In sustaining an order limiting the charges of a toll-bridge
company, against an attack based on the due process clause of the
Fourteenth Amendment,
held:
1. That a claim that a valuation of the property in an earlier
proceeding was treated as
res judicata in the proceeding
in question is not substantiated by the record. P.
291 U. S.
233.
2. The reasonable cost of constructing the bridge is good
evidence of its value at time of construction. P.
291 U. S.
234.
3. The fact that, in constructing it, a contractor who obtained
the contract under competitive bidding and performed it
expeditiously spent more than the contract price does not prove
that the value of the bridge, when constructed, was greater than
that price in the presence of evidence attributing the loss to
unusual water conditions, with no evidence to show that it could
not have been prevented by reasonable precautions. P.
291 U. S.
234.
4. It was reasonable to conclude that cost of reconstruction at
a later time would not be materially greater, the trend of
construction prices having been downward during the interim. P.
291 U. S.
236.
5. A corporation owning and operating a toll-bridge under
franchise from a state in a location formerly occupied by a bridge
constructed by the state and forming a link in a state system of
highway communication previously established is entitled to have
its real estate appraised for ratemaking purposes at its fair
market value for all of its available uses and purposes, including
particular uses to which it may be specially adapted, but not to
have that value increased by virtue of the public use.
Minnesota Rate Case, 230 U. S. 352,
230 U. S. 451.
P.
291 U. S.
237.
6. Opinion evidence that the cost of building the bridge at
other locations would be greater because of variation in the width
of the river and conditions in its bed did not warrant an increase
of fair market value. P.
291 U. S.
238.
7. While it is recognized that accrued depreciation, as it may
be observed and estimated at a given time, and an appropriate
Page 291 U. S. 228
allowance of depreciation according to good accounting practice
need not be the same, there is no rule which requires an allowance
to be made or continued which, in the light of experience, is shown
to be extravagant.
Smith v. Illinois Bell Telephone Co.,
282 U. S. 133,
282 U. S. 158.
P.
291 U. S.
239.
8. The amount that shall be allowed for annual depreciation in
fixing the charges of a public utility is a question of fact. In
reviewing the findings of a state court, this Court is not required
to prescribe an invariable method of computation, and cannot
overrule the state court's determination unless the results are
seen to be unconstitutional. P.
291 U. S.
240.
9. In the present case, involving a single structure which
deteriorates continuously from the moment of completion, annual
allowances during the life of the structure which, with reasonable
interest, will provide a sum for its replacement are not shown to
be inadequate. P.
291 U. S.
238.
10. A rate of return of 7% of the fair value of the property is
not shown to be confiscatory. P.
291 U. S.
241.
11. Where an order fixes an adequate gross revenue for a
toll-bridge and tentative rates that may be modified at any time on
application to the ratemaking body to conform to the results of
experience, the uncertainty whether, with the rates as initially
prescribed, the future traffic will bring in the prescribed revenue
is not a ground for constitutional objection. P.
291 U. S.
241.
108 Pa.Super.Ct. 49 affirmed.
Appeal from a judgment affirming (with a modification) an order
of the Public Service Commission prescribing the tolls to be
charged by the appellant bridge company. The Supreme Court of
Pennsylvania had declined to review the case.
Page 291 U. S. 231
MR. CHIEF JUSTICE HUGHES delivered the opinion of the Court.
The Superior Court of Pennsylvania affirmed (as modified) an
order of the Public Service Commission of that state prescribing a
tariff of tolls to be charged on the bridge of the Clark's Ferry
Bridge Company over the Susquehanna river, 108 Pa.Super.Ct. 49, 165
A. 261, 265. The company brings this appeal.
In its review of the facts, the Superior Court states that the
bridge is comparatively new, having been completed in May, 1925.
The bridge replaced, and was constructed
Page 291 U. S. 232
near the site of, a wooden bridge which had been acquired by the
incorporators of the present company. In August, 1925, a complaint
was filed with the Public Service Commission alleging that the
rates in effect were unreasonable. By its order of June 8, 1926,
the Commission found the fair value of appellant's property to be
$767,800, and that appellant was entitled to receive a gross annual
revenue of $85,905 on the basis of a return of 7 percent on that
fair value, after allowing operating expenses, taxes, an annual
depreciation allowance, and amortization of bond discount. An
appeal from the Commission's order was taken to the Superior Court,
but was withdrawn, and, in February, 1927, the company filed a new
tariff. The rates thus fixed were continued in effect until July,
1929, when the company made a voluntary reduction. In January,
1930, the Commission began the present proceeding on its own
motion, and, after hearings, determined that the fair value of the
appellants' property, as of February 2, 1932, was still $767,800,
and that the annual gross revenue which should be allowed was
$84,124 on the basis of a return of 7 percent on that fair value,
after allowing expenses and annual depreciation. 11 Pa. P.S.C. 222.
[
Footnote 1] In this
calculation, an item of $1,331 for annual bond amortization was
omitted. The Superior Court held that it should be included, and
modified the Commission's order accordingly -- that is, so as to
provide that the allowable gross revenue should be $85,455.
Page 291 U. S. 233
First. Appellant contends that the Commission and the
court treated the valuation in the Commission's decision of 1926 as
res judicata in the present proceeding. We do not so
construe the Commission's report or the court's opinion. The
Commission received evidence as to alleged changes in value and
estimates of the cost of reproducing the property. The Commission
determined that "cost conditions" had not "changed materially"
since 1926, and, "upon a complete examination of the entire record
in both proceedings," the Commission found that the fair value of
the property was $767,800 as of February, 1932. 11 Pa. P.S.C. at
231. The Superior Court, in construing the action of the
Commission, said:
"When the subsequent complaints were filed, the Commission
evidently did not consider its previous findings as barring
appellant from raising the question of the fair value of its
property in 1930 and the proper allowances to be made for operating
expenses and depreciation, but instituted an investigation, and, as
already stated, admitted in evidence appellant's reproduction cost
estimate and its supporting testimony, and put in evidence the
reproduction cost estimate
Page 291 U. S. 234
of one of its engineering staff, and the report of the result of
an examination of appellant's books and records."
The court acted upon what it stated to be
"the legislative mandate of the amendment of June 12, 1931, P.L.
530, that, in an appeal of this character, we shall consider the
record and 'on [our] own independent judgment . . . determine
whether or not the findings made and the valuations and rates fixed
by the Commission are reasonable and proper.'"
It was in this view that the court examined the "main
controversies" between the parties. 108 Pa.Super.Ct. p. 63.
Appellant attacks the finding of fair value upon the grounds
that it was based solely on the original cost of the bridge
property, and that the amount paid by the appellant for the bridge
was less than its fair value at that time and less than its fair
value in 1930. It is not open to question that the reasonable cost
of the bridge is good evidence of its value at the time of
construction. And we have said that
"such actual cost will continue fairly well to measure the
amount to be attributed to the physical elements of the property so
long as there is no change in the level of applicable prices."
McCardle v. Indianapolis Water Co., 272 U.
S. 400,
272 U. S. 411;
Los Angeles Gas & Electric Corp. v. Railroad
Commission, 289 U. S. 287,
289 U. S. 306.
In this instance, as the state court observed, the utility is not
"a complicated system which has taken years to construct and
enlarge, like a waterworks, or gas works, or electric light plant,
or street railway system," but is "one structure, a reenforced
concrete bridge, built, as it now is, without additions or
improvements." It appears that the bridge was built under a
contract awarded in June, 1924, after competitive bidding, and was
open to traffic in May, 1925. It is manifest that, when the
Commission made its first decision in June, 1926, the reasonable
cost of the structure furnished a proper basis for determining its
fair value. Of
Page 291 U. S. 235
the amount of the total valuation at that time, of $767,800, the
sum of $592,253 was taken as the construction cost on the basis of
the actual outlay, which included $566,301 paid to the contractor
for the bridge and approaches. Appellant then insisted, and still
insists, and it was shown, that the contractor sustained a loss.
This was said to amount to about $143,000 -- that is, on labor and
material, with overhead and depreciation of plant, as distinguished
from a loss of profits. The evidence as to this was given by the
contractor's auditor, who attributed the loss to an unusual flood.
He said: "We would have made money probably if things would have
gone alone smoothly without any high water." The court accepted
this explanation -- the only one given -- stating that "a sudden
rise in the Susquehanna river during the course of the work was
responsible for the loss; without it, there would have been a fair
profit." The court estimated that $20,000 additional, "spent on the
cofferdam construction," would probably have obviated the loss,
adding, "We have increased the cofferdam expense to cover this
amount." Appellant complains that this statement was based on
speculation, and has no support in the record. But appellant's case
is no stronger. The evidence gives no adequate ground for a
conclusion that, with reasonable care, the loss could not have been
prevented. The outstanding fact is that the contract was let in the
usual way to the lowest bidder, and the contractor received a
substantial bonus ($22,050) for finishing the work before the
stipulated date. To sustain the contention that the actual cost of
the structure was less than a reasonable cost at the time, it was
necessary for the appellant to give convincing proof. But such
proof is lacking. We find no satisfactory basis for holding that
the fair value of the property in June, 1926, was greater than
$767,800 as it was then determined to be.
Page 291 U. S. 236
The question is whether the proof shows that the value was
greater in 1932. Appellant relies upon the estimate of engineers as
to the cost of reproduction new of the physical property, as of
September 1, 1929, together with
"all additional expenditures required over and above the bare
cost of the physical property, to put the bridge in operation as an
income-producing property."
This estimate gave a total cost of reproduction new less
depreciation (the estimate being exclusive of two other elements of
alleged intangible value described as "attached business value" and
"location value") of $875,644.30. The Commission's engineer made a
similar estimate based upon prices prevailing during the last three
months of 1930, which gave the cost of reproduction new, less
depreciation, as $741,871. There were also charts showing the price
trends for labor and materials for 1924 to 1930, inclusive. As
summarized by the court, the evidence shows
"that, in 1924, when the contract for the construction of the
bridge was awarded, construction prices were reported as being 215%
of the 1913 level; that in September, 1929, when appellant's
reproduction cost estimate was made, they were 208% of the 1913
level, and that, during the last three months of 1930, they fell to
about 198%."
It would serve no useful purpose to review the details of the
estimates of reproduction cost. The court carefully considered
them, and properly concluded that the trend in prices from 1924-5,
when the bridge was built, to 1931-2, when the Commission
determined its present fair value, was "downward, rather than
upward," and that,
"in the absence of proof that the prices paid for the
construction of the bridge were abnormally low, there is no reason
why, in the short period of six years after its completion, with
the tendency of prices for both material and labor being downward,
there should be a radical increase in the fair value of the bridge
for ratemaking purposes."
We agree with this conclusion.
Page 291 U. S. 237
It does not appear that the court made any deduction from the
amount of the fair value as determined in 1926 by reason of the
depreciation accrued during the succeeding years. There was
controversy as to the extent of that depreciation. Appellant's
engineers allowed for the four and one-half years which had elapsed
to the time of their survey the sum of $16,282. The Commission's
engineer estimated the accrued depreciation for six years at
$41,403. The court thought that the latter figure was "nearer the
actual accrued depreciation than the estimate of the company," but
the court apparently treated such accrued depreciation as largely
offset by the "extra allowance, over the contractor's bid, for
concrete and cofferdams." The court decided that no harm was done
the appellant by leaving the fair value at $767,800.
A distinct question is raised by a claim for what is called "the
special value of location," in addition to the value of the bridge
property thus far considered. This "special value" was put at
$100,000. It was based, according to appellant's engineers, upon
the advantage that the location of the bridge has over any other
point for miles in either direction because the river is narrower
and the conditions of the river bed are more favorable. The
engineers made their estimate upon what they thought one would be
willing to pay for the present site, in preference to other sites
in the vicinity, because of the additional cost of building a
bridge elsewhere. It appears that the bridge is located in a rural
area. It was originally constructed as a part of an extensive
transportation system built by the Commonwealth in the first half
of the last century. As the court pointed out, the right to operate
a toll bridge across the river at this point or elsewhere
"is fundamentally the gift of the Commonwealth, contained in
appellant's franchise, and to attach a value
Page 291 U. S. 238
to it would be to capitalize the franchise contrary to the
provisions of the statute and the frequent decisions of the
courts."
In building its new bridge, appellant took advantage of the
traffic customs which had already been established. In the
determination of the value of its property, appellant was entitled
to be allowed the fair market value of its real estate for all its
available uses and purposes, which would include any element of
value that it might have by reason of special adaptation to
particular uses. But it was not entitled to an increase over this
fair market value by virtue of the public use.
Minnesota Rate
Cases, 230 U. S. 352,
230 U. S. 451,
et seq. The evidence, so far as it was properly addressed
to the question of the fair market value of appellant's real
estate, tended to support the amount allowed in the estimate of
fair value reached by the Commission and the court, and afforded no
basis for a higher valuation. There is no warrant for an increase
of fair market value by reason of opinions as to what it would cost
to build a bridge elsewhere.
We conclude that appellant has failed to show confiscation
because of the amount used as a rate base.
Second . Appellant complains that the amount prescribed
for gross revenue is inadequate. Appellant contests the annual
allowance for depreciation and the rate at which the fair return is
calculated.
The Commission fixed the annual depreciation allowance at
$7,678, and the court approved it. This amount equals 1 percent of
the fair value. Appellant contends that the allowance should be 2
1/2 percent of the value of the depreciable property on the
straight line basis. The difference,on appellant's calculation of
the fair value, amounts to $13,434. The court approved the ruling
of the Commission.
There is no question as to the fact of depreciation. It was
established, as respondent admits, that concrete
Page 291 U. S. 239
bridges deteriorate from the moment of their completion; that
there are chemical changes in their structure, absorptions of
moisture and oxidation, both within the concrete and in the
reenforcing iron covered by it, which cannot be stopped in their
process, or their effects removed. With this understanding, the
question is as to the amount which should annually be allowed which
will serve adequately to protect the investment from impairment due
to age and use. Testimony was given by one of appellant's engineers
that the average life of a concrete bridge was from 30 to 50 years;
by another, that the period for which this bridge might be expected
to remain useful was "from 40 to 80 years," he "would not figure on
over 40." Another testified that physically the bridge "might have
a life of 50 to 100 years." The Commission's engineer estimated its
life at from 40 to 50 years; for his computation, he took an
expectancy of 45 years. Respondent urges that the annual allowance
asked by appellant was plainly too large, and contrasts it with
appellant's claim for accrued depreciation -- that is, as the court
stated, appellant's engineers "allow an accrued depreciation for
the four and a half years elapsing to the time of their survey of
$16,282, but claim a yearly depreciation allowance thereafter of
$21,210." While it is recognized that accrued depreciation, as it
may be observed and estimated at a given time, and an appropriate
allowance of depreciation according to good accounting practice,
need not be the same, there is no rule which requires an allowance
to be made or continued which in, the light of experience, is shown
to be extravagant.
Smith v. Illinois Bell Telephone Co.,
282 U. S. 133,
282 U. S. 158.
After reviewing the testimony, and the methods of calculation which
the parties respectively advocated, the court thus stated its
conclusion:
"It [the Commission] allowed $7,678 annually. This sum set aside
each year, with 4%
simple interest, will
Page 291 U. S. 240
in fifty years produce approximately $767,800, sufficient to
rebuild the bridge as now valued. The straight line method
advocated by the company will in fifty years with 4% simple
interest produce a fund twice as great as that necessary to replace
the bridge. The straight line method is often used for short-lived
structures, or plants of a character that they can be restored from
time to time to the original condition of efficiency. . . . It is
not so fair or equitable when applied to a long lived structure or
one that is disintegrating gradually and continuously, and not
capable of being restored to its original condition. The company
may not be required to apply the income received from the
depreciation fund to make up any deficit of operation (
Board of
Public Utility Comm'rs v. New York Telephone Co., 271 U. S.
23), but it is not entitled to an allowance which,
exclusive of interest earned on the fund, will be sufficient to
rebuild the bridge when its life is done, but only to such an
allowance as will with reasonable interest added make a fund
sufficient to replace the bridge when it requires replacement."
In this view, the court thought the amount allowed by the
Commission to be "fair and reasonable in the circumstances." The
court added that the Commission had included in its allowance for
operating expenses an item of $1,800 for "maintenance."
The question of the amount which should be allowed annually for
depreciation is a question of fact.
Georgia Railway & Power
Co. v. Railroad Commission, 262 U. S. 625,
262 U. S. 633.
In reviewing the findings of the state court, we are not required
to enter a debatable field of fact and to choose and prescribe an
invariable method of computation. To justify the overruling of the
determination of the state court, we must be able to see that what
has been done will produce the result which the Constitution
forbids. Considering the nature of the property, and upon facts
shown by the evidence, the state court has allowed
Page 291 U. S. 241
appellant to reserve annually, and use for its own purposes, an
amount which, according to common experience, may be expected to
produce a sum adequate to replace the property on the expiration of
its life. We find it impossible to say, from a constitutional
standpoint, that another method should have been employed or a
greater amount allowed.
Appellant also insists that it is entitled to a rate of return
of 9 percent upon the fair value of its property. The Commission
and the court decided that 7 percent was sufficient. We perceive no
constitutional ground for complaint on that score.
Wabash
Valley Electric Co. v. Young, 287 U.
S. 488,
287 U. S. 502;
Los Angeles Gas & Electric Corp. v. Railroad
Commission, 289 U. S. 287,
289 U. S.
319-320.
Third. The final attack is on the form of the
Commission's order. The Commission fixed the amount of the annual
gross revenue and then prescribed a tentative schedule of rates.
[
Footnote 2] Appellant says
that it is obvious that no one can tell in advance how many
vehicles of different tariff classifications will pass over the
bridge in a year and what annual gross revenue will be produced by
a given schedule of rates. But, as the prescribed rates are
expressly stated to be tentative, there is no ground for assuming
that the Commission will reject an application to make such changes
in the schedule as experience may show to be necessary in order to
produce the stipulated revenue. There is nothing in the order which
requires that the test period should be a year or any definite
time. From the statements at the bar, it appears that appellant has
not put the tentative schedule in effect and has made no
application to the Commission for a change in the schedule. If the
allowance of gross revenue is adequate, as it has been found to be,
there is no basis for complaint
Page 291 U. S. 242
because of a schedule of rates which, on application, may be
appropriately modified.
[
Footnote 1]
The order of the Public Service Commission, of February 2, 1932,
is as follows:
"That Clark's Ferry Bridge Company file, post, and publish,
effective thirty (30) days from date hereof, upon not less than one
(1) day's notice to the public and this Commission, a new tariff
calculated to produce an annual gross revenue of not more than
$84,125."
"It is further ordered: That said tariff contains as tentative
rates intended to produce said gross annual revenue of $84,125, and
effective until further action by this Commission or the Company in
conformity with said determination of allowable gross revenue the
following charges:"
"(1) A rate of 8 cents cash toll for all ordinary passenger
automobiles and wagons now paying 10 cents."
"(2) A ticket without time limit salable at the rate of two for
15 cents for all such automobiles and wagons."
"(3) A 20-trip ticket nontransferable as between vehicles good
any time within thirty (30) days from date of issue and salable for
one dollar ($1) for all such automobiles and wagons."
"(4) Rates for all other types of vehicles as are now provided
in tariff P.S.C. Pa. No. 5."
"(5) It is further ordered: That said Company file with this
Commission monthly statements of income and operating expenses,
showing the number of vehicles passing over its bridge in each
class of traffic as contained in its tariff."
[
Footnote 2]
See note 1