C contracted to erect a federal building, and G subcontracted
with C to build the superstructure in a specified time, to be
extended to make up for delays caused by the owner, by C or by
other causes specified, and C agreed to provide all labor and
materials not included in G's contract in such manner as not to
delay the material progress of G's work, and to reimburse G for any
loss caused by failure to do so. G's work was stopped by the action
of the government in suspending the operations because of a defect
in the foundation provided by C, and, after more than two months,
there was still no prospect that G, though ready, could resume
within a reasonable time.
Held that an agreement that C
would furnish a suitable foundation so as not to delay G was
imported, which was not dependent on C's fault or the rights of the
government under the main contract,
Page 248 U. S. 335
and that G was not confined to the remedy of time extension and
reimbursement, but could treat the contract as broken and sue for
the breach. P.
248 U. S.
340.
When the complaint counts upon a special building contract, and
defendant's breach in failing to provide a proper place for
plaintiff's work under it, and also upon a
quantum meruit
for labor performed and materials furnished, evidence of materials,
etc., left on the premises by the plaintiff at the termination of
the contract and appropriated by the defendant is admissible under
the latter count without regard to its bearing on the damages
recoverable under the special contract. P.
248 U. S.
342.
Error in admitting evidence cannot be imputed to the trial court
upon the theory that a count of the complaint was waived at the
trial when the theory depends on a statement made by plaintiff's
counsel in the circuit court of appeals which was inconsistent with
the bill of exceptions.
Id.
Upon the breach by the defendant of a building contract, certain
tools and appliances, brought to the building and used by the
plaintiff in performing the contract and susceptible of further use
in completing the work, were left in place by the plaintiff and
accepted and appropriated by the defendant;
held that
their value should be considered as part of plaintiff's expenditure
under the contract, in computing damages, within the rule laid down
in
United States v. Behan, 110 U.
S. 338,
110 U. S.
344-346.
Id.
Where a building contract contemplates that the contractor's
ability to perform will depend upon his receiving stipulated
payments on account as the work progresses, a substantial failure
to pay as stipulated will justify him in declining to proceed with
the work. P.
248 U. S.
344.
A contractor agreed to do certain concrete work, furnishing the
materials, for a stated sum, payable partly in installments, and,
by a separate paragraph of the contract, offered an option,which
was afterwards accepted, to set at so much per square foot certain
granite blocks, to be furnished by the other party. There was a
general provision for monthly payments on account, not to exceed a
certain percent of the cost of work erected in the building, to be
made upon written requisition, and the parties subsequently agreed
upon a mode of estimating concrete work for this purpose.
Held: (1) that the acceptance of the option did not make a
separate contract for the granite work, and that the provision for
monthly payments applied to that as well as to the concrete work,
so that a requisition properly included both classes; (2) that, in
any event, a requisition uniting demands for both classes was
unobjectionable if the granite work had
Page 248 U. S. 336
been completed and the full compensation therefor had become
payable. P.
248 U. S. 345.
. .
In an action for breach of a building contract, the complaint
alleged defendant's failure to make payment upon demands made "in
accordance with the contract," while the demand proved were based
on a modification of the contract.
Held an unimportant
variance not requiring an amendment, particularly in view of the
relation of the matter to a former decision and mandate of this
Court. P.
248 U. S.
346.
An exception to an instruction should be specific, directing the
mind of the court to some single point of alleged error. P.
248 U. S.
348.
When the grounds relied on by the circuit court of appeals for
reversal prove untenable, this Court will consider what judgment
should have been rendered in view of other assignments of error. P.
248 U. S. 349.
241 F. 545 reversed.
The case is stated in the opinion.
MR. JUSTICE PITNEY delivered the opinion of the Court.
This case is before us for the second time, our former decision
being reported in
240 U. S. 240 U.S.
264. It was an action for damages brought by the present petitioner
as plaintiff against the present respondent as defendant in the
District Court of the United States for Porto Rico. Our first
review was upon a direct writ of error sued out by plaintiff under
§ 244, Judicial Code (Act of March 3, 1911, c. 231, 36 Stat.
1087, 1157), prior to the amendment of January 28, 1915 (c. 22, 38
Stat. 804, §§ 3, 6). Judgment was reversed and the cause
remanded for further proceedings. Upon the going down of the
mandate, a new trial was had, resulting in a verdict in plaintiff's
favor
Page 248 U. S. 337
for substantial damages. To review the judgment entered thereon,
defendant, under the Act of 1915, prosecuted a writ of error from
the Circuit Court of Appeals for the First Circuit, setting up
assignments of error based upon rulings of the trial court in
admitting and excluding evidence and in giving and refusing
instructions to the jury. The court of appeals reversed the
judgment and ordered the cause to be remanded for further
proceedings, 241 F. 545, and to review this judgment, the present
writ of certiorari was allowed, 245 U.S. 643.
The controversy arose in the course of the construction of a
federal post office and court building at San Juan, Porto Rico.
Plaintiff had a subcontract for a part of the work under defendant,
which was the general contractor under the government of the United
States. Pertinent clauses of the contract and a general history of
the case were set forth in out former opinion, and need not be
repeated at length.
The evidence at the second trial followed the general lines of
the first. Defendant was to construct the foundation complete to
the basement floor. Upon this, plaintiff was to construct the
principal part of the building, including exterior and interior
walls, floors, and roof, to be built of concrete. For this work and
the necessary materials defendant agreed to pay to plaintiff the
sum of $64,750 in certain monthly installments on account, and the
balance on completion. The plans called for certain granite work,
for which defendant was to send the cut blocks from the United
States, and, under an option set forth in paragraph 25, afterwards
accepted by defendant, plaintiff was to set this granite for 40
cents per square foot of surface.
It appeared that, after the work had been in progress for some
time, a disagreement arose between the parties about payments on
account. Paragraph 12 of the contract provided that there should
be
"monthly payments on
Page 248 U. S. 338
account, not to exceed in amount 85 percent of the cost of the
work actually erected in the building, provided that the
subcontractor furnishes to the general contractors a written
requisition, on a form to be supplied by the general contractors,
not less than twelve days before payment is required,"
etc. The contract, however, did not provide how such cost of the
work, other than the granite setting, should be ascertained. In
December, 1911, and January, 1912, plaintiff made written
requisitions which were not complied with, and, according to
plaintiff's evidence, it was agreed between the parties on or about
February 2, 1912, that future applications and payments should be
made upon the basis of a schedule which specified,
inter
alia, "Exterior and interior concrete walls, arches, and
cement work $1.07 per cubic foot." On March 9, 1912, plaintiff made
a requisition for payment computed on this basis, and showing a
balance due of $11,735.95. This requisition was in effect refused,
and no further payment was made except the sum of $674, which was
paid a few days later.
In the month of February, 1912, the government superintendent of
construction found a serious settlement in the foundation, as a
result of which work upon the building was ordered to be stopped.
This order was communicated verbally by defendant's representative
to plaintiff's agent at San Juan on the 9th of March, and was
confirmed two days later by letter, in which, however, a request
made by plaintiff's agent for instructions as to what should be
done with plaintiff's force of men pending the suspension of the
work was evaded. Plaintiff stopped work pursuant to defendant's
notice, and did nothing more upon the building.
Thus matters remained until May 22, 1912, plaintiff in the
meantime having received no payment pursuant to its requisition of
March 9 beyond the small sum mentioned above, nor any instructions
or permission to proceed
Page 248 U. S. 339
with the work upon the building, and, according to plaintiff's
evidence, it was impossible to tell when the work could proceed. On
May 22, plaintiff wrote to the defendant, referring to the stoppage
of the work and to "the very considerable cost and damage to us
caused by your breach of contract," to the inability to get
payments from defendant in accordance with the terms of the
contract, and to defendant's refusal of an offer of arbitration and
refusal of "an assurance that, even now, we would have an
opportunity within any reasonable time to proceed with our work,"
and concluding with this notification:
"Under these circumstances, and owing to your entire failure to
comply with the terms of the contract, we hereby notify you that we
now terminate the contract and shall proceed no further with the
work, and that we shall hold you liable for the damages we have
sustained by reason of your breach of contract, including your
failure to provide labor and materials not included in the contract
with us in such manner as not to delay the material progress of our
work and your failure to make payments in accordance with the terms
of the contract, and all other breaches of contract on your
part."
The principal ground of action was based upon the contention
that, in refusing to respond to plaintiff's requisitions for
payments on account, and in the complete and indefinite stoppage of
plaintiff's work under the circumstances mentioned, defendant had
committed breaches of the contract so material as to amount to a
total breach, justifying plaintiff in declining to proceed further
and in suing at once for its damages.
See Anvil Mining Co. v.
Humble, 153 U. S. 540,
153 U. S. 552.
But, as we pointed out in
240 U. S. 240
U.S. 283, plaintiff counted also upon a
quantum meruit for
work and labor performed and materials furnished in and about the
construction of the building.
The circuit court of appeals attributed error to the trial court
in the following respects:
Page 248 U. S. 340
(1) The trial court refused defendant's request to instruct the
jury that plaintiff was not justified in terminating the contract
because of delays, and in instructing them on the contrary, as the
court did in substance, that, if it was evident to the parties on
May 22, 1912, that there would be a long delay or an indefinite
delay, or if it was evidently impossible to tell when the work
could be begun again, plaintiff had a right to terminate the
contract, and was not obliged to await indefinitely the pleasure of
the government as to the resumption of work. It should be noted
that, when plaintiff took action to terminate the contract, more
than two months already had elapsed since the work was stopped.
This was undisputed, and, of course, must be considered in dealing
with the instruction referred to.
It is sufficiently obvious that a contract for the construction
of a building, even in the absence of an express stipulation upon
the subject, implies as an essential condition that a site shall be
furnished upon which the structure may be erected. In this case,
the matter was not allowed to rest upon an implication, for, as we
held in our former opinion, the eleventh paragraph of the
subcontract, providing:
"The general contractors will provide all labor and materials
not included in this contract in such manner as not to delay the
material progress of the work, and in the event of failure so to
do, thereby causing loss to the subcontractor, agree that they will
reimburse the subcontractor for such loss,"
as applied to the facts of the case, imported an agreement by
defendant to furnish the foundation in such manner that plaintiff
might build upon it without delay, and was inconsistent with an
implication that the parties intended that delays attributable to
the action of the owner should leave plaintiff remediless, and
defendant's obligation to furnish a suitable foundation was not
dependent on whether it was at fault or whether the delay was
attributable to a stoppage of work by the owner in the exercise of
a right conferred
Page 248 U. S. 341
upon it by a provision of the principal contract which was not
brought into the subcontract.
The circuit court of appeals, however, held (241 F. 549) that
although, under paragraph 11, defendant would be liable to respond
in damages for such delays if plaintiff completed or stood ready to
complete its contract, yet it did not follow that, if plaintiff was
delayed in completing its work within the 300 days specified in
paragraph 6, it could decline to go on, since by paragraph 7, it
was provided that, should the subcontractor be obstructed or
delayed in the prosecution or completion of the work by neglect,
delay, or default of the owner (among other causes), the time fixed
for the completion of the work should be extended for a period
equivalent to the time lost from such causes. The court held that
this rendered it clear that delays occasioned to the plaintiff by
the owner, the general contractor, etc., were not to excuse
plaintiff from proceeding to complete the contract, but were to
operate merely as an extension of the time within which by the
terms of the contract plaintiff was required to perform its work.
In our opinion, there was error in holding that the provisions of
the sixth and seventh paragraphs limited, thus, the provisions of
the eleventh. From the fact that, by paragraph 6, plaintiff was
obliged to finish the work in 300 days, and by paragraph 7, this
time was extended for plaintiff's benefit in the case of delays
caused by the owner, the general contractor, or otherwise as
specified, it does not follow that plaintiff was not entitled to
finish the work more speedily if it could do so, or that a breach
of paragraph 11 by defendant so serious as to result in a total
suspension of the work, with no reasonable prospect that it could
be resumed within any reasonable time, left plaintiff still under
an obligation to hold itself in readiness to proceed, and without
remedy except an action for damages under that paragraph.
Page 248 U. S. 342
(2) The court found error in the admission of evidence tending
to show that, at the time plaintiff ceased work, it had on hand and
left upon the premises certain materials, machinery, and tools of
the value of $3,500, which defendant took and appropriated to its
own use. As pointed out above, the complaint contained a general
claim in the nature of a
quantum meruit for labor
performed and materials furnished. The particular item in question
was specified in the bill of particulars. This clearly justified
the trial court in admitting the evidence over the only substantial
objection made, which was that it was immaterial, and not within
the pleadings. There is nothing to show that it was admitted only
for its bearing upon the question of damages for breach of the
special contract. It is true that, in answer to the objection of
immateriality, plaintiff's counsel said:
"I will show you a case where it says that the rule is that
plaintiff's expenditure minus any materials which he may have on
hand and plus any profits which he might have made"
-- evidently referring to
United States v. Behan,
110 U. S. 338,
110 U. S.
344-346, but, in responding to a further objection that
the material could not be charged to defendant, plaintiff's counsel
insisted, "I propose to show that the defendant took it and has
it," and followed it up with proof to this effect.
The opinion of the circuit court of appeals (241 F. 550) shows
that counsel for plaintiff in that court stated that the
quantum meruit had been disregarded, and that the trial
proceeded solely upon the ground of a breach of the special
contract, but the bill of exceptions fails to bear this out, and
error cannot be attributed to the trial court on that theory. There
was no waiver of the general claim for materials, and the evidence
referred to furnished a ground of recovery upon that claim,
irrespective of plaintiff's right to recover damages for breach of
the special contract.
But, upon the latter question also, it was admissible,
Page 248 U. S. 343
upon the assumption that the rule of damages laid down in
United States v. Behan, supra, was applicable, which is
not disputed. That rule would give the plaintiff a right to recover
what it had expended toward performance of the contract, subject to
a deduction for the value of the materials remaining on hand at the
time performance was stopped. But, of course, the deduction is
based upon the theory that those materials remained the property of
plaintiff, and subject to its disposal. If they were appropriated
by defendant to its use -- and this is what the evidence tended to
show -- it is plain that their value should not be deducted from,
but should be treated as a part of, plaintiff's contribution to the
performance of the contract, in addition to its other outlay in
respect of work performed.
The circuit court of appeals considered that the furnishing of
the materials in question was a matter so entirely outside of the
contract that it could not properly be considered as an element of
damage for its breach, and that plaintiff's remedy to recover their
value must be by action of tort for conversion. But the evidence
showed no tortious conversion; it tended to show that the articles
were appropriated by defendant with plaintiff's consent, and it
hardly is necessary to say that, if tort there were, plaintiff
could waive it and sue upon the implied assumpsit.
Great Falls
Mfg. Co. v. Attorney General, 124 U.
S. 581,
124 U. S. 598;
Hirsch v. C. W. Leatherbee Lumber Co., 69 N.J.L. 509,
513.
Nor was this a matter entirely outside of the contract. The
materials in question consisted in the main of tools and appliances
that had been brought to the building by plaintiff for use in the
performance of the contract, were so used, presumably were fitted
for further use on the building, and, upon the interruption of the
work, were left in position in the control of defendant and ready
to be employed by it whenever it should proceed with the
Page 248 U. S. 344
work that plaintiff had been prevented from doing. If they were
accepted and retained by defendant, as the evidence tended to show
was the fact, it was proper to take them into account as a part of
plaintiff's expenditures upon which the damages caused by
defendant's breach of the contract were to be computed.
(3) The next ground of error upon which the circuit court of
appeals based its decision was an instruction given to the jury, in
substance, that, if defendant failed to make payments on account as
called for by the contract --
"a substantial failure, amounting substantially to the
withholding of the whole payment, not necessarily the whole
payment, but the bulk of the payment"
-- such failure constituted a breach on the part of defendant
justifying plaintiff in stopping work and entitling it to recover
damages from defendant, and the refusal of a requested instruction
to the effect that
"the delay of defendant to make payments on estimates, in the
absence of a positive refusal to pay anything, was not ground for
rescission of termination of the contract by plaintiff,"
and that plaintiff's remedy was to recover interest on the
deferred payments.
The circuit court of appeals very properly held that, in a
building or construction contract like the one in question, calling
for the performing of labor and furnishing of materials covering a
long period of time and involving large expenditures, a stipulation
for payments on account to be made from time to time during the
progress of the work must be deemed so material that a substantial
failure to pay would justify the contractor in declining to
proceed. In addition to the provisions of paragraph 12, already
referred to, the concluding paragraph of the contract was as
follows:
"And the said general contractors hereby promise and agree with
the said subcontractor to employ, and do hereby employ him to
provide the materials and to do the said work according to the
terms
Page 248 U. S. 345
and conditions herein contained and referred to for the price
aforesaid, and hereby contract to pay the same at the time, in the
manner and upon the conditions above set forth."
As is usually the case with building contracts, it evidently was
in the contemplation of the parties that the contractor could not
be expected to finance the operation to completion without
receiving the stipulated payments on account as the work
progressed. In such cases, a substantial compliance as to advance
payments is a condition precedent to the contractor's obligation to
proceed.
Canal Co. v.
Gordon, 6 Wall. 561,
73 U. S. 569;
Phillips Construction Co. v. Seymour, 91 U. S.
646,
91 U. S.
649.
But it was held that defendant's refusal to pay was justified
because plaintiff's requisitions were not made out in accordance
with the provisions of the contract. There were but two
requisitions in evidence, one dated December 30, 1911, the other
March 9, 1912. Both were held defective in that they included not
only 85 percent of the estimated amount of the concrete
construction, which was the principal subject matter of plaintiff's
contract, but also a like percentage of the amount earned in
setting granite under the accepted option in paragraph 25. The
court held that the provision for monthly installments related only
to the former, and that, as to the granite work, plaintiff was not
entitled to payments on account in advance of its completion. In
our opinion, however, defendant's acceptance of the option to call
upon plaintiff to set the granite blocks did not make a separate
contract, but merely added something to the work that plaintiff was
to do under the contract previously made, and, by necessary
inference, it subjected the granite setting to the appropriate
general provisions respecting the method of performance and the
time when the work was to be paid for.
Were it otherwise, the requisition of March 9 could not be
rejected merely on the ground that it called for a payment
Page 248 U. S. 346
for granite work. We say this because there was clear evidence
-- apparently uncontradicted, and at least sufficient to go to the
jury -- tending to show that the granite setting was substantially
completed by the early part of February, and that, because the few
blocks remaining to be set were arriving intermittently and could
be set only at unreasonable cost, it was then, at plaintiff's
request, agreed by defendant that plaintiff should set no more
granite. This part of the work was thus brought to a close, or so
the jury might find, in which event, if it constituted a separate
contract, payable at completion, as the circuit court of appeals
held, plaintiff on March 9 was entitled to demand not only 85
percent, but the entire amount due for granite setting.
(4) The court held the requisition of March 9 to be defective
upon the further ground that it was based upon the unit price of
$1.07 per cubic foot, pursuant to the understanding said to have
been arrived at between the parties on February 2, instead of the
actual cost of the work erected in the building as required by
paragraph 12 of the contract. It was held that, since the complaint
alleged that plaintiff's demands for payment were made "in
accordance with the contract," evidence to show the agreement made
on February 2 about unit prices was not admissible without an
amendment of the complaint setting up a modification of the
contract.
This view cannot be upheld. The allegation quoted from the
complaint did but touch upon the performance of a condition
precedent, concerning which the former niceties of pleading no
longer obtain. And besides, evidence of the agreement of February 2
about unit prices was introduced at the first trial, and was
particularly referred to in our opinion reviewing it (240 U.S.
240 U. S.
273-274), and the requisition of March 9, then as now
relied upon by plaintiff, was excluded from consideration by us
only because such details as were then furnished did not appear
Page 248 U. S. 347
to bear out the estimate contained in it as to the amount of
work that had been completed (240 U.S.
240 U. S.
282), an omission that was supplied at the second trial.
As the case went back for further proceedings in conformity with
that opinion, the trial court doubtless considered that compliance
with our mandate required the admission of the testimony as to the
agreement of February 2, which furnished the basis of the
requisition of March 9, and that no amendment of the pleadings was
necessary. Were there doubt about this, we should deem it proper
that the complaint be amended, or treated as if amended, even in
the appellate court, rather than that the judgment should be
reversed for so unimportant a variance, not in the least
prejudicial to defendant.
(5) The final ground upon which the reversal was rested was an
instruction given by the trial court to the jury upon the question
of damages in the following terms:
"If you find he [meaning plaintiff] was justified in terminating
the contract as he did on May 22 upon the principles above given
you, you can consider the reasonable expenditures incurred by the
plaintiff, the unavoidable losses incident to stoppage, the amount
of work actually performed, the amount plaintiff was actually
entitled to by reason of such work at the contract price, and the
profits which plaintiff could have made if allowed to complete the
work under the contract. So the different items that you may, if
you come to the question, take into account are the outlays less
the material on hand, the amount of work actually performed, and
the profits, if you find there were any which were not speculative.
The measure of profits is the contract price less what is shown to
you as the expense of carrying out contract, if that is shown to
you to your satisfaction."
The appellate court held this instruction to be misleading
because it embodied a duplication of elements. Respecting this, a
difficult question would be presented if defendant were
Page 248 U. S. 348
in a position to raise it. When the case was here before, we
assumed (240 U.S.
240 U. S.
282-283) that an instruction similarly phrased ought to
have been granted at plaintiff's request had it been confined in
its application to a recovery based upon a finding that the
contract was rightfully terminated by the notice of May 22, 1912;
but this was an assumption
arguendo, and not a part of the
matter decided.
At the second trial, this part of the charge was given by the
court of its own motion, not at plaintiff's request; nor was it
excepted to by defendant. The statement of the circuit court of
appeals to the contrary (241 F. 555) is not borne out by the
record. The proposition criticized is not contained in any of the
instructions requested by plaintiff, and, even had it been
requested, there is no exception touching it unless it be the
following: "I will ask on behalf of the defendant an exception . .
. to the action of his honor . . . in giving all instructions
requested by plaintiff." This is altogether too general to be
regarded as directing the mind of the trial court to any single and
precise point of alleged error so as to call for a reconsideration
of the ruling, and hence could not furnish a basis for reversing
the judgment. That an exception must be specific need not be
emphasized.
McDermott v. Severe, 202 U.
S. 600,
202 U. S. 610;
United States v. U.S.
Fidelity Co., 236 U. S. 512,
236 U. S.
529.
There was another exception, couched in these terms:
"To that part of the charge to the effect that, if the plaintiff
had the right to terminate the contract under the authority of the
Behan case, the measure of damages would be not only the
expenses incurred by the plaintiff, but also reasonable
profits."
This, however, refers to another passage in which the trial
court quoted from the headnote in
110 U. S. 110 U.S.
338. This clause contained no reference to the amount of work
performed, or what plaintiff was entitled to by reason of this work
at the contract
Page 248 U. S. 349
price; it mentioned only (a) plaintiff's outlay, and (b) the
lost profits, embodied no duplication of elements, and was not
erroneous.
Having found that none of the grounds relied upon by the circuit
court of appeals for reversal of the judgment of the trial court is
tenable, it remains to consider what judgment ought to have been
rendered upon the record and bill of exceptions, in view of the
assignments of error other than those we have thus far considered.
United States v. U.S.
Fidelity Co., 236 U. S. 512,
236 U. S. 528.
There were 101 assignments in all, and these have been examined
with the aid of respondent's brief, which extends to 250 pages, in
addition to the oral argument, but we have found no ground for
reversing the judgment of the trial court.
Judgment of the circuit court of appeals reversed, and that of
the district court affirmed.