When, under a contract to furnish and to put in complete
operation in the purchaser's mill machinery of a certain
description and quality for a price payable partly upon the arrival
of the machinery at the mill and partly after the completion of the
work, the machinery furnished and set up does not, when tested,
comply with the requirements of the contract, the purchaser, upon
giving notice to the seller that, if the latter does not "put the
mill in repair so that it will do good work," the former will do
so, is entitled to deduct, in an action for the unpaid part of the
price, the reasonable cost of altering the construction and setting
of the machinery so as to conform to the contract.
Whether a witness called to testify to any matter of opinion has
such qualifications and knowledge as to make his testimony
admissible is a preliminary question for the judge presiding at the
trial, and his decision of it is conclusive unless clearly shown to
be erroneous in matter of law.
Page 130 U. S. 521
This was an action by an Ohio corporation against a citizen of
Delavan in the State of Wisconsin upon a contract in writing by
which the plaintiff agreed
"to furnish and put in complete operation for the second party,
in his flouring mill at Delavan aforesaid, one first-class
seventy-five barrel capacity roller-mill complete,"
including certain machinery specified,
"the first party to use all machinery, belting, etc., etc., now
in said flouring mill that is in proper condition for use, except
what is now in use on the rye and feed side of said mill; all of
said mill, machinery, fixtures and apparatus to be new and first
class in every way and of latest pattern, except as above
specified, and to be completed and put in complete running order
within ninety days from the date hereof,"
and the defendant agreed to pay the plaintiff "for the said
mill, fixtures, etc., complete as above specified, and put in
complete operation in his flouring mill at Delavan aforesaid" the
sum of $9,000, as follows: $3,000 "upon the arrival of said mill
and machinery at his mill in Delavan," $4,000 "when said mill is
completed and in running order to the satisfaction of the second
party," and the remaining $2,000 "within ninety days after the
completion of the said mill as aforesaid, the first party to start
the mill and see that it is in complete running order."
The complaint alleged the plaintiff's performance of the
contract on its part, the defendant's payment of $3,272.47, and his
refusal to pay the balance of $5,727.53, which the plaintiff sought
to recover, with interest. The defendant in his answer set up by
way of defense, and also under a counterclaim for $11,000, delay on
the part of the plaintiff, and defects in the manufacture and
design of the machinery furnished, whereby the defendant had been
put to great expense to complete it so as to comply with the
requirements of the contract, and had been deprived of the use of
his flouring mill and injured in his business. The plaintiff filed
a replication denying all the
allegations in the counterclaim.
At the trial, the plaintiff introduced evidence tending to show
that the machinery was put in the defendant's flouring mill in
compliance with the terms of the contract, except for a delay of
several weeks, in part chargeable to the defendant's
Page 130 U. S. 522
fault, and was tested in February, 1884, with satisfactory
results.
On the question of the damages to which the defendant was
entitled for the delay, the plaintiff called as a witness one
Geissner, who testified that he was the owner and manager of a
roller flouring mill of about seventy-five to one hundred barrels
capacity in an adjoining county, and was personally familiar with
roller mills and the milling business, but had never seen the
defendant's mill or been in Delavan, and knew nothing from personal
observation or knowledge of the extent of the custom work of the
mill, its business, or product, or of the water power.
He was then asked to state the rental value of the mill in
question, in his judgment, during the period in question. The
question was objected to
"because the witness had never seen and had no personal
knowledge of the property in question, and was therefore
incompetent to testify as to rental value."
The court sustained the objection, and the plaintiff excepted to
the ruling.
The witness was then asked to state such rental value
"upon the supposition that the said mill had a good waterpower
and all the business it could attend to, as claimed by the
defendant, and a capacity of manufacturing seventy-five barrels per
day."
To this question the same objection was made and sustained by
the court, and the plaintiff excepted as before.
The defendant then introduced evidence tending to show that the
machinery and work furnished by the plaintiff did not comply with
the contract and did not and could not operate satisfactorily, and
that his flouring mill with the machinery constructed and placed
therein by the plaintiff did not and would not do as good work as
other roller mills of like capacity; that it was necessary, in
order to put it in condition to do such work, to expend the sum of
$2,772, including $1,100 for the cost of new machinery, and that
the defendant did this after his attorneys had served upon the
plaintiff's attorney, and the plaintiff had neglected to comply
with, a notice in these words:
"If your clients do not within ten days
Page 130 U. S. 523
proceed to put the mill in repair so that it will do good work,
Mr. Phelps will employ the best millwrights he can obtain and put
the mill in order and charge the expense to your clients."
The court, at the plaintiff's request, gave to the jury the
following instructions:
"The plaintiff was entitled to a fair test of the machinery put
into the defendant's mill, and nothing short of that would justify
its condemnation. Such a test requires an ample power to operate
the machinery to the best advantage, and this means the whole of
the machinery, if the jury find that the machinery was designed and
intended to be operated together. It also contemplates competent
management by a miller who thoroughly understood such machinery and
was able to manipulate and handle it so as to secure the best
results of which it was capable."
The court also instructed the jury as follows:
"If the plaintiff broke this contract by failing to furnish the
defendant such a mill as it was bound to furnish, then the
defendant had the right to give the plaintiff notice that it was
required to remedy the defects, and on its failure to do so, the
defendant could then proceed and correct the defects himself, so
that the mill should be such as he was entitled to have under the
contract, and charge the reasonable and necessary expenses of the
work to the plaintiff. The limit to which the defendant could go in
that direction is this: he would have the right to make the mill
completely answer the demands of the contract, and nothing more --
that is, a first-class complete roller mill of the designated
capacity, capable of doing as good work as other first-class roller
mills of similar grade and capacity would do on the same kind of
stock. He would only have the right to incur and make the plaintiff
chargeable with such expenses as were reasonable and necessary to
put the mill in that condition. If the system put into the
defendant's mill could have been perfected by alterations in
matters of detail so as to make it first-class, complete, capable
of doing the work contemplated by the contract, then the additional
work on the mill should have been limited to such alterations; but
if it could not be thus perfected without more radical changes and
additions, then the defendant had the right to proceed so far
Page 130 U. S. 524
as actual necessity required, making the expense of the work as
moderate and reasonable as the circumstances permitted."
The plaintiff excepted to this portion of the instructions for
the reason that
"the same authorizes the jury to allow the defendant, and to
deduct from the claim of the plaintiff as a part of the expense of
changing the mill over so as to make it conform to the contract,
the cost of the new machinery put into the mill, amounting to
$1,100."
The jury returned a verdict by which
"they find the issue herein in favor of the defendant, but that
the defendant is not entitled to recover damages against the
plaintiff in excess of the plaintiff's claim against the
defendant."
Judgment was rendered on the verdict, and the plaintiff sued out
this writ of error.
Page 130 U. S. 526
MR. JUSTICE GRAY, after stating the facts as above, delivered
the opinion of the Court.
The principal position taken in the argument for the plaintiff
is that the defendant, having received and retained the machinery
furnished under the contract sued on, was bound to pay the contract
price, and, in support of this position, cases were cited holding
that under a contract to manufacture or to furnish a chattel
satisfactory to the purchaser, the purchaser, if he takes
possession of and uses it, thereby conclusively accepts it as
satisfactory and binds himself to pay the whole contract price.
Considering the instructions given at the plaintiff's own
request, and the grounds on which the plaintiff excepted to the
other instructions of the court, it is, to say the least, doubtful
whether this point is open. But, assuming it to be open, it clearly
cannot be sustained, and the cases cited are inapplicable.
The plaintiff's agreement was not for a sale of the machinery
subject to a condition that it should be satisfactory to the
purchaser. But it was an agreement not only to furnish machinery of
a certain description and quality, but also to set it up and put it
in complete operation in the defendant's mill. The machinery was to
be erected on the defendant's land and made part of his mill, and
one installment of the price was to be paid on the delivery of the
machinery there, and before the plaintiff had completed the work to
the satisfaction of the defendant. In such a case, it would be most
unreasonable to compel the defendant, in order to entitle him to
avoid paying the whole contract price or to recover damages for the
plaintiff's breach of contract, to undergo the expense of taking
out the machinery and the prolonged interruption of his
business
Page 130 U. S. 527
during the time requisite to obtain new machinery elsewhere. The
rule of damages adopted by the court below, of deducting from the
contract price the reasonable cost of altering the construction and
setting of the machinery so as to make it conform to the contract,
is the only one that would do full and exact justice to both
parties, and is in accordance with the decisions upon similar
contracts.
Benjamin v.
Hillard, 23 How. 149;
Railroad
Co. v. Smith, 21 Wall. 255;
Marsh v.
McPherson, 105 U. S. 709,
105 U. S. 717;
Cutler v. Close, 5 Car. & P. 337;
Thornton v.
Place, 1 Mood. & Rob. 218;
Allen v. Cameron, 3
Tyrwh. 907, 1 Cr. & M. 832.
The notice given by the defendant to the plaintiff "to put the
mill in repair so as to do good work" was sufficient to cover all
alterations necessary to accomplish that end.
No error is shown in the exclusion of Geissner's testimony as to
the rental value of a mill which he had never seen and knew nothing
of. Whether a witness called to testify to any matter of opinion
has such qualifications and knowledge as to make his testimony
admissible is a preliminary question for the judge presiding at the
trial, and his decision of it is conclusive unless clearly shown to
be erroneous in matter of law.
Perkins v. Stickney, 132
Mass. 217, and cases cited;
Sorg v. First German
Congregation, 63 Penn.St. 156.
Judgment affirmed.