue,
however, that the context of the times, other provisions of the
contracts, and the practice under the contracts deprive these
statements of their ordinary meaning. We find, on the contrary,
that each of these sources supplies additional evidence that these
provisions correctly state the true relationship between the
petitioners and respondents.
For example, we find in these contracts a reflection of the
fundamental policy of the Government to refrain, as much as
possible, from doing its own manufacturing and to use, as much as
possible (in the production of munitions), the experience in mass
production and the genius for organization that had made American
industry outstanding in the world. [
Footnote 8] The essence of this policy called for private,
rather than public, operation of war production plants. This
purpose shines through the following clause in the contract in the
Powell case:
"Whereas, The Government
desires to have the Contractor, as
an independent contractor on a cost plus a fixed fee basis, make
all necessary preparations for the operation of said plant,
including the training of operating personnel . . . but
excluding the procurement and supervision of the installation of
manufacturing facilities (to be done, under a like contract, by the
contractor's parent corporation, Western Cartridge Company),
and operate said plant. . . ."
(Emphasis supplied.)
It would have been simple for the Government to have ordered all
of this production to have been done under governmental
Page 339 U. S. 507
operation as well as under governmental ownership. To do so,
however, might have weakened our system of free enterprise. We
relied upon that system as the foundation of the general industrial
supremacy upon which ultimate victory might depend. In this light,
the Government deliberately sought to insure private operation of
its new munitions plants.
In these great projects built for and owned by the Government,
it was almost inevitable that the new equipment and materials would
be supplied largely by the Government, and that the products would
be owned and used by the Government. It was essential that the
Government supervise closely the expenditures made and the
specifications and standards established by it. These incidents of
the program did not, however, prevent the placing of managerial
responsibility upon independent contractors.
The relationship of employee and employer between the worker and
the contractor appears not only in the express terminology that has
been quoted. It appears in the substantial obligation of the
respondent contractors to train their working forces, make job
assignments, fix salaries, meet payrolls, comply with state
workmen's compensation laws and Social Security requirements, and
"to do all things necessary or convenient in and about the
operating and closing down of the Plant. . . ." [
Footnote 9]
Page 339 U. S. 508
The insertion in each of these contracts of the representations
and specifications that are set forth in the Walsh-Healey Act was,
in itself, a recognition by the Secretary of War of the independent
contractor status of the respondents.
The petitioner employees and the Government expressly disavow,
in their briefs, any employment relationship between them. The
managerial duties imposed upon the respondents were the duties of
employers. That such duties be performed by private contractors was
a vital part of the Government's general production policy. In the
light of these considerations, we conclude that the respective
respondents, in form and in substance, were the employers of these
petitioners within the meaning of the Fair Labor Standards Act.
[
Footnote 10]
Page 339 U. S. 509
II
. PETITIONERS WERE ENGAGED IN THE PRODUCTION OF GOODS
FOR COMMERCE WITHIN THE MEANING OF
THE FAIR LABOR STANDARDS ACT
Before discussing the definitions assigned by the Act to the
words "commerce" and "goods," it is helpful to examine the Act as a
whole in the light of the time of its adoption. It was adopted in
1938, during an industrial depression. It expressly stated its
purposes. [
Footnote 11] This
Court has further expounded them. [
Footnote 12] In this Act, the
Page 339 U. S. 510
primary purpose of Congress was not to regulate interstate
commerce as such. It was to eliminate, as rapidly as practicable,
substandard labor conditions throughout the nation. It sought to
raise living standards without substantially curtailing employment
or earning power.
Page 339 U. S. 511
Roland Electrical Co. v. Walling, 326 U.
S. 657,
326 U. S.
669-670. The Government's munitions plants provided an
appropriate place for the beneficial application of the Act's
standards of working conditions without danger of reduced
employment through loss of business. This Act would fail materially
in its purpose if it did not reach the producers of the tremendous
volume of wartime goods destined for interstate transportation. In
1941-1945, the manufacture of munitions was a major source of
employment. Wages and hours in that industry were a major factor in
fixing the living standards of American labor.
A.
The "transportation" of munitions of the United States to
destinations outside of the state of their production is "commerce"
within the meaning of the Act. The Act applies to "employees .
. . engaged in commerce or in the production of goods for
commerce." [
Footnote 13] The
precise question here is whether the munitions were produced for
"commerce" when such production was for transportation outside of
the state and for use by the United States in the prosecution of
war, but not for sale or exchange.
Section 3(b) of the Act contains the following definition of
"commerce":
"(b) 'Commerce' means trade, commerce,
transportation,
transmission, or communication among the several States or
from
any State to any place outside thereof."
(Emphasis supplied.) 52 Stat. 1060, 29 U.S.C. § 203(b).
Page 339 U. S. 512
This definition is an exercise by Congress of its constitutional
power "To regulate Commerce with foreign Nations, and among the
several States. . . ." U.S.Const. Art. I, § 8, Cl. 3. Such
power has been held repeatedly to include the power to regulate
interstate shipments or transportation as such, and not merely to
regulate shipments or transportation of articles that are intended
for sale, exchange or other trading activities. [
Footnote 14]
Congress could have expressly exempted from the Act employees
engaged in producing goods for interstate transportation not
leading to a sale or exchange. Congress also could have exempted
employees engaged in producing munitions for use by the United
States in war, rather than for sale or exchange by it. Congress
might even have exempted all employees producing goods in any
Government-owned plants. However, Congress stated no such
exemptions. On the contrary, Congress included, by express
definition of terms, employees engaged in the production of goods
for interstate transportation.
In view of these considerations, we find no merit in an
interpretation of the Act which would exclude from its coverage
those employees who were engaged in the production of munitions for
interstate transportation for use or consumption, as distinguished
from transportation of them for sale or exchange.
B.
The munitions produced were "goods" within the meaning of
the Fair Labor Standards Act. The respondents argue that, even
though the munitions were produced for commerce, they were not
"goods" within the meaning of the Act. Section 3(i) defines "Goods"
as follows:
Page 339 U. S. 513
"(i) 'Goods' means goods (including ships and marine equipment),
wares,
products, commodities, merchandise, or articles or
subjects of commerce of any character, or any part or ingredient
thereof, but
does not include goods after their delivery into
the actual physical possession of the ultimate consumer
thereof other than a producer, manufacturer, or processor
thereof."
(Emphasis supplied.) 52 Stat. 1061, 29 U.S.C. § 203(i).
Respondents claim that this language excludes the petitioners
from the coverage of the Act because the petitioners were engaged
in producing munitions which thereafter, and prior to their
interstate transportation, were to be delivered to the United
States as the ultimate consumer. This interpretation would deprive
the original jurisdictional fact -- that, at the time the munitions
were produced, they were intended for interstate transportation --
of its covering effect merely because those munitions, upon a later
delivery to the United States, would then cease to be "goods"
within the meaning of the Act.
We believe that the crucial fact which establishes the coverage
of the Act is the status of the munitions, as "goods," during the
time they were being produced. The literal meaning of the
exclusionary clause in § 3(i), and that which best serves the
purposes of the Act, is merely that, after the products shall have
been delivered into the actual physical possession of their
ultimate consumer, they then shall cease to be "goods." This
retains the important effect that, thereafter, it is not a
violation of § 15(a)(1) [
Footnote 15] for the ultimate consumer to transport
the
Page 339 U. S. 514
products outside of the state. This interpretation was adopted
by the Wage and Hour Administrator. 1940 WH Man. 131, 133. It was
readopted without change in the July, 1947, revision of the
Administrator's Interpretations. 12 Fed.Reg. 4585, 29 C.F.R. §
776.7(h). [
Footnote 16]
We hold, therefore, that the fact that the munitions were
produced for delivery, into the actual physical possession
Page 339 U. S. 515
of the United States as their ultimate consumer, before their
subsequent interstate shipment, does not deprive the employees who
produced the munitions of the benefits of the Fair Labor Standards
Act. It is not material whether such interstate transportation was
to take place before or after the delivery of the munitions to the
United States. In either event, the employees were engaged in the
production of "goods" for "commerce." To hold otherwise would
restrict the Act not only arbitrarily, but also inconsistently with
its broad purposes.
III
. THE WALSH-HEALY ACT AND THE FAIR LABOR STANDARDS ACT
ARE NOT MUTUALLY EXCLUSIVE
The Walsh-Healey Act was adopted about one year after the
National Industrial Recovery Act [
Footnote 17] had been declared unconstitutional.
Schechter Poultry Corp. v. United States, 295 U.
S. 495. Seeking then to regulate wages and hours of
employees, the Walsh-Healey Act kept within a narrow field of
assured constitutionality. It prescribed that, in Government
contracts for the manufacture or furnishing of materials, supplies,
articles and equipment in any amount exceeding $10,000, the
contractor pay its employees not less than the minimum wages
determined by the Secretary of Labor to be the prevailing minimum
wages for persons employed on similar work in the locality. It
prescribed also that no such employees be permitted to work in
excess of eight hours in any one day or in excess of 40 hours in
any one week, [
Footnote
18]
Page 339 U. S. 516
that no male person under 16 years of age, no female person
under 18 years of age, and no convict labor be employed by the
contractor, and that no part of the contract be performed or any of
the material, supplies, articles, or equipment be manufactured or
fabricated under working conditions unsanitary, hazardous, or
dangerous to the health and safety of the employees.
The Fair Labor Standards Act of 1938 was passed nearly two years
later by the next Congress. It presented a different and broader
approach. It was not restricted to public contracts. The sponsor of
the bill stated that it was intended to carry out the suggestions
made by the President in his message to Congress. 81 Cong.Rec.
4960, 4961 (1937). In that message, the President said:
". . . to protect the fundamental interests of free labor and a
free people, we propose that only goods which have been produced
under conditions which meet the minimum standards of free labor
shall be admitted to interstate commerce. Goods produced under
conditions which do not meet rudimentary standards of decency
should be regarded as contraband, and ought not to be allowed to
pollute the channels of interstate trade."
The Act declared its purposes in bold and sweeping terms.
[
Footnote 19] Breadth of
coverage was vital to its mission. Its scope was stated in terms of
substantial universality amply broad enough to include employees of
private contractors
Page 339 U. S. 517
working on public projects as well as on private projects. Where
exceptions were made, they were narrow and specific. It included as
employees "any individual employed by an employer," § 3(e),
and defined an employer so as amply to cover an individual or
corporation employing persons on public contracts, while expressly
excluding, as an employer, "the United States or any State or
political subdivision of a State. . . ." § 3(a) and (d). It
devoted § 13 to listing exemptions of specific classes of
employees. For example, it exempted any seaman, any employee of a
carrier by air subject to Title II of the Railway Labor Act, and
any employee employed in agriculture. It exempted certain employees
under § 204 of the Motor Carrier Act, 1935, [
Footnote 20] but limited their exemption to
the maximum hour provisions in § 7. It also exempted any
employee of an employer subject to Part I of the Interstate
Commerce Act. Such specificity in stating exemptions strengthens
the implication that employees not thus exempted, such as employees
of private contractors under public contracts, remain within the
Act.
The Act includes the following affirmative statement as to the
relation of its provisions to other laws:
"
RELATION TO OTHER LAWS"
"SEC. 18. No provision of this Act or of any order thereunder
shall excuse noncompliance with any Federal or State law or
municipal ordinance establishing a minimum wage higher than the
minimum wage established under this Act or a maximum work week
lower than the maximum work week established under this Act, and no
provision of this Act relating to the employment of child labor
shall justify noncompliance
Page 339 U. S. 518
with any Federal or State law or municipal ordinance
establishing a higher standard than the standard established under
this Act. No provision of this Act shall justify any employer in
reducing a wage paid by him which is in excess of the applicable
minimum wage under this Act, or justify any employer in increasing
hours of employment maintained by him which are shorter than the
maximum hours applicable under this Act."
52 Stat. 1069, 29 U.S.C. § 218.
The above language discloses a congressional awareness that the
coverage of the Fair Labor Standards Act overlaps that of other
federal legislation affecting labor standards. In other enactments,
we find collateral recognition that the Walsh-Healey Act might
apply to the same employment as the Fair Labor Standards Act. An
amendment to the Walsh-Healey Act in 1942 recognized this
possibility. [
Footnote 21]
Similarly, the Portal-to-Portal Act of 1947 indicated that persons
employed by Government contractors, and thus protected by the
Walsh-Healey Act, were entitled to the benefits of the Fair Labor
Standards Act. [
Footnote
22]
Page 339 U. S. 519
Despite evidence that the two statutes define overlapping areas,
respondents contend that they should be construed as being mutually
exclusive. There has been no presentation of instances, however,
where compliance with one Act makes it impossible to comply with
the other. There has been no demonstration of the impossibility of
determining in each instance the respective wage requirements under
each Act, and then applying the higher requirement as satisfying
both.
The Government has presented, as a considered analysis of the
overlapping effects of these Acts, excerpts from the Manual of
Instructions for the Administration of Contracts (War Department,
Office of the Chief of Ordnance, 1941). These are published in the
appendix to the brief of the United States. Their forthright
treatment and detailed suggested solutions of the practical aspects
of the supplementary use of the two Acts are impressive.
In some, and probably most, instances, the "prevailing minimum
wages" required by the Walsh-Healey Act were more advantageous to
employees than the minimum wages prescribed by the Fair Labor
Standards Act at the times here under review. [
Footnote 23] On the other hand, the remedial
procedure under the later Act was generally more advantageous to
employees than the procedure under the earlier Act.
We conclude that the Acts are not mutually exclusive. The
applicability of the Walsh-Healey Act to the contracts
Page 339 U. S. 520
before us therefore does not preclude the application of the
Fair Labor Standards Act to employees under the same contracts. We
find the Acts to be mutually supplementary.
IV
. NEITHER THE ACT OF JULY 2, 1940, NOR THE ACTION OF THE
SECRETARY OF WAR TAKEN PURSUANT TO IT EXCLUDES THE
APPLICABILITY OF THE FAIR LABOR STANDARDS ACT
We find in the Act of July 2, 1940, [
Footnote 24] no such recognition of the uniqueness of
War Department contracts for the private operation of
Government-owned munitions plants as is claimed in the concurring
opinion below in the
Powell case. [
Footnote 25] Without more specific provisions
than this Act contains, we cannot interpret it as excluding, or as
granting, authority to executive officers to exclude, employees in
such plants from the benefits of the general wage and hour
provisions which Congress has established in the Walsh-Healey Act
and more fully and recently in the Fair Labor Standards Act.
The purposes of this temporary Act of 1940 were the
clarification of the contract-making authority of the War
Department under existing general law, with such exceptions as were
expressly noted, the elimination of certain hazards, and the making
of additional grants of emergency authority to the President. For
example, this Act referred expressly to the Walsh-Healey Act as
applicable to the new War Department contracts when entered into
with or without advertising. This was helpful because, when the
Walsh-Healey Act was adopted, the contracts to which it applied did
not include contracts negotiated without advertising for
competitive bids. Similarly, the 1940 Act expressly suspended
certain specific limitations on the War Department,
e.g.,
requirements of the congressional
Page 339 U. S. 521
approval of estimates and the making of appropriations prior to
undertaking construction of certain buildings, § 1(a),
restrictions on leasing, § 1(b), restrictions on the
assignment of personnel, § 2(b), limitations on the number of
serviceable aircraft, § 3, and restrictions as to civil
service employees (§ 4(a)). No suggestion was made of a
suspension of part or all of the Fair Labor Standards Act, nor was
anything authorized that would violate that Act.
The single reference made in the 1940 Act to the Walsh-Healey
Act was to insure the applicability of the latter Act to negotiated
contracts. This appears from the following revealing statement made
on the floor of the Senate by Senator Wagner, the author of the
amendment containing the reference:
"A question has arisen --
and the amendment is simply to
remove the ambiguity -- as to whether the Walsh-Healey Act,
which is now definitely applicable to a contract for the purchase
of supplies as a result of advertising, will also apply to a
negotiated contract. . . ."
". . . Unless this amendment is adopted, we would have this
anomalous situation: under a contract entered into with the
Government as the result of public bidding, one set of minimum
wages, that is, the prevailing wages [under the Walsh-Healey Act]
would be applied, whereas, under another contract entered into as a
result of negotiations,
a much lower minimum wage would be
paid, that is, the flat minimum under the Wage and Hour Act
[the Fair Labor Standards Act]. This situation would present an
opportunity for exploitation, since a contractor under a negotiated
contract might be paying wages in some instances 25 percent to 75
percent below those required under the Healey-Walsh Act. I am sure
that we would not want to invite any such exploitation."
(Emphasis supplied.) 86 Cong.Rec. 7924 (1940).
Page 339 U. S. 522
See also 86 Cong.Rec. 7839-7843, and H.R.Rep. No.2685,
76th Cong., 3d Sess. 1 (1940).
We have considered the other contentions of the respondents,
including the weight to be given to the Statement of Labor Policy
issued by the War and Navy Departments in 1942, [
Footnote 26] but we do not find in them a
convincing refutation of the foregoing conclusions. We accordingly
find that the Fair Labor Standards Act of 1938, as amended, is
applicable to the issues presented in each of the instant cases. We
do not reach the validity of the individual claims of the
petitioners made in reliance upon that Act.
In No. 96,
Powell et al. v. The United States Cartridge
Company, the judgment of the Court of Appeals is reversed, and
the cause is remanded to that court for further consideration of
the errors asserted on appeal but not reviewed by that court.
In No. 79,
Aaron et al. v. Ford, Bacon and Davis, and
in No. 58,
Creel v. Lone Star Defense Corporation, the
judgments of the respective Courts of Appeals are reversed, and the
causes are remanded to the respective District Courts for further
proceedings in conformity with this opinion.
It is so ordered.
MR. JUSTICE DOUGLAS and MR. JUSTICE CLARK took no part in the
consideration or decision of any of these cases.
* Together with No. 79,
Aaron et al. v. Ford, Bacon &
Davis, Inc., on certiorari to the United States Court of
Appeals for the Eighth Circuit, and No. 58,
Creel et al. v.
Lone Star Defense Corp., on certiorari to the United States
Court of Appeals for the Fifth Circuit.
[
Footnote 1]
52 Stat. 1060
et seq., 53 Stat. 1266, 54 Stat. 615-616,
55 Stat. 756, 61 Stat. 87, 63 Stat. 446, 910-920, 29 U.S.C.
§§ 201-219, 29 U.S.C. (Supp. III) §§
201-217.
[
Footnote 2]
Congress charged the War and Navy Departments with the operation
of about 100 giant Government-owned munitions plants. Those
Departments had the option of operating them themselves or through
commercial contractors. So as to utilize fully the labor and
management resources of the nation and to minimize encroachment
upon its industrial structure, both Departments chose the latter
course. As to the general war production policies,
see Lichter
v. United States, 334 U. S. 742,
334 U. S.
767-768. Out of 143 billion dollars of contracts made by
the War Department between 1941 and 1946, over 40 billions were
cost-plus contracts. Out of 68 billion dollars of Navy contracts,
18 billions were cost-plus contracts. Hearings before Subcommittee
of the Senate Committee on the Judiciary on S. No. 70, 80th Cong.,
1st Sess. 422-423, 624-626 (1947). The quotation in the text is
from the contract in this case,
see p.
339 U. S. 505
infra.
[
Footnote 3]
54 Stat. 712-714, 50 U.S.C. App. §§ 1171, 1172.
[
Footnote 4]
Article III-F, 3 of the contract stated that:
"The title to all work under this contract, completed or in the
course of construction or manufacture, and to all the Ammunition
manufactured or in the process of being manufactured, shall be in
the Government. Likewise, upon delivery at the site of the work, or
at an approved storage site, title to all purchased materials,
tools, machinery, equipment, and supplies, for which the Contractor
shall be entitled to be reimbursed under Title II hereof, shall
vest in the Government. The Government shall bear all risk incident
to such ownership.
These provisions as to title's being vested
in the Government shall not operate however, to relieve the
Contractor from any duties imposed upon it under the terms of this
contract."
(Emphasis supplied.)
[
Footnote 5]
Adopted June 30, 1936, 49 Stat. 2036
et seq., 41 U.S.C.
§ 35
et seq.
[
Footnote 6]
61 Stat. 84-90, 29 U.S.C. (Supp. III) §§ 216,
251-262.
[
Footnote 7]
"SEC. 3. As used in this Act --"
"
* * * *"
"(d) 'Employer' includes any person acting directly or
indirectly in the interest of an employer in relation to an
employee but
shall not include the United States or any
State or political subdivision of a State. . . ."
"(e) 'Employee' includes any individual employed by an
employer."
(Emphasis supplied.) 52 Stat. 1060, 29 U.S.C. § 203(d) and
(e).
[
Footnote 8]
For a review of the development of the war production program
and its reliance on private industry,
see Lichter v. United
States, 334 U. S. 742,
334 U. S.
758-766.
[
Footnote 9]
If the workers were employees of the United States, state
workmen's compensation laws and other comparable laws would be
inapplicable. In the St. Louis and Arkansas Ordnance plants, the
contractor, in order to explain the relationships being
established, issued a booklet to each new employee. The manual thus
used at the St. Louis plant is entitled "Your Job with the St.
Louis Ordnance Plant." It opens with the statement "Every
prospective
employee of United States Cartridge Company
should read this booklet describing the Company's policy and
procedure." (Emphasis supplied.) It describes the relationship
between the United States Government, the company and "Our
Employees." For example, it says
"The Company . . . is responsible to the United States
Government for ammunition production, to the City of St. Louis in
maintaining a successful civic enterprise, and to our employees,
for the establishment of working conditions conducive to the health
and happiness of each man and woman employed in the plant."
It explains the financial basis of its cost-plus contract of
management as follows:
"In the final analysis, your wages come from the United States
Government, whose only source of income is taxes collected from you
and all other citizens. The United States Cartridge Company is
merely managing the plant for the Federal Government."
It adds that
"When production demands require a longer work day, or longer
work week, the Company will pay the legal overtime rate as provided
under the Walsh-Healey Act, and the Fair Labor Standards Act."
[
Footnote 10]
See the dissenting opinion of Circuit Judge Hutcheson
in
Kennedy v. Silas Mason Co., 164 F.2d 1016, 1019-1020,
the reasoning of which is in accord with our decision: "Here, the
whole elaborate system was designed and operated so that the United
States should not be the employer." 164 F.2d at 1020.
Cf. Curry
v. United States, 314 U. S. 14, and
Alabama v. King & Boozer, 314 U. S.
1. Those cases held that the contractors, under
Government cost plus a fixed fee contracts, were, as such, subject
to state use taxes and state sales taxes.
[
Footnote 11]
"SEC. 2. (a)
The Congress hereby finds that the existence,
in industries engaged in commerce or in the production of goods for
commerce, of labor conditions detrimental to the maintenance of the
minimum standard of living necessary for health, efficiency, and
general wellbeing of workers (1) causes commerce and the
channels and instrumentalities of commerce to be used to spread and
perpetuate such labor conditions among the workers of the several
States; (2) burdens commerce and the free flow of goods in
commerce; (3) constitutes an unfair method of competition in
commerce; (4)
leads to labor disputes burdening and obstructing
commerce and the free flow of goods in commerce, and (5)
interferes with the orderly and fair marketing of goods in
commerce."
"(b) It is hereby declared to be the policy of this Act, through
the exercise by Congress of its power to regulate commerce among
the several States, to correct and as rapidly as practicable to
eliminate the conditions above referred to in such industries
without substantially curtailing employment or earning power."
(Emphasis supplied.) 52 Stat. 1060, 29 U.S.C. § 202.
[
Footnote 12]
While one major means of spreading substandard labor conditions
was recognized to be through the lowering of prices for goods
produced under substandard conditions, there has been no attempt in
the Act, or in this Court's discussion of the Act, to limit its
coverage to employees engaged in producing goods solely for
competitive markets. An announced purpose of the Act was to raise
living standards and to eliminate
"labor conditions detrimental to the maintenance of the minimum
standard of living necessary for health, efficiency, and general
wellbeing of workers. . . ."
(§ 2(a),
see note 11 supra.) That purpose was concerned
directly with any widespread existence of substandard wages, hours,
or working conditions. That such conditions could be reached by
Congress through its regulation of interstate transportation of the
products of those conditions had been forcefully stated in the
dissent of Mr. Justice Holmes in
Hammer v. Dagenhart,
247 U. S. 251,
247 U. S.
277-281. In 1941, this Court expressly approved that
reasoning and upheld the constitutionality of the Fair Labor
Standards Act.
United States v. Darby, 312 U.
S. 100,
312 U. S.
115-117. The language of Mr. Justice Stone in speaking
for the Court in that case is significant. It extended to
interstate shipments and transportation of proscribed products in
general:
"While manufacture is not of itself interstate commerce, the
shipment of manufactured goods interstate is such commerce, and the
prohibition of such shipment by Congress is indubitably a
regulation of the commerce. . . . It is conceded that the power of
Congress to prohibit transportation in interstate commerce includes
noxious articles,
Lottery Case, supra,
[
188 U.S.
321];
Hipolite Egg Co. v. United States, 220 U. S.
45;
cf. 227 U. S. United States,
supra, [
227 U.S.
308]; stolen articles,
Brooks v. United States,
267 U. S.
432; kidnapped persons,
Gooch v. United States,
297 U. S.
124, and articles such as intoxicating liquor or convict
made goods, traffic in which is forbidden or restricted by the laws
of the state of destination.
Kentucky Whip & Collar Co. v.
Illinois Central R. Co., 299 U. S. 334."
"
* * * *"
"Whatever their motive and purpose, regulations of commerce
which do not infringe some constitutional prohibition are within
the plenary power conferred on Congress by the Commerce Clause.
Subject only to that limitation, . . . we conclude that the
prohibition of the shipment interstate of goods produced under the
forbidden substandard labor conditions is within the constitutional
authority of Congress."
"
* * * *"
"The obvious purpose of the Act was not only to prevent the
interstate transportation of the proscribed product, but to stop
the initial step toward transportation, production with the purpose
of so transporting it."
United States v. Darby, supra, at
312 U. S. 113,
312 U. S. 115,
312 U. S.
117.
For further legislative history of the Act,
see Roland
Electrical Co. v. Walling, 326 U. S. 657,
326 U. S.
668-669, n. 5.
[
Footnote 13]
"SEC. 6. (a) Every employer shall pay to each of his employees
who is engaged in commerce or in the production of goods for
commerce [certain minimum wages]. . . ."
"SEC. 7. (a) No employer shall, except as otherwise provided in
this section, employ any of his employees who is engaged in
commerce or in the production of goods for commerce [longer than
certain maximum hours]. . . ."
52 Stat. 1062, 1063, 29 U.S.C. §§ 206(a) and
207(a).
[
Footnote 14]
E.g., Edwards v. California, 314 U.
S. 160;
Gooch v. United States, 297 U.
S. 124;
Thornton v. United States, 271 U.
S. 414;
Brooks v. United States, 267 U.
S. 432;
United States v. Hill, 248 U.
S. 420;
Caminetti v. United States,
242 U. S. 470.
See also United States v. South-Eastern Underwriters
Assn., 322 U. S. 533,
322 U. S. 549;
Bell v. Porter, 159 F.2d 117, 118-119.
[
Footnote 15]
"SEC. 15. (a) . . . it shall be
unlawful for any person
--"
"(1)
to transport, offer for transportation, ship,
deliver, or sell in commerce, or to ship, deliver, or sell with
knowledge that shipment or delivery or sale thereof in commerce is
intended,
any goods in the production of which any
employee was employed in violation of section 6 [minimum wages] or
section 7 [maximum hours]. . . ."
"
* * * *"
"SEC. 16. (a) Any person who willfully violations any of the
provisions of section 15 shall, upon conviction thereof, be subject
to a fine of not more than $10,000, or to imprisonment for not more
than six months, or both. . . ."
(Emphasis supplied.) 52 Stat. 1068, 1069, 29 U.S.C. §§
215(a)(1) and 216(a).
[
Footnote 16]
"Irrespective of the question as to who is the ultimate
consumer, however, it is our opinion that the employees of the
container manufacturer are subject to the act. The fact that
products lose their character as 'goods' when they come into the
actual physical possession of the ultimate consumer does not affect
the coverage of the act as far as the employees producing the
products are concerned. The facts at the time that the products are
being produced determine whether an employee is engaged in the
production of goods for commerce, and, at the time of the
production of the containers, they were clearly 'goods' within the
meaning of the statute, since they were not, at that point of time,
in the actual physical possession of the ultimate consumer. All
that the term 'goods' quoted above is intended to accomplish is to
protect ultimate consumers, other than producers, manufacturers, or
processors of the goods in question from the 'hot goods' provision
of section 15(a)(1). This seems clear from the language of the
statute. . . . But Congress clearly did not intend to permit an
employer to avoid the minimum wage and maximum hours standards of
the act by making delivery within the State into the actual
physical possession of the ultimate consumer who transports or
ships the goods outside the State. Thus, it is our opinion that
employees engaged in building a boat for delivery to the purchaser
at the boat yard are within the coverage of the act if the
employer, at the time the boat is being built, intends, hopes, or
has reason to believe that the purchaser will sail it outside the
State."
29 C.F.R. § 776.7(h).
[
Footnote 17]
48 Stat. 195.
[
Footnote 18]
This clause was amended in 1942 by adding the following:
"
Provided, That the provisions of this subsection (c)
shall not apply to any employer who shall have entered into an
agreement with his employees pursuant to the provisions of
paragraphs 1 or 2 of subsection (b) of section 7 of an Act entitled
'Fair Labor Standards Act of 1938.'"
56 Stat. 277, 41 U.S.C. § 35(c). Those paragraphs relate to
collective bargaining agreements covering 26 or 52 consecutive work
weeks and exempting the employer making them from charges of
violation of the usual maximum hour provisions of the Fair Labor
Standards Act. This amendment thus recognized the application of
the Fair Labor Standards Act to employment to which the
Walsh-Healey Act also applied.
[
Footnote 19]
See note 11
supra.
[
Footnote 20]
See Pyramid Motor Corp. v. Ispass, 330 U.
S. 695;
Levinson v. Spector Motor Service,
330 U. S. 649;
Southland Gasoline Co. v. Bayley, 319 U. S.
44;
Overnight Motor Transport Co. v. Missel,
316 U. S. 572;
United States v. American Trucking Assns., 310 U.
S. 534.
[
Footnote 21]
See note 18
supra.
[
Footnote 22]
"SECTION 1. (a) The Congress hereby finds that the Fair Labor
Standards Act of 1938, as amended, has been interpreted judicially
in disregard of long established customs, practices, and contracts
between employers and employees, thereby creating wholly unexpected
liabilities, immense in amount and retroactive in operation, upon
employers, with the results that, if said Act as so interpreted or
claims arising under such interpretations were permitted to stand,
. . .(9) the cost to the Government of goods and services
heretofore and hereafter purchased by its various departments and
agencies would be unreasonably increased and
the Public
Treasury would be seriously affected by consequent increased cost
of war contracts . . ."
"
* * * *"
"The Congress further finds and declares that all of the results
which have arisen or may arise under the Fair Labor Standards Act
of 1938, as amended, as aforesaid, may (except as to liability for
liquidated damages) arise with respect to the Walsh-Healey and
Bacon-Davis Acts, and that it is therefore in the national public
interest and for the general welfare, essential to national
defense, and necessary to aid, protect, and foster commerce, that
this Act shall apply to the Walsh-Healey Act and the Bacon-Davis
Act."
(Emphasis supplied.) 61 Stat. 84-85, 29 U.S.C. (Supp. III)
§ 251(a).
[
Footnote 23]
The 1949 amendments to the Fair Labor Standards Act, including
especially the increase of minimum wages from 40 cents to 75 cents
and hour, demonstrate, however, the growing importance of the
application of the Fair Labor Standards Act. 63 Stat. 446, 910-920,
29 U.S.C. (Supp. III) § 202,
et seq., especially
§ 206(a)(1).
[
Footnote 24]
54 Stat. 712-714, 50 U.S.C. App. §§ 1171, 1172.
[
Footnote 25]
174 F.2d 718, 726-730.
[
Footnote 26]
This Statement of Labor Policy was emphasized by counsel for the
respondent in the
Aaron case. Much of it is published in
Regulations -- Army: Ordnance Procurement Instructions, 2 CCH War
Law Serv. §§ 9,101.1, 9,104.3, 9,104.4, 9,105.2 and
9,105.3.
MR. JUSTICE FRANKFURTER, whom MR. JUSTICE JACKSON joins,
dissenting.
These cases do not present just another one of those situations
in the long series in which the Court has been
Page 339 U. S. 523
called upon to give a sympathetic construction to the Fair Labor
Standards Act. We do not here have a controversy involving
relations between a capitalist employer and his employees. The real
controversy is between the Department of the Army, which conceived,
formulated, and administered a scheme for the production of war
materiel by means of Government-owned plants, and the Wage and Hour
Division of the Department of Labor, which administers the Fair
Labor Standards Act. We do not have here, in short, the resistance
of private employers to the demands of their employees. Here, a
vast claim on the Treasury of the United States is in issue. The
issue should be decided in light of the fact that Congress has
manifested in the most emphatic way that the Fair Labor Standards
Act is not to be stretched to the extent that sophistical
argumentation can stretch its scope, but is to be applied in a
commonsensical way. [
Footnote 2/1]
Fine distinctions in the application of the statute can hardly be
avoided. That makes it all the more necessary to hew close to the
line marked out by the specific facts of the cases before us. The
caution that general propositions do not decide concrete cases is
particularly to be heeded in dealing with an enactment framed in
terms of legal categories having diverse and conflicting contents.
It begs the real question to purport to solve a particular problem
merely by invoking such a category.
Page 339 U. S. 524
Not only is it important to be heedful of what these cases are
really about; it is no less important to be mindful of what they
are not about. The problem before us is not the applicability of
the Fair Labor Standards Act to work done under all Government
contracts, or even to work under all varieties of war production
contracts, cost plus fixed fee or otherwise. What is involved is
the particular kind of cost plus fixed fee contracts for the
operation of ordnance plants under the Act of July 2, 1940, which
authorized the Secretary of War to provide for the operation of
such plants "through the agency of selected qualified commercial
manufacturers." [
Footnote 2/2] 54
Stat. 713, 50 U.S.C. App. § 1171(b).
An analysis of the nature of the interrelationship of
Government, contractor and employees is necessary to put the issues
in their proper perspective. The facts are substantially the same
in all three cases, but, since the findings in No. 79,
Aaron v.
Ford, Bacon & Davis, Inc., are particularly detailed,
further discussion will center on that case.
The United States contracted with respondent Ford, Bacon &
Davis, Inc. in July, 1941, for the operation of the
Government-owned Arkansas Ordnance Plant and production there of
munitions for war detonators, percussion elements, artillery
primers, fuses, boosters and powder train fuses. The plant was a
military reservation under the immediate control of an ordnance
officer designated by the Chief of Ordnance. Munition quotas and
specifications were set by the Government, and inspection by
Government officials at each stage of production checked compliance
with rules promulgated by the Government not merely as to safety,
but as to production
Page 339 U. S. 525
as well. The contract was terminable at will by the Government,
and, under it, the "normal factors which go to make up commercial
profit are lacking." War and Navy Departments' Statement of Labor
Policy Governing Government-Owned, Privately Operated Plants
(1942), digested in 2 CCH War Law Serv. 24,862
et seq. The
United States owned all materials and equipment used in connection
with the operation of the plant. Ninety-five percent were furnished
by the Government directly; the remainder was obtained by the
contractor after approval by the Government. The United States
obtained title to the latter purchases at the point of origin, and
shipment to the plant was on Government bills of lading at a
reduced rate and without payment of transportation tax. Title to
all materials, equipment, and work in process in the plant was at
all times in the United States. Finished products were shipped out
of Arkansas to military facilities on Government bills of
lading.
Under the contract, the Government paid all expenses of
operating the plant, including labor costs. The contractor was even
allowed costs of production of munitions that did not meet
specifications and could not be used. The Government contracted for
electric power, telephone, teletype, and telegraph services itself
and paid the bills directly, and provided employees traveling on
business with tax-free transportation tickets. At no time did the
contractor have to advance its own money -- expenses were paid out
of available Government funds. For its services in operating the
plant, the contractor was paid a fixed fee.
The War and Navy Departments' Statement of Labor Policy forbade
agreements between the contractor and personnel
"which, in the opinion of either the Secretary of War or the
Secretary of the Navy, will have the effect of restricting or
hampering maximum output."
Although the contract provided that the contractor was to hire
all employees, and that they were to be "subject to
Page 339 U. S. 526
the control and constitute employees of the Contractor," the
Government retained the right to approve or disapprove the
employment of all personnel, and could require the dismissal of any
employee deemed "incompetent or whose retention is deemed to be not
in the public interest." No key employee could be assigned to
service until the Contracting Officer approved a statement
submitted to him on the employee's previous and proposed salary,
qualifications, and experience. All wage and salary rates and other
changes in status were subject to Government approval, and the
Government audited in advance of payment all time cards and
payrolls, and witnessed the actual payment to employees. The
requirement of approval of wage rates was neither a dead letter nor
a formality. Proposed wage scales were, in fact, rejected by the
War Department.
Work under the contract was specifically made subject to the
Walsh-Healey Act, 49 Stat. 2036, 41 U.S.C. § 35
et
seq. This statute was enacted by Congress after the National
Industrial Recovery Act was invalidated, with a view to directing
"Government purchases along lines tending to maintain the advance
in wages and purchasing power achieved under the NRA." S.Rep.
No.1157, 74th Cong., 1st Sess. 1 (1935).
See also S.Rep.
No.1193, 74th Cong., 1st Sess. (1935); H.R.Rep. No.2946, 74th
Cong., 2d Sess. (1936). To that end, § 1(b) requires that
employees of Government contractors be paid not less than the
"prevailing minimum wages for persons employed on similar work
or in the particular or similar industries or groups of industries
currently operating in the locality in which the materials,
supplies, articles, or equipment are to be manufactured or
furnished."
Provision is also made,
inter alia, for maximum hours,
with overtime permitted at "not less than one and one-half times
the basic hourly rate." Pursuant to § 2 of the statute, the
contract made the contractor liable to the
Page 339 U. S. 527
United States for any underpayment of wages for the benefit of
underpaid employees. [
Footnote
2/3]
Two years after the Walsh-Healey Act became law, Congress, by
the Fair Labor Standards Act of 1938, fixed specific minimum hourly
wages and maximum hours for employees "engaged in commerce or in
the production of goods for commerce." 52 Stat. 1062, 1063, 29
U.S.C. §§ 206, 207. Section 16(b) of that Act gives
employees a right of action against their employer for unpaid
minimum wages or overtime compensation and for
"an additional equal amount as liquidated damages. . . . The
court in such action shall, in addition to any judgment awarded to
the plaintiff . . . , allow a reasonable attorney's fee to be paid
by the defendant, and costs of the action."
The Court now holds that the Fair Labor Standards Act is
applicable to employees of cost plus fixed fee contractors
irrespective of the ultimate liability of the United States under
the contracts for whatever sums are recovered in these suits. As we
said in
Kennedy v. Silas Mason Co., 334 U.
S. 249,
334 U. S. 254,
the contractor, "in a sense, is no more than a nominal defendant,
for it is entitled to reimbursement from the Government." The reach
of the liability which today's decision establishes is indicated by
the agreed statement that, in the
Aaron case alone, a
"conservative estimate of the total amount in suit, exclusive of
liquidated damages and costs, is in excess of
Page 339 U. S. 528
$500,000.00." It was estimated by the Secretary of War in 1946
that the amount at stake in
"existing suits and potential suits . . . may in the aggregate
exceed $250,000,000, substantially all of which will be
reimbursable to the contractor. [
Footnote 2/4]"
The Court creates such a drain on the Treasury by imputing to
the Congress which enacted the Fair Labor Standards Act -- and
which, of course, could not possibly have foreseen the cost plus
fixed fee arrangements involved here -- the intention, in effect,
to open the Treasury not only to huge claims for overtime, but in
addition to demands for like amounts as "liquidated damages" and
attorney's fees. In the absence of a shred of evidence to indicate
that Congress contemplated such a result or would have countenanced
it, I cannot bring myself to attribute to Congress the desire to
place such a double burden upon the fisc.
Certainly such a result should have a more salient justification
than abstract argumentation about words not having fixed scope or
function. Our decisions have made one thing clear about the Fair
Labor Standards Act: its applicability is not fixed by labels that
parties may attach to their relationship, nor by common law
categories, nor by classifications under other statutes.
Rutherford Food Corp. v. McComb, 331 U.
S. 722;
Walling v. Portland Terminal Co.,
330 U. S. 148,
330 U. S. 150;
McComb v. McKay, 164 F.2d 40;
cf. United States v.
United Mine Workers, 330 U. S. 258,
330 U. S.
285-286. Unless we are to disregard this guidance of
wisdom in construing so dynamic a code as the Fair Labor Standards
Act, designation in the contracts of the contractors as the
"employers"
Page 339 U. S. 529
of the personnel in the ordnance plants cannot be decisive.
Again, the bare words of the definitions in that Act, never
self-applying in particular cases, are especially inconclusive here
because the cost plus fixed fee arrangements adopted for the
operation of these plants were of such an unprecedented character.
We are dealing with economic arrangements which, in their scope and
incidence, were aptly characterized by the War and Navy
Departments' Statement of Labor Policy: "The industrial units thus
created are unique." In such unique situations especially, we
should heed our admonition against perverting "the process of
interpretation by mechanically applying definitions in unintended
contexts."
Farmers Reservoir & Irrigation Co. v.
McComb, 337 U. S. 755,
337 U. S. 764.
In law, as elsewhere, words of many-hued meanings derive their
scope from the use to which they are put.
No doubt, as suggested, the purpose of the Fair Labor Standards
Act should guide our reading of it. The aim of the Act, set forth
in § 2(a), is to eliminate
"in industries engaged in commerce or in the production of goods
for commerce . . . labor conditions detrimental to the maintenance
of the minimum standard of living necessary for health, efficiency,
and general wellbeing of workers."
But to find that this Act does not fit the contracts in suit
neither negatives congressional concern for the welfare of the
employees involved nor deprives them of protection consonant with
the humane motives underlying the Act. The Walsh-Healey Act itself
serves as proof of congressional provision for civilized standards
for employees carrying out Government contracts. Pursuant to that
statute, the policy under the contracts here was to pay time and
one-half for overtime to employees in nonsupervisory
classifications. The degree of control exerted by the Government
over working conditions and wage rates, Government audit of time
cards and payrolls, the presence of Government officers at the time
employees
Page 339 U. S. 530
were paid, and the power of the Government to withhold payments
otherwise due the contractor or to sue for departure from specified
standards and use the recovery to compensate aggrieved employees
furnished a scheme of safeguards to assure fair dealing.
It is said that the Fair Labor Standards Act has been
interpreted administratively as covering the employees in these
cases. But the agency of Government charged with the formulation
and supervision of these contracts, the Department of the Army,
supports the position of the contractors here. Correspondence
between the War and Navy Departments and the Attorney General in
1944 shows the initial reluctance of the two Departments to have
suits against cost plus fixed fee contractors under the Fair Labor
Standards Act defended on the basis of the inapplicability of the
statute did not stem from lack of conviction about the validity of
the defense. Rather, the War and Navy Departments feared that its
successful assertion would have significant implications for the
construction of the National Labor Relations Act, and would
"result in an impairment of the jurisdiction of the National
Labor Relations Board over war plants or cause a substantial legal
doubt to be cast upon such jurisdiction."
This fear was engendered by the unresourceful advice of a
Government lawyer as to the subjection of the employment under
these contracts to the collectivd bargaining policy of the Wagner
Act if the Fair Labor Standards Act was not applicable. In view of
such advice, the War and Navy Departments concluded that the
interest in efficient prosecution of the war would best be served
by preserving at war plants the degree of supervision over labor
relations embodied in the National Labor Relations Act even at the
expense of abandoning attacks upon the applicability of the Fair
Labor Standards Act to cost plus fixed fee contractors.
See
also 22 Comp.Gen. 277. To find "administrative interpretation"
in a decision of Government
Page 339 U. S. 531
departments, acting under legal advice, that a concession as to
a statute's applicability was an expedient step in the war
production program is to disregard the justification for utilizing
"administrative interpretation" as a gloss on ambiguous
legislation.
The Government exerted close supervision over every phase of
operations at these ordnance plants, specifying articles to be
manufactured, production quotas and methods of production.
Government control was particularly dominant with respect to
personnel policies, including phases of hiring and firing, job
assignments, working conditions, wage rates, and overtime
compensation. The investment in plant and facilities was entirely
the Government's, and the Government bore all the expenditures and
all the risks of operation. As between the contractors and the
workers, the operation was wanting in the characteristic aspects of
the normal employer-employee relation. In view of these factors and
the applicability of the Walsh-Healey Act, with its protective
features for plant personnel, I see no basis for attributing to
Congress the intention to make these contractors "employers" within
the meaning of the Fair Labor Standards Act when such a result
would have fiscal consequences neither foreseen nor, on any
reasonable assumption, desired by Congress.
Cf. United States
v. Wittek, 337 U. S. 346.
Since the United States is not an "employer" within the meaning of
the statute, the overtime provisions are inapplicable.
These considerations call for affirmance without discussion of
other grounds which have been advanced for sustaining the judgments
below, some of which, at least, have commended themselves to
several Courts of Appeals.
[
Footnote 2/1]
Congress found that the construction which this Court placed
upon the Fair Labor Standards Act in
Jewell Ridge Coal Corp. v.
Local No. 6167, 325 U. S. 161;
Anderson v. Mt. Clemens Pottery Co., 328 U.
S. 680;
Bay Ridge Operating Co. v. Aaron,
334 U. S. 446;
Brooklyn Savings Bank v. O'Neil, 324 U.
S. 697, and
Farmers Reservoir and Irrigation Co. v.
McComb, 337 U. S. 755,
misconceived the purposes of Congress.
See
Portal-to-Portal Act of 1947, 61 Stat. 84, 29 U.S.C. (Supp. III)
§ 251
et seq.; Act of July 20, 1949, 63 Stat. 446, 29
U.S.C. (Supp. III) § 207(e)(1, 2), (f); Fair Labor Standards
Amendments of 1949, §§ 11, 14, 63 Stat. 910, 917, 919, 29
U.S.C. (Supp. III), §§ 213, 216.
[
Footnote 2/2]
The Secretary of the Navy was authorized to enter into contracts
for private operation of Navy installations on a cost plus fixed
fee basis by §§ 2(a) and 8(b) of the Act of June 28,
1940. 54 Stat. 677, 680, 50 U.S.C. App. §§ 1152(a)(1),
1158(b).
[
Footnote 2/3]
Section 2 provides:
"Any sums of money due to the United States of America by reason
of any violation of any of the representations and stipulations of
said contract . . . may be withheld from any amounts due on any
such contracts or may be recovered in suits brought in the name of
the United States of America by the Attorney General thereof. All
sums withheld or recovered as deductions, rebates, refunds, or
underpayments of wages shall be held in a special deposit account
and shall be paid, on order of the Secretary of Labor, directly to
the employees . . . on whose account such sums were withheld or
recovered."
[
Footnote 2/4]
Under the Fair Labor Standards Act, even employers who acted
with the utmost good faith are liable for liquidated damages and
attorneys' fees in addition to unpaid minimum wages or overtime
compensation. The severe impact a large, unforeseen, nonreimbursed
liability would have upon a fixed-fee contractor receiving an
annual fee of $420,000 as in the
Aaron case is
manifest.