While the jurisdiction of this Court under § 237, Judicial
Code, may not attach where the state court gave no effect to the
state enactment claimed to have impaired the obligation of a
contract, where the state does give effect to later legislation
which does impair the obligation of a contract, if one exists, this
Court has jurisdiction to, and must, determine for itself whether
there is an existing contract, even though the state court may have
put its decision upon the ground
Page 235 U. S. 165
that the contract was not made, was invalid, or had become
inoperative.
In determining whether effect has been given to later
legislation, this Court is not limited to mere consideration of the
language of the opinion of the state court.
This Court has jurisdiction under § 237, Judicial Code, to
determine whether there is a contractual obligation which plaintiff
in error is entitled to enforce without its being impaired by the
operation of subsequent legislation enacted by or under the
authority of the state.
While courts should give them a fair and reasonable
interpretation, public grants are not to be extended by implication
beyond their clear intent.
As the ordinance on which the contract claimed to have been
impaired was based was intended to confer rights exclusively with
reference to an existing plan of construction, and as that plan
proved abortive because of legal obstacles to its fulfillment, no
rights were conferred thereby, and a later ordinance on the same
subject cannot be deemed invalid under the impairment of obligation
clause of the federal Constitution.
An ordinance of the City of New Orleans regarding construction
of the Belt Railroad
held not unconstitutional because it
impaired the obligation of a contract based on a former ordinance,
as such contract was subject to a suspensive condition, and the
event in which the obligation was to arise had not happened.
127 La. 775 affirmed.
The facts, which involve the jurisdiction of this Court under
§ 237, Judicial Code, and also the constitutionality under the
impairment of obligation provision of the federal Constitution of
an ordinance of the City of New Orleans relating to the
construction and operation of a belt railroad within the city, are
stated in the opinion.
MR. JUSTICE HUGHES delivered the opinion of the Court.
The plaintiff in error seeks to review the judgment of the state
court upon the ground that it denied a federal right
Page 235 U. S. 166
asserted under the contract clause of the Constitution. Art. I,
§ 10.
The suit was brought by the Mayor of the City of New Orleans, in
his official capacity, to restrain the Louisiana Railway &
Navigation Company from proceeding under a municipal ordinance --
No.1997, New Council Series, dated September 4, 1903 -- to
construct and operate tracks over a Public Belt railroad
reservation, and from operating cars, etc., over Public Belt
railroad tracks, and to have the ordinance, so far as it granted to
that company such privileges of construction and operation,
declared null and void. The facts, so far as it is necessary to
state them, are these:
The authorities of the City of New Orleans devised the plan of
establishing a Public Belt railroad along the riverfront. On March
1, 1899, the city adopted an ordinance (No. 15,080, C.S.) under
which, in consideration of certain concessions, the Illinois
Central Railroad Company built about two miles of the projected
system -- that is, from the upper limit of the city to the upper
boundary of Audubon Park. This was followed by ordinance No. 147,
N.C.S., adopted August 7, 1900, which created a belt railroad Board
composed of the mayor and certain city officials to construct,
control, and operate the belt railroad for the benefit of the city,
and on August 12, 1902, the Board of Commissioners of the Port of
New Orleans, called the "Dock Board" -- a body exercising state
authority over a part of the area to be traversed by the proposed
road -- approved the dedication for the purpose stated. This
approval was to remain in force only so long as the belt railroad
was "operated and controlled by a public commission" in accordance
with the provisions of ordinance No. 147.
On February 10, 1903, a further ordinance was adopted -- No.
1615, N.C.S. -- which, among other things, granted to the New
Orleans & San Francisco Railroad Company
Page 235 U. S. 167
a right of way over the belt line and reservation from the upper
limit of the city to Henderson Street. The condition was that the
company, at its own expense, should construct and dedicate to
perpetual public use the tracks as projected from the end of the
line already built, on the upper side of Audubon Park, to Henderson
Street (a distance of about five miles), the construction to be
completed before July 1, 1904. Other provisions looked to still
further construction through contributions from other railroads.
The validity of this ordinance was at once challenged in a suit
brought by the mayor, on behalf of the city, which resulted in
favor of the railroad company.
Capdevielle v. New Orleans R.
Co., 110 La. 904. The terms of the ordinance, however, did not
conform to the conditions upon which the Dock Board had consented
to the building of the belt road, and, in a suit brought by that
Board against the railroad company, the carrying out of ordinance
No. 1615 was restrained so far as it authorized the construction of
the railroad upon the property subject to the Board's jurisdiction.
Board of Commissioners v. New Orleans & San Francisco R.
Co., 112 La. 1011. Following this decision, it appears that
the New Orleans & San Francisco Railroad Company abandoned the
building of the belt line contemplated by the ordinance; no part of
it was constructed thereunder.
On September 4, 1903, while the suit of the Dock Board was
pending and after the final decision in the Capdevielle suit, the
city adopted ordinance No.1997, N.C.S. -- the ordinance here in
question (127 La. pp. 784-792). Without passing now upon points in
controversy, it may be said that this ordinance, reciting that,
under ordinance No. 1615, there had already been granted to the New
Orleans & San Francisco Railroad Company the right to construct
the belt line over the reservation from the place at which the
rails then terminated to Henderson Street,
Page 235 U. S. 168
granted to the Louisiana Railway & Navigation Company -- the
plaintiff in error -- a right of way over "the double track belt
line and reservation" to that point, upon stated terms and
conditions, among which may be noted the following: that, when the
plaintiff in error had operated its equipment over the described
belt tracks for thirty days, it should pay to the city the sum of
$50,000; that, in case the New Orleans & San Francisco Railroad
company failed "without legal excuse" to build the described line
to Henderson Street, as provided in ordinance No. 1615, the
plaintiff in error should build that line in place of the
first-mentioned company, this construction to be in lieu of the
payment of $50,000, and the belt tracks so built, as soon as
completed to Henderson Street, to be "turned over to the immediate
ownership of the City of New Orleans," and to be under "the control
and management of the Public Belt authority," and further, that in
case the New Orleans & San Francisco Railroad Company should,
from any cause, complete only a portion of the described tracks,
the plaintiff in error should have the right to use so much of the
described belt line as had been built, on payment of a
proportionate part of the specified sum. This ordinance the
plaintiff in error formally accepted on September 17, 1903.
The suit brought by the Dock Board against the New Orleans &
San Francisco Railroad Company was decided by the supreme court of
the state in May, 1904, and, in the October following, the city
adopted ordinance No. 2683, N.C.S., which made comprehensive
provision for municipal construction and operation of the belt line
system. All conflicting ordinances were repealed, and it cannot be
doubted that this ordinance, if enforced, would make it impossible
for the plaintiff in error to exercise the rights it might
otherwise have under ordinance No.1997. The belt Board was
reorganized by the establishment of a new Public Belt Railroad
Commission, composed
Page 235 U. S. 169
of the mayor and sixteen "citizen taxpayers" to whom was
confided the necessary administrative authority for carrying out
the municipal scheme. This ordinance received the approval of the
Dock Board on stated conditions, and, on July 1, 1905, the new
undertaking was formally inaugurated. On November 10, 1905, the
plaintiff in error deposited with a trust company which was one of
the fiscal agents of the city $50,000 in securities in alleged
compliance with its contract under ordinance No.1997. The city,
however, went on with its own plan, arranging for bank credits to
enable it to carry on the work under ordinance No. 2683, and when,
in May, 1906, the plaintiff in error attempted to begin
construction under the earlier ordinance, it was stopped by the
city authorities. Soon after, the present suit was instituted.
The petition of the mayor, alleging upon various grounds the
invalidity of ordinance No.1997, also averred the adoption of
ordinance No. 2683, the irrevocable dedication thereby for the
reservation of the Public Belt railroad, and the undertaking by the
city, under that ordinance, of the work of construction. The
plaintiff in error, in its answer, set up the unconstitutionality
of the later ordinance as one impairing contractual obligations. At
the beginning of the suit, a preliminary injunction was granted in
accordance with the city's prayer, and the city proceeded with the
construction of the Public Belt railroad, which has since been put
in operation. In the court of first instance, judgment went "in
favor of the plaintiff, Martin Behrman, in his official capacity of
Mayor of the City of New Orleans, and as
ex-officio
president of the Public Belt Railroad Commission of the city,"
declaring ordinance No.1997, so far as it purported to grant the
privileges in dispute, to be "illegal, void, and of no effect," and
making the injunction permanent. This judgment was affirmed by the
supreme court of the state upon the ground that the contract
was
"subject to a suspensive
Page 235 U. S. 170
condition, and that this condition had become impossible of
realization, and the contract had, in consequence, fallen through
when plaintiff made its attempt to begin work and the injunction
was taken."
127 La. 775, 795-796.
The defendant in error moves to dismiss, invoking the
established rule that, where the state court gives no effect to the
subsequent enactment, the jurisdiction of this Court does not
attach.
Knox v. Exchange
Bank, 12 Wall. 379,
79 U. S. 383;
Lehigh Water Co. v. Easton, 121 U.
S. 388,
121 U. S. 392;
New Orleans Water Works Co. v. Louisiana Sugar Co.,
125 U. S. 18,
125 U. S. 38-39;
Central Land Co. v. Laidley, 159 U.
S. 103,
159 U. S. 111;
Bacon v. Texas, 163 U. S. 207,
163 U. S. 216,
163 U. S. 219;
Fisher v. New Orleans, 218 U. S. 438,
218 U. S. 440;
Missouri & Kansas Interurban Ry. v. Olathe,
222 U. S. 187,
222 U. S. 190;
Cross Lake Club v. Louisiana, 224 U.
S. 632,
224 U. S. 639.
We are of the opinion that the present case is not within this
rule. It is equally well settled that, where the state court does
give effect to later legislation which operates to impair the
obligation of a contract if one exists, this Court is not deprived
of jurisdiction because the state court has put its decision upon
the ground that the contract was not made, or that it was invalid,
or that it has become inoperative. In such a case, this Court must
determine for itself whether there is an existing contract.
Otherwise, although it was the aim of the suit and the effect of
the judgment to give vitality and operation to the subsequent law,
and this Court might be of the opinion that there was a valid
contract which thereby would be impaired, it would be powerless to
enforce the constitutional guaranty.
Jefferson
Branch Bank v. Skelly, 1 Black 436,
66 U. S.
442-443;
Bridge Proprietors v. Hoboken
Co., 1 Wall. 116,
68 U. S.
144-145;
Northwestern University v. Illinois,
99 U. S. 319,
99 U. S. 321;
Mobile & Ohio Railroad v. Tennessee, 153 U.
S. 486,
153 U. S. 492;
Douglas v. Kentucky, 168 U. S. 488,
168 U. S. 502;
Atlantic Coast Line v. Goldsboro, 232 U.
S. 548,
232 U. S. 556;
Russell v.
Sebastian, 233
Page 235 U. S. 171
U.S. 195,
233 U. S. 202.
And, in determining whether effect has been given to the later
statute, this Court is not limited to the mere consideration of the
language of the opinion of the state court.
McCullough v.
Virginia, 172 U. S. 102,
172 U. S. 116;
Houston & Texas Central Railroad v. Texas,
177 U. S. 66,
177 U. S. 76-77;
Hubert v. New Orleans, 215 U. S. 170,
215 U. S. 175;
Carondelet Canal Co. v. Louisiana, 233 U.
S. 362,
233 U. S. 376.
In the present case, it is apparent that the whole object of the
suit was to establish the right of the city to carry out the
subsequent ordinance, which conflicted with and repealed the
earlier ordinance so far as it might be construed to give to the
plaintiff in error the particular privileges therein described. It
was, as appears from the petition itself, to accomplish the purpose
of the later enactment, and the building of the belt line
thereunder, that the city asked the aid of the court's injunction
in this suit, and it was through this protection that the municipal
scheme of construction under the later ordinance was actually
carried out. The final judgment completed and made permanent this
protection, with respect to operation as well as construction, as
against the claim of contract right. It must follow that this Court
has jurisdiction to determine whether that claim is well founded --
that is, whether there is a contractual obligation which the
plaintiff in error is entitled to enforce without its being
impaired by the operation of the subsequent provision having, by
virtue of state authority, the force of state law.
It is the contention of the plaintiff in error that, although
the proposed belt road to Henderson Street was not built by the New
Orleans & San Francisco Railroad Company, and although it be
assumed that the failure of that company to build was legally
excusable, and hence that the obligation of the plaintiff in error
to build in its stead did not arise, still there was an effective
grant under ordinance No.1997, and the plaintiff in error is
entitled to
Page 235 U. S. 172
the use of the belt in the manner therein described upon the
payment of $50,000.
We agree with the state court that this is not a proper
interpretation of the ordinance.
* Provision had
already
Page 235 U. S. 173
been made for construction to the designated point by the New
Orleans & San Francisco Railroad Company. Ordinance No.1997
prefaced its grant by a recital of the right of construction which
had been given to that company,
Page 235 U. S. 174
and it was expressly stated that the grant to the plaintiff in
error was made "under the belt provisions of said ordinance No.
1615." It had been provided in the last-mentioned ordinance that
the public authorities might give to other railroad companies the
right to use the road thus to be constructed, on their making
contributions which should go into a special fund for the further
extension of the belt line system. It is manifest that the intent
was to give to the plaintiff in error the described right to use
the tracks thus to be laid. But it was also contemplated
Page 235 U. S. 175
that the New Orleans & San Francisco Railroad Company might
fail to build, and that this failure might be "without legal
excuse." In that event, it was agreed that the plaintiff in error
should step into the place of the other company and assume the
burden of construction "under the terms and conditions" of
ordinance No. 1615, such construction to take the place of the
pecuniary consideration for the use of the tracks. It was further
apparent that the fulfillment of the plan of ordinance No. 1615
might be legally impossible, and hence that the failure of the New
Orleans & San Francisco Railroad Company might be legally
excused. In this event, the plaintiff in error did not undertake to
build, and no right of construction was given to it. We cannot
imply such a right. While we are to give to public grants a fair
and reasonable interpretation (
United States v. Denver &c.
Ry. Co., 150 U. S. 1,
150 U. S. 14;
Russell v. Sebastian, 233 U. S. 195,
233 U. S.
205), they are not to be extended by implication beyond
their clear intent. The right of construction was given to the
plaintiff in error in a particular contingency, and not otherwise,
and the explicit provision for construction negatives an intention
to bind the city to permit it in a case not specified. There was
abundant reason for both expression and omission. The suit of the
Dock Board was pending, and whether the New Orleans & San
Francisco Railroad Company would be able to build, as provided in
ordinance No. 1615, was undecided. If that company did build, the
city was prepared to give, and, in that event, did give, to the
plaintiff in error, the right of way upon the agreed payment, and
if that company failed to build "without legal excuse," the city
was ready to provide, and in that event did provide, that the
plaintiff in error should build in its stead. But if there were
legal excuse for a failure of the New Orleans & San Francisco
Railroad Company to build, it was plainly desirable that neither
party should be bound. In that case, as the terms
Page 235 U. S. 176
of the ordinance show, the plaintiff in error was unwilling to
assume the burden of construction, and the city, by not binding
itself in that contingency, preserved its freedom to deal as it
might seem best with the exigency that would thus arise. Ordinance
No.1997 did not obligate the city to build the belt road or any
part of it; it did not bind the city to cause the road to be built
by others. As we read the ordinance, it was intended to confer
rights exclusively with reference to an existing plan of
construction, and if that plan proved abortive because of legal
obstacles to its fulfillment, no right was conferred upon the
plaintiff in error.
It is urged that the provisions of ordinance No.1997 [§ 3,
par.(c)] that the belt tracks to be constructed by the plaintiff in
error, as soon as they were completed to Henderson Street, should
be turned over to the "immediate ownership of the city," and should
be under the "control and management" of the Public Belt authority,
obviated the objection raised by the Dock Board with respect to
ordinance No. 1615. But an examination of other provisions of the
ordinance shows that this "control and management" was intended to
be subject to certain limitations. Thus, it was provided in
paragraph (f) that all controversies between the plaintiff in error
and the Public Belt authority, or any other company or companies to
which the use of the tracks might be granted, relating to the
movement and handling of cars, trains, and traffic thereon, should
be submitted to three arbitrators, one to be selected by the
plaintiff in error, the second by the Public Belt authority, or by
such other company or companies, as the case might be, and the
third by the two thus chosen, and that the decision of any two of
these arbitrators was to have the effect of an "amicable
composition." We find no reason to doubt the correctness of the
conclusion that the conditions, subject to which the Dock Board
approved the dedication for belt road purposes of
Page 235 U. S. 177
the portion of the proposed route under its jurisdiction, would
have been violated under the plan of ordinance No.1997, as well as
under that of ordinance No. 1615. And further, it is clear that the
proviso in paragraph (c) which related to tracks to be constructed
by the plaintiff in error did not change the event in which alone
the plaintiff in error was entitled to construct them, and this was
in case the New Orleans & San Francisco Railroad Company should
fail to build "without legal excuse."
Thus far, we have assumed that the New Orleans & San
Francisco Railroad Company was legally excused from building. But
it is insisted by the plaintiff in error that this is not the case.
That is, it is said that the grant of the right to construct was
divisible, and that, so far as the city was competent to provide
for such construction, the New Orleans & San Francisco Railroad
Company was bound to build the belt road, and therefore that its
failure to build to this extent was "without legal excuse" within
the meaning of the paragraph (c). But ordinance No. 1615 negatives
this view. It explicitly provided for construction "from the end of
the rails on the upper side of Audubon Park to Henderson Street,"
and that the city should furnish "a clear legal right of way for
the construction of said tracks." We think that there is no basis
whatever for the contention that the New Orleans & San
Francisco Railroad Company was bound to construct a part of the
belt road specified if, by reason of the successful opposition of
the Dock Board, it was without power to build the remainder. And
when the Dock Board prevailed in its suit, that company was
entitled to abandon, as it did abandon, the undertaking. This was
the event which was carefully excluded by ordinance No. 1997 in
defining the contingency in which the plaintiff in error should
build. The provision in paragraph (c) for the return of the
securities which were to be deposited by the plaintiff in error as
security for the performance of its obligation, in case
Page 235 U. S. 178
it should be prevented "from building said belt tracks or any
portion of the same on account of the city not furnishing the right
of way," or "by causes beyond its control," tends to support,
rather than to oppose, the view that the undertaking was regarded
as an entirety; for all the securities were to be returned,
although the prevention related to a portion of the route only. We
are also referred to the provision [§ 3, par. (d)] that, in
the event that the New Orleans & San Francisco Railroad Company
should, from any cause, complete "only a portion of the tracks"
described, the plaintiff in error should have the right "to operate
its own locomotives, cars," etc, "over such portion of the tracks"
as had already been built, and as might be built by the
first-mentioned company, for a proportionate part of the agreed
payment. This clause, in view of the existing situation of the
parties, was held by the state court to have reference to a
contingency in which, the opposition of the Dock Board not having
been successful, the railroad company had proceeded with its
undertaking and, having built a part of the tracks, had failed to
complete them, and this construction is in harmony with the other
provisions of the ordinance. But, in fact, the event described in
paragraph (d) did not happen, as no part of the road was built, and
this clause in no way aids the contention that the New Orleans
& San Francisco Railroad Company was under legal obligation to
undertake a partial construction if it became legally impossible to
carry out its undertaking as a whole.
We conclude that the contract upon which the plaintiff in error
relies was subject, in any aspect, to a suspensive condition (Civil
Code, La., Art. 2021), that the event in which the obligation was
to arise did not happen, and hence that the subsequent enactment
was not open to the objection raised.
Judgment affirmed.
*
"This ordinance, so far as it is material with respect to this
question, is as follows:"
" SECTION 3. Be it further ordained, etc., that, whereas, under
ordinance No. 1615, N.C.S., the New Orleans & San Francisco
Railroad Company, its successors or assigns, have been granted the
right to construct, at their own cost and expense, the double track
belt line over the belt reservation on the riverfront, from the
present end of the Public Belt on the upper side of Audubon Park to
Henderson Street, and under said ordinance the company dedicates
said tracks to perpetual public use therefore under the belt
provisions of said ordinance No. 1615, N.C.S., 'and with the
limitations therein which recognize and preserve the present and
future rights of the City of New Orleans over the projected Public
Belt railroad,' the Louisiana Railway & Navigation Company is
hereby granted a right of way over the double track belt line and
reservation on the river front of the City of New Orleans, from the
upper limits of the City of New Orleans to Henderson Street, upon
the following terms and conditions:"
" (a) That, when said Louisiana Railway & Navigation Company
shall have operated its engines, trains, and cars over said belt
tracks, as provided in this ordinance, for a period of thirty days,
the said company shall pay to the City of New Orleans the sum of
Fifty Thousand Dollars ($50,000), . . . and when said company shall
be ready to begin to operate its engines, trains, and cars as above
provided, the said company shall deliver to the fiscal agent of the
City of New Orleans, bonds or other securities, satisfactory to
said fiscal agent, of the value of $50,000, the same to be held in
escrow as security for compliance by said company with the
foregoing obligation, and to be returned to said company when said
company shall have operated its engines, trains, and cars over said
belt tracks, as provided in this ordinance for a period of thirty
days and shall have paid said sum of $50,000 to said fiscal agent.
. . ."
" (b) That, in consideration of the payment of the above sum,
the Louisiana Railway & Navigation Company shall have the right
to operate its own locomotives, cars, and equipment over the said
Public Belt from the upper city limits to Henderson Street. . .
."
"(c) That, in the event of the New Orleans & San Francisco
Railroad Company, its successors or assigns, failing, without legal
excuse, to build said belt tracks from the upper side of Audubon
Park to Henderson Street, on or before July 1, 1904, the Louisiana
Railway & Navigation Company shall build the same from the
upper side of Audubon Park to Henderson Street, under the terms and
conditions of Paragraph 10 of Section 2 of Ordinance No. 1615,
N.C.S.; and, in case said Louisiana Railway & Navigation
Company shall build said tracks, it is hereby granted the right and
privilege to operate its trains, cars, and traffic over said tracks
under all the provisions and terms of said Paragraph 10 of Section
2 of ordinance No. 1615, N.C.S., said Louisiana Railway &
Navigation Company assuming the obligation of the New Orleans &
San Francisco Railroad Company under said paragraph of said
ordinance, and being hereby granted all the rights and privileges
of said New Orleans & San Francisco Railroad Company, its
successors or assigns, under said Paragraph 10 of Section 2 of said
ordinance, except as hereinafter provided, such construction of
said tracks from the upper side of Audubon Park to Henderson Street
to be in lieu of the payment of $50,000, referred to in Paragraph
(a) of this section, provided that said Louisiana Railway &
Navigation Company shall complete the said tracks to Henderson
Street within one year from the time the city shall furnish the
clear and undisputed right of way, it being always understood that
said Louisiana Railway & Navigation Company assumes all the
obligations of the New Orleans & San Francisco Railroad Company
under Paragraph 10 of Section 2 of said ordinance No. 1615, N.C.S.,
and provided that, as soon as said belt tracks shall be completed
to Henderson Street, the same shall be turned over to the immediate
ownership of the City of New Orleans, and to be under the control
and management of the Public Belt authority, and provided, further,
that said Louisiana Railway & Navigation Company shall, on July
1, 1904, deposit with the fiscal agent of the City of New Orleans,
bonds or other securities satisfactory to said fiscal agent, of the
value of $50,000, the same to be held in escrow as security for
compliance by said company with the foregoing obligations, and to
be returned to said company when said company shall have built and
completed said belt tracks from the upper side of Audubon Park to
Henderson Street, and provided further that, in case said company
shall be prevented from building said belt tracks, or any portion
of the same, on account of the city's not furnishing the right of
way under the terms of ordinance No. 1615, N.C.S., or by causes
beyond its control, then the securities deposited shall be returned
to it by said fiscal agent. . . ."
" (d) That, in the event the New Orleans & San Francisco
Railroad Company, its successors and assigns shall, from any cause,
complete only a portion of the tracks from the upper side of
Audubon Park to Henderson Street, the Louisiana Railway &
Navigation Company, its successors and assigns, shall have the
right to operate its own locomotives, cars, and equipment over such
portion of the tracks as is already built, and as may be built by
the New Orleans & San Francisco Railway Company, its successors
and assigns, and for such privilege shall pay to the City of New
Orleans such proportion of the sum provided in clause (a) of this
paragraph as the tracks so constructed and used by said Louisiana
Railway & Navigation Company bear to the whole length of the
tracks from upper city limits to Henderson Street."
"
* * * *"
" (f) That all controversies between the Louisiana Railway &
Navigation Company, on the one side, and the Public Belt authority,
or any other company or companies to which the city or her Public
Belt authority may grant the use of said tracks and appurtenances,
on the other side, relative to the use of said tracks and
appurtenances, or the cost of construction or maintenance thereof,
or the rules and regulations relative to the movement and handling
of cars, trains and traffic thereon and thereover, shall be
submitted to the arbitration of three disinterested persons, one to
be selected by said Louisiana Railway & Navigation Company, the
second by the Public Belt authority, or such other company or
companies, as the case may be, and the third by the two thus
chosen, and the decision of this tribunal, or any two of them,
shall have the effect of an amicable composition. . . ."