Where a contract for furnishing and installing heating plants in
buildings to be erected for the government by other contractors
showed on its face that progress under it would be dependent on the
progress of the buildings, and, though strictly limiting the time
for the contractor's performance, made no reference to delays by
the government save as grounds for time extensions to the
contractor, and the contractor therein agreed to accept the
contract price in full satisfaction for all work done under the
contract, reduced by damages deducted for its delays and increased
or reduced by the price of any changes ordered by the government,
and stipulated that the contract price should cover all expenses of
any
Page 270 U. S. 5
nature connected with the work to be done,
held, that
the Government was not bound to make good losses suffered by the
contractor in performing the contract due to delays in completing
the buildings.
59 Ct. Cls. 593 affirmed.
Appeal from a judgment of the Court of Claims denying a claim
for damages due to delay in enabling the claimant to perform its
contract.
MR. JUSTICE HOLMES delivered the opinion of the Court.
This is an appeal from a judgment of the Court of Claims, taken
under § 242 of the Judicial Code before that section was
repealed by the Act of February 13, 1925, c. 229, § 13, 43
Stat. 936, 941. The claim is for damages due to delay in enabling
the plaintiff to perform a contract. The Court of Claims held that
the plaintiff waived any claim that it might have had by going on
with the work without protest and without taking any steps to
protect itself. 59 Ct.Cls. 593. The government contends that, by
the terms of the contract, it was not bound to pay damages for
delay.
The contract was that the plaintiff should furnish and install
heating systems, "one in the Foundry Building, and one in the
Machine Shop at the Navy Yard, Norfolk, Virginia." It allowed two
hundred days from the date of delivering a copy to the plaintiff
for the work to be completed. A copy was delivered on August 31,
1917,
Page 270 U. S. 6
making March 19, 1918, the day for completion. But it was
obvious on the face of the contract that this date was provisional.
The government reserved the right to make changes and to interrupt
the stipulated continuity of the work.
Wells Brothers Co. v.
United States, 254 U. S. 83,
254 U. S. 86.
The contract showed that the specific buildings referred to were in
process of construction by contractors who might not keep up to
time. "The approximate contract date of completion for the foundry"
is stated to be March 17, 1918, and that for the machine shop
February 15, 1918. The same dates were fixed for completing the
heating systems, but the heating apparatus had to conform to the
structure, of course, so that, if the general contractors were
behindhand, the heating also would be delayed. They were behindhand
nearly a year. When such a situation was displayed by the contract,
it was not to be expected that the government should bind itself to
a fixed time for the work to come to an end, and there is not a
word in the instrument by which it did so unless an undertaking
contrary to what seems to us the implication is implied.
The government did fix the time very strictly for the
contractor. It is contemplated that the contractor may be unknown,
and he must satisfy the government of his having the capital,
experience, and ability to do the work. Much care is taken,
therefore, to keep him up to the mark. Liquidated damages are fixed
for his delays. But the only reference to delays on the government
side is in the agreement that, if caused by its acts, they will be
regarded as unavoidable, which, though probably inserted primarily
for the contractor's benefit as a ground for extension of time, is
not without a bearing on what the contract bound the government to
do. Delays by the building contractors were unavoidable from the
point of view of both parties to the contract in suit. The
plaintiff agreed to accept in full satisfaction for all work done
under the
Page 270 U. S. 7
contract the contract price, reduced by damages deducted for his
delays and increased or reduced by the price of changes, as fixed
by the Chief of the Bureau of Yards and Works. Nothing more is
allowed for changes, as to which the government is master. It would
be strange if it were bound for more in respect of matters
presumably beyond its control. The contract price, it is said in
another clause, shall cover all expenses of every nature connected
with the work to be done. Liability was excluded expressly for
utilities that the government promised to supply. We are of opinion
that the failure to exclude the present claim was due to the fact
that the whole frame of the contract was understood to shut it out,
although in some cases the government's lawyers have been more
careful.
Wood v. United States, 258 U.
S. 120. The plaintiff's time was extended, and it was
paid the full contract price. In our opinion, it is entitled to
nothing more.
Judgment affirmed.