1. In an action by the maker of a building loan, secured by a
mortgage on the building, to recover on a bond indemnifying him
from loss due to the failure of the borrower to complete the
building in time and manner as specified in the loan contract, the
measure of damages should be such as will place the lender in the
same position as if the building had been completed as stipulated.
P.
297 U. S.
205.
2. Where the lender, in such a case, was obliged by the
borrower's defaults in construction of an apartment building to
foreclose his mortgage, buy in the unfinished structure for less
than the loan, and take a deficiency judgment, it was error to
limit recovery on the indemnity bond to the cost of completing the
building in accordance with the contract; in the estimation of
damages, there should be considered also the rents that might have
been impounded in the foreclosure proceedings had the building been
ready for use, and the reduced value of the building at the
foreclosure sale because of its unfinished state. P.
297 U. S.
206.
3. The difference between the value of the unfinished building
at the foreclosure sale and the value it would have had if
completed as per contract may be considered as made up of two
elements, the cost of completion and the carrying charges
meanwhile. These may
Page 297 U. S. 199
be proved by expert testimony; or where, as in this case, the
building was completed by the lender, the actual cost of that may
be shown, and the other element may be established by expert proof
of the rental value of such a building (finished) at the date of
default and later. P.
297 U. S.
206.
4. In this case, in proof of damages due to delay in completing
the building, evidence was received, without objection, of payments
for taxes and insurance and of loss of interest on investment
during the time required for its completion.
Held that an
objection that such carrying charges may have exceeded the rents
that might have been received if the building had been finished as
agreed came too late, it not having been made at the trial. P.
297 U. S.
207.
5. In an action for damages caused by impairment of a mortgage
security, through the borrower's failure to complete the mortgaged
building as agreed, loss of rents is to be classed not as special,
but as general, damage, and may be proved without having been
specifically alleged. P.
297 U. S.
207.
77 F.2d 834 modified and affirmed.
Certiorari, 296 U.S. 566, to review a judgment reversing one
recovered in the District Court, 7 F. Supp. 392, in an action on an
indemnity bond.
Page 297 U. S. 203
MR. JUSTICE CARDOZO, delivered the opinion of the Court.
We are to determine the measure of damages upon a bond
conditioned against loss through the failure to complete a building
at the time and in the manner called for by the building
contract.
Page 297 U. S. 204
In September, 1929, petitioner, the Prudence Company, Inc.,
undertook to make a mortgage loan of $6,650,000 in aid of the
construction of Essex House, an apartment hotel in the city of New
York. The borrower covenanted that the building would conform to
plans and specifications, and would be completed not later than
December 16, 1930. As part of the same transaction, two surety
companies, the respondents in this Court, signed a bond in the sum
of $3,000,000, indemnifying the lender against loss through the
failure of the borrower to construct and pay for a building
conforming to the contract, and complete it by the stated time. The
bond also provided that, in the event of the borrower's default,
the lender, if it so elected, should be at liberty to go forward
with the work, and charge the cost against the sureties. Other
conditions are believed to be immaterial to any question now before
us.
On December 16, 1930, the borrower made default under the
mortgage, abandoning the work with the building then unfinished. At
that time, the petitioner's advances under the building loan
agreement were $6,575,000, the full amount promised, less $75,000
retained by agreement. On December 18, 1930, petitioner, through
its nominee, brought suit in the state court for the foreclosure of
the mortgage. On January 6, 1931, it went into possession with the
mortgagor's consent. On January 19, 1931, there was a judgment of
foreclosure, followed by a sale on March 17, 1931, at which the
mortgagee was the buyer, the bid of $6,000,000 being applied upon
the mortgage. A deficiency judgment of $716,215.02 was entered the
next month.
Petitioner in possession of the building went on with the
unfinished work, bringing it to completion in October, 1931. An
action on the bond was then begun against the sureties. The trial
court gave judgment for damages in the sum of $798,416.81, made up
of three classes of items:
Page 297 U. S. 205
the cost of completion; the loss from omissions and inferior
substitutions, and the interest on investment, together with taxes
and insurance charges, while the building was idle because unready
for its occupants. 7 F. Supp. 392. The Circuit Court of Appeals for
the Second Circuit found this award to be excessive. In the view of
that court no award should have been made for interest, taxes, or
insurance during the period of idleness. Payments necessary to
complete the building were properly allowed, for they were evidence
of the difference in value between an incomplete and a completed
structure. Reparation was also to be made for omissions and
substitutions to the extent that they diminished value, unless
strict compliance had been waived by the lender or its agents.
However, the extent of the recovery was not susceptible of
ascertainment without the aid of a new trial. This was so because
evidence of waiver had been offered by the surety and erroneously
excluded. A remand was thus necessary to elicit all the facts. 77
F.2d 834. Before a second trial was had, a writ of certiorari
issued at the instance of petitioner to resolve a claim of conflict
between the decision to be reviewed and a decision of this Court.
Trainor Co. v. Aetna Casualty & Surety Co.,
290 U. S. 47. The
writ states that it is "limited to the question of the measure of
damages," thus excluding from our consideration the ruling of the
court below as to the effect of waiver of performance.
Limiting our review accordingly, we think the extent of the
recovery upon the new trial that will be necessary has been too
narrowly confined.
The petitioner should be placed in the same position it would
have occupied if the building had been completed on December 16,
1930.
Trainor Co. v. Aetna Casualty & Surety Co.,
supra, at pp.
290 U. S. 54-55;
Kidd v. McCormick, 83 N.Y. 391, 398;
Province
Securities Corp. v. Maryland Casualty Co., 269 Mass. 75, 94,
168 N.E. 252. To give
Page 297 U. S. 206
it nothing but the cost of doing the unfinished work, plus the
loss resulting from omissions and substitutions, would be a scant
measure of reparation, allowing nothing for delay.
Ruff v.
Rinaldo, 55 N.Y. 664;
C. W. Hunt Co. v. Boston Elevated R.
Co., 199 Mass. 220, 233, 235, 85 N.E. 446; Sedgwick, Damages
(9th Ed.) � 645. If performance had been prompt, the mortgagee
would have had the security of a finished structure, which a buyer
at a foreclosure sale could have utilized at once. During the
pendency of the suit, the rents might have been impounded at the
hands of a receiver and applied upon the deficiency resulting from
the sale.
Freedman's Saving & Trust Co. v. Shepherd,
127 U. S. 494,
127 U. S. 503;
Worthen Co. v. Kavanaugh, 295 U. S.
56,
295 U. S. 62.
With the building still unfinished, there were no rents to be
collected, and hence none to be applied in reduction of the debt.
More important still, the amount of any bid was certain to be
reduced by notice to the bidders that the building would be
unproductive until ready to be occupied. From the point of view of
bidders, the reduction in value as the consequence of delay would
be made up of two factors -- the estimated cost of finishing the
work and the estimated carrying charges, not to exceed the rental
value, during the period of idleness.
Cf. Trainor Co. v. Aetna
Casualty & Surety Co., supra, at p.
290 U. S. 398.
So, at least, an assessor of the damages might find as a fair
inference of fact, even if the finding does not follow as an
inference of law. The effect of the decision is to hold down the
recovery to the first of these factors and to eliminate the
second.
The petitioner might have relied upon the testimony of experts
as to the total depreciation and as to the weight of the component
factors. It chose a different method. To show the loss sustained
from finishing the work, it proved the actual cost, as by the
express provisions of the bond it was at liberty to do.
Cf.
Comey v.
Page 297 U. S. 207
United Surety Co., 217 N.Y. 268, 276, 111 N.E. 832;
Appleton v. Marx, 191 N.Y. 81, 85, 86, 83 N.E. 563. One of
the factors of diminished value it has thus established with
precision. To fix the weight of the other factor, it would have
done better to give evidence by experts of the rental value of such
a building at the date of the default and later.
Griffin v.
Colver, 16 N.Y. 489, 496;
Cassidy v. Le Fevre, 45
N.Y. 562, 567;
Witherbee v. Meyer, 155 N.Y. 446, 453, 454,
50 N.E. 58. Instead of doing this, it chose to give evidence of the
taxes, insurance premiums, and interest on investment. We are told
by the respondents now that for anything appearing in the record
the carrying charges may have been greater than any rents that
could have been earned if the building had been finished. No such
objection was made upon the trial. We think it comes too late when
first made upon appeal. In the absence of more specific challenge,
the trier of the facts might not improperly assume that interest on
the investment along with taxes and insurance were losses flowing
from the failure to receive a finished building.
New York &
Colorado Mining Syndicate & Co. v. Fraser, 130 U.
S. 611,
130 U. S.
622-623. The point will not be labored, for the
assumption is a safe one that evidence and objection will not be
subject to this criticism when the case is tried again.
A question is raised as to the form of the complaint. The
respondents insist that its allegations are insufficient to permit
proof of loss of rents in addition to the cost. We read the
pleading otherwise. In the circumstances of this case, loss of
rents is to be reckoned as general, not special, damage. Sedgwick,
Damages (9th Ed.) � 1261;
Griffin v. Colver, supra; Cassidy v.
Le Fevre, supra; Ruff v. Rinaldo, supra; Jutte v. Hughes, 67
N.Y. 267, 271. It is one of the factors contributing to and
measuring the diminished worth of the security. Damages when
general are recoverable under a pleading that does not
Page 297 U. S. 208
enumerate the items.
Armstrong v. Percy, 5 Wend.
535-536, 538-539;
Laraway v. Perkins, 10 N.Y. 371, 373.
Here, the complaint alleges that except for the default and in
particular the delay, the plaintiff would have obtained upon
foreclosure the full amount of principal and interest due upon the
mortgage; it alleges that through the same causes the value of the
mortgage was impaired to the extent of the deficiency judgment; it
alleges that the plaintiff has thereby been deprived of any and all
return on the amount of the investment. We find these allegations
broad enough to let in evidence of damages along the lines that
have been marked.
Another trial will permit the petitioner to show more accurately
than it has done upon the record now before us that the building
was continuously untenantable until the completion of the work and
that the time taken for completion did not outrun the bounds of
reason.
What was ruled by the Court of Appeals in respect of the scope
of the recovery for omissions and substitutions was not specified
as error in the petition for the writ, and will be assumed to be
correct.
Zellerbach Paper Co. v. Helvering, 293 U.
S. 172,
293 U. S. 182;
Helvering v. Taylor, 293 U. S. 507,
293 U. S. 511;
Clark v. Williard, 294 U. S. 211,
294 U. S. 216.
The judgment is modified by a direction that the measure of
damages upon a new trial shall be that defined in this opinion, and
as thus modified affirmed.
It is so ordered.