Final settlement of a contractor's account within the meaning of
the Act of August 13, 1894, c. 280, 28 Stat. 278, as amended
February 24, 1905, c. 778, 33 Stat. 811, is not when the final
payment is made, but is the final administrative determination by
the proper authority of the amount due; in this case,
held
that a suit by a subcontractor against the surety commenced six
months after date of such determination, but less than six months
after payment, was not prematurely brought, no action having been
brought meanwhile by the United States.
Where the action on the contractor's bond was brought within the
proper time, an amendment made after the expiration of such time,
which does not set up a new or different cause of action, but
merely corrects a defective statement, may be allowed.
Texas
Cement Co. v. McCord, 233 U. S. 157.
The contested liability of a surety on a contractor's bond is
not to be determined in equity; the action under the Act of 1894 as
amended in 1905 is one at law.
If the surety does not contest, but pays into court the full
amount of liability, discharging all liability as provided by the
statute, the proceeding is simply one for distribution of a fund in
court.
Page 240 U. S. 215
Where a sub-contractor was not one of the original plaintiffs
and there was no intervention on its behalf,
held that a
judgment could not be rendered in its favor more than a year after
final settlement of the contractor's claim; nor does the fact that
one claiming, but not proving such claim, to be its assignee was
made a party plaintiff amount to a sufficient and timely filing of
the claim of such a subcontractor.
215 F. 334 modified and affirmed.
The facts, which involve the construction of the Materialmen's
Acts of 1894 and 1905 and the rights of subcontractors thereunder,
are stated in the opinion.
MR. JUSTICE HUGHES delivered the opinion of the Court.
This action was brought by subcontractors under the Act of
August 13, 1894 (c. 280, 28 Stat. 278), as amended by the Act of
February 24, 1905 (c. 778, 33 Stat. 811), in the name of the United
States to recover upon a contractor's bond. The contract was for
the construction of a post office building in Aiken, South Carolina
(Act of March 30, 1908, c. 228, 35 Stat. 526, 528), and the
Illinois Surety Company (plaintiff in error) was the surety. The
summons and complaint were filed on March 4, 1913. Motion to
dismiss was made on September 22, 1913, upon the ground that the
complaint did not allege that there had been a completion and final
settlement of the contract between the contractor and the United
States, or that there had been such completion and settlement more
than six months, and within one year prior to the commencement of
the action.
Page 240 U. S. 216
Another ground for the motion was that the remedy under the
statute was in equity. The motion was denied, the court permitting
the complaint to be amended so as to allege that the contract was
completed in July, 1912, that final settlement was made by the
Treasury Department on August 21, 1912, and that no suit had been
brought by the United States against the contractor and his surety
within the six months' period. The defendant, reserving its
objection to the order denying the motion and allowing the
amendment, answered. Jury trial was waived by written stipulation,
and the case was heard by the district judge, who found, in
substance, the facts to be as follows:
That the building was completed, and on August 21, 1912, the
Treasury Department "stated and determined the final balance" to be
paid the contractor under the contract at the sum of $3,999.01;
that this "adjustment and determination" was communicated to the
contractor; that, on August 26, 1912, a voucher of that date was
prepared by the Department, showing the balance, as above stated,
to which the contractor appended his signature, certifying the
amount to be correct, and that, on that day, there was a definite
acceptance by the contractor of the adjustment; that, on September
11, 1912, a check for the above-mentioned sum was made out by the
disbursing clerk of the Department, payable to the order of the
contractor, who thereafter collected it; that, upon the request of
the relator (the Faith Granite Company), the Secretary of the
Treasury, on January 16, 1913,
"furnished to it a certified copy of the contract and bond, and
that, on the 6th day of March, 1913, . . . the present action was
instituted by the filing. . . . and by service of summons and
complaint on defendant Surety Company."
It also appeared that no action had been instituted by the
United States upon the bond within the six months allowed by the
statute.
Page 240 U. S. 217
The district court gave judgment for amounts found to be due to
those for whose benefit the action was brought, and to certain
interveners, and this judgment was affirmed by the circuit court of
appeals, 215 F. 334. The contentions presented are: (1) that the
action was instituted prematurely, (2) that the amendment of the
complaint was improperly allowed, (3) that there was no right of
action at law, and (4) that the court erred in giving judgment for
the Carolina Electrical Company, one of the subcontractors.
1. The statute provides:
"If no suit should be brought by the United States within six
months from the completion and final settlement of said contract,
then the person or persons supplying the contractor with labor and
materials shall, upon application therefor, and furnishing
affidavit . . . be furnished with a certified copy of said contract
and bond, upon which he or they shall have a right of action, and
shall be, and are hereby, authorized to bring suit in the name of
the United States . . . against said contractor and his sureties,
and to prosecute the same to final judgment and execution;
Provided, That . . . it shall not be commenced until after
the complete performance of said contract and final settlement
thereof, and shall be commenced within one year after the
performance and final settlement of said contract, and not
later."
In
Texas Portland Cement Co. v. McCord, * 233 U.
S. 157, we said that this act created a new right of
action upon terms named, and hence that an action brought by
creditors before six months had expired from the time of the
"completion and final settlement of the contract" could not be
sustained. In the present case, the plaintiff in error insists that
there was no final settlement within the meaning of the statute
prior to the issue of the check
Page 240 U. S. 218
for payment to the contractor on September 11, 1912, and that,
in this view, the action was brought too soon.
It was evidently the purpose of the Act of 1905 to remedy the
defect in the Act of 1894 by assuring to the United States adequate
opportunity to enforce its demand against the contractor's surety,
and priority with respect to such demand.
Mankin v.
Ludowici-Celadon Co., 215 U. S. 533,
215 U. S. 538;
United States v. Robinson, 214 F. 38, 39-40. Accordingly,
it was provided that, if the United States sued upon the bond, the
described creditors should be allowed to intervene and be made
parties to the action, but subject "to the priority of the claim
and judgment of the United States." And it was only in case the
United States did not sue within the specified period that the
creditors could bring their action. With this object in view -- to
protect the priority of the United States and at the same time to
give a remedy to materialmen and laborers on the contractor's bond
and a reasonable time to prosecute it (
Bryant v. N.Y.
Steamfitting Co., 235 U. S. 327,
235 U. S. 337)
-- it was natural that the time allowed exclusively for action by
the government should begin to run when the contract had been
completed, and the government, in its final adjustment and
settlement according to established administrative methods, had
determined what amount, if any, was due. Then the government would
have ascertained the amount of its claim, if it had one, and could
bring suit if it desired. As such determinations are regularly made
in the course of administration, nothing would seem to be gained by
postponing the date, from which to reckon the six months, to the
time of payment. Indeed, if an amount were found to be due from the
contractor, and he was insolvent, there might be no payment, and if
payment were essential, there would be no date from which the time
for the bringing of the creditors' action could be computed.
The pivotal words are not "final payment," but "final
Page 240 U. S. 219
settlement," and, in view of the significance of the latter term
in administrative practice, it is hardly likely that it would have
been used had it been intended to denote payment.
See United
States v. Illinois Surety Co., 195 F. 306, 309;
United
States v. Bailey, 207 F. 782, 784;
United States v.
Robinson, supra; United States v. Massachusetts Bonding Co.,
215 F. 241, 244;
United States v. Illinois Surety Co., 226
F. 653, 662. The word "settlement," in connection with public
transactions and accounts, has been used from the beginning to
describe administrative determination of the amount due. By the Act
of September 2, 1789, c. 12 (1 Stat. 65), establishing the Treasury
Department, the Comptroller was charged with the duty of examining
"all accounts
settled by the auditor." (§ 3.) And it
was made the duty of the auditor to receive "all public accounts
and after examination to certify the balance," subject to the
provision that any person whose account should be so audited might
appeal to the Comptroller "against such
settlement." The
Act of March 3, 1809, c. 28, § 2 (2 Stat. 536), gave authority
to the Comptroller to direct the auditor forthwith "to
audit
and settle any particular account" which he was authorized to
audit and settle, and "to report such
settlement" for his
revision and final decision. (
See Rev.Stat. § 271.)
By the Act of March 3, 1817, c. 45, § 2 (3 Stat. 366), it was
provided that
"all claims and demands whatever, by the United States or
against them, and all accounts whatever in which the United States
are concerned either as debtors or as creditors, shall be
settled and adjusted in the Treasury Department."
This provision was carried into § 236 of the Revised
Statutes. The words "settled and adjusted" were taken to mean the
determination in the Treasury Department for administrative
purposes of the state of the account and the amount due.
See 2 Op.Atty.Gen. 518, 625, 629, 630. Referring
Page 240 U. S. 220
to this provision, it was said by Mr. Chief Justice Waite, in
delivering the opinion of the court in
Cooke v. United
States, 91 U. S. 389,
91 U. S.
399:
"Thus, it is seen that all claims against the United States are
to be settled and adjusted 'in the Treasury Department,' and that
is located 'at the seat of government.' The assistant treasurer in
New York is a custodian of the public money, which he may pay out
or transfer upon the order of the proper department or officer, but
he has no authority
to settle and adjust -- that is to say, to
determine upon the validity of -- any claim against the
government. He can pay only after the adjustment has been made
'in the Treasury Department,' and then upon drafts drawn for that
purpose by the treasurer."
Again, the Act of July 31, 1894, c. 174 (28 Stat. 162, 206-208),
relating to the examination of accounts by auditors, and revisions
of accounts, etc., provides, in § 8, that
"the balances which may from time to time be certified by the
auditors to the Division of Bookkeeping and Warrants or to the
Postmaster General upon the
settlements of public accounts
shall be final and conclusive upon the executive branch of the
government,"
except that any person whose accounts may have been
"
settled," the head of the executive department, etc., to
which the account pertains, or the Comptroller of the Treasury,
may, within a year, obtain a revision in the manner stated; also
that
"any person accepting payment under a
settlement by an
auditor shall be thereby precluded from obtaining a revision of
such settlement as to any items from which payment is
accepted,"
and, further, that, "when suspended items are
finally
settled, a revision may be had as in the case of the original
settlement." By the Act of May 28, 1896, c. 252, § 4 (29 Stat.
140, 179), the Secretary of the Treasury was directed to make
report annually to Congress of such officers as were found "upon
final settlement of their accounts" to have been indebted
to the government,
Page 240 U. S. 221
and to have failed to pay the amount of their indebtedness into
the Treasury.
We should not say, of course, that instances may not be found in
which the word "settlement" has been used in acts of Congress in
other senses, or in the sense of "payment." But it is apparent that
the word "settlement" in connection with public contracts and
accounts, which are the subject of prescribed scrutiny for the
purpose of ascertaining the rights and obligations of the United
States, has a well defined meaning as denoting the appropriate
administrative determination with respect to the amount due. We
think that the words "final settlement" in the Act of 1905 had
reference to the time of this determination when, so far as the
government was concerned, the amount which it was finally bound to
pay or entitled to receive was fixed administratively by the proper
authority. It is manifestly of the utmost importance that there
should be no uncertainty in the time from which the six months'
period runs. The time of the final administrative determination of
the amount due is a definite time, fixed by public record and
readily ascertained. As an administrative matter, it does not
depend upon the consent or agreement of the other party to the
contract or account. The authority to make it may not be suspended
or held in abeyance by refusal to agree. Whether the amount so
fixed is due in law and fact undoubtedly remains a question to be
adjudicated if properly raised in judicial proceedings, but this
does not affect the running of the time for bringing action under
the statutory provision.
In the present case, the construction of the building was in
charge of the Secretary of the Treasury and under the general
supervision of the supervising architect. The Secretary of the
Treasury was authorized to remit the whole or any part of the
stipulated liquidated damages as in his discretion might be just
and equitable. Act of
Page 240 U. S. 222
June 6, 1902, c. 1036, 32 Stat. 326. On August 21, 1912, the
supervising architect having received the certificate of the chief
of the technical division of the office that all work embraced in
the contract had been satisfactorily completed, made his statement
of the amount finally due, recommending that only the actual damage
(as stated) be charged against the contractor, and that the proper
voucher should be issued in favor of the contractor for the
balance, to-wit, $3,999.01. And, on the same date, this
recommendation was approved and actual damages charged accordingly
by direction of the Secretary of the Treasury. This, in our
judgment, was the "final settlement" of the contract within the
meaning of the act. We understand that the administrative
construction of the act has been to the same effect. The regulation
of the Treasury Department, as it appears from its circular issued
for the information of persons interested in claims for material
and labor supplied in the prosecution of work on buildings under
the control of that Department (Dept. Circ. No. 45, Sept. 12,
1912), is as follows:
"The Department treats as the date of final settlement mentioned
in said acts [referring to the Acts of 1894 and 1905,
supra] the date on which the Department approves the basis
of settlement under such contract recommended by the supervising
architect, and orders payment accordingly."
We conclude that the action was not brought prematurely.
2. With respect to the amendment of the complaint, it is
apparent that, as there was an existing right of action under the
statute at the time the suit was brought, the case was not within
the decision in
Texas Cement Co. v. McCord, supra. No new
or different cause of action was alleged in the amended complaint.
The Court merely permitted the defective statement of the existing
right to be corrected by the addition of appropriate
allegations,
Page 240 U. S. 223
and in this there was no error. Rev.Stat. § 954;
Missouri, Kans. & Tex. Ry. v. Wulf, 226 U.
S. 570,
226 U. S.
576.
3. It is contended that the right given by the statute to the
described creditors is of an equitable nature, and that the court
erred in permitting recovery at law. The objection in the present
case is merely technical, as the parties stipulated to waive trial
by jury, and the case was heard and decided by the district judge
upon facts about which there is no dispute. The question has not
been raised heretofore in this Court, but it has been assumed in
many cases that the action to be brought under the statute upon the
contractor's bond, whether the action were instituted by the United
States (
United States v. Congress Construction Co.,
222 U. S. 199), or
by creditors in the name of the United States, was an action at
law.
United States Fidelity Co. v. Struthers Wells Co.,
209 U. S. 306;
Mankin v. Ludowici-Celadon Co., 215 U.
S. 533;
Title Guaranty Co. v. Crane Co.,
219 U. S. 24,
219 U. S. 35;
Bryant Co. v. N.Y. Steamfitting Co., 235 U.
S. 327. In
Title Guaranty Co. v. Crane Co.,
supra, a question arose as to the propriety of allowing a
docket fee to each claimant. Section 824 of the Revised Statutes
provides for a docket fee of $10 "in cases at law, when judgment is
rendered without a jury." The Court said:
"The allowance of a docket fee of $10 to each claimant appears
to us to be correct. Rev.Stat. § 824. The claims are several,
and represent distinct causes of action in different parties,
although consolidated in a single suit."
In the circuit and district courts and in the circuit courts of
appeals, while it seems that objection has rarely been made, there
has been almost complete uniformity in treating the creditors'
action under the Act of 1905 as one at law.
See United States
v. Winkler, 162 F. 397;
Stilzer v. United States, 182
F. 513;
United States v. Boomer, 183 F. 726;
United
States v. Illinois Surety Co., 195 F. 306;
Baker Contract
Co. v.
Page 240 U. S. 224
United States, 204 F. 390;
Eberhart v. United
States, 204 F. 884;
United States v. Bailey, 207 F.
783;
Vermont Marble Co. v. National Surety Co., 213 F.
429;
United States v. Robinson, 214 F. 38;
United
States v. Massachusetts Bonding Co., 215 F. 241;
United
States v. Emery, 225 F. 287;
United States v. Illinois
Surety Co., 226 F. 653. It was expressly held to be an action
at law in
United States v. Stannard, 207 Fed.198, 202. The
contrary conclusion was reached in
United States v. Wells,
203 F. 146, 147;
Illinois Surety Co. v. United States, 212
F. 136, 139, and
United States v. Scheurman, 218 F. 915,
919. The point was raised on rehearing in
United States v.
Illinois Surety Co., but, as it came too late, it was not
decided.
The statute provides that the bond shall have
"the additional obligation that such contractor or contractors
shall promptly make payments to all persons supplying him or them
with labor and materials in the prosecution of the work provided
for in such contract."
In this respect, the provision is substantially the same as that
contained in the Act of 1894, and the obligation in favor of the
materialmen and laborers has been held to be a distinct obligation.
Guaranty Co. v. Pressed Brick Co., 191 U.
S. 416,
191 U. S.
423-425;
Hill v. Am. Surety Co., 200 U.
S. 197,
200 U. S.
201-202. It is an obligation for the payment of money to
the persons described, which they are entitled to enforce. The
nature of the obligation is not changed by the fact that there is
to be but one action. If the United States brings the action, the
persons described are entitled to be made parties, and "to have
their rights and claims adjudicated in such action, and judgment
rendered
Page 240 U. S. 225
thereon." If the United States does not sue within the time
specified, they may bring action on the bond in the name of the
United States, and "prosecute the same to final judgment and
execution." Any creditor who duly presents his claim in such an
action becomes a party thereto with a distinct cause of action.
Title Guaranty Co. v. Crane Co. , supra. The obligation of
the surety thus enforced in a single action is a legal obligation
to the United States for the use and benefit of the several
claimants. We do not regard the requirements that "the claim and
judgment of the United States" shall have priority, and that the
aggregate recovery shall not exceed the penalty on the bond, as
insuperable obstacles to proceeding at law. It is the case of an
undertaking for the payment of many claims, not to exceed the
specified penalty. If the total amount due exceeds the penalty of
the bond, it is provided that "judgment shall be given to each
creditor
pro rata of the amount of the recovery." This,
however, merely requires an arithmetical calculation after the
different causes of action have been passed upon, and the amount
due upon each determined. We see no ground upon which the
conclusion can be justified that the liability of the surety on its
bond is to be determined in equity. The contrary has been the
generally accepted, and we think the correct, practice.
It should be added that a different situation would arise if the
surety, availing itself of the statutory privilege, should pay into
court the full amount of its liability, to-wit, the penalty on the
bond, for distribution. In that case, the legal obligation of the
surety would be discharged by the express terms of the statute, and
the proceeding would be simply for the distribution of a fund in
court.
4. The plaintiff in error contends that the court erred in
giving judgment in favor of the Carolina Electrical Company. The
record shows that among those named as the persons instituting the
action was the "Electrical
Page 240 U. S. 226
Engineering & Contracting Company, assignee of Joseph B.
Cheshire, Jr., receiver of the Carolina Electrical Company." The
complaint set forth that the Carolina Electrical Company (a North
Carolina corporation) had furnished to the contractor certain
material and labor for which there remained unpaid the sum of
$498.69; that, on October 4, 1912, Joseph B. Cheshire, Jr., was
appointed receiver of that company, and that, on March 1, 1913, its
claim had been "assigned and transferred for value" to the
above-named plaintiff by the receiver, and that the plaintiff was
the sole owner of the account, and had succeeded to all the rights
incident thereto which had belonged to the Carolina Electrical
Company. The alleged transfer was denied. Evidence was introduced
to show the incorporation and the appointment of the receiver. The
district judge found that the order proved was insufficient to
establish the authority of the receiver to assign the claim, but
held that the proceeding in the case was a sufficient filing of the
claim on behalf of the Carolina Electrical Company. Judgment was
awarded in favor of that company, with direction that it should be
paid "only to such person as may be authorized by law to receive it
for said Carolina Electrical Company," and the judgment to this
effect was affirmed.
In this we think, the court erred. The Carolina Electrical
Company was not one of the plaintiffs, and there was no
intervention on its behalf. The trial court, in its findings, sets
forth the interventions of certain other parties and states that no
more interventions appear to have been filed in the cause. It is
true, of course, that the real party in interest who is entitled to
enforce the cause of action may be substituted as plaintiff.
See McDonald v. Nebraska, 101 F. 171, 178. But the present
case is not one of misnomer, or of a nominal plaintiff for whom the
real party in interest is substituted, or indeed of any proper
substitution. The plaintiff, the Electrical Engineering
Page 240 U. S. 227
& Contracting Company, was not a nominal party, nor was the
action in any sense brought for the benefit of the Carolina
Electrical Company. The record shows that it was brought, so far as
this claim is concerned, solely for the benefit of the Electrical
Engineering & Contracting Company upon the allegation that the
claim had been assigned to it for value, and that it was the
exclusive and beneficial owner. According to the record, the
Carolina Electrical Company was not made a party at any stage of
the action unless this was accomplished by the decision and the
judgment. But, at the time of the decision, November 10, 1913, by
reason of the express limitation of the statute, it was too late
for that company to intervene.
The judgment is modified by striking out the provision in favor
of the Carolina Electrical Company, and, as thus modified, is
affirmed.
Judgment affirmed.
* The statute is set forth in full in the margin of the opinion
in the case cited.