Findings of fact made by the Court of Claims are conclusive
here, and the jurisdiction of this Court is limited to
determination of questions of law. The intent of the District of
Columbia Act of June 16, 1880, 21 Stat. 284, was to enable parties
to submit the justice of their claims against the United States for
work done in the District prior to March 14 1876, to adjudication
in a competent court, and, for that purpose, the jurisdiction
conferred was equitable as well as legal; under the equitable
jurisdiction so conferred, the Court of Claims has power to reform
a written contract between the District of Columbia and a claimant
to supply therein what was omitted by mutual mistake of the
parties, and to award money relief to the claimant on the contract
as so reformed.
It was also the intention of the Act of June 16, 1880, to permit
the Court of Claims to adjudicate claims for all work done by order
and direction of the Commissioners and accepted by them for the use
and benefit of the District of Columbia; for this purpose, the
statute is remedial, and a claimant, if the facts support his
claim, can recover for work so done and
Page 197 U. S. 147
accepted notwithstanding it was under verbal directions of the
Commissioners, and not under written contract, as required by prior
acts of Congress.
The main purpose of the Court of Claims is to arrive at and
adjudicate the justice of alleged claims against the United States,
and the court is not bound by special rules of pleading.
The action now appealed was brought under the Act of June 16,
1880, known as the District of Columbia Claims Act. 21 Stat. 284.
The original petition was filed August 4, 1880. At subsequent
stages of the case, amended petitions were filed. On October 1,
1887, the Court of Claims decided the case in favor of the District
of Columbia, giving judgment against the claimant for the sum of
$11,074.11. 22 Ct.Cl. 366. On November 18, 1887, the claimant filed
a motion for a new trial, which was submitted on March 28, 1895,
and allowed on April 1, 1895. The case was then referred, as
provided in the act, and upon report and hearing, judgment was
rendered on November 11, 1895, against the District for the
claimant in the sum of $31,754.57, being rendered for Barnes in the
sum of $22,350.54, and for Ritchie, assignee, in the sum of
$9,404.03, both sums due and payable as of January 1, 1876. On
April 20, 1896, the defendant filed its motion for a new trial,
which was granted on May 18, 1896. On March 31, 1902, the court
rendered a judgment in favor of the claimant and his assignee in
the sum of $23,694.47, due and payable as of March 1, 1876. 37
Ct.Cl. 342. On April 22, 1902, an appeal was taken by the District
from the judgment of March 31, 1902, to this Court. This appeal was
dismissed for want of jurisdiction.
District of Columbia v.
Barnes, 187 U.S. 638.
Under the Act of March 3, 1903, 32 Stat. 1031, 1070, this appeal
from the judgment of March 31, 1902, was taken by the District,
bringing the case in review before this Court.
Page 197 U. S. 149
MR. JUSTICE DAY delivered the opinion of the Court.
We deem it unnecessary, in the view taken of this case, to set
forth the voluminous findings of fact made upon the trial in the
Court of Claims. So much of the findings will be commented on as is
necessary to a determination of the legal questions involved, which
are within a narrow compass. Nor do we find it necessary to
consider the alleged discrepancies between the judgment of the
Court of Claims when the judgment was in favor of the District, 22
Ct.Cl. 366, and the findings
Page 197 U. S. 150
and conclusions when the judgment was rendered which is now
appealed to this Court. 37 Ct.Cl. 342.
This Court does not sit to review findings of fact made in the
Court of Claims. They are regarded as conclusive here, and our
jurisdiction is limited to a determination of such questions of law
as are properly brought to our attention upon the record.
United States v. Smith, 94 U. S. 214,
94 U. S.
218.
The original action was brought in part on two contracts, which
were in writing, duly executed by the claimant and in behalf of the
District of Columbia, and known as Nos. 264 and 413, and were for
certain street improvements in the City of Washington. These
contracts were entered into on April 29 and July 23, 1872,
respectively, under authority of the Act of February 21, 1871. 16
Stat. 419, 427. Certain verbal agreements are also set up as having
been entered into between the claimant and the commissioners of the
District.
The Court of Claims, under the proofs, heard the parties upon
the question as to the right to reform the two written contracts.
It refused to reform contract No. 413, and decreed in favor of the
District in the sum $13,039.79 for over payments made upon that
contract. The court did reform contract No. 264, finding that, by
mistake in the drafting of the contract, "the rate of 40 cents for
grading old gravel streets to a depth of two feet" was omitted
therefrom by mutual mistake of the parties, and that the written
contract was executed without observing the omission. Upon the
contract as reformed, the claimant was permitted to recover for
work done. Much of the discussion in the oral argument and the
brief of the learned counsel for the government is directed to the
authority of the Court of Claims to reform a written contract in
the exercise of the jurisdiction of a court of equity for that
purpose, and much discussion was had as to the various acts
conferring jurisdiction upon that court. But we think a
construction of the act under cover of which this suit was
prosecuted is all that is necessary to determine the question. The
Act of June 16, 1880, as appears by its title, was intended
Page 197 U. S. 151
to confer on the Court of Claims jurisdiction to hear and
determine all outstanding claims against the District of Columbia.
For that purpose, it was recited in the first section of the act
that the jurisdiction of the court should extend to, and it should
have original legal and equitable jurisdiction of claims arising
out of, the contracts made by the board of public works and
extensions made thereof by the Commissioners of the District of
Columbia, and also of the claims arising out of the contracts made
by the Commissioners since the Act of June 20, 1874, and broadly
for all claims for work done by order or direction of the
Commissioners, and accepted by them for the use, purposes, or
benefit of the District of Columbia, and prior to the fourteenth
day of March, 1876.
The language used is of the most comprehensive character, and
confers, for the purposes stated, original legal and equitable
jurisdiction.
It is true that the purpose of the various acts conferring
jurisdiction upon the Court of Claims has been held to be to permit
the adjudication of money demands against the United States, and it
may be that, under this act, as under others, there was no
intention to confer equity jurisdiction beyond that which is
required to enable a court to determine whether money relief should
be granted. The intent of the act was to enable parties to submit
the justice of their claims against the United States to
adjudication in a competent court. For that purpose, the act
conferred, in terms, equitable as well as legal jurisdiction.
The province of the Court of Claims is to pass upon the justice
of the claim, and adjudge accordingly. And it is obviously intended
that, when necessary to adjudicate claims against the District, the
court shall be unhampered in the exercise of jurisdiction, and as
in many courts of this country having a civil code, there has been
conferred upon the same tribunal the power to grant the necessary
legal and equitable relief. One who has the right to money relief
upon a contract mistakenly omitted to be reduced to writing, in
accordance
Page 197 U. S. 152
with the true agreement of the parties, has a claim of equitable
cognizance, for the contract must be reformed to meet the intention
of the parties, and, when corrected, may to adjudged a valid
claim.
For the purpose of adjudicating such claims, this statute gives
to the court equitable jurisdiction in order that it may determine
what the District ought to pay to the claimant. Although unable to
grant a decree for specific performance or exercise the peculiar
powers of a court of equity, the Court of Claims may determine the
money relief to which the claimant is entitled, whether arising out
of an equitable or legal demand. This principle was recognized in
United States v. Jones, 131 U. S. 1,
131 U. S. 18. The
Court of Claims in other cases has exercised the equitable
jurisdiction conferred in the Act of June 16, 1880,
Cullinane
v. District of Columbia, 18 Ct.Cl. 577, 594, and like
jurisdiction to reform contracts under the Act of March 3, 1887, 24
Stat. 505,
South Boston Iron Co. v. United States, 34
Ct.Cl. 174.
We think that the court had jurisdiction to reform the contract
upon the facts found.
It is objected that the Court of Claims awarded relief for
certain "stiff clay" excavated under claimant's contract. The
findings show that this work was not specifically covered by the
original agreement, and that the work was accepted by the
Commissioners, and the District received the benefit thereof, and
the Court finds that the excavation of the stiff clay was done
under a verbal agreement with the Commissioners after the
performance of the original contract, and that the claimant was
entitled to the rate established therefor, as paid to other
contractors for like work.
The Act of June 16, 1880, permits a recovery for work done by
order and direction of the Commissioners and accepted by them for
the benefit of the District. While it has been held that this would
not authorize a recovery for work done under the original contract
at higher prices than had been agreed upon, yet where there was a
revival of the contract for distinct
Page 197 U. S. 153
work, there might be a recovery at higher rates, which entered
into the terms of renewal as understood by the parties
notwithstanding the preexisting contract.
Campbell v. District
of Columbia, 18 Ct.Cl.193.
The act of 1874 gave limited power to the Commissioners, and in
the Act of February 21, 1871, 16 Stat. 419, providing for contracts
of the board of public works, it was distinctly provided that all
contracts should be in writing and signed by the parties making the
same. And it was held that this statute requires contracts to be
actually signed, and that mere entries on the journals of the board
would not satisfy the statute.
Barnard v. District of
Columbia, 127 U. S. 409,
127 U. S. 411.
But, under the statute, June 16, 1880, now under consideration,
the intention is manifest to permit the Court of Claims to
adjudicate claims for all work done by the order and direction of
the Commissioners, and accepted by them for the use, purpose, and
benefit of the District. For this purpose, this is a remedial
statute, and it is intended to permit parties to have an
adjudication upon their demands where the District had been
benefited by work actually done under the order and direction of
the Commissioners and duly accepted. And the findings of fact show
that the claimant was only permitted to recover for work so
performed and accepted. As we have said, this right of recovery
might not revive claims for work completed under former contracts,
but here the finding is that the new agreement applied to a
distinct subject matter, and not to work covered by and performed
under the original agreement. We find no error in the judgment of
the Court of Claims in this regard. And so as to various sums
awarded under findings of fact, establishing that more work was
made necessary by reason of the change of grade on North Carolina
Avenue by the Commissioners in 1874, the change of grade making it
necessary to further grade Third Street and to do work for that
purpose. The findings show that this was done by the direction of
the Commissioners, and upon terms mutually agreed upon. Under
finding XIV., where the work is found not to
Page 197 U. S. 154
have been done under the original contract, it is found that it
was admitted by the defendant to be correct, and is work of which
the District has received the full benefit. So, as to other
findings to which exceptions are made, there is no dispute that the
work was actually done to the satisfaction of the Commissioners
upon terms agreed upon and the work duly accepted.
As we construe the statute, we think it affords ample authority
to grant relief upon the facts found, which findings are conclusive
upon us.
It is further urged by counsel for the government that the
pleadings are not sufficient to authorize the judgment, but we
think that, under the original petition and various amendments
thereto, the court was authorized to grant the relief adjudged.
The Court of Claims is not bound by special rules of pleading.
The main purpose is to arrive at and adjudicate the justice of
alleged claims against the United States.
United
States v. Burns, 12 Wall. 246,
79 U. S. 254;
United States v. Behan, 110 U. S. 338,
110 U. S. 347.
On the whole record, we find no error of law to the prejudice of
the District.
Judgment affirmed.