In a suit to determine the relative rights of the parties to
divert water for irrigation from a stream in Nebraska, the state
court decided that superiority of the defendant's appropriation had
been conclusively established against the plaintiff, consistently
with due process, in proceedings before a state board, and, further
and independently, that the plaintiff, having without objection
stood by and permitted the defendant to go to enormous expense in
the construction of a canal and diverting works, was estopped to
question the validity of the defendant's appropriation on which it
relied. The ground of estoppel being distinct, nonfederal, and
fairly supported by the facts,
held that this Court had no
jurisdiction to review, although the state board's adjudication was
challenged under the Fourteenth Amendment.
When the judgment of a state court is placed upon two grounds,
one involving a federal question and the other not, the
jurisdiction of this Court depends upon whether the nonfederal
ground is independent of the federal ground and also broad enough
to sustain the judgment; if so, the judgment does not depend upon
the decision of any federal question, and this Court has no power
to disturb it.
Where the nonfederal is so interwoven with the federal ground as
not to be independent, or, standing alone, is not of sufficient
breadth to sustain the judgment, the jurisdiction of this Court
attaches.
Where the nonfederal ground is so certainly unfounded that it
properly may be regarded as essentially arbitrary, or a mere device
to prevent a review of the decision upon the federal question, the
judgment rests upon the latter, and may be reviewed here.
But where the nonfederal ground has fair support, this Court may
not inquire whether the decision upon it is right or wrong.
Questions of state law do not engage the due process clause of
the Fourteenth Amendment.
Writ of error to review 92 Neb. 121 dismissed.
The case is stated in the opinion.
Page 243 U. S. 158
MR. JUSTICE VAN DEVANTER delivered the opinion of the Court.
In form, this was a suit to determine the relative rights of the
parties to divert the waters of the North Platte River, in western
Nebraska, for purposes of irrigation, but the only controversy
disclosed was over the extent and priority of the right of the
Farmers Mutual Canal Company, the principal defendant. Another
defendant, the Tri-State Land Company, was interested as a
stockholder of the canal company, and need be noticed only in
another relation.
The Canal Company claimed a right to divert through its canal
1,142 6/7 cubic feet of water per second of time -- usually spoken
of as second feet -- under an appropriation dating from September
16, 1887, and the other parties severally claimed rights to divert
specific amounts under later appropriations. Insofar as the Canal
Company's claim exceeded 28 second feet, with a priority dating
from September 16, 1887, it was challenged on the grounds that the
appropriation upon which it rested had not been perfected with
reasonable diligence; that this was the situation when the
appropriations under which the others were claiming were made and
perfected; that, if the claim subsequently was enlarged, it could
not, as to the enlargement, take priority over the intervening
rights of others, and that, if it originally covered 1,142 6/7
second feet, which was disputed, all right to more than 28 feet
had
Page 243 U. S. 159
been lost by nonuser. But the Canal Company asserted the
validity of its entire claim, denied any loss by lack of diligence
of nonuser, and contended, among other things, that the State Board
of Irrigation had sustained its entire claim in 1897, when the
board was engaged under the state law (Laws 1895, c. 69,
§§ 16-27) in adjudicating claims to the waters of the
North Platte River, and that the other parties were estopped from
questioning its right by reason of their attitude and conduct after
1904, when its predecessor in interest was completing the canal and
diverting works at enormous cost. The other parties denied that
there was any ground for an estoppel, and insisted that,
consistently with the due process and equal protection provisions
of the Fourteenth Amendment, the claimed adjudication by the State
Board of Irrigation could not be treated as in any way binding upon
them, because (a) the law under which the board acted made no
provision for notice, and (b) the board had proceeded without
notice and without affording an opportunity to be heard. Other
contentions were advanced, but no purpose would be served by
stating them here.
It was conceded that, during portions of the irrigation season,
the flow of the stream had not been sufficient to satisfy all of
these claims, and that the State Board of Irrigation recently had
recognized the Canal Company's claim by refusing to restrict its
diversion in time of low water to less than 1,142 6/7 second
feet.
The cause was submitted on the pleadings and on a "stipulation
of facts" covering 84 printed pages and containing much that was
purely evidential, and not in the nature of a statement of ultimate
facts.
The stipulation disclosed that the Canal Company's canal was
about 80 miles in length, was completed in October, 1910, and was
capable of irrigating 80,000 acres; that, in 1895, it had cost
about $100,000, and was capable of irrigating 30,000 acres; that,
by reason of financial difficulties,
Page 243 U. S. 160
a foreclosure suit, and other litigation, the work of
construction was practically suspended from 1895 to 1905; that the
work was actively resumed in 1905, and continued with vigor until
October, 1910, when it was completed; that the cost of the work
from 1905 to 1910 was in excess of $1,500,000, and more than
$950,000 of this was expended before August, 1909, when this suit
was begun; that the work done after 1905 included a needle dam
across the river, costing $27,869.20, an additional headgate of
concrete and reinforced steel, costing $52,113.20, and a wastegate
or spillway of similar construction, costing $42,253.46, and that
the number of acres actually reclaimed and irrigated by the canal
was being rapidly increased, being less than 2,000 acres in 1905,
and 20,000 acres in 1910.
The trial court held that the canal company's right, although
prior in time, did not extend to more than 28.57 second feet of the
water, and entered a decree to that effect. An injunction was also
granted restraining the company from taking more than was thus
accorded to it. In the supreme court, the decree was reversed and
the suit was dismissed on the merits so far as it concerned the
Canal Company and the Tri-State Land Company, and without prejudice
in respect of any controversy between the other parties. 92 Neb.
121.
The supreme court, recognizing that the case was of great
importance to the parties and to all who were interested in
irrigated lands in the state, and that any decision therein would
almost inevitably result in serious loss to one or more of the
parties, proceeded in a painstaking way to state, discuss, and
determine all the questions presented. Among other things, it
sustained the authority of the State Board of Irrigation under the
Act of 1895 to adjudicate claims like those to the waters of the
North Platte River; described the board's power in that regard as
quasi-judicial and its adjudications as final unless
Page 243 U. S. 161
appealed from to the district court; held that the right to due
notice and a reasonable opportunity to be heard was implied in the
act, and reaffirmed its decision in
Farmers Canal Co. v.
Frank, 72 Neb. 136, made in 1904, that the board's action upon
the Canal Company's claim amounted to an unconditional adjudication
of the extent and priority of the claim, and that a leading purpose
of the Act of 1895 was to create a state board "whose records would
evidence the priorities of title to the appropriation of water in
such a public manner that no one might be misled."
As respects the notice actually given to the other parties, the
opportunity which they had for opposing or contesting the Canal
Company's claim before the board, and the knowledge of the board's
action which they reasonably should be regarded as possessing, the
court found, in substance, that, before the board began to inquire
into the claims to the waters of the North Platte, it gave due
notice of its purpose so to do; that, under that notice, all the
parties to this suit, or their predecessors in interest, appeared
before the secretary of the board at the times and places indicated
in the notice, and presented such evidence as they deemed
appropriate in support of their respective claims, the evidence
being preserved and becoming a part of the record in that
proceeding; that the board's printed rules, which were duly brought
to the attention of all the parties, permitted any claimant to
contest the claim of another, but no one sought to contest the
Canal Company's claim; that, in ordinary course, after the evidence
was presented, the claims were adjudicated, a separate opinion upon
each claim being prepared by the secretary, who was the state
engineer, and afterwards adopted by the board; that each claimant
was specially notified of the decision upon his own claim, but not
of the decisions upon the claims of others; that the decision upon
the Canal Company's claim, in addition to being entered
Page 243 U. S. 162
in the records of the state board, was shown in a list of
established claims regularly appearing in the biennial reports of
the board which the state required to be made and published, and
was recorded in 1905 in the office of the county clerk of the
county where the appropriation was made.
In these circumstances, the court concluded that the contention
that the board had proceeded without adequate notice to the
parties, or without affording them a reasonable opportunity to be
heard, had no real foundation. It also concluded that, in view of
the nature of the enterprise, the large expenditures required, and
the circumstances surrounding the temporary suspension of the work,
the contention that part of the Canal Company's claim had been lost
through lack of diligence or nonuser was highly inequitable and
untenable.
Then, coming to the question of estoppel, the court held that,
even if the other questions were decided against the Canal Company,
it was entitled to prevail upon the ground that its adversaries
were estopped by reason of their own conduct. In the course of its
opinion, the court referred at length to the admissions in the
pleadings and stipulation, and found as matter of fact that,
shortly after the decision in
Farmers Canal Co. v. Frank,
supra, the Tri-State Land Company, the Canal Company's
immediate predecessor in interest, actively took up the work of
completing the canal and diverting works and proceeded therewith in
good faith and with vigor, relying upon that decision and the state
board's adjudication, and openly claiming the amount of water and
priority specified in the latter, and that the other parties, with
knowledge of that claim and situation, made no claim of superior
right to the water, but remained silent for four years while the
work, which the court described "as comparable only to the
construction of a railroad," was being carried to completion at
enormous cost, and the water was being
Page 243 U. S. 163
diverted and used through the canal in increasing volume. And,
having thus passed upon the questions of fact, the court said:
"Under these circumstances, and having this knowledge, it would
be contrary to the plainest principles of equity if plaintiffs
might stand silently by, seeing the defendants engage in such a
monumental work under claim of right, and utter no word of warning
as to their own claims, which, if eventually established, would
deprive defendants of the water which the canal was built to carry,
condemn the whole enterprise to failure, and result in the absolute
loss of the money expended. It would be manifestly inequitable and
unjust to allow the plaintiffs, after the works were practically
finished and the money expended, to insist upon claims which, had
they been asserted in good time, would at least have put the
defendants upon their guard and have given them cause to pause and
hesitate in their expenditures until the validity of their title
had been determined."
Concisely stated, the assignments of error complain that the
supreme court infringed the due process and equal protection
provisions of the Fourteenth Amendment, first by giving decisive
effect to the state board's decision, instead of holding that it
was made without lawful notice or opportunity to be heard, and
therefore was void, and second by misconceiving or misapplying the
statute and common law of the state in disposing of other
questions.
Our jurisdiction is disputed, and must be considered, as,
indeed, it should be, even if not challenged. As has been shown,
several questions were presented to the supreme court, and all were
considered. One was whether the state board's decision could be
given any conclusive effect consistently with the due process and
equal protection clauses of the Fourteenth Amendment, and another
was whether the defense of estoppel
in pais was well
grounded. The first was plainly a federal, question and the other
as
Page 243 U. S. 164
plainly nonfederal. Both were resolved in favor of the canal
company. The other questions, none of which was federal, may be put
out of view in this connection. Thus, we are concerned with a
judgment placed upon two grounds, one involving a federal question
and the other not. In such situations, our jurisdiction is tested
by inquiring whether the nonfederal ground is independent of the
other and broad enough to sustain the judgment. Where this is the
case, the judgment does not depend upon the decision of any federal
question, and we have no power to disturb it.
Hammond v.
Johnston, 142 U. S. 73,
142 U. S. 78;
Eustis v. Bolles, 150 U. S. 361;
Berea College v. Kentucky, 211 U. S.
45,
211 U. S. 53;
Waters-Pierce Oil Co. v. Texas, 212 U.
S. 112,
212 U. S. 116;
Gaar, Scott & Co. v. Shannon, 223 U.
S. 468;
Southern Pacific Co. v. Schuyler,
227 U. S. 601,
227 U. S. 610.
It has been so held in cases where the judgment was rested upon a
federal ground and also upon an estoppel.
Pierce v. Somerset
Ry., 171 U. S. 641,
171 U. S. 648;
Lowry v. Silver City Gold & Silver Mining Co.,
179 U. S. 196.
* But where the
nonfederal ground is so interwoven with the other as not to be an
independent matter, or is not of sufficient breadth to sustain the
judgment without any decision of the other, our jurisdiction is
plain.
See Moran v. Horsky, 178 U.
S. 205,
178 U. S. 208;
Creswill v. Knights of Pythias, 225 U.
S. 246,
225 U. S. 261.
And this is true also where the nonfederal ground is so certainly
unfounded that it properly may be regarded as essentially
arbitrary, or a mere device to prevent a review of the decision
upon the federal question.
Leathe v. Thomas, 207 U. S.
93,
207 U. S. 99;
Vandalia R. Co. v. Indiana, 207 U.
S. 359,
207 U. S. 367.
But, where the nonfederal ground has fair support, we are not at
liberty to inquire whether it is right or wrong, but must accept
it, as we do other state decisions of nonfederal questions.
Murdock v.
Memphis, 20 Wall. 590,
87 U. S. 635;
Eustis v. Bolles, 150 U. S.
369;
Page 243 U. S. 165
Leathe v. Thomas, supra; Arkansas Southern R. Co. v. German
National Bank, 207 U. S. 270,
207 U. S.
275.
It does not, as we think, admit of doubt that the estoppel
in pais is made an independent ground of the judgment.
Instead of being interwoven with the validity of the state board's
adjudication, which is the other ground, it is distinct from it,
and is so treated in the court's opinion. In taking up the question
of estoppel, as also in concluding its discussion of the subject,
the court plainly shows that it is then indulging an assumption
that the other ground is not tenable. True, the board's proceedings
and adjudication are referred to as having some bearing upon the
good faith of the Canal Company, and upon the knowledge which the
other parties had of that company's claim, but in this the court
neither departs from the assumption indulged nor confuses the two
grounds of the judgment. Even if invalid, the board's proceedings
and adjudication could well have a real bearing upon the matters
indicated.
In view of the facts before recited, we think it cannot be said
that the ruling upon the question of estoppel is without fair
support, or so unfounded as to be essentially arbitrary, or merely
a device to prevent a review of the other ground of the judgment.
We therefore are not at liberty to inquire whether the ruling is
right or wrong. And it may be well to add that the question did not
originate with the court. It was presented by the pleadings, was in
the minds of the parties when the stipulation was made, and was
dealt with by counsel and court as a matter of obvious
importance.
It is not urged, nor could it well be, that, as a ground of
decision, the estoppel is not broad enough to sustain the
judgment.
The claim that the court, in disposing of some of the questions,
including that of the estoppel, misconceived or misapplied the
statutory and common law of the state, and thereby infringed the
due process and equal protection
Page 243 U. S. 166
clauses of the Fourteenth Amendment, requires but brief notice.
The due process clause does not take up the laws of the several
states and make all questions pertaining to them constitutional
questions, nor does it enable this Court to revise the decisions of
the state courts upon questions of state law.
Sayward v.
Denny, 158 U. S. 180,
158 U. S. 186;
Central Land Co. v. Laidley, 159 U.
S. 103,
159 U. S. 112;
Castillo v. McConnico, 168 U. S. 674,
168 U. S.
683-684. The questions presented, other than those
relating to the validity of the state board's adjudication, all
turned exclusively upon the law of the state, and the state court's
decision of them is controlling.
Preston v. Chicago,
226 U. S. 447;
St. Louis & Kansas City Land Co. v. Kansas City,
241 U. S. 419,
241 U. S. 427;
Old Colony Trust Co. v. Omaha, 230 U.
S. 100,
230 U. S. 116.
The reference to the equal protection clause evidently is
inadvertent, for there is no claim of unwarranted or arbitrary
discrimination.
It results from what has been said that the judgment is one
which is not open to review by this Court.
Writ of error dismissed.
*
See also Sherman v. Grinnell, 144 U.
S. 198,
144 U. S. 202;
Gillis v. Stinchfield, 159 U. S. 658,
159 U. S. 660;
Hale v. Lewis, 181 U. S. 473,
181 U. S. 479,
181 U. S.
480.