A surety on a contractor's bond, conditioned for the performance
of a contract to construct a dry dock, is released by subsequent
changes in the work made by the principals without his consent.
The obligation of a surety does not extend beyond the terms of
his undertaking, and when this undertaking is to secure the
performance of an existing contract, if any change is made in the
requirements of such contract in matters of substance without his
consent, his liability is extinguished.
If the government's pleader had evidence of facts showing such
knowledge and consent, he should have asked leave to amend the
declaration by adding the averment necessary to state it.
The case is stated in the opinion of the Court.
MR. JUSTICE SHIRAS delivered the opinion of the Court.
In September, 1898, the United States of America brought an
action in the Circuit Court of the United States for the Eastern
District on New York against John Gillies, Henry Hamilton, and Hugh
McRoberts, Catharine Freel, Edward J. Freel, and Frank J. Freel, as
executors of Edward Freel, deceased.
The complaint alleged that theretofore, and on the 17th of
November, 1892, the defendant John Gillies entered into a contract
in writing with the plaintiff to construct a timber dry dock, to be
located at the United States Navy Yard, Brooklyn, New York,
according to certain plans and specifications attached to and made
part of said contract; that, on said 17th November, 1892, the said
John Gillies, as principal, and Henry
Page 186 U. S. 310
Hamilton and Hugh McRoberts, and Edward Freel, as sureties,
executed their joint and several bond to the United States in the
penal sum of $120,600, conditioned for the faithful performance by
the said Gillies of his contract to construct said dry dock; that
Gillies entered upon the performance of said contract; that
subsequently, on June 16, 1893, Gillies and the United States
agreed in writing to change and modify the plans and specifications
so as to increase the length of said dry dock from six hundred to
six hundred and seventy feet; that, on August 17, 1893, Gillies and
the United States further agreed in writing to change and modify
the contract in certain particulars; that Gillies proceeded with
the work under said original and supplemental contracts so slowly,
negligently, and unsatisfactorily that the Secretary of the Navy,
under the option and right reserved to him by the said contract,
declared the said contract forfeited on the part of said Gillies;
that thereupon, by a board duly appointed, the market value of the
work done and of the materials on hand was appraised at the sum of
$170,175.40; that thereafter, under the provisions of said
contract, the Secretary of the Navy proceeded to complete said dry
dock and appurtenances in accordance with the said contracts,
plans, and specifications at a cost to the United States of the sum
of $370,000; that the sum of $72,414.16 represented the damages
sustained by the plaintiff by reason of said Gillies' breach of
contract; that Edward Freel died on the 24th day of December, 1896,
leaving a last will appointing Catharine Freel, Edward J. Freel,
and Frank J. Freel executors thereof; that the said defendant John
Gillies neglected and refused to perform the terms and conditions
of said contract on his part, and that the plaintiff has performed,
fully and completely, all the terms and conditions of said contract
on its part. Wherefore the plaintiff demanded judgment against the
said defendants in the said sum of $72,414.16, with interest from
April 1, 1897.
On November 26, 1898, Edward J. Freel, as executor of Edward
Freel, deceased, appeared and demurred to the complaint upon the
ground that it appeared upon the face thereof that said complaint
did not state facts sufficient to constitute a
Page 186 U. S. 311
cause of action. On May 24, 1899, after hearing the counsel of
the respective parties, the circuit court sustained the demurrer
and dismissed the complaint as to said Edward J. Freel as executor.
92 F. 299. The case was taken to the Circuit Court of Appeals for
the Second Circuit, and on January 5, 1900, that court affirmed the
judgment of the circuit court. 99 F. 237. On December 22, 1900, a
writ of error was allowed, and the cause was brought to this
Court.
The question in this case is whether a surety on a contractor's
bond conditioned for performance of a contract to construct a dry
dock was released by subsequent changes in the work made by the
principals without his consent.
As the question is presented to us on a general demurrer to the
complaint, it is necessary to set forth, with some particularity,
portions of the original and of the supplemental contracts, which
form parts of the complaint.
The original contract, dated November 17, 1892, contained, after
alleging that proposals had been made and accepted for the
construction by contract of a timber dry dock, to be located at the
United States Navy Yard, Brooklyn, New York, the following
provisions:
"First. The contractor will, within twenty days after he shall
have been tendered the possession and occupancy of the site by the
party of the second part, which possession and occupancy of the
said site during the period of construction and until the
completion and delivery of the work hereinafter mentioned, shall be
secured to the contractor by the party of the second part,
commence, and within twenty-seven calendar months from such date,
construct and complete, ready to receive vessels, a timber dry
dock, to be located at such place on the water line of the navy
yard, Brooklyn, N.Y. as shall be designated by the party of the
second part."
"
* * * *"
"Seventh. The construction of said dry dock and its accessories
and appurtenances herein contracted for shall conform in all
respects to and with the plans and specifications aforesaid, which
plans and specifications are hereto annexed and shall be deemed and
taken as forming a part of this contract
Page 186 U. S. 312
with the like operation and effect as if the same were
incorporated herein. No omission in the plans or specifications of
any detail, object, or provision necessary to carry this contract
into full and complete effect, in accordance with the true intent
and meaning hereof, shall operate to the disadvantage of the United
States, but the same shall be satisfactorily supplied, performed,
and observed by the contractor, and all claims for extra
compensation by reason of or for or on account of such extra
performance are hereby, and in consideration of the premises,
expressly waived, and it is hereby further provided, and this
contract is upon the express condition that the said plans and
specifications shall not be changed in any respect except upon the
written order of the Bureau of Yards and Docks, and that, if at any
time it shall be found advantageous or necessary to make any
change, alteration, or modification in the aforesaid plans and
specifications, such change, alteration, or modification must be
agreed upon in writing by the parties to the contract, the
agreement to set forth fully the reasons for such change, and the
nature thereof, and the increased or diminished compensation, based
upon the estimated actual cost thereof, which the contractor shall
receive, if any;
Provided, That whenever the said changes
or alterations would increase or decrease the cost by a sum
exceeding five hundred dollars ($500), the actual cost thereof
shall be ascertained, estimated, and determined by a board of naval
officers to be appointed by the Secretary of the Navy for the
purpose, and the contractor shall be bound by the determination of
said board, or a majority thereof, as to the amount of increased or
diminished compensation he shall be entitled to receive in
consequence of such change or changes:
Provided further,
That if any enlargement or increase of dimensions shall be ordered
by the Secretary of the Navy during the construction of said dry
dock, that the actual cost thereof shall be ascertained, estimated,
and determined by a board of naval officers, to be appointed by the
Secretary of the Navy, who shall revise said estimate and determine
the sum or sums to be paid the contractor for the additional work
that may be required under this contract:
And provided
also, That no further payment shall be made unless such
supplemental or modified
Page 186 U. S. 313
agreement shall have been signed before the obligation arising
from such change or modification was incurred and until after its
approval by the party of the second part:
And further
provided, That no change herein provided for shall in any
manner affect the validity of this contract."
The supplemental contract of June 16, 1893, contained, among
other things, the following:
"This agreement, entered into this 16th day of June, 1893,
between John Gillies, contractor, for the construction of a dry
dock at the U.S. Navy Yard, Brooklyn, New York, party of the first
part, and Norman H. Farquhar, Chief of the Bureau of Yards and
Docks of the Navy Department, for and in behalf of the United
States, party of the second part,"
"Witnesseth: That whereas the Navy Department has decided to
lengthen the said dry dock from six hundred (600) feet, as called
for in the specifications forming a part of the contract for the
construction of a dry dock at the above-mentioned location, entered
into by the above-mentioned parties of the first and second parts
on the 17th of November, 1892, to six hundred and seventy (670)
feet from the outer gate sill to the coping at the head of the
dock."
"And whereas a board of naval officers, consisting of Captain J.
N. Miller, U.S.N., Civil Engineer P. C. Asserson, U.S.N., and Civil
Engineer, F. C. Prindle, U.S.N., was ordered by, and did convene,
by order of the Secretary of the Navy, in compliance with the
requirements of paragraph 7, page 2, of the contract, to fix this
additional compensation to be allowed to said party of the first
part for the additional labor and material required for said
extension."
"And whereas said board of naval officers, after careful and
mature deliberation, did fix the additional compensation to be paid
said party of the first part for the said extension of the said dry
dock at forty-five thousand five hundred and fifty-six ($45,556)
dollars, and did allow an extension of three (3) months' time on
account of said extension of said dry dock:"
"Now therefore the party of the first part does hereby agree to
extend the said dry dock to a length of six hundred and seventy
(670) feet, measuring from the outer gate sill to
Page 186 U. S. 314
the coping at the head of the dock in the same manner and under
the same conditions as though said extension had been included in
the original contract."
"And it is further agreed by the party of the first part to
accept from the United States, as a just compensation for said work
of extension, the sum of forty-five thousand five hundred and
fifty-six ($45,556) dollars, in full therefor, payment to be made
under the same conditions and requirements as exacted by the
original contract."
"And it is further agreed by the party of the second part that,
in full and just compensation to the party of the first part, the
sum of forty-five thousand five hundred and fifty-six ($45,556)
dollars shall be paid for the additional labor and material
necessary to extend the said dry dock, as heretofore agreed to,
payments to be made under the same conditions and requirements as
exacted in the original contract."
"And it is therefore agreed that the time fixed in the original
contract for the completion of the said dry dock shall be extended
three (3) months on account of the extra labor necessary to carry
out the extension of the said dry dock as called for by this
agreement."
The supplemental contract of August 17, 1893, contained the
following:
"This agreement, made and concluded this seventeenth day of
August, A.D. 1893, by and between John Gillies, of the City of
Brooklyn, in the New York, party of the first part, and the United
States, represented by N. H. Farquhar, U.S. Navy, Chief of the
Bureau of Yards and Docks, Navy Department, acting under the
direction of the Secretary of the Navy, party of the second
part,"
"Witnesseth: That whereas it has been deemed desirable to change
the location of the dry dock now being constructed at the U.S. Navy
Yard at Brooklyn, New York, under contract with the said John
Gillies, party of the first part, dated November 17th, A.D.
1892:"
"Now therefore this agreement witnesseth that, in consideration
of the premises and for and in consideration of the payment to be
made as hereinafter provided for, the party of the
Page 186 U. S. 315
first part, for himself, his heirs and assigns, and his legal
and personal representatives, agrees to and with the United States
that he will, in the construction of the said dry dock, change its
location to one sixty-four (64) feet further inland than that laid
down and staked out when the said contract was entered into, and
that he will perform all the additional excavation necessary at the
entrance of the dry dock in consequence of the said change of
location; also all the additional work necessary to lengthen the
suction pipes provided to be laid from the present pump house,
including the piping, round piles, sheet piles, timber, iron work,
excavation and back filling, etc., and all other work incident to
said change of location, supplying all the labor and materials
therefor."
"And this agreement further witnesseth that the United States,
party of the second part, in consideration of the stipulations,
agrees that, for the faithful performance of this agreement by the
party of the first part, there shall be paid to the said party of
the first part the sum of five thousand and sixty-three dollars and
eighteen cents ($5,063.18), United States currency, as full
compensation. Said payment to be made in accordance with all the
terms and conditions of payments as provided in the said contract
and specifications."
"And the United States further agrees that the time limited by
the said contract for the completion of the dry dock shall be
extended for a period of eight (8) weeks on account of the said
change in the position of the dry dock."
"It is also agreed that the provisions and conditions contained
in the said contract and the specifications thereto attached, in
regard to the character and quality of the materials and
workmanship, shall apply to the work as herein modified."
"This agreement is made under the provisions of and in
accordance with article 'seventh' of the said contract."
Before addressing ourselves directly to the question before us,
it may be well to briefly examine some of the decisions of this
Court on the subject of the alteration of contracts without the
assent of the surety.
Miller v.
Stewart, 9 Wheat. 680, was an action on a bond
conditioned for the faithful performance of the duties of the
office
Page 186 U. S. 316
of deputy collector of direct taxes for eight certain townships
in the fifth collection district of New Jersey, and it appeared
that the instrument of the appointment, referred to in the bond,
was afterwards altered, so as to extend to another township,
without the consent of the sureties. It was held that the surety
was discharged from his responsibility for moneys subsequently
collected by his principal, the court saying, per Mr. Justice
Story:
"That the liability of a surety is not to be extended by
implication, beyond the terms of his contract; that his undertaking
is to receive a strict interpretation, and not to extend beyond the
fair scope of its terms, and that the whole series of authorities
proceeded upon this ground.
Miller v. Stewart was followed
and approved in
Leggett v. Humphrey, 21
How. 76;
Smith v. United States, 2
Wall. 219."
In
United States v.
Boecker, 21 Wall. 652, in the case of a distiller's
bond, which recited that the person is about to be the distiller at
one place, to-wit at the corner of Hudson Street and East Avenue,
situated in the Town of Canton, it was held that his sureties were
not liable for taxes in respect of business carried on by him at
another place, to-wit at the corner of Hudson and Third Streets in
the same town, even though he had no distillery whatever at the
first-named place.
However, the proposition that the obligation of a surety does
not extend beyond the terms of his undertaking, and that, when this
undertaking is to assure the performance of an existing contract,
if any change is made in the requirements of such contract in
matters of substance without his consent, his liability is
extinguished, is so elementary that we need not cite the numerous
cases in England and in the state and federal courts establishing
it. Many of these cases will be found cited in the opinion of
Thomas, J., in this case. 92 F. 299.
At the trial in the circuit court, it was contended on behalf of
the surety that this proposition was applicable, and exonerated him
by reason of the changes made in the original contract by the
supplemental contracts of June 16 and August 17, 1893. It was
claimed on behalf of the United States that the changes made in the
original contract by the supplemental agreements were within
contemplation of that contract, and
Page 186 U. S. 317
must be deemed to have been assented to in advance by the
surety.
It was held by the learned trial judge that the government's
position was well taken in respect to the supplemental agreement of
June 16, 1893, which he regarded as fairly within the meaning of
the provisions in the seventh section of the contract, which refers
to and provides for changes, alterations, or modifications in the
plans and specifications, and therefore within the undertaking of
the surety. But his view was otherwise in respect to the
alterations made by the supplemental contract of August 17, which,
as respects the change of the site of the dock and the extension of
the time of completion of the contract, he held to be changes not
within the scope of the seventh section, but to be such as to
exonerate the surety from liability for the subsequent dereliction
of his principal.
We agree with the circuit court of appeals in thinking that, if
the learned judge's opinion was sound in respect to the agreement
of August 17, 1893, it is not necessary to determine whether the
seventh section warranted so wide a departure from the plans and
specifications of the original contract as was made by the
agreement of June 16, 1893.
Coming, then, to the question of the effect on the
responsibility of the surety of the supplemental agreement of
August 17, we agree with the circuit court and the circuit court of
appeals in holding that the alternations thereby caused were beyond
the terms of the undertaking of the surety, and extinguished his
liability. The seventh section had in view such changes as might be
found advantageous or necessary in the plans and specifications.
But the changes called for by the new agreement had no reference to
the original plans and specifications, but changed the location of
the dry dock, requiring the contractor to make additional
excavations and connections with the water at an increased expense,
and gave an increased time of performance.
A few cases illustrating the principles involved may be properly
cited, and reference is made to the opinion of the circuit court,
in which many more are cited.
In
Mundy v. Stevens, 61 F. 77, it was held by the
Page 186 U. S. 318
Circuit Court of Appeals of the Third Circuit that sureties for
the payment by a contractor to a subcontractor of all moneys
received for work under a government contract as provided in the
contract were released by an alteration of such agreement whereby
the right secured to the original contractors to deduct from the
monthly payments three cents per yard for material dredged,
subsequently was modified so that payments of two and a half cents
per cubic yard should be made monthly, and it was also held that,
as the plaintiff had set forth the supplementary agreement in his
statement of claim, he thereby made it part of his case, and the
burden of proof that the change was consented to by the sureties
was upon the plaintiff.
Rowan v. Sharpe's Rifle Mfg. Co., 33 Conn. 1, is an
important case. There, it was held by the Supreme Court of
Connecticut that, where a contract provided that the guns
contracted for should be made "with all possible dispatch," and a
supplemental contract, made before performance, provided that three
hundred guns per week should be delivered for a certain period, and
six hundred per week afterwards, the surety was discharged, the
court saying:
"But it appears to us very clear that a contract to manufacture
and deliver a large quantity of any description of goods in a
reasonable time, and a contract to manufacture and deliver the same
quantity either at a specified time for the whole or a specific
quantity from time to time, monthly or weekly, as the case may be,
are materially variant."
The Supreme Court of Indiana, in
Zimmerman v. Judah, 13
Ind. 286, held that a supplementary agreement to put an additional
story on a house released the surety for the contractor in the
original contract.
Whitcher v. Hall, 5 B. & C. 269, is cited in the
opinion of the circuit court. There it was held by the Court of
King's Bench that a surety engaged for another to the plaintiff for
the milking of thirty cows at a given price each per annum was
released by a subsequent agreement without his consent, whereby the
hirer was to have twenty-eight cows for one-half the year and
thirty-two for the remainder.
Page 186 U. S. 319
A further contention is made in the government's brief that,
even if such substantial changes were made in the contract as would
release the surety if made without his assent, the fact of such
changes should have been set up by the defendant as an affirmative
defense by answer or plea, and not by demurrer.
The declaration set out, by attaching them as exhibits, the
original and the two supplemental contracts, and it alleged that
the changes effected by the latter were made "pursuant to, and in
conformity with, paragraph "seventh" of the first contract." If,
upon the face of the agreement of August 17, 1893, it appeared that
substantial changes were made in the location of the proposed
structure, requiring additional excavations and connections at an
increased expense and extending the time limited by the contract
for the completion of the dry dock for a period of eight weeks on
account of the change in the position of the dry dock, and if, as
is conceded by this objection, such substantial changes in the
location, cost, and time necessary for the completion of the work
operated to release the surety if made without his knowledge and
consent, then the declaration put the plaintiff out of court, so
far as the defendant surety was concerned, unless it was averred
that the latter had knowledge of the changes and consented thereto.
If the government's pleader had evidence of facts showing such
knowledge and consent, and was surprised by the action of the trial
judge in sustaining the demurrer, it was open to him to ask leave
to amend the declaration by adding the necessary averment. This was
not done, and we think it is too late to urge this objection in
this Court.
The judgment of the circuit court of appeals is
Affirmed.
MR. JUSTICE GRAY took no part in the disposition of this
case.