The mere location by the Secretary of War of a harbor line does
not amount to a taking of property within the line or its
appropriation to public use, nor does a taking result from the
request of an officer of the United States to a riparian owner to
vacate if such request is neither acceded to nor enforced.
The fact that the government make a contract to cut away
land
Page 240 U. S. 573
within a harbor line location does not amount to a taking of
such land if there was no attempt to perform the contract.
Whatever rights a riparian owner may have in land below mean
high water line of a navigable and tidal river, they are
subordinate to the public right of navigation and the power of
Congress to employ all appropriate means to keep the river open and
navigation unobstructed.
Congress may prevent renewal of existing obstructions below mean
high water, if navigation may be injuriously affected thereby, and
the owner is not entitled to compensation therefor.
In this case, a riparian owner on the Savannah River was held
not to be entitled to recover as upon an implied contract for
taking his property by reason of damages alleged to have been
sustained by him in consequence of the exercise of the power of
Congress over navigable waters.
38 Ct.Cl. 693, 49 Ct.Cl. 701, affirmed.
The facts, which involve the right of the owner of a wharf in
the harbor of the Savannah River to recover from the government as
upon an implied contract for the taking of his property in the
improvement of that harbor, are stated in the opinion.
Page 240 U. S. 577
MR. JUSTICE VAN DEVANTER delivered the opinion of the Court.
Henry F. Willink sued to recover as upon an implied contract for
an alleged taking of his property in the improvement of the harbor
in the Savannah River at Savannah, Georgia. A recovery was denied,
38 Ct.Cls. 693, 49 Ct.Cls. 701, and the claimant's executrix
prosecutes this appeal.
The material facts disclosed by the findings are these: at
Savannah, the river is navigable and within the ebb and flow of the
tide. Opposite the city is Hutchinson's Island, a strip of which on
the side towards the city was owned by the claimant. He there
conducted a plant for repairing vessels. Among his facilities used
in the business were a marine railway and a wharf. The former
extended into the river, and was protected by sheet piling "where
in the water." A substantial portion of it lay below the mean high
water line, and the wharf seems also to have been below that line,
although its location is not precisely stated. In the conduct of
the claimant's business, the vessels subjected to repair were drawn
out of the river and lowered into it by means of the railway, and
to prevent its lower end, "which was under water at high tide,"
from becoming seriously obstructed by deposits of mud, the piling
was driven on both sides. The piling was effectual for the purpose,
but decayed in time and had to be replaced.
Prior to 1887, many improvements had been made in the harbor,
and in that year, a plan for further and extensive improvements was
submitted to Congress, but was not approved. Among other changes,
this plan contemplated
Page 240 U. S. 578
a widening of the river by cutting away a portion of
Hutchinson's island, including that whereon the claimant's
facilities were situate. On May 4, 1889, the harbor line, which
theretofore had not reached the island or the claimant's
facilities, was reestablished by the Secretary of War under §
12 of the Act of August 11, 1888, c. 860, 25 Stat. 400, 425, in
such manner that a part of the claimant's land and all of his
facilities were brought within the harbor area. In 1890, another
extended project, retaining the earlier proposal to widen the river
by cutting away a portion of the island, was submitted to Congress
and was approved. The estimated cost of this project was
$3,500,000, which included $45,000 for "possible land damages" to
the island. A part of the larger sum was appropriated each year
until the appropriations equaled the full estimate, which was in
1895. The appropriation of July 13, 1892, c. 158, 27 Stat. 88, 92,
was accompanied by a provision that
"contracts may be entered into by the Secretary of War for such
materials and work as may be necessary to complete the present
project of improvement, to be paid for as appropriations may from
time to time be made by law, not to exceed in the aggregate"
so much of the estimate as remained unappropriated. A contract
was then made for cutting away a portion of the island, including
that whereon the claimant's facilities were situate, but this work
never was done or undertaken, and the appropriations were otherwise
exhausted and the project treated as completed.
In the summer of 1892, the condition of the claimant's wharf and
piling became such that it was necessary to rebuild the one and to
renew the other. While he was so engaged, the engineer officer in
charge of the harbor improvements requested him to desist and to
remove all of his facilities that were within the harbor area as
defined by the Secretary of War in 1889. The request was followed
by a letter from the United States Attorney for
Page 240 U. S. 579
that district notifying the claimant that, in driving the
piling, he was obstructing navigation contrary to the Act of
September 19, 1890, c. 907, 26 Stat. 426, 454, 455, and that,
unless he desisted and "all piling outside of the bulkhead line"
was removed, he would be prosecuted. Because of this request and
notice, he ceased work upon the piling and wharf, but did not
remove any of his facilities or surrender them or his land to the
United States or any of its officers. On the contrary, he continued
to operate his plant and use his marine railway and other
facilities as best he could. Theretofore he was able to haul up on
the railway and repair vessels of considerable draft, and the chief
profit in his business came from that work; but thereafter, the
renewal of the piling being prevented, deposits of mud filled up
the entrance to the railway to such an extent that he was obliged
to confine his work to smaller vessels. Even then, it was necessary
to be almost constantly dredging the entrance. This condition
continued until December, 1897, when the Secretary of War
reestablished the harbor line as it was prior to May 4, 1889. The
expense incurred by the claimant in dredging was $7,697, and the
loss consequent upon his inability to handle the larger vessels was
$12,500.
Upon these facts, as before indicated, the court held that he
was not entitled to recover.
We reach the same conclusion, and for the following reasons:
There was no actual taking of any of the claimant's property,
nor any invasion or occupation of any of his land. As respects his
upland, he was not in any wise excluded from its use, nor was his
possession disturbed. Something more than the location of a harbor
line across the land was required to take it from him and
appropriate it to public use.
Yesler v. Washington Harbor Line
Commissioners, 146 U. S. 646,
146 U. S. 656;
Prosser v. Nor. Pac. R. Co., 152 U. S.
59,
152 U. S. 65;
Philadelphia Co. v.
Stimson, 223 U.S.
Page 240 U. S. 580
605,
223 U. S. 623.
No taking resulted from the request that he remove his facilities,
for it was neither acceded to nor enforced. And the contract for
cutting away a part of the land was also without effect, because
there was no attempt at performance. Thus, at best, the asserted
taking rested upon the acts of the engineer officer and the
district attorney in preventing the claimant from renewing his
piling and rebuilding his wharf. But in this no right of his was
infringed. The river being navigable and tidal, whatever rights he
possessed in the land below the mean high water line were
subordinate to the public right of navigation and to the power of
Congress to employ all appropriate means to keep the river open and
its navigation unobstructed.
Gibson v. United States,
166 U. S. 269,
166 U. S. 271;
Scranton v. Wheeler, 179 U. S. 141,
179 U. S. 163;
Philadelphia Co. v. Stimson, 223 U.
S. 605,
223 U. S. 634,
223 U. S. 638;
United States v. Chandler-Dunbar Water Power Co.,
229 U. S. 53,
229 U. S. 62;
Lewis Blue Point Oyster Co. v. Briggs, 229 U. S.
82,
229 U. S. 88;
Greenleaf Lumber Co. v. Garrison, 237 U.
S. 251,
237 U. S. 263.
The piling and wharf were below the mean high water line, and so,
if navigation was likely to be injuriously affected by their
presence, Congress could prevent their renewal without entitling
him to compensation therefor.
See cases,
supra.
By the legislation in force at the time, Congress not only
authorized the Secretary of War to establish the harbor lines, but
made it unlawful to extend any wharf or other works, or to make any
deposits, within the harbor area as so defined, except under such
regulations as the Secretary might prescribe, and laid upon the
district attorney and the officer in charge of the harbor
improvements the duty of giving attention to the enforcement of its
prohibitive and punitive provisions, Aug. 11, 1888, c. 860, §
12, 25 Stat. 400, 425; c. 907, §§ 11, 12, 26 Stat. 426,
455. When the claimant attempted to renew the piling and rebuild
the wharf, they were not only below the mean high water line,
but
Page 240 U. S. 581
within the harbor area as defined under this legislation.
Consistently with its prohibitions, he could not proceed with the
work except under a permissible regulation of the Secretary of War.
It is not contended that the work was thus made permissible, and so
the conclusion is unavoidable that the claimant was proceeding in
violation of the statute, and that the engineer officer and the
district attorney rightly requested him to desist. Such
inconvenience and damage as he sustained resulted not from a taking
of his property, but from the lawful exercise of a power to which
it had always been subject.
Gibson v. United States,
supra, 166 U. S. 276;
Bedford v. United States, 192 U.
S. 217,
192 U. S.
224.
Judgment affirmed.
MR. JUSTICE McREYNOLDS took no part in the consideration and
decision of this case.