A mail service contractor cannot claim that he accepted a
contract under misapprehension when between the time of his
proposal and its acceptance he took a temporary contract for
carriage of the identical mails contracted for.
A contract for delivery of all mails at Union Station, Omaha,
was properly construed by the Postmaster General as including mail
delivered by three railroads not in the schedule, it appearing,
however, that the mail so delivered had formerly been delivered by
one of the railroads mentioned in the schedule and were included in
a route specified in the contract.
A mail service contractor whose contract had been cancelled for
failure to perform sued in the Court of Claims for balance due and
for damages for cancellation; that court held he was not entitled
to judgment for the balance due because it appeared that the
contract was properly cancelled and that the government had
sustained damages in excess of the balance due. In this Court,
held that, as the objection that the balance due could
not, in the absence of a counterclaim pleading, be offset against
the damages sustained by the government had not been raised in the
Court of Claims, that court rightly offset it, and the objection
cannot be raised for the first time on appeal in this Court.
Quaere whether the rules of practice in the Court of
Claims would not permit the offset to be made in absence of any
pleading setting up counterclaim or offset.
44 Ct.Cl.19 affirmed.
The facts, which involve the construction of a contract for
screen-wagon mail service in Omaha, Nebraska, are stated in the
opinion.
Page 222 U. S. 499
MR. JUSTICE LURTON delivered the opinion of the Court.
The appellant had a four-year contract, commencing
Page 222 U. S. 500
July 1, 1902, for screen-wagon mail service between the post
office and railway mail stations at Omaha, Nebraska. On May 20,
1903, the Postmaster General cancelled the contract and relet it to
other parties. Thereupon appellant brought this suit in the Court
of Claims, asserting that he had faithfully performed his
agreement, but that he had been required to carry mails to and from
three railway companies not included in his contract. That his
equipment was ample for the service he contracted to render, but
that he had been ordered to provide equipment adequate to the
excessive service demanded, and that the cancellation of his
contract was therefore unauthorized. His suit was to recover,
first, the balance due under the contract as construed by the
Department; second, the reasonable value of the excess service he
had, under protest, been compelled to render; third, the loss of
profit resulting from the wrongful annulment of his contract; and,
finally, the loss sustained in disposing of equipment which had
been bought for the purpose of carrying out his contract.
As is the case with mail contracts, the manner and means of
performance were carefully prescribed, and power was reserved to
the Postmaster General to require other and further facilities if
it should be found necessary for the good of the service. The power
of the Postmaster General to supervise and the duty of the
contractor to conform to his regulations were plainly written down.
That vigilant and prompt service might be enforced, he was given
the right to make deductions, by way of fines, from compensation
earned, for defects in equipment or negligence in the performance
of the service. For repeated failures in performance, or acts of
neglect or disobedience to orders, he was given power to annul the
contract without impairing the right of the government to recover
damages for nonperformance.
The findings of the court below as to the repeated
Page 222 U. S. 501
failures of the appellant in the performance of his contract,
the inadequacy of his equipment, and his disobedience to the
requirements that he should enlarge and improve his facilities make
it clear that the Postmaster General did not act arbitrarily, nor
exceed the power reserved, by the inflicting of fines or the final
cancellation of the agreement on May 20, 1903. When the contract
was cancelled, it was directed that compensation due should be
withheld and the contract relet at the contractor's expense. This
reletting was at a price of some $14,000 in excess of what the cost
would have been if appellant had performed his agreement. The court
below found that, when the contract was annulled, there was due
appellant $2,984.72. For this a judgment was asked, but denied, the
court below finding that the loss to the government as a result of
reletting the contract was greatly in excess of the amount due to
appellant. His petition was therefore dismissed.
If the contract, fairly construed, exacted the amount of service
which the Department claimed, the case of appellant must fail in
view of the facts found as to his insufficient performance and the
loss resulting to the government from the necessity of reletting
the unfinished term of the agreement.
The Postmaster General construed the contract as requiring
appellant to receive from and deliver to all railroads using the
Union Station at Omaha. This construction required him to receive
from and deliver to three railroad companies not specified in the
contract, namely, the Wabash, the Chicago & Northwestern, and
the Chicago, Milwaukee & St. Paul. The case must therefore turn
upon the question as to whether the service contemplated by his
contract included mails to and from the railways mentioned.
Coming, then, to the service required by the contract. The
proposal for the Omaha mail-wagon service and its acceptance were
according to a printed official form. This
Page 222 U. S. 502
proposal and acceptance, making the contract proper, refer to
and make the public advertisement of the Postmaster General for
proposals a part of the agreement, and from it the service
contemplated is discovered. That advertisement included certain
"instructions to bidders," of which they were required to take
notice. Among other things, these "instructions" included the
following provision:
"The foregoing schedules show approximately the service as
performed during the week named in the statement of service for
each route. Bidders, however, must personally inform themselves of
the amount and character of the service that will be required
during the contract term, beginning with July 1, 1902. Bidders and
their sureties are warned that they should familiarize themselves
with the terms of the contract, schedules of service, and
instructions contained herein before they shall assume any
liabilities as such bidders or sureties, to prevent misapprehension
or cause of complaint thereafter."
Under the heading "Union Station," in the schedule referred to,
there appear the names of four railroad companies opposite the
words "Union Station," applicable to each of the named companies,
thus: "Union Station; Illinois Central R. Co. (143,077); Union
Pacific R. Co. (157,001); Chicago, Rock Island & Pacific Ry.
Co. (157,064); Missouri Pacific Ry. Co. (157,075)."
It will be noticed that the named railroads bringing mail into
the Union Station do not include the Wabash, the Chicago &
Northwestern, or the Chicago, Milwaukee & St. Paul.
Notwithstanding this omission, appellant was required to carry to
and from the Union Station the mails delivered there by these three
companies, and to be delivered there from the post office, to be
carried by the same companies. This appellant did under protest,
and upon this his suit is grounded.
But the explanation and answer is simple: originally,
Page 222 U. S. 503
the contract routes of these companies terminated at the Union
Pacific transfer at Council Bluffs, Iowa, where the mail was
transferred to the Union Pacific Railway and carried into Omaha.
After the construction of the Union Station, each of these
companies procured the right to carry their mail over the Union
Pacific Railway into the Union Station. This saved delay in
transfer. The court below found that
"the trains so performing said service were known and treated by
the Post Office Department as mail trains of the Union Pacific
Railroad Company, route No. 157,001, and were operated under the
rules of said Union Pacific Railroad Company, and payment was made
therefor to the said Union Pacific Company. All weights of mail
carried by said three roads were credited to the Union Pacific
Railroad route and weighed thereon. The screen-wagon contractor
under the preceding advertisement and contract, which were similar
to the one in this case, carried mails to and from the the trains
of said three roads as part of his contract, and these facts were
known to persons having knowledge of the service."
This had for many years been the method of handling the mails
carried by the three companies referred to when appellant made his
proposal. True, he says he did not know it, but the advertisement
warned him of the necessity of making himself familiar with the
"terms of the contract, schedule of services and instruction
herein, before they should assume any liabilities as such bidders
or sureties, to prevent misapprehension."
Among the facts found is this:
"Prior to submitting said proposal, the claimant carefully read
the advertisement and instructions to bidders, and familiarized
himself with their terms, and knew that the trains of the Chicago
& Northwestern Railroad, the Chicago, Milwaukee & St. Paul
Railroad, and the Wabash Railroad entered the Union Station at
Omaha, and to further inform himself as to the amount and
character
Page 222 U. S. 504
of the service to be performed, he consulted the postmaster and
superintendent of mails at Omaha, who called his attention to the
Instructions to Bidders; also a Mr. Anderson, who had been in
charge of the work under a former contract, who explained to him
the three depots, including the Union Station, and the mail to be
taken from them, and the number of wagons it would take to perform
the service."
Knowing of the manner in which the mails carried by the three
railroads in question were handled, acquired after the contract was
signed, is not, of course, fatal to his contention that the
contract did not include that mail matter. It does, however, appear
that, after his proposal had been accepted, and before the
beginning of performance, he actually took a temporary contract for
the carriage of the identical mails, so that, when he entered upon
his own regular contract, he was fully aware of the conditions.
This must at least weaken the force of his going forward under
protest. But aside from this information, the advertisement and
instructions warned him to familiarize himself with the situation
by personal investigation and inquiry. This he asserted he had
done, for in his printed proposal he stated that
"this proposal is made after due inquiry into and with full
knowledge of all particulars in reference to the service, and also
after careful examination of the conditions attached to said
advertisement, and with intent to be governed thereby."
But it is urged that appellant is at least entitled to a
judgment for $2,984.72, which the court below found to be the
amount due when the contract was terminated. This contention is
based upon the absence of any pleading setting up as a counterclaim
or set-off the difference between the cost of the service under the
reletting and the entire contract price for the full term under
appellant's contract. But no such objection seems to have been made
in the Court of Claims. That court had all the facts before it.
Page 222 U. S. 505
It found that there was due on May 20, 1903, for services under
the contract prior thereto, $2,984.72. But it found, on the other
hand, that at that date the contract had been lawfully annulled,
and that the necessary reletting had resulted in a loss to the
government of a very much larger sum. Upon this showing, it
properly concluded that the amount due was more than offset by the
loss resulting from reletting at a higher price. How it might be if
this objection had been seasonably made, it is not an error for
which this Court will reverse when not made until upon appeal. In
Wisconsin Central Railroad v. United States, 164 U.
S. 190,
164 U. S. 212,
a like objection was made as to claims coming from the Court of
Claims, and this Court said:
"The petition sets forth, among other things, that the
Postmaster General wrongfully and unlawfully withheld the
$12,532.43 out of moneys due petitioner, which was therefore
entitled to recover the full amount, and to each and every
allegation of the petition the government interposed a general
traverse. It is now said that a counterclaim or set-off should have
been pleaded, but the record does not disclose that this objection
was raised below, while the findings of fact show that the entire
matter was before the court for, and received, adjudication.
Moreover, it which was therefore entitled to recover of pleading in
the Court of Claims are not of so strict a character as to require
omissions of this kind to be held fatal to the rendition of such
judgment as the facts demand."
Judgment affirmed.