1. Orders of the Emergency Fleet Corporation directed to a
shipbuilder expropriated a vessel in process of construction under
a contract between the builder and the plaintiff, together with the
materials purchased by the builder for its completion, the benefits
and advantages of payments made, and of plans, specifications and
prior inspection service provided, by the plaintiff, and placed the
Fleet Corporation in the plaintiff's shoes with respect to the past
and future execution of the contract by the builder. The United
States thus obtained the ship early, and the benefit of prices much
lower than those prevailing at time of requisition.
Held:
(a) That the plaintiff's rights under the contract with the
builder were taken. P.
265 U. S.
119.
(b) That the just compensation to which the plaintiff was
entitled did not depend upon the title to the materials used in the
construction, and was not to be gauged by the progress payments
made, or by the compensation payable if the government had merely
cancelled the contract, but was to be measured by the value of the
plaintiff's rights under the contract at the time of the taking. P.
265 U. S.
121.
(c) Just compensation is the sum which, considering all the
circumstances, uncertainties of the war, etc., probably could have
been obtained for an assignment of the plaintiff's rights under the
contract --
i.e., the sum that would in all probability
result from fair negotiations between an owner willing to sell and
a purchaser desirous of buying. P.
265 U. S.
123.
Page 265 U. S. 107
(d) The value of such ships at the time of requisition, the then
probable value at the time fixed for delivery, the contract price,
payments made and to be made, the time to elapse before completion
and delivery, the possibility that, by reason of the government's
activity in controlling materials, the contractor might not have
been able to complete the ship on time, loss of the use of money to
be sustained, other expenditures to be made between requisition and
delivery -- all should be given consideration in determining the
plaintiff's loss caused by the taking. P.
265 U. S.
125.
2. Replacement cost not necessarily the sole measure of or guide
to value in ascertaining just compensation.
Id.
58 Ct.Clms. 274 reversed.
Appeal and cross-appeal from a judgment of the Court of Claims
in an action to recover a balance alleged to be due as just
compensation for the taking by the Shipping Board of the
plaintiff's rights under a contract for the construction of a
ship.
Page 265 U. S. 114
MR. JUSTICE BUTLER delivered the opinion of the Court.
This case arises out of the exertion of the power of requisition
conferred on the President by c., 40 Stat. 182, approved June 15,
1917, known as the Emergency Shipping Act. [
Footnote 1] There is involved the question whether
Page 265 U. S. 115
a certain contract for the construction of a ship was
requisitioned, and, if it was, upon what basis is just compensation
to be ascertained.
The act empowered the President (a) to order from any person for
government use ships or ship material of kind and quantity usually
produced by such person; (b) to requisition contracts for the
building of ships; (c) to require the owner of any shipbuilding
plant to place at the disposal of the United States the whole or
any part of the output of the plant; (d) to requisition any
shipbuilding plant or part thereof; (e) to requisition any ship in
process of construction, and compliance with all orders issued
under the act was made obligatory. By executive order of July 11,
1917, he delegated these powers to the United States Shipping Board
Emergency Fleet Corporation. On August 3, 1917, the claimant was
the assignee
Page 265 U. S. 116
and owner of a contract by which the New York Shipbuilding
Corporation agreed to construct a ship, known as hull No.193. The
contract was made March 28, 1916, and, after some modification, it
provided for the construction of a ship of 8,597 deadweight tons,
to be completed and delivered on or before February 1, 1918. T he
contract price was $831,630.
Prior to August 3, 1917, the claimant or its assignor had
secured the services of an architect, furnished plans and
specifications to the builder, employed a bureau to inspect the
work as it progressed, and had paid to the builder on account of
the contract price installments amounting to $419,500, which with
interest paid, architect's fees, and the value of the plans and
specifications, amounted to $473,710.58, exclusive of the cost of
inspection.
Immediately after the execution of the contract, the builder
ordered all materials required for which sufficient data then
existed, and, before August 3, 1917, completed its orders for
substantially all that were needed to perform the contract. Between
35 and 40 percent of the required materials had been delivered to
the builder ready for use, and, on that date, the ship was about 19
percent completed. The Court of Claims found that all materials so
ordered were delivered at the prices fixed in the orders and were
used in the construction of the ship, and that nothing was
purchased after that date, except materials used for construction
at a cost of $31,000, ordered for military protection. At that
time, claimant held on deposit in various solvent banks a sum of
money sufficient to pay all the remaining installments of the
contract price, and the builder was ready and willing to perform
the contract.
On August 3, 1917, the Emergency Fleet Corporation served on the
builder its order and notice requisitioning all of the ships,
including hull No.193, under construction in
Page 265 U. S. 117
the builder's shipyard, and the materials necessary for their
completion. The order required the builder to complete the ships.
It stated that compensation would be paid for "ships, materials and
contracts requisitioned." The builder was required to furnish plans
and specifications of the requisitioned ships, and a statement of
the payments made and amounts still due, and other information
"necessary to a fair and just determination of the obligations of
the Emergency Fleet Corporation in taking over these ships and
contracts."
On August 22, the Fleet Corporation caused its district officer
to deliver to the builder a formal written notice which recited
that the ships had been requisitioned and that an order had been
given the builder to complete them, and ordered the builder to
"proceed . . . in conformity with the requirements of the
contract, plans and specifications under which construction
proceeded prior to the requisition of August 3, 1917 . . . ,"
and stated:
"For the work of completion heretofore and herein ordered the
corporation will pay to you amounts equal to payments set forth in
the contract and not yet paid. . . ."
The builder accepted the order. The Fleet Corporation gave
directions to the claimant not to make, and to the builder not to
accept from claimant, any further payments on account of the
contract.
On August 28, the Fleet Corporation notified the claimant that
it had issued to the builder notice of requisition, and enclosed a
copy. The letter advised that the Fleet Corporation's district
officer had been authorized to take over claimant's inspection
officers. It requested a verified statement of the payments made to
the builder prior to requisition. It said:
"It is the present intention of the corporation to reimburse you
promptly, so far as funds are available, for the payments
heretofore made to the shipbuilder if . . . such payments are found
in order and in conformity with the contract requirements."
In requested
Page 265 U. S. 118
a statement of indirect expenditures, such as the cost of
superintendence, original design, and interest on funds already
paid, and said that the owner might submit any other matters deemed
pertinent; that it presumed that it was addressing those entitled
to receive compensation on account of the requisition of the
vessels, and asked that there be included in claimant's answer "all
evidence of ownership which is necessary to establish the right of
those who are entitled to receive the compensation provided by
law."
On December 8, 1917, the Fleet Corporation made a contract with
the builder and the American International Corporation relating to
the completion and disposal of hull No.193 and other ships
requisitioned. It required the builder to complete the ship
"in accordance with the specifications annexed to the respective
contracts under which such hulls were being constructed for the
former owners prior to August 3, 1917. . . ."
It also provided that the Fleet Corporation should have credit
for all sums theretofore received by the builder from former
owners. The Fleet Corporation agreed to indemnify the builder from
all loss or liability arising out of claims of the former owners
occasioned by the requisition order, or any subsequent acts or
orders.
January 23, 1920, the Fleet Corporation awarded claimant
$442,683.82 as just compensation. It paid the builder for
construction of the ship $412,130, which, added to the award, makes
$854,813.82. This would be the total cost to it of the ship if its
award as to compensation were accepted. The contract price was
$831,630. The cost of construction for military protection was
$31,000. The Court of Claims found that at the time of the
requisition, the value of such ships was $200 per deadweight ton,
and was the same on February 1, 1918. The Court of Claims also
found that claimant had paid to the builder $239,500 in cash,
$180,000 in notes, and $28,433.33 interest on notes,
Page 265 U. S. 119
making $447,933.33, and that it also paid architect's fees
amounting to $5,500, and furnished plans and specifications of the
value of $20,277.25, making in all $473,710.58. The amount of the
award was unsatisfactory to claimant, and 75 percent of it,
$332,012.87, was paid. The judgment was for $231,549.12. [
Footnote 2]
Both parties appeal.
Did the United States requisition claimant's
contract?
The act of Congress conferred upon the President the power to
take claimant's contract, and also to take the ship materials and
the ship in process of construction. It required compliance with
all orders issued under it. No question is raised or involved as to
the obligation of the builder to comply with orders given it to
complete the ship in accordance with the contract. It was ordered
to do so, and it accepted the order. We are not here concerned
with
Page 265 U. S. 120
its rights or obligations, but the orders given the builder show
that expropriation of claimant's contract and rights was intended.
By its orders, it put itself in the shoes of claimant, and took
from claimant and appropriated to the use of the United States all
the rights and advantages that an assignee of the contract would
have had. The credit for, and advantages under the contract
resulting from, payment of $419,500, made by claimant to builder
were taken. The use of the plans and specifications for the
construction of the ship as well as the benefit of inspection prior
to the requisition date, August 3, 1917, were also taken over. The
contract was not terminated. The direct and immediate result of the
requisition orders and acts of the Fleet Corporation was to take
from claimant its contract and its rights thereunder. Because of
material ordered and furnished and work performed prior to
requisition, the United States was enabled to obtain the ship
earlier than it could have caused a like ship to have been planned
and built, and secured the benefit of prices prevailing immediately
after the making of the contract, when the builder ordered
materials for the construction of the ship. At the time of
requisition, costs were higher than the contract prices. At that
time, and on February 1, 1918, the date fixed for completion, the
value of such ships was greatly in excess of the contract price,
and in excess of the amount awarded to claimant plus the amount
paid by the Fleet Corporation to the builder.
Omnia Commercial Co. v. United States, 261 U.
S. 502, does not support the contention that claimant's
contract was not expropriated. There, claimant had a contract
giving it an opportunity to purchase a large quantity of steel
plate from a steel company at a price under the market. If the
contract had been carried out, large profits would have resulted.
Before any deliveries were made, the United States requisitioned
the steel company's entire production of steel plate. No specific
steel plate had been
Page 265 U. S. 121
appropriated to the contract, and no part of the purchase price
had been paid. The action taken by the United States applied to the
steel company only, and created no relations with the claimant. The
contract was not kept alive nor resorted to in order to determine
anything involved in the transaction between the United States and
the steel company; the benefit of the low prices was not taken; no
payments made on account of the purchase price were taken; nothing
belonging to the Omnia Company was taken. Damages claimed were held
too remote. The differences between that case and this are
essential and obvious.
The situation in this case is well stated in the dissenting
opinion of the Chief Justice of the Court of Claims:
"If the plaintiff had voluntarily assigned its contract with the
builder to the government, and the latter had expressly assumed the
unfulfilled obligations and later received the completed vessel, it
would not more effectively have acquired plaintiff's contract, its
rights, and obligations than actually resulted from what was done
in this case. The government requisitioned the incomplete vessel
with the purpose of requiring the completion in accordance with the
existing contract; it did require the carrying out of that contract
(with slight modifications); it took plaintiff's right to have the
vessel; it received the vessel and appropriated plaintiff's partial
payments thereon to its own use and benefit."
It must be held that the claimant's contract and its rights and
interests thereunder were expropriated.
Upon what basis is just compensation to be
ascertained?
The expropriation enabled the Fleet Corporation to obtain the
ship when completed by paying the builder the installments of the
contract price remaining unpaid at the time of the requisition. The
builder was not entitled to more, because the Fleet Corporation
took over the contract and succeeded to the rights of claimant.
Page 265 U. S. 122
The award by the Fleet Corporation was made up of two items: one
was stated to be the "computed value" of material in the yard of
the builder at the time of requisition, and the other the amount of
progress payments "in excess of the cost of the materials
requisitioned." The Court of Claims held that the materials were
not the property of the claimant, but belonged to the builder, and
should not have been taken into account in arriving at the
compensation due the plaintiff. But we are of opinion that the
amount of claimant's compensation did not depend upon the legal
title to the materials during construction, that the progress
payments did not constitute the amount claimant was entitled to
have, and that the award was erroneous because of failure to find
the value of claimant's contract rights taken.
The judgment of the Court of Claims was based upon the
assumption that the money paid by claimant in furtherance of
planning and building the ship was expropriated. In the opinion, it
is said: "And the plaintiff is entitled to recover the amounts of
money requisitioned and appropriated by the United States." But
plainly there was no requisition of money.
The United States contends that nothing whatever was
requisitioned from the plaintiff, and that the judgment should be
reversed and the claim dismissed unless claimant shall be held
entitled to compensation for cancellation of its contract, and
that, in such event, it should have judgment only for an amount
sufficient, with what already has been paid to it, to make up "the
amount actually invested in the ship taken." [
Footnote 3] As we hold that claimant's contract
rights were expropriated, it is not necessary to consider what
would be just compensation in case of mere cancellation of the
contract.
Page 265 U. S. 123
The contract rights of claimant taken are to be distinguished
from its expenditures for the production of the ship. The value of
property may be greater or less than its cost, and this is true of
contract rights and other intangibles as well as of physical
things. It is the property, and not the cost of it, that is
protected by the Fifth Amendment.
Minnesota Rate Cases,
230 U. S. 352,
230 U. S. 454.
By the taking, the claimant lost and the United States obtained the
right to have the completed ship delivered to it on or before
February 1, 1918, upon payment of the installments remaining to be
paid under the contract. It is settled by the decisions of this
Court that just compensation is the value of the property taken at
the time of the taking.
Vogelstein & Co. v. United
States, 262 U. S. 337,
262 U. S. 340;
United States v. New River Collieries, 262 U.
S. 341,
262 U. S. 344;
Seaboard Air Line Ry. v. United States, 261 U.
S. 299,
261 U. S. 306;
Monongahela Navigation Co. v. United States, 148 U.
S. 312,
148 U. S. 341.
And, if the taking precedes the payment of compensation, the owner
is entitled to such addition to the value at the time of the taking
as will produce the full equivalent of such value paid
contemporaneously. Interest at a proper rate is a good measure of
the amount to be added.
Seaboard Air Line Ry. v. United States,
supra; United States v. Benedict, 261 U.
S. 294,
261 U. S. 298;
United States v. Brown, 263 U. S. 78.
Claimant insists that just compensation is the value of the
contract and its rights and interests thereunder, and is measured
by the difference between the value of the ship, as found by the
court at the time of the taking and on the date specified for
delivery, and the amount which claimant was then required under the
contract to pay in order to get the ship.
We think it not permissible so to calculate compensation. It is
the sum which, considering all the circumstances -- uncertainties
of the war and the rest -- probably
Page 265 U. S. 124
could have been obtained for an assignment of the contract and
claimant's rights thereunder -- that is, the sum that would in all
probability result from fair negotiations between an owner who is
willing to sell and a purchaser who desires to buy.
In re Mersey Docks and Admiralty Commissioners, [1920]
3 K.B. 223, is a case quite similar to this. There, the admiralty
requisitioned a barge nearing completion, altered her construction,
and paid, or undertook to pay, the builder the original contract
price. It was impossible for the board, for whom the barge was
being constructed, to replace her by another at a cost less than
three times the contract price of the original barge. By agreement,
the ascertainment of compensation to be paid by the admiralty to
the board was referred to an arbitrator. The board claimed the
difference between the contract price and cost of replacing the
barge, regard being had to the fact that replacement would be
impossible for three years, and also claimed compensation for loss
of services during the period required for replacement. The
admiralty contended that the measure of compensation should be the
difference between the contract price and value of the vessel when
taken. A special case was stated by the arbitrator. The Earl of
Reading, Lord Chief Justice, gave judgment, and held that the board
was entitled to recover the difference between the contract price
and the increased cost of replacing the barge; that the board was
not entitled to any compensation for loss of services, the damage
being too remote. He said (p. 233):
"On a broad view of the facts and without undue regard to minute
details, the court has to determine upon what principle the
compensation to be awarded to the board ought to be measured. In my
judgment, it is sufficient for the purpose of this case to say that
the board are entitled to have the property which, but for the
action of the admiralty, would have been in their possession in
April, 1917, replaced by
Page 265 U. S. 125
the admiralty. As it cannot be replaced except by the
expenditure of money, they are entitled to the amount of money
which will represent the cost to them of the replacement. This must
be measured with regard to the special circumstances arising from
the war, and, more especially, to the increase in the value of
labor and materials which has continued up to the present time. . .
. I can see no very material difference between the respective
principles contended for by counsel on behalf of the board and
counsel on behalf of the admiralty. In truth, I think that both
these principles lead to the same conclusion."
This Court has held in many cases that replacement cost is to be
considered in the ascertainment of value, [
Footnote 4] but that it is not necessarily the sole
measure of or guide to value. We are of opinion that value, so far
as material, rather than replacement cost, should be taken into
account for the ascertainment of just compensation. If the ship had
been complete and ready for delivery at the time of requisition,
claimant's just compensation would be the value of the ship less
the unpaid balance of the contract price. But the ship was not
ready, and the builder was not bound to deliver before February 1,
1918. Claimant had a right to its delivery at that time, and the
builder was ready to perform the contract. The Court of Claims,
being of opinion that claimant's contract was not taken, did not
find its value at the time of taking, and failed to find facts from
which such value appears. Determination of just compensation is to
be based on the fact that claimant's contract and its rights and
interest thereunder were expropriated, and that it is entitled to
have their value at the time of the taking. The value of
Page 265 U. S. 126
such ships at the time of requisition, and the then probable
value at the time fixed for delivery, the contract price, the
payments made and to be made, the time to elapse before completion
and delivery, the possibility that, by reason of the government's
action in control of materials, etc., the contractor might not be
able to complete the ship at the date fixed for performance, the
loss of use of money to be sustained, the amount of other
expenditures to be made between the time of requisition and
delivery, together with other pertinent facts, are to be taken into
account and given proper weight to determine the amount claimant
lost by the taking (
Minnesota Rate Cases, supra,
230 U. S. 451;
United States v. Chandler-Dunbar Co., 229 U. S.
53,
229 U. S. 76;
Boston Chamber of Commerce v. Boston, 217 U.
S. 189,
217 U. S. 195;
Monongahela Navigation Co. v. United States, supra,
148 U. S.
343); that is, the sum which will put it in as good a
position pecuniarily as it would have been in if its property had
not been taken.
United States v. New River Collieries,
supra, 262 U. S. 343;
Seaboard Air Line Ry. v. United States, supra,
261 U. S.
305.
Reversed and remanded for further proceedings in conformity
with this opinion.
MR. JUSTICE SUTHERLAND took no part in the consideration of this
case.
[
Footnote 1]
"The President is hereby authorized and empowered . . ."
"(a) To place an order with any person for such ships or
material as the necessities of the government, to be determined by
the President, may require during the period of the war and which
are of the nature, kind and quantity usually produced or capable of
being produced by such person."
"(b) To modify, suspend, cancel, or requisition any existing or
future contract for the building, production, or purchase of ships
or material."
"(c) To require the owner or occupier of any plant in which
ships or materials are built or produced to place at the disposal
of the United States the whole or any part of the output of such
plant, to deliver such output or part thereof in such quantities
and at such times as may be specified in the order."
"(d) To requisition and take over for use or operation by the
United States any plant, or any part thereof without taking
possession of the entire plant, whether the United States has or
has not any contract or agreement with the owner or occupier of
such plant."
"(e) To purchase, requisition, or take over the title to, or the
possession of, for use or operation by the United States any ship
now constructed or in the process of construction or hereafter
constructed, or any part thereof, or charter of such ship."
"Compliance with all orders issued hereunder shall be obligatory
on any person to whom such order is given, and such order shall
take precedence over all other orders and contracts placed with
such person. . . ."
"Whenever the United States shall cancel, modify, suspend or
requisition any contract, . . . it shall make just compensation
therefor, to be determined by the President, and if the amount
thereof, so determined by the President, is unsatisfactory to the
person entitled to receive the same, such person shall be paid
seventy-five percentum of the amount so determined by the President
and shall be entitled to sue the United States to recover such
further sum as, added to said seventy-five percentum, will make up
such amount as will be just compensation therefor, in the manner
provided for by section twenty-dour, paragraph twenty, and section
one hundred and forty-five of the Judicial Code."
"The President may exercise the power and authority hereby
vested in him, and expend the money herein and hereafter
appropriated through such agency or agencies as he shall determine
from time to time. . . ."
[
Footnote 2]
Claimant paid out:
Architect's fees . . . . . . . . . . $ 5,500.00
Cash to builder . . . . . . . . . . 239,500.00
Notes to builder . . . . . . . . . . 180,000.00
Interest on notes . . . . . . . . . 28,433.33
-----------
Total. . . . . . . . . . . . . . . $453,433.33
Value of plans and specifications. . 20,277.25
-----------
$473,710.58
Less 75 percent of award . . . . . . 332,012.87
-----------
Balance . . . . . . . . . . . . . $141,697.71
Interest was computed and allowed as follows:
On $473,710.58 minus $28,433.33, or $445,277.25, from August 3,
1917 (date of requisition), to February 24, 1920 (date of payment
of 75 percent of award), $68,350.06.
On $445,277.25 minus $332,012.87, or $113,264.38, from February
24, 1920 to April 23, 1923 (date of judgment), $21,501.35.
Total of interest . . . . . . . . . $ 89,851.41
Added to . . . . . . . . . . . . . . 141,697.71
-----------
Produces amount of judgment. . . . . $231,549.12
[
Footnote 3]
The figure contended for is $425,000, made up of $419,506 paid
by claimant to builder and $5,500 architect's fee. Nothing is
included to cover the value of plans, interest, or cost of
inspection.
[
Footnote 4]
Southwestern Telephone Co. v. Public Service
Commission, 262 U. S. 276,
262 U. S. 287,
and cases cited;
Bluefield Co. v. Public Service
Commission, 262 U. S. 679,
262 U. S. 689;
Georgia Railway v. Railroad Commission, 262 U.
S. 625,
262 U. S.
629.
Separate Opinion of MR. JUSTICE McREYNOLDS.
This case is of special importance because of the immense sums
involved in similar pending claims. Ten ships, some larger than
No.193, were requisitioned at Camden alone. Speaking with
constraint, the findings of the Court of Claims leave much to be
desired for ready understanding, but enough appears, I think to
support its final judgment.
Through change of name, the Brooks-Scanlon Corporation became
successor to Carpenter-O'Brien Company and
Page 265 U. S. 127
party to the written contract of March 28, 1916, under which the
New York Shipbuilding Corporation undertook to construct at its
Camden Yard a steamship of about eighty-five hundred tons
(freighter No.193), according to designated plans, on or before
February 1, 1918; $595,000, payable in installments, was the price
first stated; prior to May 25, 1917, because of changes, this was
increased to $811,130. The East Coast Transportation Company and
the New York Shipbuilding Company were the original contracting
parties. The Brooks-Scanlon Corporation acquired the former's
interest; the New York Shipbuilding Corporation those of the
latter.
The Act of Congress approved June 15, 1917, c. 29, 40 Stat. 182,
provides:
"The President is hereby authorized and empowered, within the
limits of the amounts herein authorized --"
"(a) To place an order with any person for such ships or
material as the necessities of the government, to be determined by
the President, may require during the period of the war and which
are of the nature, kind and quantity usually produced or capable of
being produced by such person."
"(b) To modify, suspend, cancel, or requisition any existing or
future contract for the building, production, or purchase of ships
or material."
"(c) To require the owner or occupier of any plant in which
ships or materials are built or produced to place at the disposal
of the United States the whole or any part of the output of such
plant, to deliver such output or part thereof in such quantities
and at such times as may be specified in the order."
"(d) To requisition and take over for use or operation by the
United States any plant, or any part thereof without taking
possession of the entire plant, whether the United States has or
has not any contract or agreement with the owner or occupier of
such plant."
"(e) To purchase, requisition, or take over the title to, or the
possession of, for use or operation by the United States any ship
now constructed
Page 265 U. S. 128
or in the process of construction or hereafter constructed, or
any part thereof, or charter of such ship."
"Compliance with all orders issued hereunder shall be obligatory
on any person to whom such order is given, and such order shall
take precedence over all other orders and contracts placed with
such person. . . ."
"Whenever the United States shall cancel, modify, suspend or
requisition any contract, make use of, assume, occupy, requisition,
acquire or take over any plant or part thereof, or any ship,
charter, or material, in accordance with the provisions hereof, it
shall make just compensation therefor, to be determined by the
President, and if the amount thereof, so determined by the
President, is unsatisfactory to the person entitled to receive the
same, such person shall be paid seventy-five percentum of the
amount so determined by the President and shall be entitled to sue
the United States to recover such further sum as, added to said
seventy-five percentum, will make up such amount as will be just
compensation therefor, in the manner provided for by section
twenty-four, paragraph twenty, and section one hundred and
forty-five of the Judicial Code. . . ."
"The cost of purchasing, requisitioning, or otherwise acquiring
plants, material, charters, or ships now constructed or in the
course of construction and the expediting of construction of ships
thus under construction shall not exceed the sum of $250,000,000,
exclusive of the cost of ships turned over to the Army and Navy. .
. ."
July 11, 1917, the President delegated his powers granted by the
statute to the United States Shipping Board Emergency Fleet
Corporation -- the "Fleet Corporation." Purporting to act as thus
authorized, and referring to ten vessels then under construction at
the Camden Yard, the Fleet Corporation notified the New York
Shipbuilding Corporation, August 3, 1917:
"All power-driven cargo-carrying and passenger ships above
Page 265 U. S. 129
2,500 tons d.w. capacity under construction in your yard, and
certain materials, machinery, equipment, outfit, and commitments
for materials, machinery, equipment, and outfit necessary for their
completion, are hereby requisitioned by the United States. On
behalf of the United States, by virtue of said act and said order,
you are hereby required to complete the construction of said
requisitioned ships under construction and will prosecute such work
with all practicable dispatch. The compensation to be paid will be
determined hereafter, and will include ships, material, and
contracts requisitioned. You will furnish immediately general plans
and detail specifications of the ships requisitioned, and copies of
contracts and all supplemental agreements in relation thereto, and
full particulars as to owner, date of completion, payments made to
date, amounts still due, and any other information necessary to a
fair and just determination of the obligations of the Emergency
Fleet Corporation in taking over these ships and contracts. You
will report immediately whether any additional contracts are under
consideration, and their character and extent, and will not enter
into any additional contracts or commitments with respect to
merchant tonnage without express authority from this
corporation."
August 18, 1917, the Fleet Corporation addressed a letter to the
East Coast Transportation Company (predecessor of Brooks-Scanlon
Corporation) giving notice of the requisition order of August 3d
and on August 28, 1917, served on the Carpenter-O'Brien Company a
substantially identical letter, which stated:
"On August 3, 1917, the United States Emergency Fleet
Corporation issued to the New York Shipbuilding Corporation the
notice or requisition set forth in enclosure 'a.'"
"In response to this communication, the New York Shipbuilding
Corporation, the shipbuilders, informed us
Page 265 U. S. 130
that the East Coast Transportation Company, as owners, or
representatives of owners, had entered into a contract with them
for the following vessel:"
"Hull No.193; type, cargo; d.w. tons, 8,100; date of contract,
3-28-16 (assigned 5-24-17)."
"Under date of August 23d, you advised that this contract had
been assigned to you."
"The corporation's district officer having charge of vessels in
the district in which the shipbuilders are located has been
instructed to take charge, for the corporation, of the completion
of vessels now under construction, and has been authorized
temporarily to take over your local inspecting officers at their
present compensation. Will you please inform the district officer,
Mr. G. R. McDermott at room 302, 1319 F. Street N.W. Washington,
D.C. the names of your representatives and their compensation,
sending a duplicate to this office. Your cooperation with the
corporation is invited."
"The corporation will consider payments to the contractor
accruing since the date of requisition, upon the receipt of proper
vouchers and adequate information to be forwarded through its
district officers."
"You are requested, as soon as possible, to report to the
corporation a statement in detail of the payments already made by
you on each ship named above prior to the date of the
requisitioning, August 3, 1917. This statement should be
accompanied by the original vouchers and receipts, and should be
verified under oath by the proper corporate officer of your
company."
"It is the present intention of the corporation to reimburse you
promptly, so far as funds are available, for the payments
heretofore made to the shipbuilder if after investigation of data
submitted by you such payments are found in order and in conformity
with the contract requirements."
"At your further and early convenience, you are requested to
submit to the corporation a statement of such
Page 265 U. S. 131
indirect expenditures as you have made on account of each vessel
-- for instance, the cost of superintendence, original design,
interest on funds already paid, and the like. The matters mentioned
will require careful audit, and in addition you may submit any
other matters you deem pertinent."
"It will be perceived that the corporation presumes it is
addressing this letter to the owners, or responsible
representatives of the owners, or persons entitled to receive
compensation on account of the requisition of the vessels listed
above. The corporation requests that there be included in your
response to this letter all evidence of ownership which is
necessary to establish the right of those who are entitled to
receive the compensation provided by law."
"The consummation of the orders herein and heretofore
transmitted will be made the subject of later appropriate corporate
action."
August 22, 1917, the Fleet Corporation, through General Manager
Capps, forwarded the following letter to Agent McDermott, and, as
directed, the latter promptly delivered a copy thereof to the New
York Shipbuilding Corporation with request that it govern itself
accordingly.
"Dear Sir: Referring to the vessels under construction in the
yard of New York Shipbuilding Corporation, Camden, N.J.,
requisitioned under the corporation's order of August 3d precedent
to the final examination of the contract for the vessels in
question, you are requested to inform the shipbuilder as
follows:"
"The ships now under construction at your plant and referred to
above having been requisitioned by the duly authorized order of
this corporation and title thereto taken over by the United States,
and an order having been placed with you by due authority to
complete the construction of said ships with all practicable
dispatch, you
Page 265 U. S. 132
are further ordered by the President of the United States,
represented by this corporation, to proceed in the work of
completion heretofore ordered, in conformity with the requirements
of the contract, plans, and specifications under which construction
proceeded prior to the requisition of August 3, 1917, insofar as
the said contract describes the ship, the materials, machinery,
equipment, outfit, workmanship, insurance, classification, and
survey thereof, including the meeting of the requirements of the
said contract and all tests as to efficiency and capacity of the
ship on completion, and insofar as the contract contains provisions
for the benefit and protection of the person with whom the contract
was made, but not otherwise."
"All work will proceed under the inspection of such persons as
have been or may hereafter, from time to time, be designated by
this corporation for that purpose."
"For the work of completion heretofore and herein ordered the
corporation will pay to you amounts equal to payments set forth in
the contract and not yet paid: Provided, that, on acceptance in
writing of this order, you agree that, on final acceptance of the
vessel to give a bill of sale to the United States in satisfactory
form, conveying all your right, title, and interest in the vessel,
together with your certificate that the vessel is free from liens,
claims, or equities, with the exception of those of the owner, and
then only to those set forth in the contract. Compensation to the
shipbuilder for expedition and for extra work will, when deemed
appropriate, be made the subject of a subsequent order."
"This order applies only to vessels actually under construction,
and, in accepting it, the corporation expects you to inform it of
the actual stage of construction of each vessel or the part to be
assembled therein on the date of requisitioning, August 3, 1917.
The corporation reserves the right to decide whether or not a
vessel was actually under construction on August 3, 1917, on
consideration of the ascertained facts. "
Page 265 U. S. 133
"In replying to this communication, please arrange to specify
separately the vessels to which this order refers, and refer to the
corresponding contract in sufficient terms for identification of
it."
"Please furnish a copy of this to New York Shipbuilding
Corporation and ask for an early reply."
"Very truly yours,"
"W. L. Capps, General Manager"
Replying, September 20, 1917, the Shipbuilding Corporation
advised the Emergency Fleet Corporation:
"Referring to the order dated August 22, 1917, made by United
States Shipping Board Emergency Fleet Corporation, and delivered to
this company, we beg to say:"
"We understand that, by the Act of Congress of June 15, 1917,
entitled 'An act making appropriations for the Military and Naval
Establishments on account of war expenses for the fiscal year
ending June 30, 1917, and for other purposes,' and the executive
order dated July 11, 1917, made by the President with respect to
said act, and transmitted to us by the Emergency Fleet Corporation
under date of August 3, 1917, we are under obligation to comply
with the order of the Emergency Fleet Corporation dated August 3,
1917, requisitioning ships at this company's plant."
"This corporation therefore accepts United States Shipping Board
Emergency Fleet Corporation's order dated August 22, 1917, for the
completion of the vessels under contract in this yard on August 3,
1917, known as hull No. ___, and agrees that, upon the completion
and acceptance of said vessels and upon complete payment [by]
United States Shipping Board Emergency Fleet Corporation, together
with such additional compensation as may be agreed upon, this
company will execute and deliver to the United States of America a
bill of sale conveying all this company's right, title, and
interest in the vessels without prejudice to any claim of the
person or corporation
Page 265 U. S. 134
who originally contracted for the construction of said vessels,
and those claiming rights under such original contractor, together
with our certificate that the vessels are free from liens, claims
or equities except such liens, claims, or equities as may be
asserted by, or exist in favor of, the person or corporation who
originally contracted for the construction of the vessels, and
those claiming rights under such original contractor."
September 13, 1917, the Fleet Corporation telegraphed the
Shipbuilding Corporation: "Do not accept further payments from
former owners on account of requisitioned ships. This is
mandatory."
December 8, 1917, the Shipbuilding Corporation and the Fleet
Corporation agreed --
"On and prior to August 3, 1917, the Shipbuilding Corporation
was constructing under private contract with the corporations named
below [hereinafter called 'former owners'] ships bearing the hull
numbers of the type and for the contract prices set opposite their
respective names. . . . [There were 10 of them.]"
"Due to war conditions, such contract prices have proved and
will prove to be less than the actual cost of constructing such
ships. On August 3, 1917, all of such ships, together with the
materials assembled therefor, were requisitioned by the Fleet
Corporation, acting in accordance with the provisions of the Urgent
Deficiency Act of June 15, 1917, and the executive order of July
11, 1917. The Shipbuilding Corporation. by such requisition. was
directed to complete such ships on behalf of the United
States."
"The parties hereto desire to fix the just compensation to be
paid to the Shipbuilding Corporation in accordance with the
provisions of such Urgent Deficiency Act, and to that end the Fleet
Corporation is willing to increase such contract prices. . . ."
"The Fleet Corporation hereby agrees to pay to the Shipbuilding
Corporation as just compensation for the
Page 265 U. S. 135
completion of said ten ships, hulls Nos. ___ the entire cost of
construction of said ships, figured from the commencement by the
Shipbuilding Corporation of the construction of said ten ships up
to the times of completion thereof respectively, and in addition
thereto with respect to each ship ten dollars ($10) per dead-weight
ton for profit. There shall be credited, however, in favor of the
Fleet Corporation all sums heretofore received by the Shipbuilding
Corporation on account of the construction of such ten ships
respectively, either from the former owners or from the Fleet
Corporation."
The amended petition, filed June 12, 1920 -- prior to our
decision of
Omnia Commercial Co. v. United States,
261 U. S. 502,
261 U. S. 513
-- and upon which the cause was tried, alleges:
"That said builder, the New York Shipbuilding Company, had, up
to the 3d day of August, 1917, duly contracted for all of the
materials, equipment and supplies sufficient to complete said ship
as specified in said contract, and that a large portion of such
material, equipment and supplies had been duly prepared and
delivered to the yard of said builder on said day, and that the
remainder thereof, sufficient to complete said ship, had been duly
contracted for by said builder and was thereafter delivered under
the provisions of said contracts and entered into the construction
and completion of said ship, and that said builder had performed
and caused to be performed a large amount of labor under said
contract upon, in, and about the construction of said ship, and
that said builder had duly paid for said contracts for material,
equipment, and supplies, the delivery thereof, and for the labor
furnished and performed in and about such construction by moneys so
paid to said builder by said owner as herein stated, and that said
builder, on the 3d day of August, 1917, on its part, had fully
complied with the terms of said contract, and was then and was
always thereafter
Page 265 U. S. 136
ready, able, and willing to complete the same in all
particulars. . . ."
"That, on June 15, 1917, by Chapter 29, 40 Statutes at Large
182, Congress authorized the President, among other things, to
modify, suspend, and cancel or requisition any existing or future
contract for the building, production, or purchase of ships or
materials, etc., and further to purchase, requisition, or take over
the title to or the possession of, for use or operation by the
United States, any ship then constructed or in the process of
construction, or thereafter constructed, or any part thereof, or
the charter of said ship. In further accordance with said act of
the President, by order dated July 11, 1917, deputed to the United
States Shipping Board Emergency Fleet Corporation full power to act
thereunder including the power to provide just compensation
therefor, and the said corporation, by its order of August 3, 1917,
on behalf of the United States, took over all the property of the
claimant in or under said contract, including the said ship under
construction and all materials, machinery, equipment, outfit and
commitments therefor, and all labor performed thereon necessary for
its completion, meaning thereby everything in existence and as
expressed in said order 'required to complete the construction of
said requisitioned ships under construction,' as will more fully
appear by reference to the order of W. L. Capps, General Manager,
which reads as follows. [Here follows copy of requisition notice to
the Shipbuilding Corporation dated August 3d and enclosed in letter
of August 28th addressed to Carpenter-O'Brien Company.] . . ."
"That said requisition order was fully complied with, and all of
the property of said owner, the claimant herein, hereinbefore
described, was taken by the said United States Shipping Board
Emergency Fleet Corporation for and on behalf of the United States,
and was thereafter retained by and used for the purposes of the
United States
Page 265 U. S. 137
as provided by law, and that the said owner was thereby and
thereafter deprived of all of its use and value. That said ship so
taken was then under construction by said builder, and thereafter
was fully completed without change of plans or specifications from
those set forth in the said construction contract as amended and
supplemented, and that the said materials, equipment, outfit, and
supplies, and the said commitments and contracts for materials,
equipment, outfit, and supplies as described in said requisition
order and paid for by the said owner and taken as aforesaid, were
actually used in the construction and completion of said ship and
were substantially sufficient to so construct, complete, equip, and
supply said ship as described in said plans and specifications as
amended and supplemented. . . ."
"That a fair and reasonable value of the said property so
requisitioned and taken, and of which said owner was deprived on
said 3d day of August, 1917, as aforesaid, was at the rate of two
hundred fifty dollars ($250) per ton for 8,597 dead weight tons,
the sum of two millions one hundred forty-nine thousand two hundred
fifty dollars ($2,149,250) less the sum of four hundred twelve
thousand one hundred thirty dollars ($412,130) as aforesaid
(required to be paid by said owner to said builder under the
provisions of said construction contract as amended and
supplemented, in order to fully complete, supply and equip said
ship in accordance with the terms and conditions of said
construction contracts hereinbefore set forth), so that the total
amount due to said claimant on the said 3d day of August, 1917, on
account of the transactions hereinbefore set forth was the sum of
one million seven hundred thirty-seven thousand one hundred twenty
dollars ($1,737,120)."
The ship was finally completed and delivered September 20,
1918.
Departing from the theory of the complaint, petitioner now
maintains that its right and interest in the shipbuilding
Page 265 U. S. 138
contract were expropriated by the United States for public use;
that the contract itself was requisitioned, not frustrated, and
that compensation must be made for the full value of the contract
as of the date when so taken. The Court of Claims denied this
demand, but held petitioner should receive the sum of partial
payments which it made to the shipbuilder under the contract prior
to the requisition order of August 3, 1917, with interest.
I can find no sufficient basis for holding that the Fleet
Corporation expropriated the claimant's contract or intended so to
do, or consciously assumed liability for the value thereof.
Claimant never had either title to or possession of the vessel. It
was only a responsible party to an executory contract for
construction, always subject to frustration by condemnation of the
vessel.
The order of August 3d addressed only to the Shipbuilding
Corporation, plainly recites that:
"all power-driven cargo-carrying and passenger ships above 2,500
tons d.w. capacity, under construction in your yard, and certain
materials, machinery, equipment, outfit, and commitments for
materials, machinery, equipment, and outfit necessary for their
completion are hereby requisitioned by the United States."
On that date, the Shipbuilding Corporation had possession of the
ship as well as title thereto. The United States then assumed
control and the immediate result was to frustrate the building
contract. Frustration by the exercise of the power of eminent
domain was an implied condition. The United States became liable to
the owner -- the Shipbuilding Corporation -- for the value of
property actually taken. What that value was we need not inquire;
the builder accepted the requisition order and the agreement of
December 8th, and does not now seek to recover more.
Certainly no notice concerning requisition went to the
Brooks-Scanlon Corporation prior to the letters of August 18th and
28th, whereas the building contract had been frustrated by taking
the ship on August 3d.
Page 265 U. S. 139
The communication of August 22d to the Shipbuilding Corporation
referred to the vessels in the yard as having been "requisitioned
under the corporation's order of August 3d precedent to the final
examination of the contract for the vessels in question," and
"title thereto taken over by the United States," directed their
completion in conformity with contract, etc., which existed on that
date, and stated that
"for the work of completion heretofore and herein ordered the
corporation will pay to you amounts equal to payments set forth in
the contract and not yet paid,"
with a certain important proviso.
On September 20th, the Shipbuilding Corporation recognized that
the ship had been requisitioned by the order of August 3d and
promised to complete upon payment of compensation named in original
contract and "such additional compensation as may be agreed
upon."
The telegram of September 13th referred to "requisitioned
ships." The contract of December 8th recites that, "on August 3,
1917, all of such ships, together with the materials assembled
therefor, were requisitioned by the Fleet Corporation."
The notices addressed to East Coast Transportation Company and
Carpenter-O'Brien Company, August 18th and 28th, indicate that, on
August 3d, the Fleet Corporation was unaware of the parties to or
the terms of the building contract. These notices declared a
purpose to "consider payments to the contractor accruing since the
date of requisition," and an intention "to reimburse you promptly,
so far as funds are available, for the payments heretofore made to
the shipbuilder," and further:
"It will be perceived that the corporation presumes it is
addressing this letter to the owners, or responsible
representatives of the owners, or persons entitled to receive
compensation on account of the requisition of the vessels listed
above."
The reported facts seem inconsistent with any definite purpose
by the Fleet Corporation to requisition the contract,
Page 265 U. S. 140
as distinguished from the vessel itself -- certainly, there was
no apparent reason for any such action. It expressed a purpose to
reimburse for payments made under the building contract and to
consider such sums when seeking to determine compensation for the
shipbuilder. It also demanded that the builder should complete the
vessel as provided by the contract. The builder acquiesced, and its
rights are not now in controversy. The right of the claimant to
reimbursement for the actual payments which it made under the
contract prior to frustration is not challenged; it was properly
considered in adjusting the sums to be paid to all parties. I can
see no sufficient reason for awarding the value of a contract which
perhaps might have been realized if the United States had not
exercised their clear right to take over the partially completed
vessel. No such claim was advanced by the petition; there was ample
power in the Fleet Corporation to frustrate the building contract,
and there seems no necessity for interpreting its action as
accomplishing more. The Fleet Corporation evidently intended to
requisition the vessel, and when claimant filed its petition in
1920, it does not seem to have thought the contract had been
requisitioned. A few vague and general words used in the hurry of
the times and without full information ought not to place an
enormous, wholly unnecessary, and unanticipated burden on the
public treasury.
The amended petition upon which the cause was tried proceeds
upon the theory that claimant was owner of the vessel; that, prior
to August 3, 1917, the builder had duly contracted for all
necessary material and supplies to complete the ship, performed
much labor thereon, and had paid for all these things out of moneys
received from the
owner. It distinctly alleges that the
Fleet Corporation,
"by its order of August 3, 1917, on behalf of the United States,
took over all the property of the claimant in or under said
contract, including the said ship under construction
Page 265 U. S. 141
and all materials, machinery, equipment, outfit and commitments
therefor, and all labor performed thereon necessary for its
completion, meaning thereby everything in existence and as
expressed in said order 'required to complete the construction of
said requisitioned ships under construction.' . . . That said
requisition order was fully complied with and all of the property
of said owner, the claimant herein, hereinbefore described, was
taken by the said United States Shipping Board Emergency Fleet
Corporation for and on behalf of the United States, and was
thereafter retained by and used for the purposes of the United
States as provided by law."
The court below -- rightly, I think -- declared:
"The intent and purpose of the Shipping Board was therefore to
requisition ships under construction, which was done in
unmistakable language. It is admitted that the ships under
construction, the materials, and so forth in the yard of the New
York Shipbuilding Corporation were the property of that
corporation, and the title to that property was in the Shipbuilding
Corporation alone. Among the ships under construction so
requisitioned was hull 193, which the Shipbuilding Corporation was
building for the Carpenter-O'Brien Corporation, but it is not
contended by the plaintiff that it had any title to or interest in
said ship or the materials for its completion. All the interest it
had was the right to the delivery of the ship when it should be
completed. It follows that the United States did not take or
requisition the ship or materials from the Carpenter-O'Brien
Corporation, nor did the United States take over or requisition the
contract which the Carpenter-O'Brien Corporation had with the
Shipbuilding Corporation."
"It was made plain to the Carpenter-O'Brien Corporation that the
United States did not intend to requisition the contract, for on
August 28, 1917, after notifying the
Page 265 U. S. 142
Carpenter-O'Brien Corporation that it had taken over and
requisitioned this ship from the Shipbuilding Corporation, the
Shipping Board, by letter of that date, stated what its intention
was. A copy of said letter is set forth in full in finding VI. As
further evidence showing the intention of the Shipping Board,
reference is made to the letter of the board to G. R. McDermott,
its officer, and which was communicated to the Shipbuilding
Corporation. A copy of this letter is set forth in finding VIII.
And as final evidence that the United States did not requisition
the contract, and never intended to, the United States entered into
a contract with the Shipbuilding Corporation for the completion of
all ships under construction in its yard, included in which ships
was hull 193, thereby making its own contract for the completion of
this ship. This contract is set out in finding XVI. It is true that
the plaintiff, by reason of the requisitioning of the ship by the
United States, was deprived of the right to have delivered to it
the ship when completed."
"But there has been in this case no direct taking of the
contract. The injury inflicted upon the plaintiff is a
consequential injury resulting from the exercise of a lawful power
in the requisitioning of the ship under construction. The
requisitioning has worked indirectly harm and loss to the
plaintiff, but not such harm and loss as can be held to obligate
the government to pay for it. The action of the government may have
destroyed the worth of the contract, but the law affords no remedy.
The government, by requisitioning the subject matter of the
contract, does not thereby take the contract. The subject matter in
this case was the ship under construction, and that was what the
government requisitioned, not the contract which was the agreement
and obligation to perform. The performance of the contract in this
case was frustrated, and not appropriated. 'Frustration and
appropriation are essentially different things.'
Omnia
Commercial Co. v. United States, supra. "
Page 265 U. S. 143
The principles involved have been so recently discussed in
Omnia Commercial Co. v. United States that it seems
unnecessary to restate them. We there said:
"In the present case, the effect of the requisition was to bring
the contract to an end, not to keep it alive for the use of the
government. The government took over during the war railroads,
steel mills, ship yards, telephone and telegraph lines, the
capacity output of factories and other producing activities. If
appellant's contention is sound, the government thereby took and
became liable to pay for an appalling number of existing contracts
for future service or delivery, the performance of which its action
made impossible. This is inadmissible. Frustration and
appropriation are essentially different things."
The evidence fails to show any definite purpose by the Fleet
Corporation to requisition the contract. Up to the time of
instituting suit, the claimant evidently was unaware of any such
requisition. And it seems to me clear enough that the court below
rightly concluded that the demand now advanced is without
merit.
MR. JUSTICE SANFORD concurs in this opinion.