On the 16th of August, 1889, a statute was in force in the
Territory of Utah providing for the creation of mechanic's liens
for work done or materials furnished under contracts in making
improvements upon land, but, in order to enforce his lien, a
contractor was required within 60 days after completion of the
contract to file for record a claim stating his demand and
describing the property to be subjected to it, and no such lien was
to be binding longer than 90 days after so filing unless proper
proceedings were commenced within that time to enforce it. On that
day, G contracted with an irrigation company to construct a canal
for it in Utah. He began work upon it at once, which was continued
until completion, December 10, 1890. He claimed (and it was so
established) that after crediting the company with sundry payments,
there was still due him over $80,000, for which amount he filed his
statutory claim on the 23d day of the same December. On the 1st day
of October, 1889, the company mortgaged its property then acquired
or to be subsequently acquired to a trustee to secure an issue of
bonds to the amount of $2,000,000, the proceeds of which were used
in the construction of the company's works, including the canal. On
the 12th of March, 1890, the Legislature
Page 164 U. S. 2
of Utah repealed said statute and substituted other statutory
provisions in its place, and enacted that the repeal should not
affect existing rights or remedies and that no lien claimed under
the new act should hold the property longer than a year after
filing the statement unless an action should be commenced within
that time to enforce it. On the 1st day of May, 1890, C contracted
with the company to do work on its canal, and did the work so
contracted for. The balance due G not having been paid, he brought
an action to recover it, making the company, the mortgage trustees,
and C defendants, which action was commenced more than 90 days
after the filing of his claim. To this suit C replied, setting up
his mechanic's lien. The court below made many findings of fact,
among which were, (29th) that the right of way upon which the canal
was constructed was obtained by the company under Rev.Stat. §
2339 and (33d) that the work done by G and C, respectively, had
been done with the consent of the company after its entry into
possession of the land. Exception was taken to the 29th finding as
not supported by the proof. The court below gave judgment in favor
of both G and C, establishing their respective liens upon an
equality prior and superior to the lien of the mortgage trustees.
Held:
(1) That this Court will not go behind the findings of fact in
the trial court to inquire whether they are supported by the
evidence.
(2) That G's action was commenced within the time required by
the statutes existing when it was brought.
(3) That the judgment of the court below thus establishing the
respective liens of G and of C was correct.
A clause in a mortgage which subjects subsequently acquired
property to its lien is valid, and extends to equitable as well as
to legal titles to such property.
Under Rev.Stat. §§ 2339, 2340, no right or title to
land or to a right of way over or through it or to the use of water
from a well thereafter to be dug vests, as against the government,
in the party entering upon possession from the mere fact of such
possession, unaccompanied by the performance of labor thereon, and
as the title in this case did not pass until the ditch was
completed, the mortgage was not a valid encumbrance until after the
liens of G and of C had attached, and will not be held to relate
back for the purpose of effecting an injustice.
The Act of March 12, 1890, is to be construed as a continuation
of the act in force when the Garland contract was made, extending
the time in which an action to foreclose its lien should be
commenced, and, as this was done before the time came for taking
proceedings to effect a sale under the lien, it was not an
alteration of the right or the remedy as those terms are used in
the statute.
The appellants herein have appealed from a judgment of the
Supreme Court of the Territory of Utah affirming a judgment of the
District Court of the first Judicial District of the territory
Page 164 U. S. 3
in favor of the respondents, William Garland and Corey Brothers
& Company.
The action was brought be the plaintiff, William Garland,
against the Bear Lake Company, the Jarvis-Conklin Mortgage Trust
Company, as trustees, Corey Brothers & Company and others for
the purpose of enforcing an alleged mechanic's lien in favor of the
plaintiff and against the Bear Lake Company for work done by the
plaintiff for that company in the construction of its canal from
its initial point (the Bear River Canyon) for a distance of twelve
miles on both sides of the river. The complaint alleged that on the
16th of August, 1889, the plaintiff and the Bear Lake Company
entered into a contract for the construction by plaintiff of the
portion of the work above mentioned, and under that contract the
plaintiff commenced work on the 31st of August, 1889, and continued
it to and including December 10, 1890. Various payments on account
of the work were made the plaintiff, and after crediting the same,
the plaintiff alleged there was still due him from the Bear Lake
Company at the time of filing his claim for a lien (December 23,
1890), the sum of $80,250.50, and interest thereon, as set forth in
the complaint. The Jarvis-Conklin Mortgage Trust Company and Corey
Brothers & Company and the other defendants were made parties
to the action as subsequent mortgagees or other encumbrancers. The
answer of the mortgage trust company set up the fact that it was
the mortgagee in a mortgage executed by the Bear Lake Company to
it, as trustee, on the 1st day of October, 1889, to secure the
payment of $2,000,000 of the bonds of the mortgagor company, and
that such mortgage covered all the water rights, franchises, lines
of canal, and other property upon the whole or any part of which
the plaintiff claimed a lien, and that the mortgage also, by its
terms, covered all after-acquired property of every kind. The
mortgage was duly recorded in Box Elder County, Utah, November 14,
1889; in Bear Lake County, Idaho, December 24, 1889; in Weber
County, Utah, February 6, 1890. The bonds secured by the mortgage
were all delivered between October 1, 1889, and February 1, 1891,
and in large part paid for, and the balance was to be paid for
Page 164 U. S. 4
by drafts drawn upon the mortgage company by the treasurer of
the Bear Lake Company as fast as the money was needed to pay for
the construction of the works. At the time the plaintiff, Garland,
entered into the contract already mentioned, and when he commenced
work thereunder, the statutes of Utah provided a mechanic's lien,
under the provisions of which a contractor, within 60 days after
the completion of his contract, was to file for record with the
county recorder a claim stating his demand, and giving a
description of the property to be subjected to the lien. By §
3814, s. 1065, no lien provided for by the chapter upon liens was
to bind any of the property longer than ninety days after the claim
was filed, "unless proceedings be commenced in a proper court
within that time to enforce the same." 2 Compiled Laws of Utah
1888, p. 406, from § 3806 to and including § 3820. The
answer further set up the fact that while the above act was in
force, and on the 12th of March, 1890, the Legislature of Utah
passed an act in relation to mechanics' liens, and § 32
thereof repealed the former and above-mentioned lien act, but added
the following proviso:
"Provided, that the repeal of said acts or parts of acts or any
of them shall not affect any right or remedy, nor abate any suit or
action or proceeding existing, instituted or pending under the laws
hereby repealed."
The answer then set forth that the plaintiff did not commence
his action to enforce his lien within the ninety days given by the
act in force when the work was commenced under the contract, and
therefore the lien no longer existed at the time the action was
commenced to enforce it.
The answer of Corey Brothers & Company was in the nature of
a cross-complaint, and set up the fact that they entered into a
contract with the Bear Lake Company on the 1st of May, 1890, to
construct certain portions of the canal of the company, and that
between such date and the 5th of December, 1890, they did the work
provided for in the contract, and on the 7th of January, 1891, they
filed their claim for a lien for the balance of the money due them
under the contract (which was about eleven thousand dollars),
and
Page 164 U. S. 5
they asked for a decree enforcing their lien as a prior
encumbrance to that of the mortgage upon the property of the Bear
Lake Company.
The Bear Lake Company set up the same facts as a defense against
the plaintiff's cause of action that were alleged by the Mortgage
Trust Company, and it answered the claim of Corey Brothers &
Company by alleging that the mortgage to the mortgage trust company
had been executed and duly recorded, and was in existence long
before and at the time of the execution of the agreement which
Corey Brothers & Company made with the Bear Lake Company, and
that therefore the lien of Corey Brothers & Company was
subsequent and subject to the lien of the mortgage upon the
after-acquired property of the Bear Lake Company.
No question arises with reference to the other defendants.
The case came on for trial upon the issues thus found, and the
court, after hearing the evidence, gave judgment in favor of
plaintiff and of Corey Brothers & Company, establishing their
liens, respectively, upon an equality, and making them prior and
superior to the lien of the mortgage trust company by reason of its
mortgage, and decreeing the sale of the property to satisfy such
liens. 9 Utah 350.
Page 164 U. S. 10
MR. JUSTICE PECKHAM, after stating the facts in the foregoing
language, delivered the opinion of the Court.
The contest in this case lies between the plaintiff and the firm
of Corey Brothers & Company, on the one hand, and the mortgage
trust company, on the other. The former demand priority of lien for
their respective claims over that of the mortgage held by the
mortgage trust company upon the property of the Bear Lake
Company.
It will be convenient to separately examine these claims.
First. As to the plaintiff's alleged lien. At the time when the
plaintiff entered into his contract and commenced work under it,
the lien law of 1888 was in force, one of the sections of which,
§ 3810, s. 1061, provided that the lien mentioned in the act
was to be preferred to any other which might attach subsequently to
the time when the building, improvement, or structure was
commenced, work done, or materials were commenced to be furnished.
As the work of the plaintiff under his contract was commenced on
the 31st of August, 1889, and continued up to December, 1890, while
the mortgage to the mortgage trust company was not executed until
October, 1889, it is conceded by the counsel for the latter company
that if the plaintiff had complied in all respects with the
provisions
Page 164 U. S. 11
of the act of 1888, and had commenced his action to enforce his
lien within ninety days from the time when he filed his claim for a
lien (December 23, 1890), his action could have been maintained and
his lien would have had priority. Inasmuch, however, as he failed
to commence his action within the time mentioned, it is insisted
that the lien had then expired by the express provisions of the act
of 1888. The plaintiff makes answer to this objection by citing
§ 21 of the Act of the 12th of March, 1890, which reads as
follows:
"SEC. 21. No lien claimed by virtue of this act shall hold the
property longer than one year after filing the statement firstly
described in section 10 unless an action be commenced within that
time to enforce the same."
This action was commenced within one year after filing the
statement of the plaintiff's claim, and he therefore insists that
it was commenced in time, and that his lien should have priority.
In that contention, he is met by the claim of the mortgage company
that the section referred to does not affect the plaintiff's case,
as the contract between him and the Bear Lake Company was entered
into, and a large amount of the work was done under it, prior to
March, 1890, and while the act of 1888 was in force, and that, by
the express terms of the proviso in § 32 of the act of 1890,
the repeal of the act of 1888 did not affect any right or remedy
nor abate any suit or proceeding existing, instituted, or pending,
under the laws thereby repealed.
The terms of the act of 1890 are thus cited as a limitation of
the plaintiff to the provisions of the act of 1888. If plaintiff be
thus confined, he cannot maintain this action, as he did not
commence it until sometime after the expiration of the ninety days
from the date of filing his claim.
Upon comparing the two acts of 1888 and 1890 together, it is
seen that they both legislate upon the same subject, and in many
cases the provisions of the two statutes are similar, and almost
identical. Although there is a formal repeal of the old by the new
statute, still there never has been a moment of time since the
passage of the act of 1888 when these similar
Page 164 U. S. 12
provisions have not been in force. Notwithstanding, therefore,
this formal repeal, it is, as we think, entirely correct to say
that the new act should be construed as a continuation of the old
with the modification contained in the new act. This is the same
principle that is recognized and asserted in
Steamship Co. v.
Joliffe, 2 Wall. 459. In that case, there was a
repeal in terms of the former statute, and yet it was held that it
was not the intention of the legislature to thereby impair the
right to fees which had arisen under the act which was repealed. As
the provisions of the new act took effect simultaneously with the
repeal of the old one, the Court held that the new one might more
properly be said to be substituted in the place of the old one, and
to continue in force, with modifications, the provisions of the old
act, instead of abrogating or annulling them and reenacting the
same as a new and original act.
It is true that the law in the
Joliffe case did not
contain any saving of or provision for the rights and remedies of
the pilot, but the foundation of the reasoning by which the court
concluded that the new should be treated as a continuation of the
old statute with modifications did not rest alone upon this
omission. It was chiefly based upon the facts above stated -- the
similarity of the subject matters of the two statutes, and that the
effect was a continuation of the old statute as modified by the
new, notwithstanding the use of language which formally repealed
the old statute.
The omission to provide for the rights of the pilot does not,
therefore, detract from the authority of the case for the purpose
for which it is here cited.
The two acts in question here are of a similar nature, relating
to the same general subject matter and making provisions for the
creation and enforcement of mechanics' liens. The new act of 1890,
although in terms repealing the earlier act, is yet in truth and
for the reasons already given a continuation of that act with the
modifications as provided in the new one. One of those
modifications is the extension of the time in which to commence the
action to foreclose the lien after the filing of the statement
which claims it. Where at the time of
Page 164 U. S. 13
the passage of the new act, the proposed lienor has only entered
upon the execution of his contract and has not yet completed the
work under it, we think that, at least as to him, the provision
enlarging the time in which to commence the action to foreclose the
lien is applicable, and there is no retroactive effect thereby
given to that provision of the new act.
It may be asked what effect is given under this construction to
the language of the proviso contained in § 32 of the act of
1890, already quoted. The answer is that the mere enlargement of
the time in which to commence the action, at least in a case where
the time had not yet arrived in which to file any statement of the
plaintiff's claim for a lien, does not affect any right or remedy
provided for in the old act. The right, as that term is used in the
statute, consisted of the right of sale of the property in order,
if necessary, to obtain payment of the money due the contractor.
The remedy consisted of the taking of certain proceedings by which
this sale was to be accomplished. Prior to the arrival of the time
when one of these steps was to be taken, an alteration of the
statute by which the time to take that step might be enlarged was
not an alteration of the right or of the remedy, as those terms are
used in the statute, nor did it in any way affect either. It was
simply an alteration of the mere procedure in the course of an
employment of a remedy, the remedy itself remaining untouched or
unaffected by such alteration. In this case, such an enlargement of
time to commence an action was given before the time had arrived in
which the action could have have been commenced under the old
statute. The new statute was prospective in its operation, even as
applied to this case. Of course, if the new act had curtailed the
time in which to bring the action, after the time had commenced to
run under the old statute, totally different considerations would
spring up, and what was a mere alteration of procedure, having
really nothing to do with a remedy in the one case, might, in the
other, most seriously affect it, and hence come within the proviso
in question. Under the facts of this case, the right or remedy of
the plaintiff was not touched, or, in the language of the proviso,
was not "affected," by the enlargement of the time in
Page 164 U. S. 14
which to commence the action, and therefore the proviso did not
take the plaintiff's case out of the application of the section in
the new act providing such enlarged time.
Under the construction given by us to the act of 1890, as a
continuation of that of 1888, with modifications, the question as
to which act the lien is claimed under is not specially material.
In effect, it is one act, and those labors, etc., which were
performed before the passage of the act of 1890 are added to those
performed thereafter. The lien is really claimed by virtue of the
fact that, at the time when the contract was entered into, the
statute of Utah provided such a right or remedy, and, although the
action to foreclose the lien was commenced under the provisions of
the act of 1890, yet the right itself commenced under the old act.
That right is not affected by any provision of the new act, and
although it is claimed that the right and the remedy must go
together under the old act, as they are preserved by the same
language, yet, for the reasons already given, the time in which to
commence the action is no part of the remedy as that word is used
in the proviso, and an extension of that time may be provided for
in the new act without in any way affecting the right or remedy of
the lienor where the facts are the same as in this case.
It may be assumed that where a statute creates a right not known
to the common law, and provides a remedy for the enforcement of
such right, and limits the time within which the remedy must be
pursued, the remedy in such case forms a part of the right, and
must be pursued within the time prescribed or else the right and
remedy are both lost; but it does not therefore follow that the
plaintiff's right to a lien and to maintain this action must be
based solely upon the act of 1888.
We must bear in mind the position of the plaintiff when the act
of 1890 was passed. He had not then completed his contract, and
could not therefore file any statement of claim, nor could he
commence any action. The particular time in which he would be
allowed to commence his action (provided a sufficient time in fact
were given) was, under such circumstances, mere matter of
procedure, as distinguished from remedy. The
Page 164 U. S. 15
remedy would not thereby be altered, because the remedy
consisted in filing the statement and in commencing the action. The
time in which to do either would be matter of procedure only.
Hence, when the act of 1890 was passed, which enlarged the time in
which to commence the action already provided for, such enlargement
did not affect any right or remedy of the plaintiff. It did not
affect either, because the provision applied only to procedure, and
not to right or remedy, and therefore the plaintiff could avail
himself of the time given him by the act of 1890 in which to
commence his action, as one of the steps in procedure by which the
remedy for a violation of the contract by the enforcement of
foreclosure of the lien would be accomplished.
We conclude that the lien of the plaintiff was valid, and
superior to the mortgage of the mortgage trust company.
2. We are of the opinion also that the claim of Corey Brothers
& Company for a lien superior to that of the mortgage trust
company was properly allowed. That company claims a superiority of
lien because of the clause in its mortgage by which the Bear Lake
Company mortgaged to it, in addition to the property then owned by
the lake company, all its after-acquired property.
A clause in a mortgage which subjects subsequently acquired
property to the lien of the mortgage is a valid clause.
Toledo,
Delphos &c. Railroad v. Hamilton, 134 U.
S. 296;
Central Trust Co. v. Kneeland,
138 U. S. 414;
Galveston Railroad v.
Cowdrey, 11 Wall. 459,
78 U. S.
481.
Such a mortgage, as against the mortgagor and subsequent
encumbrancers, attaches itself to the after-acquired property as
fast as it comes into existence or as fast as the canal or railroad
is built, and the lien of the mortgagee is held to be superior to
that of the constructor. The lien of the mortgage extends also to
an equitable as well as to a legal title to the property
subsequently acquired. 134 and 138 U.S.,
supra.
The company claims that under the principles decided in these
cases, the lien of its mortgage is superior to the claim of Corey
Brothers & Company.
On the contrary, the latter claim to bring their case within
Page 164 U. S. 16
the rule recognized in this Court -- that even under the
after-acquired property clause in a mortgage, if property be
burdened with an encumbrance or lien at the very time of coming
into the possession or ownership of the mortgagor, such encumbrance
remains prior and superior to the lien of the mortgage, although it
was actually subsequent thereto in point of time.
United
States v. New Orleans, 12 Wall. 362;
Fosdick v.
Schall, 99 U. S.
251.
Some further facts are material to this inquiry, and have been
found by the court below. The work done by Corey Brothers &
Company is set forth in findings 19 and 23 as made by the trial
court. It consisted of work and labor and the furnishing of
materials in the construction of the canal from May 1 to December
5, 1890. The canal was constructed on land over which the company
had what is termed in the finding the right of way. The land is
described in the nineteenth finding, and the manner in which the
right of way was acquired is set forth in finding 29, which reads
as follows:
"The right of way upon which the canal was constructed, which
right of way is described in the finding 19, consisted largely of
public land, and was obtained by the defendant the Bear Lake &
River Waterworks & Irrigation Company under and by virtue of
the act of Congress of 1866, being section ___, Revised Statutes of
the United States. A large portion of said right of way was
obtained under contract with one Kerr by which Kerr agreed, upon
the construction of said canal through his land, to give said right
of way. The other portions of said canals were purchased by the
Bear Lake Company at various times from individual proprietors
after May 1, 1890."
The section of the Revised Statutes above referred to is section
2339, and it is taken from the ninth section of the Act of
Congress, c. 262, approved July 26, 1866, 14 Stat. 253, which reads
as follows:
"SEC. 2339. Whenever, by priority of possession, rights to the
use of water for mining, agricultural, manufacturing or other
purposes have vested and accrued and the same are recognized and
acknowledged by the local customs, laws and the decisions
Page 164 U. S. 17
of courts, the possessors and owners of such vested rights shall
be maintained and protected in the same, and the right of way for
the construction of ditches and canals for the purposes herein
specified is acknowledged and confirmed,
provided however
that whenever after the passage of this act any person or persons
shall, in the construction of any ditch or canal, injure or damage
the possession of any settler on the public domain, the party
committing such injury or damage shall be liable to the party
injured for such injury or damage."
Congress subsequently passed another Act, approved July 9, 1870,
entitled "An act to amend an act granting the right of way to ditch
and canal owners over the public lands and for other purposes." 16
Stat. 217, 218.
Section 17 of that act is section 2340 of the Revised states,
and part of the section reads as follows:
"SEC. 2340. None of the rights conferred by sections five,
eight, and nine of the act of which this is amendatory shall be
abrogated by this act, and the same are hereby extended to all
public lands affected by this act, and all patents granted or
preemption or homesteads allowed shall be subject to any vested and
accrued water rights or rights to ditches and reservoirs and in
connection with such water rights as may be acquired under or
recognized by the ninth section of the act of which this act is
amendatory."
The trial court made one other finding of fact (the
thirty-third), by which it was found that the work done by Garland
and by Corey Brothers & Company was done for the Bear Lake
Company, which company, with the consent of the owners of the legal
title, entered into possession of the land through which the canal
ditches were dug, and then, after so entering into possession, the
company consented to and permitted the plaintiff Garland, and also
Corey Brothers & Company, to do the work under their contracts
with the company in digging and excavating the canal.
The counsel for the mortgage company excepted to the
twenty-ninth finding of the court on the grounds (1) that there was
no evidence upon which to base the finding, (2) the evidence did
not support the finding, (3) there was no pleading
Page 164 U. S. 18
upon which to base the same. This exception as to the lack of
evidence to support the findings we cannot consider, and we think
that the objection as to the pleading is not well taken.
Upon appeal from the supreme court of a territory, this Court is
precluded under the statute from reviewing any question of fact,
and the finding of the court below is conclusive upon this Court as
to all such questions. The jurisdiction of this Court on such an
appeal, apart from exceptions duly taken to rulings on the
admission or rejection of evidence, is limited to determining
whether the findings of fact support the judgment.
Stringfellow
v. Cain, 99 U. S. 619;
Neslin v. Wells, 104 U. S. 428;
Eilers v. Boatman, 111 U. S. 356;
Idaho & Oregon land Co. v. Bradbury, 132 U.
S. 509;
Mammoth Mining Co. v. Salt Lake Machine
Co., 151 U. S.
450.
The findings of the trial court are approved and adopted by the
supreme court of the territory by a general judgment of affirmance.
Neslin v. Wells, supra.
We must therefore, in the examination of the question now under
consideration, be confined to the facts as found by the trial
court, approved as they have been by the general affirmance of the
judgment by the supreme court of the territory.
So far as the public land is concerned, over or through which
these ditches for the canal were dug, the statutes above cited
create no title, legal or equitable, in the individual or company
that simply takes possession of such land. The government enacts
that anyone may go upon its public lands for the purpose of
procuring water, digging ditches for canals, etc., and when rights
have become vested and accrued which are recognized and
acknowledged by the local customs, laws, and decisions of courts,
such rights are acknowledged and confirmed. Under this statute, no
right or title to the land, or to a right of way over or through
it, or to the use of water from a well thereafter to be dug, vests,
as against the government, in the party entering upon possession,
from the mere fact of such possession, unaccompanied by the
performance of any labor thereon.
Undoubtedly rights, as against third persons, are acquired
Page 164 U. S. 19
by priority of possession, and the government will and does
recognize such rights as between those parties. This is the
principle running through the cases cited by the counsel for
appellants. In
Sullivan v. Northern Spy Mining Co., 11
Utah 438, which is one of those cases, the priority of possession
of the person who entered upon the public land and dug the well was
recognized as thereby making a superior title to the use of the
water from the well over that acquired by a person who was the
subsequent purchaser of the land from the government. In that case,
the well had been dug and the condition fulfilled. If no well had
ever been dug and a reasonable time for digging it had passed, the
mere priority of possession would have given no superior title to
the land over that acquired by the grantee from the government. It
is the doing of the work, the completion of the well, or the
digging of the ditch within a reasonable time from the taking of
possession, that gives the right to use the water in the well, or
the right of way for the ditches of the canal upon or through the
public land. Until the completion of this work, or, in other words,
until the performance of the condition upon which the right to
forever maintain possession is based, the person taking possession
has no title, legal or equitable, as against the government. What,
if any, equitable claims a party might have upon the government who
did a large amount of work but finally failed to complete the
necessary amount to secure the water or right of way it is not
necessary to determine or discuss. Those equities would not, in any
event, amount to an equitable title to the right of way, or to the
use of the water, and so need not be here considered.
The Bear Lake Company therefore never had any legal or equitable
title to the land over or through which the ditch for the canal was
dug, as against the government, until the ditch was completed. As
the ditch was completed by the labor of the contractor, and the
very title of the mortgagor thereto was itself created by his
labor, the lien attached to the property as it was created and came
into being, and arose coincident with the ownership of the ditch by
the mortgagor, and the property came into the hands of the
mortgagor burdened
Page 164 U. S. 20
with this lien, which remains superior to that of the mortgage.
The point is that the mortgagor never had any claim or title of a
legal or equitable nature to the land upon which this work was done
during the whole time that the work was going on, and when the
title did thereafter vest in the Bear Lake Company by virtue of the
work done by Corey Brothers & Company, it became burdened with
the lien created by virtue of the work so done upon it. If, prior
to the doing of the work, the Bear Lake Company had simply
purchased the land or entered into any such agreement with the
owner thereof as gave it an equitable title to the same, then the
property would not have come to the Bear Lake Company burdened with
any lien and the work thereafter done upon it in the shape of
digging the ditch, etc., would not have given ground for any
priority of lien as against the mortgage of the trust company.
The material fact to remember is that the sole title to the land
or the right of way which the Bear Lake Company has, whether legal
or equitable, is transferred to that company only by virtue of the
work previously done upon the land by the constructors, who thereby
fulfill the condition upon the performance of which such transfer
or the right of such transfer depended. Under these circumstances,
it is proper to say that the title to the land was transferred
subject to the constructors' lien for the work which made the
transfer possible, and by means of which it was accomplished. The
claim is also urged that, even upon the theory of the appellees,
the title to the portion of the land or right of way upon which
Garland, the plaintiff, had worked, had passed to the Bear Lake
Company, and had come under the lien of the mortgage before any
work was done by the Corey Brothers & Company firm, and as to
that portion of the work, the claim is made that the firm could
have no lien prior to the mortgage. The fact is that, at the time
when the firm commenced work, in May, 1890, the plaintiff Garland
had not completed his work, and did not complete it until along in
December following. The title had not, therefore, passed to the
Bear Lake Company when Corey Brothers & Company commenced their
work.
Page 164 U. S. 21
Nor is there any priority given to the mortgage, as claimed by
the appellants, by reason of the provision contained in that
portion of section 19 of the act of 1890, which reads as
follows:
"All such liens shall relate back to the time of the
commencement to do work or to furnish materials, and shall have
priority over any and every lien or encumbrance subsequently
intervening, or which may have been created prior thereto, but
which was not then recorded, and of which the lienor under this act
had no notice. Nothing herein contained shall be construed as
impairing any valid encumbrance upon any such land, duly made and
recorded before such work was commenced or the first of such
materials were furnished."
The very question in issue is whether the mortgage was a valid
encumbrance upon any after-acquired land prior to these liens.
Inasmuch as the title to the right of way did not pass until the
completion of the work, we hold the mortgage was not a valid
encumbrance upon such right of way until that time, and that the
title came to the Bear Lake Company burdened with the lien claimed
by the lienor, which attached to the property at the very moment
of, and simultaneously with, the vesting of such title in the
company, and in priority to the lien of the mortgage.
This principle is in entire harmony with that laid down in the
already cited cases of
Galveston Railroad v.
Cowdrey, 11 Wall. 459, and
Toledo, Delphos
&c. Railroad v. Hamilton, 134 U.
S. 296, and with the cases therein referred to. In
neither of the above-mentioned cases did the title to the property
come into the hands of the company burdened with any lien. Most of
the property in the first above-cited case came to the company
before any work was done, and a small portion only was purchased by
it after the work was done, and it was held that the lien of the
mortgage upon the property, as after acquired, was superior to that
of the constructor who did the work. His work did not transfer the
title or create the condition upon which the vesting of the title
could take place in the mortgagor, and consequently there was no
basis for the claim that the property came to the mortgagor
burdened with the lien.
Page 164 U. S. 22
In the
Toledo case, the dock was built upon property to
which the mortgagor had a good equitable title, and which was
covered by the mortgage, just the same as if the title were a legal
one, and it was held that the dock became subject to the lien of
the mortgage, as prior and superior to any lien of the mechanics
for construction. It was urged in that case that at the time the
mechanic's lien was claimed to have been created, the legal title
to the property sought to be affected was not in the railroad
company, but was in one George W. Ballou, and therefore the
mortgage of the property by the railroad company created no legal
lien, and although, by the decree of foreclosure, the legal title
was transferred to the mortgagor, yet it was transferred subject to
the burden of the mechanic's lien. The Court held that the
mortgagor had the equitable title to the property before
foreclosure, and that the mortgage given by the mortgagor covered
property to which it had an equitable title, as well as property to
which it had a legal title. In the case at bar, the mortgagor never
had any title at all, legal or equitable, until after the work had
been performed by the constructors, and only then by virtue and
through the means of such work.
This case bears great similarity to that of
Botsford v. New
Haven, Middletown &c. Railroad, 41 Conn. 454, the
principle of which case was approved in
Toledo &c. Railroad
v. Hamilton, supra. The mortgage executed by the company in
the Connecticut case covered after-acquired property. After the
execution of the mortgage, it entered into an agreement with the
owner of land by which the owner agreed to thereafter convey the
land to the company upon condition that the depot of the company
should be established thereon and other things done in connection
therewith. The court held that the agreement amounted to a
conditional sale, and that no title to the property passed to the
railroad company unless and until it performed the conditions.
Hence it was held that the lien acquired by the constructor of the
depot, who was employed by the railroad company for that purpose,
attached to the land, and that when the title subsequently came to
the railroad company by reason of the performance
Page 164 U. S. 23
of the conditions by it, the land came burdened with the lien
upon it in favor of the constructor of the depot, and such lien was
therefore superior to the lien of the mortgage.
It is said that, in any event, the title which finally vested in
the Bear Lake Company by virtue of the completion of the work, as
claimed by the respondents, relates back to the time when
possession of the land over which the right of way existed was
first taken, and that such possession was taken by the Bear Lake
Company prior to any work's being done by either the plaintiff
Garland or by the defendants Corey Brothers & Company, and the
title thus became subject to the lien of the mortgage before the
work was done by the lienors. This doctrine of relation, by which
it is claimed that the lien of the mortgage attached to the right
of way prior to the lien of the constructor, is a fiction only. It
is indulged in for the purpose of thereby cutting off intervening
adverse claims of third parties against the right or title set up
and acquired by the first possessor. It will not be indulged in for
the purpose of thereby effecting an injustice by subjecting the
right of way to the prior lien of a mortgage when the existence of
the title to the right of way in the Bear Lake Company was made
possible only after and by the labor of the lienors. In such case,
the actual fact will be considered, and not the fiction.
It is also said that the mortgagee occupies a position superior
in equity to that of the Corey firm because the mortgage was
executed and on record a long time before the firm did any work
upon the ditches, and it must have known, or at any rate notice
from the record will be imputed to the firm, that the mortgage lien
was in existence. The answer to this position is that under the law
as above stated, the firm knew that prior to the completion of the
work by it, the Bear Lake Company would have no title, and the
mortgage would not be a lien upon the property, and that when the
work was completed, the title would pass to the Bear Lake Company
burdened with the lien of the firm and such lien would be superior
to that of the mortgage. To one occupying the position of these
lienors, the mortgage was not in existence. Upon the same
principle, the mortgagee would know that it could acquire no lien
on
Page 164 U. S. 24
this property superior to that of the lienors and that the title
to the property created by the lienors would come to the Bear Lake
Company burdened with their lien. It is plain that in this light,
the equity of the lienors is superior to that of the mortgagee, and
their lien should, if possible, be preferred.
The general principle upon which the lien of Corey Brothers
& Company upon the right of way over the public lands is
claimed as being prior to that of the mortgage also applies to and
covers the case of the land procured by the Bear Lake Company from
Kerr and mentioned in the foregoing twenty-ninth finding of fact.
It was a conditional gift by Kerr to the company of the right of
way, to take effect and be valid upon the construction of the canal
through the lands of Kerr. As to the portion of the land which was
obtained by purchase by the Bear Lake Company at various times from
individual proprietors after May 1, 1890, the finding is too
general upon which to predicate error calling for a reversal of the
whole judgment. The party alleging error should clearly show it,
and where it is of a kind that ought not to carry a reversal of the
whole judgment because of it, he should in that case show the
amount of the error and the extent to which it affected the
judgment. Here, the case is barren of any finding as to extent of
the purchase from private individuals and whether the purchases
were made prior to the work being done or after the same had been
performed. Interpreting the thirtieth finding of the court upon
this subject as being one of fact, we should say the purchase was
not fully accomplished, nor was the title finally transferred,
until after the work had been done. The thirtieth finding is as
follows:
"All the right of way of the Bear Lake & River Company, as
described in finding 19, was acquired by said Bear Lake & River
Waterworks & Irrigation Company after the mechanic's lien of
the plaintiff William Garland and the mechanic's lien of the
defendants Corey Brothers & Company attached to the same."
The appellants criticize this finding as a conclusion of law. It
is made by the court as one of fact, and it may be there is some
matter of fact mixed with a legal conclusion. At any rate, the
whole matter is left in some uncertainty as to the
Page 164 U. S. 25
exact facts relating to the purchase of the right of way after
May 1, 1890, and as to the extent of such purchases from
individuals, and as to the conditions upon which the purchases were
made.
They may have been made under such circumstances as to bring
them directly within the principle of the case last cited. If so,
the lands would be subject to a lien to the same extent as the
lands otherwise acquired.
We will not in such case indulge in any presumptions unfavorable
to the judgment and for the purpose of reversing it unless they are
natural and probable, and such as ought to be drawn from the facts
actually found by the court below. We do not find this to be the
case here.
As another answer to the claim of Corey Brothers & Company,
the appellants assert that if the Bear Lake Company were not the
owner of the right of way over or through the public lands or lands
of Kerr or of the other individuals until after the completion of
the work, then, of course, it was not owner thereof at the time
when the contract with Corey Brothers & Company was entered
into, and in that case they would be entitled to no lien under the
Act of March 12, 1890
The first section of that act provides "that whoever shall do
work or furnish materials by contract, express or implied, with the
owner of any land to any amount" shall be entitled to a lien. The
same section also provides that for the purposes of the act,
"any person having an assignable, transferable or conveyable
interest or claim in or to any land, building, structure, or other
property mentioned in this act, shall be deemed an owner."
We think the Bear Lake Company was such an owner as comes within
the meaning of the statute of 1890 providing for a lien. Although
without a legal or an equitable title until the work was done, yet
the Bear Lake Company, when the work was completed, became such
owner, and in the meantime, and after the execution of the contract
with Corey Brothers & Company and with the plaintiff Garland,
it occupied such a position with regard to the property as brings
it within the equity of the statute for the purpose of the lien
for
Page 164 U. S. 26
work done, and we think such lien, when the work was completed
and the statement of claim filed, was superior to the lien of the
mortgage.
Our conclusion is that the whole judgment should be
Affirmed.