1. In determining what is a final judgment or decree of a state
supreme court within the meaning of § 237 of the Judicial
Code, this Court is not controlled by the designation applied to it
in state practice. P.
319 U. S.
582.
2. A rescript from the Supreme Judicial Court of Massachusetts
to the state Superior Court embodied an order directing that the
final decree of the latter court dismissing a suit on the merits be
modified by the insertion of a clause "to the effect that the bill
is dismissed on the ground that the questions raised have become
moot," and declaring that "the decree, as so modified, is affirmed
with cost,"
held final within the meaning of § 237 of
the Judicial Code, so that an appeal applied for more than three
months from the date of the order was too late. P.
319 U. S.
582.
312 Mass. 523, 45 N.E.2d 400, appeal dismissed.
PER CURIAM.
The question for our decision is whether the appeal was applied
for within the three months period provided by law. 28 U.S.C.
§ 350. The suit was dismissed on the merits by the Superior
Court of Suffolk County, Massachusetts, and appealed to the Supreme
Judicial Court of Massachusetts, which, on December 4, 1942,
decided that the case had become moot. 312 Mass. 523, 45 N.E.2d
400. On the same day, that court sent to the Superior Court from
which the appeal was taken a rescript which contained the following
order:
"Ordered, that the clerk of said court . . . make the following
entry under said case in the docket of said court:
viz.,
Final Decree to be modified by the insertion of a clause to the
effect that the
Page 319 U. S. 582
bill is dismissed on the ground that the questions raised have
become moot; decree, as so modified, is affirmed with costs."
The rescript was filed that day in the Superior Court, which, on
January 7, 1943, entered a decree as had been directed.
Applications for the allowance of an appeal to this Court,
presented within three months after December 4th, were denied by
the Chief Justice of the Superior Court of Massachusetts and by an
Associate Justice of this Court. An application presented to
another Associate Justice on March 6th was allowed. But this last
application was not timely if the time to take an appeal ran from
December 4th.
Matton Steamboat Co. v. Murphy, 319 U.
S. 412.
Massachusetts local practice regards the decree entered by the
Superior Court on the rescript, rather than the order of the
Supreme Judicial Court contained in the rescript, as the "final
decree" in the case.
See Boston v. Santosuosso, 308 Mass.
189, 194, 31 N.E.2d 564;
Carilli v. Hersey, 303 Mass. 82,
84, 20 N.E.2d 492. But, in determining what is a final judgment or
decree within the meaning of Section 237 of the Judicial Code, 28
U.S.C. § 344, we are not controlled by the designation applied
to it in state practice.
Dept. of Banking v. Pink,
317 U. S. 264,
317 U. S. 268;
Gorman v. Washington University, 316 U. S.
98,
316 U. S. 101. The
order of the Supreme Judicial Court of Massachusetts, incorporated
in its rescript, was an order of the same nature and with the same
incidents as those of the highest courts of other states which we
review. It was an order of the court, and one which finally
disposed of all the issues in the case, leaving nothing to be done
but the ministerial act of entering judgment in the trial court.
The appeal is dismissed on the ground that it was not applied for
within the time provided by law.
Dept. of Banking v. Pink,
supra, and
Matton Steamboat Co. v. Murphy, supra.
Dismissed.