Even though contractors may not be entitled to a mechanics' lien
under the statute unless the contract be completed, they may be
entitled thereto if absolute completion is waived, and in this
case, this Court will not go behind the finding of the master
followed by the court below that there was a waiver and the
contractor was justified in stopping work.
Where the state trial court had upheld a mechanics' lien before
the petition and the trustee in bankruptcy seeks in the federal
court to prevent the enforcement of the lien, this Court will not
go behind the state judgment because exceptions thereto had not
been passed upon owing to the action of those representing the
estate.
In this case, this Court is satisfied that substantial justice
has been
Page 231 U. S. 693
done in enforcing a lien for over $45,000 admittedly due to the
contractor but contested because about $1,000 of work remained
uncompleted on a contract of $187,000, the contractors having
ceased work after the owner of the building had failed in its
payments and was hopelessly insolvent.
175 F. 501 affirmed.
The facts, which involve the validity of lien for labor and
materials on property of a bankrupt, and the necessity for
completion of the contract in order to maintain the lien, are
stated in the opinion.
Page 231 U. S. 699
MR. JUSTICE HOLMES delivered the opinion of the Court.
This case arises upon a petition by a trustee in bankruptcy to
prevent the enforcement of a lien for labor and materials in a
state court. The proceedings in the state court were begun and had
passed to a judgment in the Superior Court of New Hampshire,
subject to exceptions, before the adjudication of bankruptcy.
Afterwards, the exceptions were overruled on technical grounds not
touching the merits, the trustee in bankruptcy being heard at this
stage. The action upon the matter in the courts of the United
States will be seen in 169 F. 586, 175 F. 501, and 184 F. 409, a
rehearing being denied upon the last decision in 185 F. 1006, and
an appeal to this Court allowed in 191 F. 811. The allowance of the
appeal was correct.
Knapp v. Milwaukee Trust Co.,
216 U. S. 545;
Greey v. Dockendorff, ante, p.
231 U. S. 513.
The Head & Dowst Company had agreed with the bankrupt to
erect a grandstand, clubhouse, and other buildings and structures
for $187,644, and had completed the work, with the exception of
shutters on the grandstand that would cost about $1,000 to finish.
At this point,
Page 231 U. S. 700
it was told by the bankrupt of the hopeless insolvency of the
latter, and was informed that it must look to its lien to support
its claim. Thereupon the company stopped work and began its lien
suit. When the present attempt was made to reopen the matter, the
case was sent to a master, who reported in great detail the facts
just summed up, and concluded that the company was entitled to a
lien for $45,995.02, exclusive of interest, that being the part of
the contract price remaining unpaid, less $1,000 for the shutters,
etc., and being also very nearly the same sum that was found due in
the state court. The judge of the district court thereupon
dismissed the trustee's petition, and his decree was affirmed by
the circuit court of appeals. 175 F. 501,
supra.
We shall consider such questions only as are sufficient to
decide the case, omitting others that would have to be considered
before the decree below could be reversed. The trustee argues that
the failure to take the proper steps to get exceptions heard by the
supreme court of the state on the merits constitutes an equitable
ground for going behind the state judgment in order to defeat it by
an objection of the most narrowly technical sort. The objection, of
course, is that the contract was entire, and that whatever
justification there may have been for stopping work, or ground for
a
quantum meruit, nothing short of complete performance
would earn the contract price as such, or establish a lien for the
same. It is argued in the same connection that the facts did not
justify the company in stopping work, but we shall not go behind
the finding of the master in this respect, followed as it has been,
or say more than that, as we construe the facts and finding, it was
quite right, and that putting on the last touches was waived.
We are of opinion that the decision was equally right. The case
was tried upon its merits and decided in favor of the lien by the
state court. The failure to get the
Page 231 U. S. 701
exceptions considered was due to no fault of the appellee, but
solely to the conduct of those then representing the interests of
the estate. It is a doubtful suggestion that an equity could be
founded upon this. Certainly it is an inadequate ground for the
intervention of equity to enforce forfeiture of a claim that could
not be defeated, if at all, except by a most technical application
of the law, and on the assumption that the state court did not know
the law of the state. We shall not speculate upon that point beyond
saying that we see no reason to doubt that the state court was
right,
Bergfors v. Caron, 190 Mass. 168, and cases in 27
Cyc. 85, 87, and 20 Am. & Eng. Enc.Law, 2d ed. 366-368, as we
are satisfied that substantial justice has been done. Some
subordinate matters of detail were argued, but they do not seem to
us to need mention; the whole strength of the case lay in the
matter of which we have disposed.
Decree affirmed.