It was error for the Court of Claims to give a judgment to a
manufacturer against the United States for loss of anticipated
profits under a contract for the manufacture of gun mounts for the
Navy which was canceled a few days after it was awarded when the
Court failed to make any affirmative finding that the manufacturer
was ready and able to perform its contractual obligations and when
it made affirmative findings which precluded any inference that
such readiness and capacity existed. Pp.
337 U. S. 199,
337 U. S.
210-214.
(a) In the absence of actual tenders of the required gun mounts,
the manufacturer's readiness and capacity to deliver them in the
quantities and at the times required by the contract was essential
to its right to receive payments under the contract. Pp.
337 U. S.
210-211.
(b) The affirmative findings in this case add up to an
inescapable ultimate finding that the manufacturer was neither
ready nor able to make the deliveries required by the contract. Pp.
337 U. S.
202-203,
337 U. S.
212-213.
(c) A finding that, "[i]f the plaintiff had been permitted to
perform its contract, it would have made a net profit of not less
than $80,000" was no more than a rough estimate of the amount of
its reasonably anticipated profits (if the contract were
completed), and cannot be taken as a finding that it was ready and
able to make the deliveries upon which such profits depended. P.
337 U. S.
213.
(d) The mere hope of being able to obtain from the Government
gratuitous extensions of time or concessions in the numbers of gun
mounts to be delivered cannot justify an award of money damages for
loss of unearned anticipated profits dependent upon such gratuitous
extensions or concessions. Pp.
337 U. S.
213-214.
110 Ct.Cl. 374, 75 F.2d 319, reversed.
The Court of Claims awarded a judgment to a manufacturer for
loss of anticipated profits under a contract for the manufacture of
gun mounts for the Navy which was cancelled a few days after it was
awarded. 110 Ct.Cl.
Page 337 U. S. 199
374, 75 F.2d 319. This Court granted certiorari. 335 U.S. 857.
Reversed, p.
337 U. S.
214.
MR. JUSTICE BURTON delivered the opinion of the Court.
This is an action in the Court of Claims by the respondent, Penn
Foundry and Manufacturing Company, Inc., against the United States
for loss of anticipated profits alleged to have been caused by the
latter's cancellation of a contract for gun mounts for the Navy.
The cancellation occurred a few days after the contract had been
awarded by the United States to the respondent on February 23,
1942. The question presented is whether the findings of fact made
by the Court of Claims are sufficient to sustain its judgment
requiring the United States to pay for such loss. 110 Ct.Cl. 374,
75 F. Supp. 319. We hold that they are not. We so hold because of
(1) the absence of any finding of the readiness and capacity of the
respondent to perform certain of its contractual obligations upon
which its profits were contingent, and (2) the presence of certain
affirmative findings which preclude the drawing of any sufficient
inference of such readiness and capacity from the other
findings.
The record includes only the pleadings and accompanying exhibits
filed in the Court of Claims and that court's special findings of
fact, conclusion of law, opinion, judgment, and refusal to grant a
new trial. We do not have before us the report which its
Commissioner made to the
Page 337 U. S. 200
Court of Claims or the testimony upon which he or that court
relied. While additional claims were made by the respondent in its
original petition to the Court of Claims, and while the United
States originally contested the binding force of the contract, the
errors specified in the present proceeding question only the right
of the respondent to recover $80,000 as damages for its alleged
loss of anticipated profits. We granted certiorari because of the
possible relation of the result in this case to claims under many
war contracts cancelled by the United States. 335 U.S. 857.
The findings of fact show the following:
In 1911, the respondent bought a manufacturing plant consisting
of six buildings in Waynesboro, Virginia. The main buildings, each
57 x 100 feet, had been built in 1890, and were referred to
respectively as the machine shop, the foundry, and the blacksmith
shop. At one time, the respondent manufactured circular saws, and,
at another, did work on brake shoes. Since 1931, the plant had been
used only for minor engagements, requiring not more than four or
five employees. It had been idle for some years when, late in 1940
or early in 1941, the respondent's officers became desirous of
engaging in the National Defense Program. Most of those officers
were then in other businesses at or near Pittsburgh, Pennsylvania.
One stockholder and director was in the real estate business in
Waynesboro. He had been the local manager of the plant when it was
in operation, and had continued thereafter as such, and as the
statutory agent of the company.
In January, 1941, the respondent engaged an additional man as
assistant to the president, and, on February 24, 1942, an engineer
as general manager. In April, 1941, it submitted a proposal to the
Navy for the manufacture of 500 3-inch 50-caliber gun mounts. In
July, a representative of the Gun Mount Section of the Navy
Department inspected the plant. Following a conference in
Page 337 U. S. 201
September, the respondent was asked by the Government to furnish
information as to financial ability, commitments of subcontractors,
and a detailed study of the machine tool operations, predicated
upon a possible award of 150 3-inch 50-caliber mounts. In October
and December, the respondent submitted additional information and
slightly modified its proposals. December 22, the respondent's
proposal as to prices, quantities, delivery schedule, payments, and
options for additional mounts was accepted as satisfactory, and the
respondent agreed to secure a letter from a surety company
indicating that a bond of the nature required by the Navy's Bureau
of Supplies and Accounts would be furnished.
The respondent received a "letter of intent," dated December 29,
1941, signed by the Paymaster General of the Navy as contracting
officer and approved by the Under Secretary of the Navy. It stated
that it was anticipated that the Navy Department would place an
order with the respondent for the manufacture of 150 gun mounts. It
specified the delivery of two complete mounts in May, 1942, three
in June, five in July, and thereafter at a minimum rate of ten
mounts per month. The letter also authorized the respondent to
purchase materials and spare parts, subject to confirmation by the
Government's purchasing officer, and to proceed with the production
of the mounts in anticipation of the placing of the order for their
production. However, under date of January 7, 1942, the Government
held up this authorization of expenditures until such time as the
respondent furnished the Government with the firm commitment of an
approved surety company to act as surety on a performance bond.
January 10, the respondent accepted the letter of intent. January
29, the Navy Department stated that the necessary letter from a
surety company had not been received, and that failure promptly to
submit such a letter might result in the termination of the
Page 337 U. S. 202
letter of intent. February 3, the respondent's representatives
submitted a letter from a surety company indicating that that
company thought that a bond in connection with a contract of this
size would have to be reinsured, and that, unless some change were
made in the financial setup, reinsurance would be declined. It
added, however, that if either of two suggested plans relative to
refinancing were accomplished, and if the respondent furnished
certain information as to new key personnel to be engaged by the
respondent, then the reinsurance could be obtained and the surety
company could execute a bond. The findings of fact disclose a
difference in the testimony as to the reaction of the Government's
representative to this letter. There is no finding that the
Government's requirement in this regard ever was met.
Much in the following findings of fact Nos. 5-8 is vital to the
issue before us:
"5. On January 16 and 17, 1942, plaintiff's plant was visited by
inspectors of the Philadelphia Inspection District of the Navy
Department to instruct plaintiff's personnel as to the Navy
inspection requirements.
At the time, there was no one at the
plant except the watchman and the local manager. No work at all was
being performed at the time. On February 19, 1942, a
production specialist from the War Production Board visited the
plant. His duties were to assist production in factories in the
production of naval ordnance.
At that time, only the watchman
was at the plant. The production specialist inspected the
plant with the local manager, who was called from his real estate
office, and also talked with Mr. Johnson (the new assistant to the
president), who was called to Waynesboro for that purpose. Reports
of these visits were given to the Navy Department.
At that
time, the company was
Page 337 U. S. 203
not prepared to undertake work of the character proposed by
the contract, and would not for an indefinite time be prepared
successfully to complete a contract for 150 gun mounts. Plaintiff's
foundry was incapable of production of the cast steel forgings
required for the gun mounts. It was plaintiff's plan, as shown
by its proposal to the Government, to subcontract for these
castings, as well as for other parts of the work. Plaintiff had
contacted certain producers, who were willing to furnish castings
and other parts,
but no contracts for the castings or any other
parts had been made by plaintiff. There was no reason to suppose
that the plaintiff could not have obtained these parts from
subcontractors. Plaintiff planned to use around 150 mechanics,
skilled, semi-skilled, and unskilled, in the machining and
assembling of the gun mounts. Plaintiff had expected to secure
former railroad shop mechanics residing near Waynesboro as the bulk
of its employees.
The construction of gun mounts is difficult
and exacting work. Manufacturers experienced in somewhat similar
work with large organizations and trained mechanics required from
seven months to one year from the time of receiving notice to
proceed until the first gun mounts were produced. Plaintiff had no
manufacturing organization, and no force of trained personnel to
train unskilled employees. Plaintiff's proposed general manager was
at this time a regular employee of another company in Ohio. He
had been assisting plaintiff in its plans under the expectation
that he would sever his connection with the other company and
become plaintiff's general manager. A contract between plaintiff
and the engineer under the terms of which the engineer was engaged
as general manager was executed on February 24, 1942. "
Page 337 U. S. 204
"6. Under date of February 23, 1942, the Navy Department mailed
to plaintiff a notice of award of contract, No. LL96553, for gun
mounts, in the amount of $2,087,555, which notice of award was
received by the plaintiff on February 24, 1942. On February 24,
1942, after it had received the notice of award, plaintiff received
a telegram as follows: "
"NOTICE OF AWARD CONTRACT NOS 96553 FORWARDED IN ERROR RETURN
FOR CANCELLATION NO AWARD TO YOU ACKNOWLEDGE REFERRING SYMBOL SPF
--"
"RAY SPEAR PAYMASTER GENERAL NAVY"
"On March 5, 1942, the Navy Department prepared and mailed to
plaintiff a letter as follows:"
"
* * * *"
"
As it is apparent that you cannot secure a bond to insure
faithful performance of the contract, no contract will be
issued to you, and the Letter of Intent LL-NOs-96553 (SPC), dated
29 December 1941, is hereby cancelled."
"Since no authority has been given you to incur any expenses
under the Letter of Intent, there can be no liability on the
Government by reason of the cancellation of the Letter of
Intent."
"Please return the original and all copies of the Letter of
Intent, unsigned, to the Bureau of Supplies and Accounts for
cancellation "
"7. . . .
The evidence does not disclose that any
expenditures or expenses were incurred in reliance on the letter of
intent or notice of award of contract."
"8.
If the plaintiff had been permitted to perform its
contract, it would have made a net profit of not less than
$80,000."
(Emphasis supplied.) 110 Ct.Cl. at pp. 378-381.
Page 337 U. S. 205
We are bound by the foregoing findings in testing the court's
conclusion of law and judgment that the respondent is entitled to
recover $80,000 for the loss of anticipated but unearned profits.
United States v. Causby, 328 U. S. 256,
328 U. S. 267;
United States v. Seminole Nation, 299 U.
S. 417,
299 U. S. 422;
United States v. Esnault-Pelterie, 299 U.
S. 201,
299 U. S.
205-206;
Crocker v. United States, 240 U. S.
74,
240 U. S. 78;
Stone v. United States, 164 U. S. 380,
164 U. S.
382-383.
The restricted scope of the errors sought to be reached by the
petition for certiorari has eliminated all questions as to the
binding force of the contract. [
Footnote 1] The Government, however, argues that, under
the then existing statutes and regulations, it had a right to
cancel the contract at its option without incurring liability for
the respondent's alleged loss of anticipated profits caused by such
cancellation. [
Footnote 2] It
argues also that the practice of inserting,
Page 337 U. S. 206
in each contract for war supplies, an express provision
permitting such a cancellation by the United States had developed
to such an extent that we should recognize the provisions as
constituting a part of the formal contract which the Government
stated was to follow the award made to the respondent, February 23,
1942. [
Footnote 3] It is
Page 337 U. S. 207
not necessary, however, to sustain those claims in order to
support the disposition which we are making of this case.
The Government argues further that the amount of the damages
claimed by the respondent is not established with reasonable
certainty by the findings of fact. The only finding as to the
amount of such damages is the ultimate finding of fact No. 8, which
says that,
"If the plaintiff had been permitted to perform its contract, it
would have made a net profit of not less than $80,000. [
Footnote 4] There are no findings of
evidentiary or primary facts on the subject of damages or the
computation of anticipated net profits. The total payment to be
made to the respondent for full performance of its part of the
contract was fixed by the award at $2,087,555. Accordingly, the
amount of the gross receipts anticipated by the respondent is not a
remote or speculative estimate of the kind often encountered
Page 337 U. S. 208
in claims for anticipated profits. This Court long has
recognized the right to recover damages for the loss of anticipated
profits when they result from a breach of contract and when there
is a sufficient basis for estimating them with reasonable
certainty. [
Footnote 5]
However, finding No. 8, as to the anticipated net profits in the
instant case, stands alone. Its sufficiency is open to argument in
the absence of any findings as to the costs of production. The
respondent seeks support for it in the indirect light
Page 337 U. S. 209
thrown upon it by the opinion of the court below. However, even
if that opinion may be resorted to to help interpret, although not
to supplement, the court's findings of fact, it does not materially
strengthen the respondent's position. For example, after reciting
certain of the respondent's handicaps in supplying the gun mounts,
to say nothing of supplying them at a net profit, the opinion says
(p. 387): "
"We think that the consideration and tolerance with which the
Government, during the time here in question, treated contractors
actually engaged in producing defense material, if the contractor
in good faith did his best to perform, is an indication that the
plaintiff, if allowed to perform, would probably have succeeded in
making a profit."
"On the other hand, it must be said that the plaintiff would
have had problems and difficulties that an active, going concern
would not have had, and those difficulties would probably have
adversely affected its profits. On the whole, we can do only what a
jury would do in a similar case. We conclude that the plaintiff
would probably have made net profits of about 4% of the gross
contract price, and we award it $80,000."
The opinion contributes nothing on the subject of costs except
an emphasis upon the burden of them. The opinion points only to a
suggested rule of thumb as a means of estimating the respondent's
anticipated net profits.
Page 337 U. S. 210
It suggests that the net profits, under the circumstances of
this case, should be "about 4% of the gross contract price. . .
."
Whether or not a reexamination of all the evidence that was
before the court below might cure this uncertainty we cannot tell.
We can conclude only that, on the limited findings before us, the
amount, if any, of the respondent's anticipated net profit rests
upon that court's rough estimate, rather than upon its findings of
evidentiary facts. We do not, however, decide the case on that
issue. More fundamental to the respondent's case than the amount of
its anticipated profits is the need for proof of the highly
material facts of its willingness, readiness, and capacity to
manufacture and deliver the required gun mounts in the quantities
and at the times specified.
1.
There is no finding of the readiness and capacity of the
respondent to deliver the gun mounts in the quantities and at the
times required by the contract. -- In the absence of actual
tenders of the required gun mounts, such readiness and capacity are
essential facts material to the respondent's right to receive
payments under the contract. Without a right to such payments, the
respondent could realize no profits.
See Restatement,
Contracts §§ 284, 280(1), 281, 318(c), 395, 397 (1932).
This issue goes deeper than that of the required reasonable
certainty of the amount of the anticipated net profits claimed as
damages. In a number of cases where this Court has allowed recovery
for the loss of anticipated profits, it has emphasized its finding
of a demonstrated willingness, readiness, and capacity, on the part
of the claimant, to perform the obligations which, if performed,
would have entitled the claimant to payment under the contract. For
example, in
United States v. Purcell Envelope Co.,
249 U. S. 313, the
United States, without adequate cause to do so, cancelled a
recently made contract to purchase, from the
Page 337 U. S. 211
Purcell Envelope Company, a four-years' supply of envelopes and
wrappers for the Post Office Department for $2,460,556.22. This
Court affirmed a judgment of the Court of Claims awarding the
company $185,331.76 for its loss of anticipated net profits which
it would have received if it had been allowed to perform the
contract. In that case, this Court said, 249 U.S. at
249 U. S.
316:
"The Envelope Company had, however, already made arrangements
and contracts for the supplying to it of the necessary materials to
fulfill the terms of the contract, and was ready and willing at all
times to fully perform it according to its terms."
Again (p.
249 U. S.
319): "There is no charge of default against the
Envelope Company, no charge of inability to perform its contract. .
. ." And finally (p.
249 U. S.
321):
"The court [of Claims], in its opinion expressly declares that
the findings showed that the Envelope Company had fulfilled all the
requirements of the Postmaster General and was ready and willing to
furnish the envelopes and wrappers. . . ."
See also Hinckley v. Pittsburgh Steel Co., 121 U.
S. 264,
121 U. S. 276;
Smoot's Case,
15 Wall. 36,
82 U. S. 44;
United States v.
Speed, 8 Wall. 77,
75 U. S. 84.
In its petition for a writ of certiorari in the instant case,
the United States specified that the Court of Claims erred in
failing to make the finding that the respondent had not proved that
it could have successfully performed the contract and made a profit
thereon. Whether or not it was error to fail to make such an
express finding of the respondent's failure of proof, it is clear
that there was wholly absent from the court's findings any express
statement that the respondent was ready and capable of performing
its obligations under the contract. It did constitute error to
render judgment for recovery of damages by the respondent in the
absence of that material fact. There remains only the question
whether an inference of the required readiness and capacity of the
respondent
Page 337 U. S. 212
to perform its obligations under the contract can be inferred
from the other findings.
2.
The presence of certain affirmative findings precludes
the drawing of any sufficient inference of the respondent's
readiness and capacity to deliver the gun mounts in the quantities
and at the times required. -- The respondent has the burden of
proof. Finding of fact No. 5, quoted in full
supra at at
337 U. S.
202-203, tells the story. The affirmative evidentiary
findings there made add up to an inescapable ultimate finding that
the respondent was not either ready or capable of making the
required deliveries of two complete gun mounts in May, 1942, three
in June, five in July and thereafter at a minimum rate of ten gun
mounts a month. February 19, about three and one-third months
before the first delivery was due, production was not under way,
even in a preliminary stage.
"At that time, the company was not prepared to undertake work of
the character proposed by the contract, and would not for an
indefinite time be prepared successfully to complete a contract for
150 gun mounts. . . . Manufacturers experienced in somewhat similar
work with large organizations and trained mechanics required from
seven months to one year from the time of receiving notice to
proceed until the first gun mounts were produced. Plaintiff had no
manufacturing organization and no force of trained personnel to
train unskilled employees."
Finding No. 5, 110 Ct.Cl. at p. 379.
The findings of fact show also that the following statement was
made to the respondent in the Government's letter of March 5, 1942,
after the Government's insistence upon a performance bond:
"As it is apparent that you cannot secure a bond to insure
faithful performance of the contract, no contract will be issued to
you. . . ."
Finding No. 6,
id. at p. 380. There is no
Page 337 U. S. 213
finding that the respondent ever met or was capable of meeting
this requirement.
As against these devastating findings, only finding of fact No.
8 even suggests the respondent's readiness and capacity to perform
the obligations necessary to entitle it to compensation under the
contract. It says: "If the plaintiff had been permitted to perform
its contract, it would have made a net profit of not less than
$80,000."
Id. at p. 381.
This is no more than a rough estimate by the Court of Claims of
what would be the amount of the respondent's reasonably anticipated
profits if the contract were completed. It is not a finding that
the respondent was ready and capable of making the deliveries upon
which such profits must depend. The striking fact is that the other
findings of the Court of Claims show that the respondent was not
prepared to make those deliveries, and that this was due to the
respondent's own lack of capacity to perform its obligations. To
support the judgment of the court below, this ultimate finding of
fact No. 8 would have to be read as itself supplying the missing
finding of the respondent's readiness and capacity to perform its
full obligations. In that role, it fails utterly. It not only
contains no evidentiary findings on the subject, but if it is
regarded as implying them they come into direct conflict with the
evidentiary findings of fact Nos. 5 and 6 to the contrary.
The possibility, suggested in the opinion, of securing from the
Government gratuitous extensions of time or concessions in the
numbers of gun mounts to be delivered may have justified the
respondent's hope that it might ultimately produce, with
inexperienced labor in its rehabilitated plant, the new products
called for by the contract. Such a possibility, however, cannot
justify the award of money damages by the Court of Claims to equal
a loss of unearned anticipated profits dependent
Page 337 U. S. 214
upon such possible gratuitous extensions or concessions. Even
assuming the willingness of the respondent to perform its
obligations, proof of its essential readiness and capacity to do so
is missing.
The judgment of the Court of Claims accordingly is reversed, and
the cause is remanded with direction to enter judgment in favor of
the United States.
Reversed.
MR. JUSTICE REED and MR. JUSTICE JACKSON concur in the reversal
and dissent from the order to enter judgment in favor of the United
States. In their opinion, respondent should have an opportunity to
meet the stated requirements of proof.
[
Footnote 1]
The Government's brief says in a footnote that "The finding of
the court below that a binding contract was consummated is, in our
view, of doubtful soundness." However, in the same brief, the
Government says that
"The United States does not question in this Court the Court of
Claims' holding that the notice of award sent by the Award Section
of the Navy Department's Bureau of Supplies and Accounts created a
binding contract between the United States and respondent on
February 23, 1943 (1942)."
The Court of Claims said in its opinion:
"We think that the Government made a contract with the
plaintiff, and that no mistake of the kind which would vitiate a
contract occurred."
110 Ct.Cl. at 385. In its specification of errors to be urged,
and in its statement of the questions presented by its petition for
a writ of certiorari, the Government does not question the binding
force of the contract. "Only the questions specifically brought
forward by the petition for writ of certiorari will be considered."
Rule 38, � 2, of this Court.
[
Footnote 2]
Title II, First War Powers Act of 1941, c. 593, 55 Stat. 839,
§ 201, 50 U.S.C. App. § 611; Executive Order No. 9001, 3
C.F.R.Cum.Supp. 1054-1056.
See also Contract Settlement
Act of 1944, c. 358, 58 Stat. 649, 41 U.S.C. § 101
et
seq.; Act of August 7, 1946, c. 864, 60 Stat. 902, 41 U.S.C.
§ 106 note, Regulation No. 7, Office of Contract Settlement,
32 C.F.R.1944 Supp., § 8006.3(c), p. 3065; Office of Contract
Settlement, A History of War Contract Terminations and Settlements,
p. 27 (July, 1947). As to comparable legislation affecting
contracts for supplies in World War I,
see Act of June 15,
1917, c. 29, 40 Stat. 182; Act of March 2, 1919, c. 94, 40 Stat.
1272;
Delaval Steam Turbine Co. v. United States,
284 U. S. 61;
Barrett Co. v. United States, 273 U.
S. 227;
College Point Boat Corp. v. United
States, 267 U. S. 12;
Russell Co. v. United States, 261 U.
S. 514.
[
Footnote 3]
See letter from James Forrestal, Acting Secretary of
the Navy, October 10, 1943, Hearings before a Subcommittee on
Contract Termination of the Senate Committee on Military Affairs on
S. 1268, S. 1280 and S.J.Res. 80, 78th Cong., 1st Sess. 270-273
(1943), in which he said (p. 271):
"The Navy Department commenced in the summer of 1941 the
consideration of contract termination as it might affect
procurement. At that time, there were few actual terminations in
contemplation. Contractors were nevertheless questioning the
Government's right to terminate contracts, and fair provisions
permitting such termination without cause and defining the rights
of the parties in such event were deemed necessary to facilitate
the urgently needed procurement and to minimize difficulties in the
event of changing needs. A contract clause endeavoring to meet the
procurement problem and safeguard the interests of both the
Government and the contractors was then adopted, and, except in
respect of the ship construction contracts (a special problem), is
in general form and substance in use in Navy contracts today."
See also memorandum of the Industrial Readjustment
Branch, submitted by James Forrestal, as Under Secretary of the
Navy, January 11, 1944, in which it was stated that, in the Navy
--
"Standard termination clauses for fixed price contracts were
developed late in 1941, and in general form and substance have been
inserted in most contracts entered into since that time except for
ship construction contracts, which constitute a separate problem.
The Department has not undertaken to modify outstanding contracts
by the insertion of such clauses."
Appendix II,
id. at p. 553 (1944).
[
Footnote 4]
The scope of our review of judgments of the Court of Claims is a
limited one. The early practice and rules are discussed in
Luckenbach S.S. Co. v. United States, 272 U.
S. 533,
272 U. S.
536-540. At the time of all the proceedings in the Court
of Claims in the instant case, the authority of this Court to
review causes upon petition for a writ of certiorari was set forth
expressly in the Act of February 13, 1925, c. 229, 43 Stat. 939,
§ 3(b), as amended by the Act of May 22, 1939, c. 140, 53
Stat. 752, which became 28 U.S.C. § 288(b). It provided:
"(b) In any case in the Court of Claims, . . . it shall be
competent for the Supreme Court, upon the petition of either party,
whether Government or claimant, to require, by certiorari, that the
cause be certified to it for review and determination of all errors
assigned, with the same power and authority, and with like effect,
as if the cause had been brought there by appeal. In such event,
the Court of Claims shall include in the papers certified by it the
findings of fact, the conclusions of law, and the judgment or
decree, as well as such other parts of the record as are material
to the errors assigned, to be settled by the Court."
"
* * * *"
"In such cases, the Supreme Court shall have authority to
review, in addition to other questions of law, errors assigned to
the effect that there is a lack of substantial evidence to sustain
a finding of fact;
that an ultimate finding or findings are not
sustained by the findings of evidentiary or primary facts; or that
there is a failure to make any finding of fact on a material
issue."
(Emphasis supplied.)
The foregoing expressly controlled the practice until repealed
by the new Judicial Code, effective September 1, 1948. The new
Code, 28 U.S.C. § 1255, said merely:
"Cases in the Court of Claims may be reviewed by the Supreme
Court by the following methods:"
"(1) By writ of certiorari granted on petition of the United
States or the claimant. . . ."
The Reviser's Notes to that Section said:
"Provisions for authority to review, in addition to other
questions of law, 'errors assigned to lack of evidence to sustain a
finding of facts; that an ultimate finding or findings are not
sustained by findings of evidentiary or primary facts; or that
there is a failure to make a finding of fact on a material issue,'
were omitted as unnecessary."
(Emphasis supplied.) H.R.Rep. No.308, 80th Cong., 1st Sess. A107
(1947).
[
Footnote 5]
After discussing the general rule against the recovery of remote
and speculative anticipated profits, this Court said, in
Howard
v. Stillwell & Bierce Mfg. Co., 139 U.
S. 199,
139 U. S.
206:
"But it is equally well settled that the profits which would
have been realized had the contract been performed, and which have
been prevented by its breach, are included in the damages to be
recovered in every case where such profits are not open to the
objection of uncertainty or of remoteness, or where, from the
express or implied terms of the contract itself, or the special
circumstances under which it was made, it may be reasonably
presumed that they were within the intent and mutual understanding
of both parties at the time it was entered into.
United States
v. Behan, 110 U. S. 338,
110 U. S.
345-347;
Western Union Tel. Co. v. Hall,
124 U. S.
444,
124 U. S. 454-456;
Philadelphia, Wilmington & Baltimore
Railroad Co. v. Howard, 13 How. 307."
See also Anvil Mining Co. v. Humble, 153 U.
S. 540,
153 U. S. 550;
Cincinnati Gas Co. v. Western Siemens Co., 152 U.
S. 200,
152 U. S. 206;
United States v. Behan, 110 U. S. 338,
110 U. S. 344;
United States v.
Speed, 8 Wall. 77,
75 U. S. 84;
Masterton v. The Mayor of Brooklyn, 7 Hill, N.Y. 61, 71;
Restatement, Contracts § 331 (1932).
MR. JUSTICE DOUGLAS, with whom MR. JUSTICE BLACK, MR. JUSTICE
MURPHY, and MR. JUSTICE RUTLEDGE agree, concurring.
It is clear and undisputed that the contract which the parties
made was to be reduced to formal terms. Both the "letter of intent"
[
Footnote 2/1] and the "official
award," [
Footnote 2/2] by their
express terms, state that a "formal contract" was contemplated.
That circumstance raises difficulties for respondent which neither
it nor the Court of Claims nor this Court has surmounted.
During the period of time relevant here, the Navy (apart from
exceptions inapplicable to the type of contract involved in this
case) had "standard termination clauses for fixed price contracts"
which "in general form
Page 337 U. S. 215
and substance" were inserted "in most contracts." [
Footnote 2/3] They provided that, in the
event of cancellation "for the convenience of the Government," the
contractor would be paid
"for all costs, including a proper allocation of overhead
expenses to the contract, incurred up to the time of termination,
plus an allowance of 6% or 7% profit on all such costs except
purchases of materials and unfinished goods, for which the
contractor was reimbursed at cost. [
Footnote 2/4] "
Page 337 U. S. 216
That policy of the Navy, revealed as it was in official
communications to Congress, is a matter of which we can take
judicial notice. We have heretofore amplified findings of facts by
reports of the Secretary of War.
Tempel v. United States,
248 U. S. 121,
248 U. S. 130.
The official communications which disclose the policy of the Navy
in this case, like reports, rules and regulations of agencies
[
Footnote 2/5] or other
communications to Congress, [
Footnote
2/6] are equally reliable and authoritative, and need no
further proof.
Respondent, however, has not carried the burden of showing that
it would have been saved from the application of that policy. It
has not shown that its contract falls in an exempt class. It has
not shown that what was usual or customary for other contracts of
this type would not be written into the formalized agreement to
which its contract with the Government was to be reduced. It has
not shown how it could escape application of the Navy's general
policy and be granted the favor of a contract without a termination
clause.
Yet, unless it can make that showing, it has not established by
"clear and direct proof," as
United States v. Behan,
110 U. S. 338,
110 U. S. 344,
requires, that it would have been free to make the profits which it
claims as damages for breach of the contract. For the customary
termination clause relieved the promisor of any liability for
unearned profits of the character claimed here. Since respondent
did not show that, at least in all probability, its contract would
have been free of that provision, it failed at the threshold of the
case to carry the burden which rested on it.
[
Footnote 2/1]
The "letter of intent" indicated the manner in which respondent
could approve the proposal, "thereby constituting this letter a
contract until the execution of a formal contract. . . ."
[
Footnote 2/2]
The "official award" stated that the Navy's acceptance of
respondent's proposal was authority to commence performance
"without waiting for the formal contract."
[
Footnote 2/3]
Memorandum from James Forrestal, Under Secretary of the Navy,
Jan. 11, 1944, Sen. Hearings on Sen. 1268, Sen. 1280, and
Sen.J.Res. 80, 78th Cong., 1st Sess., 551, 553, where it is
said:
"Standard termination clauses for fixed price contracts were
developed late in 1941, and, in general form and substance, have
been inserted in most contracts entered into since that time except
for ship construction contracts, which constitute a separate
problem. The Department has not undertaken to modify outstanding
contracts by the insertion of such clauses. It is difficult to
estimate the time which would be required to incorporate such a
clause by amendment in all contracts. However, it is doubted that
such action would be administratively feasible except upon the
initiative of the contractor."
And see letter of the Acting Secretary, Oct. 10, 1943,
id. 270-271.
[
Footnote 2/4]
See record p. 177 in
Pournall v. United
States, 334 U. S. 742, and
record p. 227 in
Alexander Wool Combing Co. v. United
States, 334 U. S. 742.
And see H.R. Hearings on H.R. 3022, 78th Cong., 1st Sess.,
27. At the time, Title II of the First War Powers Act, § 201,
55 Stat. 839, 50 U.S.C. App. § 611, was in effect empowering
the President to authorize any department or agency exercising
functions in connection with the prosecution of the war effort
under regulations prescribed by him
"to enter into contracts and into amendments or modifications of
contracts heretofore or hereafter made . . . without regard to the
provisions of law relating to the making, performance, amendment,
or modification of contracts whenever he deems such action would
facilitate the prosecution of the war. . . ."
By Executive Order 9001, dated Dec. 27, 1941, 6 Fed.Reg. 6787, 3
C.F.R.1941, Supp. 330, the President delegated this authority to
various agencies including the Navy Department. He also authorized
the Navy "by agreement" to modify or amend or settle "claims" under
contracts and provided that the amendments and modifications
"may be with or without consideration and may be utilized to
accomplish the same things as any original contract could have
accomplished hereunder, irrespective of the time or circumstances
of the making of or the form of the contract amended or modified,
or of the amending or modifying contract, and irrespective of
rights which may have accrued under the contract, or the amendments
or modifications thereof."
[
Footnote 2/5]
See Lilly v. Grand Trunk R. Co., 317 U.
S. 481,
317 U. S. 488;
Labor Board v. Atkins & Co., 331 U.
S. 398,
331 U. S.
406-407.
[
Footnote 2/6]
See Ludecke v. Watkins, 335 U.
S. 160,
335 U. S.
166-170.