1. The construction of a library building at Howard University
in the District of Columbia -- a project for which federal funds
were appropriated by Act of February 14, 1931, and which
subsequently was approved, and funds allotted therefor, by the
Administrator of the Federal Emergency Administration of Public
Works under Title II of the National Industrial Recovery Act of
June 16, 1933 -- was a "public work" within the meaning of the
Miller Act of August 24, 1935, and therefore the contractors were
properly required to post a payment bond securing materialmen, and
a materialman who supplied materials for the project and had not
been paid therefor was entitled to sue on the bond in the name of
the United States. P.
316 U. S.
27.
2. The Miller Act was intended to apply to the "public works"
authorized by the Administrator under the National Industrial
Recovery Act, and, under the latter Act, the library at Howard
University was a "public work," since it was a project "of the
character heretofore constructed or carried on . . . with public
aid to serve the interests of the general public." P.
316 U. S.
30.
122 F.2d 73 reversed.
Certiorari, 314 U.S. 602, to review the reversal of a judgment
overruling a motion to dismiss the complaint in a suit upon a
bond.
Page 316 U. S. 24
MR. JUSTICE BYRNES delivered the opinion of the Court.
By Act of February 14, 1931, [
Footnote 1] making appropriations for the Department of
the Interior, Congress authorized the construction of a library
building at Howard University in the District of Columbia. The cost
was not to exceed $800,000, of which sum $400,000 was made
immediately available. Only a small part of this money had been
used for architects' fees when the President, shortly after his
inauguration in 1933, ordered impounded these and all other funds
appropriated for construction.
Title II of the National Industrial Recovery Act of June 16,
1933, [
Footnote 2] created a
Federal Emergency Administration of Public Works, with all of its
powers vested in an Administrator. By § 202, the Administrator
was directed to
"prepare a comprehensive program of public works, which shall
include, among other things, the following: . . . (c) any projects
of the character heretofore constructed or carried on either
directly by public authority or with public aid to serve the
interests of the general public. . . ."
And § 203 provided that,
"with a view to increasing employment quickly . . . , the
President is authorized and empowered, through Administrator or
through such other agencies as he may designate or create, (1) to
construct, finance, or aid in the construction or financing of any
public works project included in the program prepared pursuant to
§ 202. . . ."
On August 24, 1935, Congress passed the Miller Act. [
Footnote 3] By the terms of this
statute,
"before any contract, exceeding
Page 316 U. S. 25
$2,000 in amount, for the construction, alteration, or repair of
any public building or public work of the United States is awarded
to any person, such person shall furnish to the United States . . .
a payment bond with a surety or sureties satisfactory to such
officer for the protection of all persons supplying labor and
material in the prosecution of the work provided for in said
contract for the use of each such person."
The Act also permitted persons who supplied materials and labor
to bring suit on the bond in the name of the United States.
Page 316 U. S. 26
These are the statutes applicable to this dispute.
After the passage of the National Industrial Recovery Act, the
Secretary of the Interior (who had been named Administrator
pursuant to Title II) approved the library building at Howard
University as a part of the public works program and allotted
$1,120,811.58 for its construction. On December 5, 1936, the
Assistant Secretary of the Interior, on behalf of the United
States, entered
Page 316 U. S. 27
into a contract with respondent, Irwin & Leighton, for the
construction of the library building. As a condition of the
contract, Irwin & Leighton was required to furnish a bond to
secure the laborers and material men under provisions of the Miller
Act. [
Footnote 4] Accordingly,
it posted such a bond in the amount of $408,618, with respondent
United States Guarantee Company as surety.
Petitioner furnished to a subcontractor materials worth
$23,649.35. Of this sum, it was paid $11,146.80, leaving due
$12,502.55 with interest. When payment of this amount was refused,
petitioner brought this suit on the bond in the name of the United
States. Respondents moved to dismiss the complaint on the ground
that the construction of the library building at Howard University
was not a "public work" within the meaning of the Miller Act. The
District Court overruled the motion to dismiss. The Court of
Appeals allowed a special appeal and reversed on the authority of
its own earlier decision in
Maiatico Construction Co. v. United
States, 65 App.D.C. 62, 79 F.2d 418. The case is here on
certiorari.
The question before us, therefore, is whether the construction
of the library was a "public work" as that term is used in the
Miller Act. We think that it is, that the Assistant Secretary of
the Interior was consequently authorized to require respondents to
post a bond securing materialmen, and that petitioner is entitled
to sue on the bond in the name of the United States.
Page 316 U. S. 28
No aid in ascertaining the meaning of "public works" is to be
found in the Miller Act itself. But, in the National Industrial
Recovery Act, passed two years before the Miller Act, Congress
defined it as including
"any projects of the character heretofore constructed or carried
on either directly by public authority or with public aid to serve
the interests of the general public."
The library at Howard University was not only a project "of the
character heretofore constructed or carried on . . . with public
aid;" it had been directly and specifically authorized by Congress
in 1931, and money had actually been appropriated for it. And it
requires no discussion that Howard University, established by the
authority of Congress "for the education of youth in the liberal
arts and sciences," [
Footnote
5] serves "the interests of the general public."
In
Maiatico Construction Co. v. United States, supra,
upon which the Court of Appeals principally relied in reaching an
opposite conclusion, the same court had construed a different
statute, the Heard Act of August 13, 1894. [
Footnote 6] That Act required that
"any person or persons entering into a formal contract with the
United States for the construction of any public building, or the
prosecution and completion of any public work, or for repairs upon
any public building or public work, shall be required"
to post a bond for the security of both the United States and
the suppliers of labor and materials. It permitted the laborers and
material men to enforce their claims by intervening in any suit by
the United States on the bond. The plaintiffs in the
Maiatico case supplied labor and materials in the
construction of three dormitory buildings at Howard University, the
contract for which had been let to the defendant construction
company by the United States in November,
Page 316 U. S. 29
1930. The Court of Appeals decided that the plaintiffs could not
recover on the defendant's bond because the dormitories were not
"public buildings" and their construction was not a "public work."
It based this conclusion on the theory that "public buildings" or
"public works," within the meaning of the Heard Act, included only
buildings which belonged to the United States. Since Howard
University is a private institution and since it held title to the
dormitories, recovery on the bond was denied to the suppliers of
materials and labor. [
Footnote
7]
Whatever may have been the validity of this narrow formula when
applied to the Heard Act, we cannot approve its application to this
suit under the Miller Act. In the first place, the whole concept of
"public works" has been considerably altered since the enactment of
the Heard Act in 1894, and particularly within the last dozen
years, and the question of title to the buildings or improvements
or to the land on which they are situated is no longer of primary
significance. [
Footnote 8] But
we are not left to such vague guidance. Two and a half years after
the execution of the contract involved in the
Maiatico
case, Congress, in the National Industrial Recovery Act,
specifically defined "public works" as including
"any projects of the character heretofore constructed or carried
on either directly by public authority or with public aid to serve
the interests of the general public."
The Miller Act was passed two years later for the purpose of
enlarging the protection which the Heard Act had afforded to
laborers and materialmen by facilitating the procedure for
enforcing their claims against the contractor. During the hearings
on the several bills from which the Miller Act evolved, Congressman
Duffy,
Page 316 U. S. 30
of Ohio, the author of one of the bills and a member of the
subcommittee that drafted the Act, declared without dissent by any
Representative: "If this bill were passed by this Congress, it
would certainly be applicable to the public works program, and that
is the reason for its importance." [
Footnote 9]
We have no doubt that the Miller Act was intended to apply to
the "public works" authorized by the Administrator under the
National Industrial Recovery Act. The National Industrial Recovery
Act did not leave to speculation the nature of the "public works"
that Congress envisaged. Its language was not technical, but plain
and specific. Expressly included were "projects of the character
heretofore constructed or carried on . . . with public aid to serve
the interests of the general public." Beyond question, the library
at Howard University was such a project.
The respondents evidently had no difficulty interpreting the
language of the Recovery Act or the Miller Act until they were
called upon to meet the claims of petitioner. The record does not
reveal that Irwin & Leighton objected to posting the bond when
the contract was executed. It paid a premium of $8,172.25 for the
bond, and the surety company accepted it without question.
Presumably, these are the circumstances which caused the Court of
Appeals, 122 F.2d 73, 78, to remark upon "the strong equities" of
petitioner's case.
We hold that the Administrator had the authority to require the
bond, and that petitioner was entitled to bring this action on it.
Holding this view, we find it unnecessary to consider the other
questions raised by petitioner.
Reversed.
[
Footnote 1]
46 Stat. 1115, 1160.
[
Footnote 2]
48 Stat. 195, 201.
[
Footnote 3]
49 Stat. 793, U.S.C. Title 40, §§ 270a-270d:
"Sec. 1. (a) Before any contract, exceeding $2,000 in amount,
for the construction, alteration, or repair of any public building
or public work of the United States is awarded to any person, such
person shall furnish to the United States the following bonds,
which shall become binding upon the award of the contract to such
person, who is hereinafter designated as 'contractor':"
"(1) A performance bond with a surety or sureties satisfactory
to the officer awarding such contract, and in such amount as he
shall deem adequate, for the protection of the United States."
"(2) A payment bond with a surety or sureties satisfactory to
such officer for the protection of all persons supplying labor and
material in the prosecution of the work provided for in said
contract for the use of each such person. Whenever the total amount
payable by the terms of the contract shall be not more than
$1,000,000 the said payment bond shall be in a sum of one-half the
total amount payable by the terms of the contract. Whenever the
total amount payable by the terms of the contract shall be more
than $1,000,000 and not more than $5,000,000, the said payment bond
shall be in a sum of 40 percentum of the total amount payable by
the terms of the contract. Whenever the total amount payable by the
terms of the contract shall be more than $5,000,000 the said
payment bond shall be in the sum of $2,500,000."
"(b) The contracting officer in respect of any contract is
authorized to waive the requirement of a performance bond and
payment bond for so much of the work under such contract as is to
be performed in a foreign country if he finds that it is
impracticable for the contractor to furnish such bonds."
"(c) Nothing in this section shall be construed to limit the
authority of any contracting officer to require a performance bond
or other security in addition to those, or in cases other than the
cases specified in subsection (a) of this section. . . ."
"Sec. 2. (a) Every person who has furnished labor or material in
the prosecution of the work provided for in such contract, in
respect of which a payment bond is furnished under this Act and who
has not been paid in full therefor before the expiration of a
period of ninety days after the day on which the last of the labor
was done or performed by him or material was furnished or supplied
by him for which such claim is made, shall have the right to sue on
such payment bond for the amount, or the balance thereof, unpaid at
the time of institution of such suit and to prosecute said action
to final execution and judgment for the sum or sums justly due him:
Provided, however, That any person having direct
contractual relationship with a subcontractor but no contractual
relationship express or implied with the contractor furnishing said
payment bond shall have a right of action upon the said payment
bond upon giving written notice to said contractor within ninety
days from the date on which such person did or performed the last
of the labor or furnished or supplied the last of the material for
which such claim is made, stating with substantial accuracy the
amount claimed and the name of the party to whom the material was
furnished or supplied or for whom the labor was done or performed.
Such notice shall be served by mailing the same by registered mail,
postage prepaid, in an envelop addressed to the contractor at any
place he maintains an office or conducts his business, or his
residence, or in any manner in which the United States marshal of
the district in which the public improvement is situated is
authorized by law to serve summons."
"(b) Every suit instituted under this section shall be brought
in the name of the United States for the use of the person suing,
in the United States District Court for any district in which the
contract was to be performed and executed and not elsewhere,
irrespective of the amount in controversy in such suit, but no such
suit shall be commenced after the expiration of one year after the
date of final settlement of such contract. The United States shall
not be liable for the payment of any costs or expenses of any such
suit."
[
Footnote 4]
Bulletin No. 51 of Federal Emergency Administration of Public
Works, "Information Relating to the Negotiation and Administration
of Contracts for Federal Projects under Title II of the National
Industrial Recovery Act" (Revised, Oct. 1, 1935). Part I, §
2(a):
"The forms required for general use in connection with
construction and repair projects are as follows: . . . U.S.
Government Standard Form of Payment Bond No. 25A for the protection
of labor and materialmen, Pursuant to Public Act. No. 321,
Seventy-fourth Congress, approved August 24, 1935 [The Miller
Act]."
[
Footnote 5]
14 Stat. 438.
[
Footnote 6]
28 Stat. 278, as amended by the Act of Feb. 24, 1905, 33 Stat.
811 and the Act of March 3, 1911, 36 Stat. 1167.
[
Footnote 7]
This emphasis upon title to the building or project or to the
land on which it is situated finds support, as far as the Heard Act
is concerned, in
Title Guaranty & Trust Co. v. Crane
Co., 219 U. S. 24; 23
Op.Atty.Gen. 174.
[
Footnote 8]
See Peterson v. United States, 119 F.2d 145 at 147,
148.
[
Footnote 9]
Hearings on H.R. 2068, H.R. 4027, H.R. 4231, H.R. 4461, H.R.
5054, H.R. 6018, H.R. 6115, H.R. 6677, H.R. 8519 (March 8, 22,
April 26, and May 3, 1935), Committee on the Judiciary, House of
Representatives, 74th Cong., 1st Sess., p. 71.