Contracts for the purchase of lands by the Government stipulated
the purchase price, granted the right of immediate possession, but
contained no provision for interest. The Government subsequently
instituted condemnation proceedings, filed a declaration of taking,
and deposited in court sums substantially less than the contract
prices. The landowners asserted their contract rights. The validity
of the contracts having thereafter been judicially established, the
Government paid into court the full contract price.
Held:
1. The Government is not obligated in these circumstances to pay
interest, since the compensation of the landowners is controlled by
the contracts, which contained no provision for interest, rather
than by the Fifth Amendment. Pp.
329 U. S. 600,
329 U. S.
602.
2. The landowners having relied upon the purchase price
provisions of their contracts, the interest provisions of the
Declaration of Taking Act are inapplicable. P.
329 U. S.
604.
155 F.2d 73, 77, affirmed.
In condemnation proceedings instituted by the Government, the
landowners, petitioners here, relied upon the purchase price
provisions of earlier contracts and, in addition, claimed interest.
In No. 151, the District Court, on the question of interest, held
for the Government. 60 F. Supp. 741. In the other cases, the
District Court held for the landowners. 61 F. Supp. 199. The
Circuit Court of Appeals held for the Government. 155 F.2d 73, 77.
This Court granted certiorari. 329 U.S. 694.
Affirmed, p.
329 U. S.
606.
Page 329 U. S. 600
MR. JUSTICE BLACK delivered the opinion of the Court.
The question here is whether the Government is obligated to pay
interest in connection with the following land purchase
arrangements and condemnation proceedings. The Government made
separate contracts with the petitioners to buy certain lands from
them to be used for a public purpose. The contracts stipulated a
purchase price to be paid at an indefinite future time when certain
conditions had been fulfilled. [
Footnote 1] They also granted the Government the right to
immediate possession. Later, the Government questioned the validity
of the contracts, and attempted to rescind them on the ground that,
by reason of fraud and other things, the contract prices were
grossly excessive, and represented far more than the "just
compensation" required by the Fifth Amendment. It filed
condemnation proceedings in District Courts under 40 Stat. 241, as
amended, 50 U.S.C. § 171, asking the Courts to fix "just
compensation" after hearing evidence on that subject. It also filed
a declaration of taking under 46
Page 329 U. S. 601
Stat. 1421, 40 U.S.C. § 258a, at the same time depositing
in the Courts sums of money, substantially less than the contract
prices, which it estimated to be the true "just compensation" for
the property taken. The Courts then entered orders divesting the
property owners of all title and vesting it in the Government. A
companion case in which a District Court held an identical contract
valid was appealed, and eventually reached this Court. Prior to and
pending this appeal, these petitioners vigorously asserted the
validity of the terms of the contracts which fixed the agreed
prices for transfer of possession and title to their properties.
Several years later, this Court upheld the validity of the
identical contract in the companion case. [
Footnote 2] Thereupon, the Government, complying with
that decision, paid the full contract purchase prices into the
District Courts. It prayed that the landowners' compensation be
fixed as the contract price without interest. Petitioners asserted
that they had a right to interest from the time of the "taking"
guaranteed by the Fifth Amendment's provision for "just
compensation." The Government contended that the "just
compensation" provision was not applicable, and that petitioners
had no right to interest, because their purchase contracts did not
provide for it. One District Court decided this question in favor
of the Government, 60 F. Supp. 741, but two decided against it. 61
F. Supp. 199. [
Footnote 3] The
Circuit Court of Appeals
Page 329 U. S. 602
held for the Government. 155 F.2d 73, 77. In a case involving
somewhat similar facts,
United States v. Baugh, 149 F.2d
190, the Circuit Court of Appeals for the Fifth Circuit had decided
against the Government. Because of the apparent conflict presented,
and because the question is of widespread importance, we granted
certiorari. The facts and issues, so far as we deem them relevant
to disposition of all the cases, are identical, and so we consider
all of them together.
We agree with the Circuit Court of Appeals that the Government
is not obligated to pay interest in these cases. It is true that,
in cases submitted to them for determination of "just
compensation," courts have evolved a rule whereby an element of
compensation designated as interest is sometimes allowed. Under
this rule, and in the absence of an agreement of the parties fixing
compensation, courts first fix the fair market value of property as
of the time it is taken. The property owner, against whom there is
no counterclaim, is always entitled to payment of this much. But,
where payment of that fair market value is deferred, it has been
held that something more than fair market value is required to make
the property owner whole, to afford him "just compensation." This
additional element of compensation has been measured in terms of
reasonable interest. Thus, "just compensation" in the
constitutional sense, has been held, absent a settlement between
the parties, to be fair market value at the time of taking plus
"interest" from that date to the date of payment. [
Footnote 4]
But the method used by courts to determine "just compensation"
in an adversary proceeding where the parties
Page 329 U. S. 603
have failed previously to agree on its amount is not the
exclusive method for determining that question. The Fifth Amendment
does not prohibit landowners and the Government from agreeing
between themselves as to what is just compensation for property
taken.
See Danforth v. United States, 308 U.
S. 271. Nor does it bar them from embodying that
agreement in a contract, as was done here. And certainly, where a
party to such a contract stands upon its terms to enforce them for
his own advantage, he cannot at the same time successfully disavow
those terms so far as he conceives them to be to his disadvantage.
That is precisely the position of the petitioners here. They made
contracts for the transfer and possession of lands at prices
concerning which they have never complained. At the end of the
prolonged litigation, the Government was barred from showing that
compensations fixed by the contracts were not just, but were
excessive. Having thus bound the Government to the contract prices
as the measure of "just compensation," which prices, to say the
least, generously meet the Fifth Amendment's "just compensation"
requirement, they now seek to escape the burdens of these identical
contract provisions. They invoke the Fifth Amendment in pursuit of
something more than the compensation for which their contracts
provide -- contracts which they are not willing to abandon.
The answer to their contention is that, in this posture of the
cases, these transactions have passed out of the range of the Fifth
Amendment. For the reasoning on which interest is added to value as
a part of "just compensation" in court condemnation proceedings is
not applicable to this situation. That reasoning is that, when a
court determines just compensation, it first fixes bare value at
the time of the taking, and adds a sum to compensate for deferred
payment of bare value so as to make the property owner whole as
required by the Fifth Amendment. We
Page 329 U. S. 604
do not think this formula fits contractual arrangements for
compensation. Exactly what factor the parties consider, in addition
to bare value, cannot easily be ascertained. This very group of
transactions illustrates that there may be many such additional
factors. For example, all the contracts here provided for immediate
Government possession, though none contemplated immediate payments.
We cannot know what amounts were added in the bargains to the bare
market values as estimated, though unarticulated, allowances for
the anticipated delays in payment. And other factors which need not
be enumerated entered into the contract prices. These things
demonstrate the inadvisability of applying a constitutional rule as
to interest, specially designed to enable courts to calculate "just
compensation," to an entirely different situation in which parties,
supposedly with due regard to their own interests, bargain between
themselves as to compensation. Since these petitioners have chosen
to stand on their contract terms as to the amount they will receive
for their property, rather than to have "just compensation," in the
constitutional sense, fixed by the courts, we must look to those
terms for the measure of their compensation, including their right
to that part of compensation which courts have called interest.
We have not overlooked the contention that this conclusion is in
conflict with our holding in
Danforth v. United States,
308 U. S. 271. We
do not think it is. That was also a case in which a statute
authorized Government agents to purchase property, and a price had
been agreed on prior to condemnation proceedings. But the asserted
interest claim was there denied. The decision in that case
reasserted the principle that interest in condemnation proceedings
does not begin until there has been a taking. After noting the
several incidents asserted to constitute a taking, we held that
there was no interval between the
Page 329 U. S. 605
taking of the property there and payment for it. Thus, the
question we have considered here was neither directly involved,
raised, nor given special consideration. A further incidental
distinction between that case and this is that, in the
Danforth case, the contract did not anticipate that the
taking would precede payment.
Turning now to the right to interest under the contracts, and
apart from the contention regarding the Fifth Amendment, we find
that the contracts have no provision for payment of interest. No
statute authorizes the payment of interest in cases like this. In
the absence of specific contract or statutory provisions, no
interest runs against the Government, even though the Government's
payment for the contract purchases be delayed.
See Smyth v.
United States, 302 U. S. 329,
302 U. S. 353;
United States v. Thayer-West Point Hotel Co., 329 U.
S. 585,
329 U. S. 588;
United States v. New York Rayon Importing Co.,
329 U. S. 654,
329 U. S.
659.
There is some argument that interest should be allowed because
the Declaration of Taking Act, 46 Stat. 1421, 40 U.S.C. §
258a, under which condemnation proceedings were filed, authorizes
payment of interest from the date property is taken.
Cf. United
States v. Thayer-West Point Hotel Co., supra, p.
329 U. S. 588.
This provision, however, is no more than a statutory embodiment of
the rule for determining constitutional "just compensation" in the
absence of a governing contract, and what we have already said is
equally applicable to the claim for interest under the statute. It
contains no specific provision for interest on Government contracts
of purchase. And here, while the litigation was under the
condemnation statute, the petitioners' reliance on the purchase
price provisions of the contracts as to value took these claims for
interest outside the purview of the interest provisions of the
Declaration of Taking Act, and left them to be governed by the
interest rules which would have applied had suit been
Page 329 U. S. 606
brought by petitioners to enforce the contract terms.
Petitioners were barred from receiving interest in any proceeding
for the reason that their contracts contained no promise to pay
interest.
Affirmed.
* Together with No. 149,
Linnenbringer v. United
States; No. 150,
Pitman et al. v. United States; No.
151,
Oliver, Executor, et al. v. United States, and No.
155,
Q.W.S.S. Fealty & Investment Co. v. United
States, also on certiorari to the Circuit Court of Appeals for
the Eighth Circuit.
[
Footnote 1]
The first contract condition as to payment was that it should be
made upon conveyance of a good and merchantable title. The second
was that, if, "for any reason," the Attorney General did not
approve the title, the Government could obtain a good title by
condemnation proceedings in an appropriate district court, in which
event the agreed compensation was to be deposited in court.
[
Footnote 2]
Muschany v. United States, 324 U. S.
49.
[
Footnote 3]
Some of the petitioners claimed interest from the date the
Government took possession of the lands under the contract to the
date the Government deposited the full contract price. One
petitioner claimed interest only from the date of the filing of the
declaration of taking on the difference on that date between the
sum the Government deposited as the estimated "just compensation"
and the full contract price finally deposited. Interest was awarded
by the two District Courts on this latter theory only from the date
of the declaration of taking.
[
Footnote 4]
Seaboard Air Line Ry. Co. v. United States,
261 U. S. 299,
261 U. S. 306;
Shoshone Tribe v. United States, 299 U.
S. 476,
299 U. S.
496-497;
Jacobs v. United States, 290 U. S.
13,
290 U. S. 16-17;
United States v. Klamath Indians, 304 U.
S. 119,
304 U. S.
123.
MR. JUSTICE REED and MR. JUSTICE DOUGLAS, dissenting.
"The stipulation merely had the effect of relieving the
Government from having to make proof as to what was just
compensation and of running the risk of having an amount fixed
which might be unsatisfactory."
United States v. Baugh, 149 F.2d 190, 192. The
landowners' "right to have interest is found in the Constitution
and is neither found nor lost in the contract."
Id. 149
F.2d at 193. The justness of the claim for interest in these cases
is underlined by the fact that the land was taken over four years
before full payment was made. The United States renounced these
contracts, and retained possession of the properties by the
Declaration of Taking Act, which, by its terms, 46 Stat. 1421, 40
U.S.C. § 258a, entitled the condemnee to interest on the value
from the date of taking except as to sums paid into court. After
the decision in
Muschany v. United States, 324 U. S.
49, the Government carried out its condemnation suits
and obtained titles to these properties by condemnation.
In these condemnation actions, the agreed price, stated in the
contracts, became the "just compensation" of the Declaration of
Taking Act, and, by that Act, interest was due for such amount as
had not been deposited with the trial court when the declaration
was filed. Interest for the period between the declaration and the
payment of the value into the trial court should be allowed on the
amount by which the sum fixed in the final decree exceeded the sum
deposited with the declaration of taking.