A judgment of the Circuit Court of Appeal, in an action on a
contractor's bond brought by a creditor under the Federal
Materialmen's Act, which affirm the district court in holding the
action not premature and in adjudicating the amount due the
plaintiff, but remanded the case for jury trial of the claim of
intervening creditors, and settles neither the amount of the claim
to be allowed against the bond nor the proportionate share of each
creditor if the bond prove inadequate to pay all, does not finally
and completely dispose of the subject matter of the litigation
either as to the parties or the causes of action involved, and
cannot be brought here by writ of error. P.
263 U. S.
432.
Writ of error or to review 280 F. 338 dismissed.
Error to a judgment of the circuit court of appeals which
modified a judgment of the district court in an action under the
Materialmen's Act and remanded the cause for further
proceedings.
MR. JUSTICE SANFORD delivered the opinion of the Court.
This action was brought by a subcontractor, in the name of the
United States, in a federal district court in South Carolina under
the Materialmen's Act Aug. 13, 1894, c. 280, 28 Stat. 278, as
amended by the
Page 263 U. S. 428
Act of Feb. 24, 1905, c. 778, 33 Stat. 811, to recover on a
contractor's bond for the construction of a naval storehouse.
Judgment was had against the contractor and his surety for the full
penalty of the bond. The circuit court of appeals modified this
judgment and remanded the cause to the district court for further
proceedings. 280 F. 338.
The case has been brought here by writ of error, and many errors
have been assigned going to the merits of the controversy. The
record, however, presents the preliminary question whether the
judgment of the circuit court of appeals has such finality and
completeness that it may be reviewed by this Court under the
writ.
The Materialmen's Act, as amended, provides [
Footnote 1] that the usual penal bond executed by
anyone entering into a contract with the United States for the
construction of any public work shall contain an additional
obligation for the payment by the contractor of all persons
supplying labor and materials in the prosecution of the work. Any
such person not thus paid may intervene in any action instituted by
the United States on the bond and obtain judgment
pro rata
with other intervenors, subject to the priority of the claim of the
United States. And if no suit is brought by the United States
within six months from the completion and final settlement of the
contract, any such person shall have a right of action upon the
bond, and may, within a specified time, bring suit against the
contractor and his surety, in the name of the United States, for
his use and benefit, in the federal court of the district in which
the contract was performed and prosecute the same to final judgment
and execution. Where suit is so instituted by a creditor, only one
action shall be brought, and any creditor may file his claim
therein and be made a party thereto within
Page 263 U. S. 429
a specified time. And if the recovery on the bond is inadequate
to pay the amount due to all of said creditors, judgment shall be
given to each creditor
pro rata of the amount of the
recovery.
The independent right of action given a materialman or laborer
by the amended Act is to be enforced in a proceeding at law, and
not in equity.
Illinois Surety Co. v. Peeler, 240 U.
S. 214,
240 U. S. 224.
All claims under the bond are to be presented in a single action,
in which every claimant may intervene and be heard as a party, and
this action is to proceed as a single case, in which the several
claimants are not entitled to separate trials as of right, although
in exceptional instances, for special and persuasive reasons, the
distinct causes of action asserted by them may be made the subject
of separate trials.
Miller v. Bonding Co., 257 U.
S. 304,
257 U. S.
307-308.
The situation presented in the instant case is this: Arnold, one
of the plaintiffs in error, in October, 1917, entered into a
contract with the United States to construct a storehouse in the
Navy Yard at Charleston, South Carolina. He executed a bond for
$65,190 in conformity to the act with the Globe Indemnity Co., the
other plaintiff in error, as surety.
In November, 1920, the firm of Guimarin & Co., as use
plaintiff, brought this action on the bond in the Federal District
Court at Charleston, against Arnold and the Indemnity Company to
recover a balance of $7,725.52, with interest, alleged to be due it
from Arnold under a subcontract for supplying the plumbing and
other material in the storehouse. The complaint alleged that
Arnold's contract with the United States had been completely
performed and finally settled on April 17, 1920, and that the
United States had not entered suit on the bond. The defendants
answered, denying liability on
Page 263 U. S. 430
various grounds, specifically denying that Arnold's contract had
been finally settled on April 17, or that more than six months had
elapsed since its completion or final settlement, and averring that
the court was without jurisdiction because no such final settlement
had been made. [
Footnote 2]
Various other creditors filed intervening petitions in the case,
setting up their claims, but neither the number nor the amount of
these claims appears in the record.
At the hearing, in June, 1921, the court held, over the
defendant's objection, that the principal cause should be tried
first, and that, "if a breach of the bond was established,"
judgment could then be rendered and other claimants permitted to
assert their several claims "to share in the fund thus created."
[
Footnote 3] The case was then
tried upon the issues relating to the claim of Guimarin & Co.,
and a verdict rendered by direction, finding that Arnold's contract
had been completely performed and finally settled on April 16,
1920, and that Guimarin & Co. was entitled to recover under its
subcontract $7,693.31, with interest. The court thereupon, without
entering any separate judgment upon this verdict in favor of
Guimarin & Co., ordered that the cause be referred to a special
master to take proof and report as to the claims of intervening
creditors, and entered a judgment that the United States recover of
the defendants $65,190, the penalty of the bond, with costs.
Page 263 U. S. 431
Arnold and the Indemnity Company, before execution of the order
of reference, sued out a writ of error for the review of this
judgment by the circuit court of appeals. There appears to have
been no citation under this writ to the intervening creditors, and
no appearance by them in the circuit court of appeals. [
Footnote 4]
The circuit court of appeals, after disposing, adversely to
Arnold and the Indemnity Company, of various assignments of error
relating to the alleged prematurity of the suit and the claim of
Guimarin & Co., said:
"Considering the action to be taken upon the judgment in this
case, it seems to us, the same having been fully tried so far as
the plaintiffs are concerned, . . . that the action of the lower
court should not be disturbed in its ascertainment of the amount
due plaintiffs. The court instructed the jury to find for the
plaintiffs, and properly so, . . . and the judgment should be
treated as that of a judgment on the bond, along with other
petitioners, when judgments are rendered in their favor. The
judgment . . . directing the reference to a master to pass upon the
claims of the several petitioners should be modified, and a jury
trial awarded, to determine in a single trial the amounts due the
several petitioners. . . . The court's idea, manifestly, in
entering this judgment for the full penalty, was that, under South
Carolina practice, such action constituted a forfeiture of the
bond, and enabled persons in the position of the plaintiffs and the
petitioners to come in and assert their claims, the aggregate not
to exceed the amount of the bond, so far as the surety was
concerned. . . . It is evident . . . that
Page 263 U. S. 432
the court held, and meant to hold, that the contract between R.
H. Arnold & Co. and the United States . . . had been fully
performed, and final settlement made on the 16th day of April,
1920, and that there was due to the plaintiffs from the general
contractor the sum of $7,693.31, with interest, . . . and that,
suit having been instituted upon the bond in the name of the United
States, suing for the use of W. B. Guimarin & Co., judgment
should be entered in favor of the United States for the sum of
$65,190, the penal sum of the bond, . . . to be discharged by the
payment to the said Guimarin & Co. of $7,693.31, with interest
. . . until paid, together with costs; . . . it appearing [
Footnote 5] that the plaintiffs' and
petitioners' claims combined do not exceed the penal sum of said
bond. We think the judgment, as thus understood, is correct, and
should be so modified, and that the several petitioners, upon
ascertainment of the amounts respectively due them, should be
entitled to like judgments, the total judgments, including that of
the plaintiffs herein, not to exceed the penalty of the bond. The
decision of the lower court, as herein modified, will be approved
and affirmed."
Judgment was thereupon entered modifying the judgment of the
district court "as set forth in the opinion," affirming it as
modified, and remanding the cause for further proceedings in
accordance with the opinion.
It is evident that this judgment of the circuit court of appeals
does not finally and completely dispose of the subject matter of
the litigation, either as to the parties or the causes of action
involved. Looking to its substance, it adjudges, at the most, that
the action was not prematurely brought and is to be sustained for
the benefit of Guimarin & Co. and of the intervening creditors,
and that
Page 263 U. S. 433
the defendants are liable on the bond for the amount found by
the verdict to be due Guimarin & Co. and for such additional
amounts as may hereafter be found, on the jury trial awarded, to be
due the intervening creditors, the aggregate amount of such
recoveries, however, not to exceed the penalty of the bond. It does
not adjudge the amounts which either Guimarin & Co. or the
intervening creditors will ultimately be entitled to recover on the
bond, but, for these purposes, remands the cause to the district
court for further proceedings. If, upon the ascertainment of the
amounts due the intervening creditors, the aggregate amount of the
claims of Guimarin & Co. and of the intervening creditors are
less than the penalty of the bond, it is adjudged that they will be
entitled to recoveries for the full amount of their claims; but if
the aggregate amount exceeds the penalty of the bond, they can only
recover, under the express provision of the statute,
pro
rata of the amount of such penalty. In short, this judgment
does not determine the ultimate amount which Guimarin & Co. may
recover on the bond, the amounts which the intervening creditors
may recover, or the amount of the ultimate liability of the
defendants on the bond; it adjudicates neither the amount of the
claims which are to be finally allowed against the fund created by
the bond nor the proportionate share of each creditor in such fund
if inadequate to pay the amounts due all the creditors.
In
La Bourgogne, 210 U. S. 95,
210 U. S. 112,
a proceeding in admiralty by the owner of a vessel for limitation
of liability arising from a collision, it was held that a decree
adjudging that the owner was entitled to the limitation sought,
declaring that one class of claims could not be proved against the
fund, and remitting all questions concerning other claims for proof
prior to final decree was not a decree from which an appeal lay to
this Court, since the case not only involved primarily the owner's
right to limitation of liability,
Page 263 U. S. 434
but "further involved the nature and amount of claims which
would be allowed against the fund," which had not been finally
disposed of by the decree. So here, the action brought by Guimarin
& Co. involves not merely the liability of the defendants on
the bond, but also the amount of the claims which may be allowed
against the fund created by the bond, which cannot be determined
until after further proceedings are had in the district court on
the remanding of the cause pursuant to the judgment of the circuit
court of appeals.
It is well settled that a case may not be brought here by writ
of error or appeal in fragments; that, to be reviewable, a judgment
or decree must be not only final, but complete -- that is, final
not only as to all the parties, but as to the whole subject matter,
and as to all the causes of action involved, and that, if the
judgment or decree be not thus final and complete, the writ of
error or appeal must be dismissed for want of jurisdiction.
Hohorst v. Packet Co., 148 U. S. 262,
148 U. S. 264;
Collins v. Miller, 252 U. S. 364,
252 U. S. 370;
Oneida Navigation Corp. v. Job, 252 U.
S. 521,
252 U. S. 522,
and cases therein cited.
And it is clear that the present case does not come within the
seeming exception to this rule that an adjudication, final in its
nature as to a matter distinct from the general subject of the
litigation and affecting only the parties to the particular
controversy, may be reviewed without awaiting the determination of
the general litigation.
See Williams v. Morgan,
111 U. S. 684,
111 U. S. 699,
and
Collins v. Miller, supra, p.
252 U. S. 371.
There has been no final adjudication of the amount which Guimarin
& Co. is entitled to recover on the bond, and, furthermore, its
right to a recovery is not distinct from the general subject of the
litigation, but involves the determination of questions affecting
the intervening creditors, who are likewise parties to the suit, as
well as itself, and which, under the statute, are to be determined
in a single action.
Page 263 U. S. 435
For these reasons, although, as in
Oneida Navigation Corp.
v. Job, supra, the objection was not raised by the defendant
in error, [
Footnote 6] the writ
of error to the circuit court of appeals is
Dismissed for want of jurisdiction.
[
Footnote 1]
The amended Act is set forth in full in the margin of the
opinion in
Texas Cement Co. v. McCord, 233 U.
S. 157,
233 U. S. 161,
n. 1.
[
Footnote 2]
Under the provisions of the amended Act, an action brought by a
creditor before six months have expired from the time of the
completion and final settlement of the principal contract is
premature, and cannot be sustained.
Texas Cement Co. v.
McCord, 233 U. S. 157,
233 U. S. 163;
Illinois Surety Co. v. Peeler, supra, p.
240 U. S.
217.
[
Footnote 3]
This was several months before the decision in
Miller v.
Bonding Co., supra. The defendants stated at the time that, if
the claims of all intervenors were not tried in the main case
before the same jury, they would oppose any subsequent trial of
claims not then presented on the ground that such claims would be
"foreclosed."
[
Footnote 4]
The record does not contain either the writ of error or the
citation, but shows the entry of appearance for "the defendant in
error." The circuit court of appeals, in its opinion, refers to
Guimarin & Co. as "the defendant in error," and the citation
under the present writ of error is directed only to the United
States for the use of Guimarin & Co.
[
Footnote 5]
The words "it appearing" are manifestly used, as the context
shows, in the sense of "if it appears," the amount of the
petitioners' claims, as already stated, not appearing in the
record.
[
Footnote 6]
A motion to dismiss the writ of error, the consideration of
which was passed to the hearing, was based on other grounds.