A building contract, made through the War Department, provided
that the contractor should be reimbursed for such actual net
expenditures in the performance of the work as might be approved or
ratified by the contracting officer, including "such bonds, fire,
liability, and other insurance as the contracting officer may
approve or require;" that monthly statements of costs should be
made, upon which, in case of disagreement, the decision of the
contracting officer should govern, and that statements so made and
all payments made thereon should be final and binding on both
parties.
Held that where a payment made by the contractor
as a premium on its bond to secure the performance of the contract
was thus approved and repaid as part of the cost of the work, the
decision and action of the officer were conclusive, and that the
Comptroller of the Treasury was without power to deduct the amount
from other moneys due the contractor upon the ground that the
expense was not among those for which the contract promised
reimbursement. P.
260 U. S.
325.
56 Ct.Clms. 238 affirmed.
Appeal by the United States from a judgment of the Court of
Claims. A rehearing was granted in this case, but, after
reargument, the judgment below was again affirmed, April 9, 1923,
by a per curiam decision, which will be reported in volume 261.
Page 260 U. S. 324
MR. JUSTICE McKENNA delivered the opinion of the Court.
Appeal from a judgment of the Court of Claims which awards the
appellee, plaintiff in the Court of Claims, the sum of $12,064.52,
composed of three sums, which are, respectively, of the amounts of
$2,500, $450, and $9,114.52. The last two sums the United States
does not contest. The sum of $2,500 is only therefore in question.
The amount is charged to be due (as the other sums were) upon what
are called "cost plus contracts" for the construction of certain
buildings at Camp Zachary Taylor, near Louisville, Kentucky.
It is provided in Article II of the contract that
"the contractor shall be reimbursed . . . for such of its actual
net expenditures in the performance of said work as may be approved
or ratified by the contracting officer. . . . (h) Such bonds, fire,
liability, and other insurance as the contracting officer may
approve or require, and such losses and expenses, not compensated
by insurance or otherwise, as are found and certified by the
contracting officer to have been actually sustained (including
settlements made with the written consent and approval of the
contracting officer) by the contractor in connection with said
work, and to have clearly resulted from causes other than the fault
or neglect of the contractor. . . ."
The United States contends that, within the meaning of Article
II, the premium paid on a bond of $250,000, that being the amount
fixed by the War Department, was not an expenditure in the
performance of the work. The Court of Claims decided the contrary,
and supported its decision by the action and approval of the War
Department. And there was no hesitation on the part of the
department. It recognized the obligation of the government under
the contract to pay to the contractor the
Page 260 U. S. 325
amount of premium, and negotiated with the surety companies for
a reduction of it in the interest of the government. The premium
was approved by the contracting officer as required by Article II
and paid as part of the cost of the work, and was not questioned
for over two years. Its amount was later deducted from other sums
due the contractor.
What is the import of this practical interpretation? The
government does not contend that the words of the contract were
dictated by statute. They are therefore the words of the
contracting officer to express and provide for the purpose of the
government in exercise of the duty with which he was charged, and
used as a declaration and measure of the rights and obligations of
the parties to the contract. His subsequent conduct is necessarily
to be considered a definition of them. The officer, in a sense, is
a party to the contract, not only representing, but speaking for,
the impersonality of the government. Competent, therefore, it would
seem, to declare the meaning of the contract.
We are, however, not called upon to pass upon the conflicting
contentions. The contract contains other provisions that determine
the liability of the government.
Article IV of the contract provides for a monthly statement of
the elements of costs upon which, if there be disagreement, the
decision of the contracting officer "shall govern." It is further
provided that "the settlement so made and all payments made thereon
shall be final and binding upon both parties hereto, except as
provided in Article XIV hereof." Article XIV requires the contract
to be interpreted as a whole, not by any special clause, and takes
care to reserve the determining decision to the officers concerned
with the work, the final decision being that of the Secretary of
War. Article IV, indeed, is the complement and elaboration of the
provision of Article II (quoted above), which provides that the
contractor is to
Page 260 U. S. 326
be reimbursed for such of its expenditures "as may be approved
or ratified by the contracting officer."
We have decided that the parties to the contract can so provide,
and that the decision of the officer is conclusive upon the
parties.
Kihlberg v. United States, 97 U. S.
398;
Martinsburg & Potomac Railroad Co. v.
March, 114 U. S. 549;
United States v. Gleason, 175 U.
S. 588;
Ripley v. United States, 223 U.
S. 695. This is extending the rule between private
parties to the government.
There were such decisions, and settlement and payments in
consequence of them, as we have seen. Over the effect of these the
Comptroller of the Treasury has no power. They were the acts and
duty of the officer in charge, in the expression of which there was
no ambiguity, and were therefore conclusive in effect.
Judgment affirmed.