Ability to perform a contract is of its very essence, and delay
resulting from absence of such ability is not due to unavoidable
causes such as fires, storms, labor strikes, actions of the United
States, etc., as enumerated in the contract involved in this
action.
The fact that a contractor engaging to deliver armor plate of
specified qualifications as to thickness, hardness, etc., was
delayed by unforeseen
Page 240 U. S. 157
difficulties in the then new art of manufacturing does not
excuse performance if such delays were not within the excepted
reasons for delay.
49 Ct.Cl. 391 affirmed.
The facts, which involve the construction of a contract for
armor plate with the United States and the right of the contractor
to recover sums withheld for delay in completion of the contract,
are stated in the opinion.
Page 240 U. S. 160
MR. JUSTICE McKENNA delivered the opinion of the Court.
Petition in the court of claims for the recovery of $8,595.35,
alleged to be due claimant as a balance of the price of armor plate
furnished the government under a contract between it and
claimant.
The contract is an elaborate one, and by it claimant engaged to
manufacture for the Ordnance Department armor plates of a certain
designated thickness, in conformity with instructions,
specifications, and drawings attached to and made a part of the
contract. And claimant agreed to provide certain of the 18-inch
plates for the purpose of the ballistic test prescribed by the
specifications, and that such plates, when subjected to the
ballistic test, should fulfil certain requirements set forth in the
specifications. The dates of delivery were to be on or before
September 7, 1911, and November 7, 1911, and the place of delivery
the Bethlehem Steel Company, South Bethlehem, Pennsylvania.
The government engaged to receive the plates when manufactured,
tested, and approved as provided, and make payment for them in
installments from time to time as the manufacture of the armor and
material progressed
Page 240 U. S. 161
and after delivery. In the event of the claimant's failing to
prosecute the manufacture of the armor and material properly, or to
complete delivery on or before the dates named in the contract, the
Chief of Ordnance might complete such manufacture at the expense of
claimant, charging it with the cost thereof in excess of the
contract price,
"or else (2) waive the time limit named in the contract and
permit the claimant to complete the delivery of the armor and
material within a reasonable time, and thereupon deduct from the
sum stipulated to be paid the claimant for all of the armor and
material, as liquidated damages, a sum equal to one-thirtieth of
one percentum of the contract price of all armor and material
remaining undelivered on November 7, 1911, for each day of delay in
its delivery; Provided, however, that in computing the amount of
any such deduction, the claimant should be given credit for delays
occurring during the performance of the contract, which the Chief
of Ordnance might determine to have been due 'to unavoidable
causes, such as fires, storms, labor strikes, actions of the United
States, and so forth,' and that the date of completion of the
delivery, for the purposes of the final settlement between the
parties, should be a date to be ascertained by deducting, from the
whole period between the signing of the contract and the date of
the actual delivery, all delays which were found to have been due
to unavoidable causes."
It is alleged that claimant encountered difficulties which were
unforeseen by both parties when the contract was made, and were
then unforeseeable, and in consequence thereof the delivery of the
armor and pertaining material was delayed unavoidably.
That, prior to the manufacture of the armor, no face-hardened
armor 18 inches in thickness had been manufactured in this or any
foreign country, and no information with respect to the process or
processes to be employed in its manufacture was obtainable.
Page 240 U. S. 162
That, for the purpose of learning what manner of treatment or
face-hardening process should be applied to the 18-inch plates, and
in order that they might attain the highest degree of efficiency
possible, and meet all the requirements of the specifications,
claimant completed one of the plates, applying to it a treatment or
face-hardening process deduced from the formula which claimant and
every other manufacturer of armor plate in this and every foreign
country had followed in the manufacture of armor plate, and which
was recognized by authorities on the subject as the one which would
give the best results.
That, upon its completion, the plate was, on April 19, 1911,
subjected to the ballistic test, and it met the requirements of the
specifications. Thereupon claimant proceeded to complete all of the
plates, certain of which were selected for the purpose of the
ballistic test and failed to fulfil the requirements of the
specifications. Other plates were selected and failed. Thereupon
claimant, with all due diligence and dispatch, made or caused to be
made by metallurgical experts exhaustive tests and experiments, and
it was ascertained that, in order to pass the test required by the
Ordnance Department, the plates must possess certain metallurgical
qualities or conditions which, up to that time, were unknown to
anyone, and the necessity for which was not foreseeable when the
contract was made. In conducting the test, it was necessary to use
plates of full size and the tests were conducted with all due
diligence and dispatch. From the plates thus tested the Ordnance
Department selected a third plate which was tested January 19th and
24th, 1912, and was found to fulfill the requirements of the
specifications. Claimant in due course finished all of the plates
which the contract called for, and they were approved and delivered
as in the manner prescribed.
It is alleged that, by reason of the circumstances detailed,
Page 240 U. S. 163
there were delays in the delivery of the plates, and that the
delays were due to causes which were unavoidable within the meaning
of the contract.
On account of the delays, however, the Ordnance Department
proposed to deduct from the contract price of the armor and
pertaining material the sum of $8,598.15 as liquidated damages on
account of a portion of the delay. Claimant made protest, asserting
that the delays were due to causes provided for in articles 4 and 8
of the contract.
By article 4, it was provided that, in case of failure of
claimant to deliver any or all of the armor contracted for, there
would be deducted from any payment to be made to claimant 1/30 of
1% of the contract price of all of the armor remaining undelivered
for each and every day of delay in the completion of the contract,
not, however, by way of penalty, but as liquidated damages.
It was, however, provided in article 8 of the contract, that the
Chief of Ordnance, in case of delay in the delivery of the armor,
as provided in article 1 of the contract, instead of completing the
manufacture or delivery of the material at the expense of claimant,
might waive the time limit and deduct from any payment due or to
become due the liquidated damages, if any, provided for in article
4:
"
Provided, however, that in making final settlement
based upon the date of completion of the delivery, the party of the
first part [claimant] shall receive credit for such delays
occurring during the performance of the contract as the Chief of
Ordnance may determine to have been due to unavoidable causes, such
as fires, storms, labor strikes, action of the United States, etc.,
and the date of completion shall be considered for the purposes of
final settlement as the date of the actual completion of the
delivery, less the delays due to unavoidable causes; but none of
the above causes shall constitute a basis for an action against the
United States for damages. "
Page 240 U. S. 164
The government filed a demurrer to the petition. It was
sustained as to $7,564.08 of the amount sued for and overruled as
to $1,031.08. The damages on account of delay to the amount of the
latter sum the court found was due to the government's delay. The
other sum, that is $7,564.08, the court attributed to the claimant,
the court saying, through Chief Justice Campbell, that
"the difficulties under which claimant labored . . . were not
due to 'unavoidable causes' within the meaning of those terms in
the contract, and, though unforeseen, did not render the
performance impossible,"
and added:
"The court cannot make a different contract from that which the
parties made for themselves.
The Harriman, 9 Wall. 161,
76 U. S. 172;
Sun
Printing & Publishing Ass'n v. Moore, 183 U. S.
642;
Satterlee's Case, 30 Ct.Cls. 31;
Pacific Hardware Co. v. United States, 48 Ct.Cls.
399."
It will be observed that the point in the case is a short one.
It is whether the causes of delay alleged in the petition were
unavoidable, or were of the character described in the contract --
that is, "such as fires, storms, labor strikes, action of the
United States, etc." The contention that the alleged causes can be
assigned to such category creates some surprise. It would seem that
the very essence of the promise of a contract to deliver articles
is ability to procure or make them. But claimant says its ignorance
was not peculiar, that it was shared by the world, and no one knew
that the process adequate to produce 14-inch armor plate would not
produce 18-inch armor plate. Yet claimant shows that its own
experiments demonstrated the inadequacy of the accepted formula. A
successful process was therefore foreseeable and discoverable. And
it would seem to have been an obvious prudence to have preceded
manufacture, if not engagement, by experiment, rather than risk
failure and delay and their consequent penalties by extending an
old formula to a new condition.
Page 240 U. S. 165
But even if this cannot be asserted, the case falls within
The Harriman, supra, where it is said that
"the principle deducible from the authorities is that, if what
is agreed to be done is possible and lawful, it must be done.
Difficulty or improbability of accomplishing the undertaking will
not avail the defendant. It must be shown that the thing cannot by
any means be affected. Nothing short of this will excuse
nonperformance."
And it was held in
Sun Printing Ass'n v. Moore, supra,
that
"it was a well settled rule of law that, if a party by his
contract charges himself with an obligation possible to be
performed, he must make it good unless its performance is rendered
impossible by the act of God, the law, or the other party.
Unforeseen difficulties, however great, will not excuse him."
Cases were cited, and it was said the principle was sustained by
many adjudications.
It was said, however, in
The Harriman,
9 Wall. 161,
76 U. S. 172,
that "the answer to the objection of hardship in all such cases is
that it might have been guarded against by a proper stipulation,"
and such a stipulation is relied on in the case at bar. Ignorance
of the scientific process necessary for face-hardening 18-inch
armor plate is asserted to be an unavoidable cause of the character
of the enumeration of article 8 of the contract -- that is, "such
as fires, storms, labor strikes, action of the United States, etc."
The contention is that it is the same "genus or kind," because (1)
it was not foreseeable when the contract was made; (2) was not the
result of any act or neglect on the part of claimant; (3) was not a
cause the company could prevent. What we have already said answers
these contentions. Ability to perform a contract is of its very
essence. It would have no sense or incentive, no assurance of
fulfillment, otherwise, and a delay resulting from the absence of
such ability is not of the same kind enumerated in the contract --
is not a cause extraneous to it and
Page 240 U. S. 166
independent of the engagements and exertions of the parties.
Judgment affirmed.
MR. JUSTICE McREYNOLDS took no part in the consideration and
decision of this case.