A finding by the Court of Claims that a delay by the government
in approving a contract was reasonable is a finding of ultimate
fact, binding upon this Court unless made without evidence or
inconsistent with other facts found. P.
249 U. S.
463.
Quaere whether unreasonable delay on the part of the
government in approving a contract can entitle the contractor to an
extension where the contract fixes a definite date for completion
of the work?
Page 249 U. S. 461
Id. District of Columbia v. Camden Iron Works,
181 U. S. 453,
distinguished.
A provision for deducting, in addition to an amount fixed as
liquidated damages, the expense of superintendence and inspection
in case of failure to complete the work by the time specified will
be enforced when clearly expressed in the contract. P.
249 U.S. 464.
A contention that sufficient credit of time was not allowed by
the Government to the contractor for extra work
held not
reviewable in this Court, it not having been made in the Court of
Claims.
Id.
52 Ct.Clms. 267 affirmed.
The case is stated in the opinion.
Page 249 U. S. 462
MR. JUSTICE BRANDEIS delivered the opinion of the Court.
The United States solicited sealed proposals for the repair of a
revetment in Michigan, and J. E. Hathaway & Co. became the
successful bidders. Under a contract dated May 11, 1910, they
agreed to complete the work by December 1, 1910. It was not
completed until 68 days later. Of this delay, the government
conceded that 29 days were attributable to extra work required by
it, and 10 more days were not counted against the contractor, being
Sundays and holidays. For the remaining 29 days' delay the
government deducted from the contract price $3,082, claiming that
amount under the provisions for liquidated and other damages. To
recover the amount disallowed, J. E. Hathaway & Co. brought
suit in the Court of
Page 249 U. S. 463
Claims, which denied them relief (52 Ct.Clms. 267), and the case
comes here on appeal.
First. Claimants contend that they were entitled to an
extension of more than these 29 days' time for completing the work,
because the contract and bond were delivered by them to the
government May 18, duly executed, but were not approved by the
Chief of Engineers until June 9, and notice of approval was not
given them until June 13. The origin of this delay was the failure
of the surety company to file with the War Department a copy of the
vote of its directors giving him who signed the bond as attorney in
fact authority so to do. But claimants insist that this omission
could have been quickly supplied if the government had telegraphed
for a copy of the vote, and that practically all the delay was due
to its unreasonable failure so to do.
The Court of Claims found: "There was no unreasonable delay on
the part of the government in approving the contract." This
finding, like one of reasonable value,
Talbert v. United
States, 155 U. S. 45,
155 U. S. 46, is
a finding of an ultimate fact by which this Court is bound, unless
it appears that the finding was made without supporting evidence,
Cramp v. United States, 239 U. S. 221,
239 U. S. 232;
Stone v. United States, 164 U. S. 380;
United States v. Clark, 96 U. S. 37, or is
inconsistent with other facts found,
United States v. Berdan
Fire-Arms Co., 156 U. S. 552,
156 U. S. 573.
There is no such lack of supporting evidence or inconsistency here.
We have consequently no occasion to determine whether, as was held
in
American Dredging Co. v. United States, 49 Ct.Clms.
350, unreasonable delay on the part of the government in approving
a contract for an accepted bid can entitle the contractor to a
corresponding extension of time, where a definite date is fixed by
the contract for completion of the work.
Compare Monroe v.
United States, 184 U. S. 524. The
case of
District of
Columbia
Page 249 U. S. 464
v. Camden Iron Works, 181 U. S. 453,
181 U. S. 461,
strongly relied upon by claimants, is clearly distinguishable.
There, the contract, as interpreted by the court, provided that the
work should be completed not (as here) by a date fixed, but within
a certain number of days, and the number of days was to be measured
not from the date of the contract, but from "the date of the
execution of the contract." What was there decided is merely that,
under such circumstances, it may be "shown that a deed, bond or
other instrument was in fact made, executed and delivered at a date
subsequent to that stated on its face."
Second. Claimants contend also that the Court of Claims
erred in allowing, in addition to the sum of $100 a day as
liquidated damages, the sum of $182 for the expense of
superintendence and inspection. But the contract expressly provided
that time should be deemed of the essence, and that, in case of
failure to complete within the time specified, "the contractor
shall pay, in addition to the liquidated damages hereinbefore
specified, all expenses for inspection and superintendence." There
is no reason why parties competent to contract may not agree that
certain elements of damage difficult to estimate shall be covered
by a provision for liquidated damages and that other elements shall
be ascertained in the usual manner. Provisions of a contract
clearly expressed do not cease to be binding upon the parties
because they relate to the measure of damages.
Wise v. United
States, ante, 249 U. S. 361.
Third. Claimants further contend that the credit of
time allowed by the government on account of the extra work should
have been greater. On this matter, no issue appears to have been
raised below, and it is obviously not open for review here.
The judgment of the Court of Claims is
Affirmed.