1. Under the government construction contract here involved, for
installation of lighting of the runways of an airport, the
Government was not liable for damages for delay in making the
runways available to the contractor, though the delay prevented
completion within the specified time, since the contract did not
obligate the Government expressly or impliedly to make the runways
available promptly, it contained provisions anticipating delays
caused by the Government and providing remedies other than an award
of damages to the contractor, and no fault actually was chargeable
to the Government. Pp.
329 U. S.
66-67.
Page 329 U. S. 65
2. The fact that no other contractor was involved in this case
does not require a result different from that reached in
Crook
Co. v. United States, 270 U. S. 4, and
United States v. Rice, 17 U. S. 246. P.
329 U. S.
68.
105 Ct.Cl. 161, 63 F. Supp. 209, reversed.
Respondent brought suit in the Court of Claims upon a contract
and was awarded a judgment against the United States. 105 Ct.Cl.
161, 63 F. Supp. 209. This Court granted certiorari. 327 U.S. 777.
Reversed, p.
329 U. S. 69.
MR. JUSTICE BLACK delivered the opinion of the Court.
The Court of Claims rendered a judgment for the respondent and
against the Government for an asserted breach of a construction
contract. 63 F. Supp. 209, 215. We granted the Government's
petition for certiorari, which alleged that the Court of Claims'
decision was in direct conflict with
Crook v. United
States, 270 U. S. 4, and
United States v. Rice, 317 U. S. 61. We
hold that the Government's contention is correct.
The respondent, an electrical contractor, agreed for a fixed fee
to supply the materials for and install a field lighting system at
the National Airport, Gravelly Point, Virginia, then under
construction. The agreement was embodied in a standard form
Government contract. Respondent promised to complete the job within
120 days after notice to proceed. In fact, the job was not finished
until 277 days after notice was given. The delay came
Page 329 U. S. 66
about in this way. The site of the airport was being built up
from under water by a fast but then unique method of hydraulic
dredging. As portions of the earth base for the runways and
taxiways settled, they were to be paved and the shoulders
"rough-graded." As segments of this work were finished, respondent
was to move in, wire them, and install the lighting fixtures. The
dredging took longer than Government engineers had anticipated,
because some of the dredged soil, proving to be too unstable for
runways and taxiways, had to be replaced. This, in turn, delayed
completion of the runway sections, and, until each was finished,
the lighting equipment for each segment could not be installed. The
157 days' delay resulted from the consequently long and irregular
intervals between the times when these segments were made available
to respondent to do its job. But for these delays, respondent
apparently could have finished its work in 120 days.
The Court of Claims considered that the Government breached its
contract by failing to make the runways available in time for
respondent to do its work within 120 days. The judgment against the
Government was for certain overhead and administrative expenses
which respondent incurred during the consequent period of delay.
*
In no single word, clause, or sentence in the contract does the
Government expressly covenant to make the runways available to
respondent at any particular time.
Cf. United States v.
Blair, 321 U. S. 730,
321 U. S.
733-734. It is suggested that the obligation of
respondent to complete the job in 120 days can be inverted into a
promise by the Government not to cause performance to be delayed
beyond that time by its negligence. But even if this provision,
standing
Page 329 U. S. 67
alone, could be stretched to mean that the Government obligated
itself to exercise the highest degree of diligence and the utmost
good faith in efforts to make the runways promptly available, the
facts of this case would show no breach of such an undertaking. For
the Court of Claims found that the Government's representatives did
this work "with great, if not unusual, diligence," and that "no
fault is or can be attributed to them." Consequently, the
Government cannot be held liable unless the contract can be
interpreted to imply an unqualified warranty to make the runways
promptly available.
We can find no such warranty if we are to be consistent with our
Crook and
Rice decisions,
supra. The
pertinent provisions in the instant contract are, in every respect
here material, substantially the same as those which were held in
the former cases to impose no obligation on the Government to pay
damages for delay. Here, as in the former cases, there are several
contract provisions which showed that the parties not only
anticipated that the Government might not finish its work as
originally planned, but also provided in advance to protect the
contractor from the consequences of such governmental delay, should
it occur. The contract reserved a governmental right to make
changes in the work which might cause interruption and delay,
required respondent to coordinate his work with the other work
being done on the site, and clearly contemplated that he would take
up his work on the runway sections as they were intermittently
completed and paved. Article 9 of the contract entitled "Delays --
Damages," set out a procedure to govern both parties in case of
respondent's delay in completion, whether such delay was caused by
respondent, the Government, or other causes. If delay were caused
by respondent, the Government could terminate the contract, take
over the work, and hold respondent and its sureties liable. Or, in
the alternative, the Government
Page 329 U. S. 68
could collect liquidated damages. If, on the other hand, delay
were due to "acts of the government" or other specified events,
including "unforeseeable causes," procedure was outlined for
extending the time in which respondent was required to complete its
contract, and relieving him from the penalties of contract
termination or liquidated damages.
In the
Crook and
Rice cases, we held that the
Government could not be held liable for delay in making its work
available to contractors unless the terms of the contract imposed
such liability. Those contracts, practically identical with the one
here, were held to impose none.
See also United States v.
Blair, supra. The distinction which the Court of Claims found
between this and the prior cases is not in point. It seems to be
this: in the
Crook and
Rice cases, the Government
had a prime and a subcontractor; the Government reserved a right to
make changes by which the prime contractor must thereafter be
governed; the Government exercised this right; these changes made
it impossible for the prime contractor and ultimately the
subcontractor to do their work in time; since the Government had
reserved the right against the prime contractor to make these
changes, and the subcontractor knew this, the Government was not
contractually responsible for the delay. Therefore, it is suggested
that the subcontractor in the
Rice and
Crook
cases could know in advance that the performance time was
"provisional," whereas here the contractor had reason to believe
that it was certain. But, in this case, there is ample indication
both in the extrinsic facts and in the contract terms that changes
and delays were anticipated, and remedies therefor provided. The
contractor here only lacked the one additional indication that
changes were anticipated which he could have read from the prime
contract had there been a prime contract and if a prime contract
had been available for his to read. If this be a distinction, it is
a distinction
Page 329 U. S. 69
with no significant difference. This contract, like the others,
shows that changes and delays were anticipated and provided for.
The question on which all these cases turn is did the Government
obligate itself to pay damages to a contractor solely because of
delay in making the work available? We hold again that it did not,
for the reasons elaborated in the
Crook and
Rice
decisions.
Reversed.
MR. JUSTICE REED, MR. JUSTICE FRANKFURTER, and MR. JUSTICE
JACKSON dissent. It is admitted that the Government had given the
contractor "notice to proceed," which, in our opinion, had the
legal consequences set forth in the opinion of the court below
whose judgment we would affirm.
* The damages awarded were for the wages respondent paid
supervisory employees who stood by during the delay intervals, and
for certain expenses of respondent incurred on account of these
employees for unemployment and similar taxes.