The "fifty percentum on the contract as originally let" to which
the power of the Postmaster General to expedite service under a
contract for carrying the mails is restricted by the proviso in
§ 2 of the Act of April 7, 1880, c. 48, 21 Stat. 72, is fifty
percent on the compensation for all the service, both as originally
stipulated and as increased by additional service, which is to be
determined by the rates fixed in the original contract.
Decisions of the Postmaster General imposing forfeitures on
contractors for failure to carry the mails according to their
contracts are not subject to review by this Court.
The appellant, George Allman, on the 31st of January, 1885,
filed a petition in the Court of Claims against the United States
asking judgment for the sum of $3,607.13, which he alleged was the
balance due for services rendered by him under two contracts for
carrying the United States mail from July 1, 1878, to July 1,
1882.
It appears from the statements of the petition that the
appellant carried the mails for four years over each of two routes,
No. 46,210 and No. 46,211, under these contracts entered into with
the Postmaster General, and in conformity to the orders
subsequently issued by him. Whilst the services were being
rendered, the Postmaster General, in the exercise of authority
expressly reserved in these contracts, by successive orders
increased the number of trips per week on both routes, on the first
by raising the number from six to seven trips per week (afterwards
reduced back to six), and on the second by raising the number from
one to seven trips per week. For this increase he allowed the
contractor a
pro rata increase of compensation, raising
the pay on the first route to a rate of $5,238.33 per annum for
increasing the trips from six to seven a week, and on the second
route $4,893 for the increase from one to seven trips a week. This
increased compensation was paid by the department, and is not
involved in this litigation except as incidental to another demand
hereinafter stated. On both these routes, the Postmaster General
increased the rate of
Page 131 U. S. 32
speed by shortening the running time between the termini; on the
first from 36 to 28 hours per trip and on the second from 34 to 18
hours per trip. In consideration of this increased expedition,
additional pay was allowed the contractor on the first route,
$2,619.16 per annum, and on the second route $2,446.50 per annum,
for the additional stock and carriers thus rendered necessary. This
allowance was computed at the rate of 50 percent of the annual sum
paid, in accordance with the contract, for the services expedited,
and was less than the proportionate increase of the cost of the
service demanded by the changes in the schedule according to the
sworn statements of the contractor.
On the 1st of August, 1881, the Postmaster General promulgated
an order reducing all the allowances for the increased expedition
heretofore recited, and directed that the 50 percent paid to the
contractor for such service should be computed upon the service
rendered at the time the contracts were entered into before any
additional trips had been ordered on either route, and not upon the
service as actually expedited. This order making the reduction did
not change the number of trips on either of the routes. The
contractor was still required to make daily trips on the second
route and to make these trips upon the expedited schedule. The
effect of the order was simply to reduce his compensation in the
case of the first route to fifty percent upon the pay of six trips
only, instead of seven per week, and in the case of the second
route, its effect was to allow him the compensation at the rate of
50 percent upon the pay for one trip her week, although he
continued to make daily trips in accordance with the expedited
schedule.
The difference between the amounts paid to the claimant under
this last order and the amount he would have received under the
allowance fixed by the former orders, according to the stipulation
of the contracts, constitutes the principal demand in the present
suit. A short time after the number of trips was increased on the
first route from six to seven per week, it was reduced back to six,
and one month's extra pay allowed to the contractor as indemnity
for the discontinuance. The petition sets up a demand for the 50
percent thereon, which has been withheld by the Postmaster
General.
Page 131 U. S. 33
Another claim set up in the petition is for the amount deducted,
as forfeitures alleged to be wrongfully imposed by the Postmaster
General, for failures by the contractor to cause the mail to be
carried within the time prescribed. The petition was demurred to,
and this appeal is from the judgment of the court sustaining the
demurrer.
MR. JUSTICE LAMAR, after stating the facts as above, delivered
the opinion of the Court.
The contracts in question were made in conformity with the
provisions of §§ 3960 and 3961 of the Revised Statutes.
Section 3960 is as follows:
"Compensation for additional service in carrying the mail shall
not be in excess of the exact proportion which the original
compensation bears to the original service, and when any such
additional service is ordered, the sum to be allowed therefor shall
be expressed in the order, and entered upon the books of the
department, and no compensation shall be paid for any additional
regular service rendered before the issuing of such order."
Section 3961 provides:
"No extra allowance shall be made for any increase of expedition
in carrying the mail unless thereby the employment of additional
stock and carriers is made necessary, and in such case the
additional compensation shall bear no greater proportion to the
additional stock and carriers necessarily employed than the
compensation in the original contract bears to the stock and
carriers necessarily employed in its execution."
All the orders made by the Postmaster General subsequent to the
execution of these contracts and while the service was in course of
performance, were made after the Act of Congress of April 7, 1880,
which contained this proviso:
"
Provided that the Postmaster General shall not
hereafter
Page 131 U. S. 34
have the power to expedite the service under any contract either
now existing or hereafter given to a rate of pay exceeding fifty
percentum upon the contract as originally let."
21 Stat. 72. The Attorney General, construing the provision last
quoted in a letter to the Postmaster General dated July 20, 1881,
held that "the original letting, and not any subsequent increase of
service and pay," was made "the standard of limitation." It was in
conformity with this opinion that the Postmaster General withheld
from the appellant the 50 percent on the expedited service under
his contract.
We think it is clear that the language of the proviso may be
interpreted in accordance with the original orders of the Post
Office Department and pursuant to the terms of the contracts sued
on. Those orders allowed the contractor, for expedition, 50 percent
additional upon the sum paid, for the service actually performed.
These allowances did not exceed 50 percent of the rate of
compensation fixed by the contracts as originally let, though they
did exceed 50 percent of the sum named in those contracts. The
proviso, in express terms, refers to the "rate of pay" established
in the contracts as originally let, and it is the rate of pay, not
the amount expressed in the first contract, which is manifestly
intended to be the unit of computation.
Our construction of this legislation, considered
in pari
materia with the provisions of §§ 3960 and 3961, is
this: section 3960 treats the rate of pay for additional service as
definitely fixed by the original contract, and under its provisions
the compensation which the contractor is to receive for each extra
trip placed upon his route is to bear an exact proportion to the
additional service performed -- that is, it is to be based upon the
rate established by the original contract. Section 3961 has direct
reference to the compensation to be paid for the expedited service,
and expressly provides that, in computing such compensation, the
rate of pay fixed in the original contract is to be taken as the
standard of limitation, which shall not be exceeded. These two
sections left it within the discretion of the Postmaster General to
expedite the service
Page 131 U. S. 35
to an indefinite extent, and to allow a
pro rata
compensation therefor. The proviso added in 1880 was clearly
intended to limit that discretion by providing that thereafter he
should not have authority to expedite the service, under any
contract, beyond 50 percent of the rate fixed in the original
contract. The circumstances under which contracts for the
transportation of the mails are awarded, we think, sustain this
construction. Such awards are made after public advertisement, and
upon competitive bids, and it is presumed that the contract price
is at as low a rate as can be made consistently with a proper
performance of service. In the present case, it appears from the
record that the actual cost of the expedition ordered upon the
single one of the seven weekly trips upon the second route was more
than 50 percent of the aggregate sum named in the original
contract. The interpretation on which the last order is based
assumes that Congress intended to leave with the Postmaster General
the power to exact from a contractor seven times the service
stipulated in the contract as originally let, and to allow but 50
percent compensation on the amount named in that contract.
The construction contended for by the appellant is in harmony
with the previous legislation on the subject and the established
policy of the mail service, and is entirely equitable.
As to so much of the demand as is claimed in the petition to be
due to the petitioner under the contracts, and as to the 50 percent
of one month's extra pay, we hold and decide that the Court of
Claims erred in sustaining the demurrer.
But with regard to the claim for the amount deducted as
forfeitures imposed by the Postmaster General, because the
contractor failed to cause the mail to be carried between the
termini within the time prescribed, it is considered that these
forfeitures were made by virtue of the power conferred upon the
Postmaster General by the statutes, and also recognized by the
terms of the contracts to be within his discretion, and are not
subject to review by this Court.
Chicago Railway Company v.
United States, 127 U. S. 406,
127 U. S. 407;
Eastern Railroad Co. v. United States, 129 U.
S. 391,
129 U. S.
396.
Page 131 U. S. 36
As far as the claim for the deduction of the amount of these
forfeitures is concerned, the demurrer was properly sustained.
The judgment is reversed, and the case remanded for action
in accordance with the principles of this decision.