Where, in an action on a contract, a counterclaim to the amount
of $10,000 is interposed by the defendant, and judgment is given
for plaintiff for less than $5,000, this Court has jurisdiction to
review that judgment when brought here by defendant below.
When one party contracts to set up a machine for another party
and the other party contracts to pay for it, one-third when the
machine is steamed up ready to run, and the balance at a future
time, with interest, and it is mutually agreed that the buyer shall
satisfy himself before payments are due that the machine works to
his satisfaction, and if it does not, that the seller shall within
60 days after notice, comply with the terms
Page 151 U. S. 627
of his contract or the buyer may declare it paid in full, the
proper remedy of the seller, after delivery of the machine and
refusal of the buyer to accept it, is an action on the contract to
recover the contract price, and not an action for breach of the
contract by refusal to accept the machine.
The requirement that an assignment of error based upon the
admission or rejection of evidence must, in the case of a
deposition excluded in whole or in part, state the full substance
of the evidence so admitted or rejected, does not apply where the
witness testifies in person and where the question propounded to
him is not only proper in form, but is so framed as to clearly
admit of an answer favorable to the claim or defense of the party
producing him.
When the court in such case does not require the party in whose
behalf the question is put to state the facts proposed to be proved
by the answer, the rejection of the answer will be deemed error or
not according as the question, upon its face, if proper in form,
may or may not clearly admit of an answer favorable to the party in
whose behalf it is propounded.
When objection is made to a question to a witness as
incompetent, irrelevant, and immaterial, and the objection is
sustained, the court may or may not, within its discretion, require
the party in whose behalf the question is put to state the facts
proposed to be proved by the answer.
This was an action in contract. Judgment for plaintiff to which
defendant sued out this writ of error. The case is stated in the
opinion.
MR. JUSTICE HARLAN delivered the opinion of the Court.
1. It is suggested that the amount in dispute is less than
$5,000. This point is not well taken. The amount for which Russell
& Co. sued in their original petition was $4,206.07, with
interest from October 9, 1888. That amount was increased by the
supplemental petition to $5,882.20. The plaintiffs in error, who
were defendants below, denied their liability in any sum, and by
way of counterclaim, in accordance with the practice in Nebraska,
asked for judgment
Page 151 U. S. 628
against Russell & Co. in the sum of $10,000. The verdict and
judgment were in favor of the plaintiff, and for the sum of $4,450.
That sum, and the amount sued for in the counterclaim, are in
dispute upon this writ of error. This Court therefore has
jurisdiction.
2. By an agreement in writing made June 22, 1888, between
Russell & Co., a corporation, and Buckstaff and Utt, the former
agreed to furnish and deliver to the latter on cars at Lincoln,
Nebraska, three boilers, 60 inch x 14 feet; one automatic cut-off
engine, 125 horsepower; one automatic cut-off engine, 50
horsepower; one Gordon Maxwell duplex pump; one Garfield injector;
one heater, and any necessary fittings of sufficient size and
dimension to properly run such plant; also, two smokestacks,
32-inch diameter, 60 feet long, made of No. 12 iron, with fancy
tops, guy rods, and stays. For those articles Buckstaff and Utt
agreed to pay $4,950, as follows: one-third cash when the machinery
was
"steamed up ready to run; the balance in six and twelve months,
with interest at the rate of seven percent per annum from time of
erection in Lincoln; providing that, with proper and careful
management, said engines, boilers, and pumps are hereby guarantied
to work, and that said engines do give the amount of horse power as
herein specified, and to be as economical of fuel and as durable as
a Corliss noncondensing engine."
"It is also understood and agreed," the contract proceeded,
"that said Buckstaff and Utt shall use fair and honorable means
to satisfy themselves, before payments are due, that said engines,
boilers, and pumps are working to their entire satisfaction, and,
should they not be, then, in that event, the said Buckstaff and Utt
are to notify said Russell & Co., and said Russell & Co.
must as once comply with the terms of this contract within sixty
days, and, in the event they do not, the said Buckstaff and Utt may
declare this contract paid in full, or said Russell & Co. shall
pay back to said Buckstaff and Utt all money paid to them, and said
Russell & Co. shall pay said Buckstaff and Utt such damage as
shall be declared fair by competent judges, and, after paying such
damages, may remove said machinery without cost to
Page 151 U. S. 629
said Buckstaff and Utt. It is hereby agreed that Russell &
Co. shall ship said machinery not later than July 15, 1888."
Attached to and made part of the contract are certain proposals
from Russell & Co. to Buckstaff and Utt. One of them is a
proposal to furnish three eighty horsepower boilers, fully
described, and contains this stipulation:
"All boilers tested to 150 pounds hydraulic pressure;
workmanship and material guarantied to be first class; plans for
setting boilers to be furnished without expense to purchaser."
Another is a proposal to furnish one right-hand automatic
cut-off engine, fully described, and contains this stipulation:
"We guaranty the above engine to be well made, of first-class
material, and in operation to work as economically as any similar
engine in the market."
A third is a proposal for another right-hand automatic cut-off
engine, accompanied by a similar guaranty.
In the first count of the petition it was alleged that all the
machinery covered by the contract was delivered by the plaintiff to
the defendants in strict accordance with its terms; that the
defendants were to pay for it the sum of $4,950, one-third in cash
when the machinery was steamed up ready to run, one-third in six
months, and the remaining one-third in twelve months, with interest
at the rate of seven percent per annum from the time of the
erection of said machinery; that all of the machinery had been
delivered, was set up, put in operation, and commenced running on
the 9th day of October, 1888 at which time one-third of the $4,950
became due; that another one-third became due on the 9th day of
April, 1889; that neither of those amounts, nor any part thereof,
have been paid by the defendants, and that they have refused and
neglected to pay the same or any part thereof, although often
requested so to do. The second count was for piping and other
machinery, of the value of $392.86, and the third for granted bars,
of the value of $450, alleged to have been sold and delivered by
Russell & Co. to the defendants. By a supplemental petition,
the plaintiff enlarged its claim so as to embrace the last
installment of the $4,950 for which the contract stipulated.
Page 151 U. S. 630
At the trial below, the defendants objected to the introduction
of any evidence in support of the first count of the petition on
the ground that it did not state facts sufficient to constitute a
cause of action. This objection was overruled, and to that ruling
the defendants excepted.
In support of this exception, it is said that if it had been
alleged, or indeed proven, that the plaintiffs did not "use fair
and honorable means to satisfy themselves," before payment was due,
that the machinery was "working to their entire satisfaction," or
that the refusal to accept was fraudulent, still no action could
have been properly maintained for the sale and delivery of the
property, because at all events there would have been no
acceptance, and, in its absence, the contract would have remained
executory. Consequently, it is argued, the only action
maintainable, if any, would have been one to recover damages for
fraudulently refusing to accept the machinery and articles
furnished. The counsel for the defendants refer to numerous cases
which, it is insisted, sustain the construction of the contract
upon which this exception is founded. It may be well to refer to
some of those cases.
In
Mansfield Machine Works v. Village of Lowell, 62
Mich. 546, 552, which was a suit upon a contract with a village for
the sale of a steam engine and attachments, and which contract
provided that a named sum should be paid
"when engine and hose are accepted; balance in equal payments:
first on or before six months; second on or before eighteen months,
with interest at six percent from date of acceptance,"
it was held that the contract, fairly construed, did not provide
for the payment for the engine and machinery until they were tried
and accepted; that under its terms the property remained in the
vendor until acceptance and after trial of it, the village never
becoming the owner of it, and that the remedy of the plaintiff, if
any, would be a suit for a breach of the contract and refusal to
accept on the part of the defendant.
In
Zaleski v. Clark, 44 Conn. 218, 223, which was a
suit for the price agreed to be paid for a plaster bust of the
deceased husband of the defendant, the agreement being
Page 151 U. S. 631
that she was not bound to take it unless she was satisfied with
it, the question was as to the liability of the defendant upon
proof that the bust was not only a fine piece of work, and a
correct copy of a photograph furnished by the defendant, but that
it accurately portrayed the features of the deceased. The court
said:
"In this case, the plaintiff undertook to make a bust which
should be satisfactory to the defendant. The case shows that she
was not satisfied with it. The plaintiff has not yet, then,
fulfilled his contract. It is not enough to say that she ought to
be satisfied with it, and that her dissatisfaction is unreasonable.
She, and not the court, is entitled to judge of that. The contract
was not to make one that she ought to be satisfied with, but to
make one that she would be satisfied with. Nor is it sufficient to
say that the bust was the very best thing of the kind that possibly
could be produced. Such an article might not be satisfactory to the
defendant, while one of inferior workmanship might be entirely
satisfactory. A contract to produce a bust perfect in every
respect, and one with which the defendant ought to be satisfied, is
one thing, and undertaking to make on with which she will be
satisfied is quite another thing. The former can only be determined
by experts or those whose education and habits of life qualify them
to judge of such matters. The latter can only be determined by the
defendant herself. It may have been unwise in the plaintiff to make
such a contract, but, having made it, he is bound to it."
In
Brown v. Foster, 113 Mass. 136, 138, which was an
action to recover the price of a suit of clothes which it was
agreed should be satisfactory to the purchaser, but with which he
was not satisfied, and for which he refused to pay, the court
said:
"If the plaintiff saw fit to do work upon articles for the
defendant, and to furnish materials therefor, contracting that the
articles, when manufactured, should be satisfactory to the
defendant, he can recover only upon the contract as it was made,
and even if the articles furnished by him were such that the other
party ought to have been satisfied with them, it was yet in the
power of the other to reject them as unsatisfactory. It is not for
anyone else to decide whether a refusal to accept is or is not
reasonable when the contract permits
Page 151 U. S. 632
the defendant to decide himself whether the articles furnished
are to his satisfaction. Although the compensation of the plaintiff
for valuable service and materials may thus be dependent upon the
caprice of another who unreasonably refuses to accept the articles
manufactured, yet he cannot be relieved from the contract into
which he has voluntarily entered."
Among many other cases of the same class are
Singerly v.
Thayer, 108 Penn.St. 291;
Goodrich v. Van Nortwich,
43 Ill. 445;
McCarren v. McNulty, 7 Gray 139;
Cole v.
Common Council of Homer, 53 Mich. 438;
Gibson v.
Cranage, 39 Mich. 49;
Krum v. Mersher, 116 Penn.St.
17;
Ellis v. Mortimer, 4 Bos. & Pul. (1 N.R.) 257.
These authorities do not control the determination of the
present case. There is no provision in the contract of June 22,
1888, which either expressly or by necessary implication justified
the defendants in withholding payment for the articles furnished on
the ground alone that they were not satisfied with them. They
agreed to pay in cash one-third of the stipulated price when the
machinery was "steamed up, ready to run," the balance in six and
twelve months, with interest at seven percent "from time of
erection in Lincoln." If, after using fair and honorable means,
before the payments became due, to test their efficiency, the
engines, boilers, and pumps did not work to their entire
satisfaction, then Buckstaff and Utt were entitled to notify
Russell & Co. to comply with the contract within sixty days, in
default of which, but in that event only, they could have declared
the contract "paid in full," or Russell & Co. could have been
required to pay back all money paid to it, and, in addition, such
damage as was declared fair by competent judges, Russell & Co.
having the right to remove the machinery after paying such damage.
The plaintiff was entitled to recover the price stipulated unless
it appeared that such means had been used, and that the engines,
boilers, and pumps were in that way ascertained not to work to the
entire satisfaction of the defendants; that due notice thereof was
given to the plaintiff, and that plaintiff did not comply with the
contract within due time after receiving such notice. But these
were matters to be disclosed
Page 151 U. S. 633
in the defense of the action, and need not have been made the
subject of specific allegations in the petition. It was not
necessary to allege in the petition that the engine, boilers, and
pumps were ascertained by the defendants to work to their entire
satisfaction. It was sufficient to allege the delivery of the
articles and the expiration of the time limited in the contract for
the payments.
In respect to the guaranty of the plaintiff that the engines,
boilers, and pumps would work and that the engines would furnish
the stipulated amount of horsepower and be as economical of fuel
and as durable as a Corliss noncondensing engine, it need only be
said that those were also matters to be alleged and proved by
defendants in support of their counterclaim.
For these reasons, we are of opinion that the court properly
overruled the motion of defendants to exclude all evidence in
support of the first count of the petition.
3. The defendants, in their answer, deny the material
allegations of the petition, and by way of counterclaim allege that
on or about the twenty-second day of June, 1888, the defendants, as
the plaintiff then well knew, were the owners of all the capital
stock of the Lincoln Paper Manufacturing Company, a corporation
duly organized under the laws of Nebraska for the purpose of
manufacturing paper in the City of Lincoln, in that state, and that
on or about that date, the plaintiff entered into the contract with
the defendants set forth in the first count of the petition for the
furnishing of boilers, engines, and machinery to generate and apply
the power with which to drive the machinery to be used by them in
said mill for the manufacture of wrapping and straw building board;
that the plaintiff then well knew that if said boilers, engines,
and machinery were not of the capacity and efficiency specified in
the contract, then the defects and inefficiency of such machinery
would of necessity cause the defendants great injury, cost, and
damage in and about their manufacturing business by reducing the
quantity and degrading the quality of the paper to be manufactured
at their mill and by putting them to great cost and expenses for
loss of time and for labor, fuel, and material used, lost, and
expended above such as
Page 151 U. S. 634
would be required with the use of boilers, engines, and
machinery of the kind, power, effectiveness, and economy specified
in the contract; that the defendants entered into the contract in
the expressed confidence, assurance, and belief that the plaintiff
would furnish for use in their mill boilers, engines, and machinery
of the kind, quality, power, and description in the contract set
forth, yet the plaintiff, in pretended compliance with the
contract, furnished and erected in said mill three boilers of a
capacity not exceeding sixty-five horsepower each, and one engine
of one hundred and twenty-five and one of fifty horsepower, and
that said engines and boilers have at all times, and still do,
consume, in the performance of the work of which they are capable,
not less than fifty percent more fuel than would be consumed in the
performance of the same work by a noncondensing Corliss engine, and
that plaintiff furnished with said boilers and engines defective
and insufficient grates, fixtures, and appliance therefor, so that
the same were for a long time less capable and effective than they
would otherwise have been.
The defendants further alleged in their counterclaim that, at
the request of plaintiff, they allowed it, after the date of the
erection of said machinery, to consume a long time in the attempt,
or pretended attempt, to adjust the boilers, engines, and machinery
and supply them with grates and fittings, so that the same would
meet the requirements and descriptions of the contract, all of
which attempts, or pretended attempts, have wholly and completely
failed; that thereupon, on or about the eleventh day of January,
1889, and the eleventh and twenty-fifth days of February of said
year, they duly notified the plaintiff, by letters properly
transmitted through the United States mails that such boilers,
engines, and machinery were wholly inadequate, inefficient, and
wasteful of fuel, as compared with the requirements and
descriptions of the contract, and demanded of it to remove the same
from said mill and pay defendants the amount of money, to-wit,
$690.68, paid by them to and for the use of plaintiff under the
contract, and the damages suffered by reason of the premises, as by
the contract it had undertaken to do, with which request
Page 151 U. S. 635
the plaintiff has at all times neglected and still wholly
neglects and refuses to comply, and that, by reason of the
premises, of the wasteful consumption of fuel and lack of power,
said boilers, engines, and machinery and the consequent loss of
time and labor, and the diminution in quantity, and deterioration
in quality, of the output of said mill resulting from the
noncompliance by plaintiff with the contract in the respects and
particulars set forth, and in the purchase and supplying new
granted bars and heater fittings and fixtures for such boilers and
engines, the defendants have been damaged in the sum of $10,000. An
account of the moneys so alleged to have been paid was annexed to
the counterclaim.
The plaintiff, in reply, denies that the machinery, etc.,
furnished by it under the contract were defective, and charges that
their inefficiency, if they became inefficient, was due entirely to
the unskillful and incompetent management of the defendants, their
agents and servants. While it denies that the defendants were the
owners of "all" the capital stock of the Lincoln Paper
Manufacturing Company, it does not deny that the machinery, etc.,
were purchased to be used in the mill of that company.
The defendant Utt was sworn as a witness for the defense, and,
as we infer, in support of the counterclaim. Having stated that he
and Buckstaff, in April, 1888, first commenced negotiations for the
purchase of the boilers with Mr. Giddings, representing Russell
& Co., the following questions were put, successively, to
him:
"(1) What conversation did you have with him, if any, about the
purpose for which the machine must be used, and the necessity for
steam capacity in the boilers?"
"(2) You may state in what your damages consisted, and the
amount, in consequence of the defective construction, and the
failure of this machinery to perform its labor, and the labor
required of it by the terms of the contract, from the time of its
erection up to the first day of March."
"(3) You may state what damage you sustained in consequence of
the failure of this machinery to do the work at the paper
mill."
"(4) You may state what loss you suffered in consequence of the
defective construction and failure in the machinery."
"(5) In
Page 151 U. S. 636
what particular did you and the defendant Buckstaff sustain loss
by reason of the defects in the construction and the failure of
this machinery?"
Each of these questions was objected to upon the ground that it
was incompetent, irrelevant, and immaterial. No one of them was
objected to upon the ground that it was a leading question.
In the case of
Shauer v. Alterton, ante, 151 U. S. 607,
just decided, it was held to be the settled construction of the
twenty-first rule of this Court that an assignment of error based
upon the exclusion of an answer to a particular question in the
deposition of a witness would be disregarded here unless the record
sets forth the answer or its full substance.
Packet
Company v. Clough, 20 Wall. 528,
87 U. S. 542;
Railroad Co. v.
Smith, 21 Wall. 255,
88 U. S. 262;
Thompson v. First National Bank of Toledo, 111 U.
S. 529,
111 U. S.
535-536. Our rule, thus construed, is one to which
parties can easily conform. Having access to the deposition
containing the answer of the witness to the interrogatory, parties,
as well as the trial court, are informed of the precise nature of
the evidence offered. The requirement that an assignment of error
based upon the admission or rejection of evidence must, in the case
of a deposition excluded in whole or in part, state the full
substance of the evidence so admitted or rejected, means that the
record must show in appropriate form the nature of such evidence in
order that this Court may determine whether or not error has been
committed to the prejudice of the party bringing the case here for
review.
But this rule does not apply where the witness testifies in
person, and where the question propounded to him is not only proper
in form, but is so framed as to clearly admit of an answer
favorable to the claim or defense of the party producing him. It
might be very inconvenient in practice if a party, in order to take
advantage of the rulings of the trial court in not allowing
questions proper in form, and manifestly relevant to the issues,
were required to accompany each question with a statement of the
facts expected to be established by the answer to the particular
question propounded. Besides, and this is a consideration of some
weight, such a statement in
Page 151 U. S. 637
open court, and in the presence of the witness, would often be
the means of leading or instructing him as to the answer desired by
the party calling him. If the question is in proper form and
clearly admits of an answer relevant to the issues and favorable to
the party on whose side the witness is called, it will be error to
exclude it. Of course, the court, in its discretion, or on motion,
may require the party in whose behalf the question is put to state
the facts proposed to be proved by the answer. But if that be not
done, the rejection of the answer will be deemed error or not
according as the question, upon its face, if proper in form, may or
may not clearly admit of an answer favorable to the party in whose
behalf it is propounded.
Tested by these views, the court below erred in not permitting
the defendant Utt to answer the above questions. Each one of them
was relevant to the counterclaim, and each admitted of an answer
that tended to support it.
After the court below refused to allow the defendant Utt to
answer the above questions, he was asked: "You may state in what
manner your industry was affected by the failure of this
machinery." The witness answered:
"When our mill was erected, we made contracts with different
parties to put in certain machinery. In cutting straw, there is a
large amount of steam required. We purchased from Neill patent
boilers at an expense of five thousand dollars, to be cooked with
steam coming from the boilers. That was the proper way to do it. A
lack of steam in the plant that we purchased made it impossible for
us to cook this straw in these boilers, so, after trying six or
eight weeks to do this with this steam, and succeeding very poorly,
we took steam from the escape system that we had made in connection
with the big engine, and since that time we have been using that
steam; but it does not cook the straw well, because the water
condenses in these globe bleachers, and has to be let out, and with
them the liquor passes out that the straw is cooked in, and it
makes an uneven cooking of the straw -- it is not uniform. The
straw is frequently tough, so that we take it over to the grinding
machine, where it is ground up. Instead of grinding it up in two
hours and a
Page 151 U. S. 638
half to three hours, it takes from four to four and a half to
get it in proper shape."
To this question the plaintiff objected, and moved to strike out
the answer as incompetent and irrelevant. The objection and motion
were sustained by the court, and the defendants excepted. As we are
informed by the bill of exceptions what were the facts intended to
be elicited by the question, and which, after being detailed, were
excluded from the jury, it is competent for this Court to inquire
whether those facts were competent under the issues in the case and
whether the defendants were prejudiced by their exclusion from the
jury; but, as the judgment below must be reversed for the errors
already stated, we deem it unnecessary at this time to express any
opinion as to the competency of this evidence. We adopt this course
because it is not entirely clear that the matters referred to by
the defendant Utt in his answer to this question had any connection
in fact with the counterclaim, or that they referred to any defects
in the machinery covered by the written guaranty of Russell &
Co. This difficulty may be removed at the next trial of the
case.
In the brief of counsel for Russell & Co., there is some
discussion as to the measure of damages in the event it was found
that the defendants were entitled to recover upon their
counterclaim. No question of that kind arises upon this writ of
error. The only questions now presented for determination are those
to which we have referred.
For the error indicated in this opinion, the judgment must
be
Reversed, and the cause remanded for a new trial.