In this case,
held that a bond given in pursuance of an
ordinance, for faithful performance of a contract, was solely for
the complete result at the end of the period specified, and that it
did not permit a recovery of the whole penalty upon any
intermediate breach.
Breaches of subordinate requirements, which are specified in a
contract for a public utility and bond for performance and are
simply means to an end, cannot be made the basis of recovering the
whole penalty after final completion or after cancellation by the
obligee of the franchise.
If within time for completion of a public utility authorized by
ordinance, the municipality itself makes performance impossible, it
cannot, under any system of law in Porto Rico or elsewhere, recover
upon the bond for failure to perform.
180 F. 641 affirmed.
The facts, which involve the liability of a surety company on a
bond given for faithful performance of a contract, are stated in
the opinion.
Page 227 U. S. 383
MR. JUSTICE HOLMES delivered the opinion of the Court.
This is a suit upon a joint and several bond executed by the
defendant in error as surety for the Vandegrift Construction
Company. In the circuit court, a nonsuit was ordered, and the order
was affirmed by the circuit court of appeals on the ground that the
plaintiff, by its own act, had made performance of the condition
impossible. 180 F. 641. The facts are these:
By an ordinance of March, 1903, Porto Rico granted to the
Vandegrift Company the right to build and operate an electric
railway and also a power plant in specified places in the island.
Within one year from acceptance of the grant, the grantee was to
have its roadbed completely graded between the Island of San Juan
and the urban portion of the municipality of Caguas, and the
foundations and approaches of a certain bridge completed. Section
15. Within two years, it was to have the parts of the railway lying
between the urban portion of San Juan and Caguas and certain other
points finished and ready for service. Section 16. Within three
years, it was to have the whole line completed and in operation.
Section 17. It was stated to be expressly understood and agreed
that, upon the grantee's failure to have the line in full operation
within the time limited,
i.e., three years, the grantee's
right to operate any part of it or to sell electric light and power
should cease unless the failure should be declared by the executive
council to be due to one of certain excuses, such as the Act of
God. Section 16.
A power dam at Comerio Falls was to be completed in one year and
the greater part of the electric apparatus
Page 227 U. S. 384
contracted for; the whole power plant and transmission lines
necessary for operating the railway to be completed within three
years. Section 18. The grantee was to pay the government two
percent of its gross receipts from the sale of light and power to
private consumers, Section 23, was not to charge above certain
maxima fixed for passengers and freight, Section 25, and was to
carry certain persons, such as prisoners and police on duty, free
of charge, Sections 27, 28. The rights, privileges, and concessions
granted by the ordinance were expressed to be subject to amendment,
alteration, or repeal by the executive council. Section 30. Then it
was provided that the rights granted
"shall be accepted by the grantee in writing and by executing a
bond in favor of the Porto Rico, in the sum of $100,000,
satisfactory, etc., . . . and conditioned upon the full completion
of the work herein authorized within three years after such
acceptance, and in accordance with the conditions herein contained,
and in accordance with the plans and specifications therefor
approved as herein provided, and conditioned also upon the payment
by the grantee to the Porto Rico of any loss or damage or costs
accruing against the People of Porto Rico, by reason of the
construction of the works herein authorized at any time during the
period of construction herein limited,"
etc. Section 34.
Upon presentation of a certificate of completion from the
Commissioner of the Interior,
"and upon the full compliance with the terms of this ordinance
to the satisfaction of the executive council, and upon the full
payment by the grantee of any loss, damage, and costs accruing
against the People of Porto Rico, as in said bond provided, the
said bond shall be cancelled."
§ 35. Finally, the ordinance is to "take effect immediately
upon the acceptance by the grantee of the terms and conditions
hereof, as above provided." Section 38.
Page 227 U. S. 385
The bond in suit was executed, referring to and annexing the
ordinance, and conditioned, among other things, that the principal,
within three years from the date of the acceptance by it of the
ordinance, should fully complete the work "in accordance with the
conditions therein contained," and again, that it should
"duly perform within the said period of three (3) years, all
other terms and conditions in said ordinance required to be
performed by the principal within the said period.
* "
Page 227 U. S. 386
The principal failed to do within the year the work required by
§ 15 to be completed in that time, as has been stated, and, a
little more than two months after the year elapsed, in July, 1904,
the executive council passed an ordinance amending §§ 15,
18, and 30 of the former one, the amendment being approved by the
President on August 2. The time allowed in § 15 was extended
to January 1, 1905, provided that the number of men employed on or
before August 7 should be not less than 250, and that the number
should be increased up to 500 or thereabouts, the intent expressed
being that as many men should be engaged as was necessary to
complete the work, and provided that the men should be paid weekly,
and provided further that, upon failure to comply with the terms
and conditions of the amendment, the franchise should be subject to
immediate forfeiture. The requirement in § 18 as to the power
dam at Comerio Falls, etc., also was extended to January 1, 1905.
Finally, to the provision in § 30 as to amendment, &c., of
the concession, there was added the express requirement of the
approval of the Governor of Porto Rico and of the President of the
United States, and the statement that it was subject to the power
of Congress to annul or modify the same. This amendment seems to
have been sought and accepted
Page 227 U. S. 387
by the principal, but was not known to the defendant surety
company, so far as appears.
In February, 1905, a further ordinance was passed, approved by
the Governor in March and by the President on May 12, which recited
a failure by the company to comply with the terms of §§
15 and 18, either in their original form or as amended, and
therefore repealed and revoked the grant, and declared all
"sureties or obligations . . . given by the said grantee as a
guaranty . . . forfeited to the Porto Rico to all and whatsoever
extent the same shall be liable under the law."
In September, 1906, this suit was begun.
The main question is the scope of the condition of the bond. The
plaintiff says that it was for the due performance of all the terms
required by the ordinance, and, since the bond was a contract made
in Porto Rico, as no doubt it was at least, as between these
parties, that, upon any breach of condition the whole penalty
became due by the local law. Civil Code §§ 1120, 1121.
The circuit court of appeals, on the other hand, assumed that the
bond was only for the result at the end of three years.
After some hesitation, we have come to the conclusion that the
court was right. It is true that the bond is to be read in
connection with the original ordinance, and that the latter
contained terms that were not complied with. But the ordinance only
required a bond for the full completion of the work within three
years, and in accordance with the conditions therein contained and
the plans. Section 34. In the ordinance, the only condition
properly so called, the only fact that warranted a revocation of
the grant apart from the general power to repeal, was, by §
16, a failure to have the whole railway in operation, as required
by § 17. There was no forfeiture for falling short of the
requirements in §§ 15 and 16 as to the progress to be
made in one and two years. The bond in like manner has for its
principal condition the completion of the work within
Page 227 U. S. 388
three years. It is true that the completion was to be in
accordance with the terms contained in the ordinance, but this
clause cannot mean that, if the road and works were in satisfactory
operation within three years the obligee could recur to the history
of events and, if it found that some item was not finished within
the time allowed for it, could set up that fact as a breach, and,
by its interpretation of Porto Rican law, recover the whole penalty
of the bond. The subordinate requirements were simply means to an
end, and if the end was reached, their importance disappeared. The
very contentions of the plaintiff as to the liability incurred upon
any breach are arguments against supposing that such incidental
failures to be on time had such a consequence attached.
There is a further provision for the principal performing,
"within the said period of three (3) years, all other terms and
conditions in said ordinance required to be performed by the
principal within the said period."
This, perhaps, affords the plaintiff its strongest argument. But
this is a residuary clause to cover matters that may have escaped
consideration. The building of the road and works already have been
dealt with, and this clause as to "other" terms hardly can be
supposed to have reference to them. If it does, however, it would
seem to us that the limitation of time should be construed as
looking to the end of the three years, and allowing that period,
rather than distributively, and as meaning from time to time during
three years. The same considerations that apply to the construction
of the principal condition apply to this, and it appears to us that
the provision for the cancellation of the bond upon certificate
showing the completion of the work, "and upon the full compliance
with the terms of this ordinance to the satisfaction of the
executive council," is not enough to change what we understand to
be the import of the instrument upon its face. Finally, the proviso
that no extension of the time or times limited for
Page 227 U. S. 389
the completion of the work "or any part thereof" shall discharge
the surety at most merely recognizes that the principal, by
accepting the ordinance, contracted to do the parts of the work as
required, as well as the whole, and with natural caution saves the
rights of the obligee against the surety in case of any extension
of time, a matter that obligees have learned to fear.
If our construction of the bond is right, it does not need much
argument to show that the plaintiff is not entitled to recover,
seeing that, within three years, it took the franchise back. It was
said at the bar, though not admitted, that the principal had given
up work. But there had been no repudiation of the contract, and the
plaintiff could not accelerate the forfeiture simply on the ground
that it was likely to come about. If, within the time allowed for
performance, the plaintiff made performance impossible, it is
unimaginable that any civilized system of law would allow it to
recover upon the bond for a failure to perform. 2 Bl.Com. 340, 341;
United States v.
Arredondo, 6 Pet. 691,
31 U. S.
745-746.
Judgment affirmed.
* The whole condition of the bond was as follows:
"Now therefore the condition of this obligation is such that, if
the said principal shall, within three years from the date of the
acceptance by it of said ordinance, fully complete the work therein
authorized in accordance with the conditions therein contained, and
in accordance with the plans and specifications therefor, approved
as therein provided, and within the said period of three (3) years
from the date of the acceptance by it of the said ordinance shall
build, complete, and have in operation the entire line of railway
authorized therein for such terminal in the municipality of San
Juan, as may be determined by the said executive council, to its
terminal on the playa of Ponce, on a route from Ponce to be
determined by the said executive council, in accordance with the
conditions in said ordinance contained, and in accordance with the
plans and specifications therefor approved, as in said ordinance
provided, and within the said period of three (3) years from the
date of the acceptance by it of the said ordinance, shall also
complete and have in operation the entire power plant and
transmission lines necessary for operation the said entire line of
railway, in accordance with the conditions therein contained, and
in accordance with the plans and specifications therefor, approved
as therein provided, and shall duly perform within the said period
of three (3) years, all other terms and conditions in said
ordinance required to be performed by the principal within the said
period, and shall pay to the obligee any loss or damage accruing
against the said obligee by reason of the construction of the works
in said ordinance authorized at any time during the period of
construction therein limited, and before the completion of said
work shall have been certified by the commissioner of the interior,
as in § 35 of said ordinance provided, then this obligation
shall be void; otherwise to remain in full force and effect."
"Provided, however, and upon the following express
conditions:"
"First: that no extension of the time or times limited in said
ordinance for the completion of the work therein authorized, or any
part thereof, whether granted with or without the knowledge and
consent of the sureties, shall in any way discharge the sureties
from liability upon this bond; and,"
"Second: that no suit, action, or proceeding shall be brought or
instituted against the sureties after the period of five (5) years
from the date hereof upon or by reason of any default on the part
of the principal in the performance of any of the terms, covenants,
or conditions of this bond. But all extensions of time granted
under the term of the franchise shall be added to the term of five
(5) years, so that the life of the bond shall be kept in full force
for the five (5) years, and so much additional time as shall be
covered by the extension granted."