In an action at law in a circuit court of the United States in
New York, an order was made referring the action to a referee "to
determine the issues therein." He filed his report finding facts
and conclusions of law and directing that there be a money judgment
for the plaintiff. The defendant applied to the court for a new
trial on a "case and
Page 124 U. S. 65
exceptions," in which he excepted to three of the conclusions of
law. The court denied the application and directed that judgment be
entered "pursuant to the report of the referee," which was done. On
a writ of error from this Court,
held that the only
questions open to review here were whether there was any error of
law in the judgment on the facts found by the referee, and that, as
the case had not been tried by the circuit court on a filing of a
waiver in writing of a trial by jury, this Court could not review
any exceptions to the admission or exclusion of evidence, or any
exceptions to findings of fact by the referee, or to his refusal to
find facts as requested.
The defendant agreed to make for the plaintiff 400 tons of iron,
and to ship it about September 1st, or as soon as he could
manufacture it, for $19.50 per ton. He did not deliver any of it at
or about that date, nor as soon as he had manufactured the required
amount. The referee found that the defendant "postponed the
execution of the contract from time to time" and that, on November
7th, he insisted, as conditions of delivering the iron, on certain
provisions not contained in the original agreement. The plaintiff
did not comply with those conditions, and the iron was not
delivered. The referee found that the market value of such iron on
November 7th was $34 per ton, and did not find what the market
value of such iron was at any other time. In a snit by the
plaintiff against the defendant to recover damages for a breach of
the contract, he was allowed $14.50 per ton. On a writ of
error,
Held:
(1) The postponement of the execution of the contract must be
inferred from the findings to have been with the assent of the
plaintiff.
(2) The rule of damages applied was proper.
A counterclaim set up by the defendant was, on the facts,
properly disallowed.
At law in contract. Judgment for plaintiff. Defendants sued out
this writ of error. The case is stated in the opinion of the
Court.
Page 124 U. S. 66
MR. JUSTICE BLATCHFORD delivered the opinion of the Court.
This is an action at law brought in the Circuit Court of the
United States for the Northern District of New York by Henry M.
Benjamin, a citizen of Wisconsin, against Henry C. Roberts and
Archibald S. Clarke, citizens of New York, composing the firm of H.
C. Roberts & Co., doing business at Rochester, New York, to
recover damages for the alleged failure of the defendants to
deliver to the plaintiff a quantity of iron on a contract for its
sale by the former to the latter. The complaint alleged that at the
time of the breach of the contract by the defendants, the market
value of iron of the kind and quality agreed to be sold was much
greater than the contract price of the iron, and that, if the iron
had been delivered pursuant to the contract, the plaintiff could
have sold it at a large profit. The defendants, in their answer,
besides denying any liability
Page 124 U. S. 67
to the plaintiff, set up by way of counterclaim (1) that the
plaintiff was indebted to them in the sum of $796.99, for coal and
iron sold and delivered by them to him, and that, as a part of the
contract for the sale of the iron upon which the action was
brought, it was a condition that the plaintiff should pay to the
defendants the $796.99, which he had not done; (2) that on the sale
and delivery to the plaintiff by the defendants of certain coal,
the plaintiff had claimed various items of shortage in the Coal,
for which the defendants had allowed to him $1,926.73; that they
had afterwards ascertained that the statements of the plaintiff as
to the shortage were untrue, and that they were ready to deliver
the iron upon the payment to them by the plaintiff of the
$1,926.73.
The reply of the plaintiff admitted an indebtedness to the
defendants of $112.73 on account of the item of $796.99 claimed in
the answer, and in regard to the $1,926.73 it alleged that the
items of shortage had been allowed and agreed to by the
defendants.
After issue was joined, it was stipulated in writing by the
parties, that the action be referred to a person named, "as sole
referee, to hear, try, and determine the issues therein." Upon this
stipulation an order was entered by the court that the action be
referred to such person "to determine the issues therein."
The referee filed his report as follows:
"I, the undersigned, the referee to whom were referred the
issues in the action above entitled, do respectfully report that I
have heard the allegations and proofs of the respective parties,
and the arguments of counsel thereon, and, after due deliberation,
report the following as my findings of facts:"
"First. The plaintiff is a citizen of the State of Wisconsin,
and resides in the City of Milwaukee in said state, and the
defendants, on and prior to the seventeenth day of July, 1879,
were, have since then continued to be, and now are citizens of the
State of New York, residing at Rochester in said state, and
partners in business in said city under the firm name of H. C.
Roberts & Co."
"Second. On or about the seventeenth day of July, 1879, the
Page 124 U. S. 68
plaintiff inquired of the said defendants by telegraph their
lowest price for four hundred tons of number two iron and four
hundred tons of number one iron, or one cargo of each, delivered
afloat at Milwaukee, to which, on the twenty-second day of July,
1879, the said defendants replied by telegram, stating the price at
nineteen dollars and fifty cents cash per ton for number one
foundry iron delivered afloat at Milwaukee, and declining to put
any price or to make any agreement for the sale of number two iron,
and in a letter, written on the following day, promised and agreed
to ship a cargo of the iron about the first day of September, 1879,
if the plaintiff should accept the offer."
"On the 25th of July, 1879, the plaintiff, by letter, accepted
the offer of a cargo of the iron at $19.50 per ton afloat at
Milwaukee, provided that the plaintiff should be allowed the
deduction from the price per ton if freight could be had for less
than one dollar per ton and also provided that the terms should be,
instead of cash, a credit of four months, with interest at the rate
of seven percent per annum after thirty days."
"The defendants, by letter dated July 28, 1879, accepted the
modification of the terms and conditions of sale, and agreed to
ship the iron about September 1, 1879, or as soon as they could
manufacture it."
"Third. The term 'cargo,' employed in this correspondence, was
understood by the plaintiff and the defendants to mean a cargo of
four hundred tons."
"Fourth. The contract for the delivery of the cargo of iron had
no relation to or connection with any other dealings between the
parties, and the performance thereof by the defendants was not
conditioned upon the performance of any act on the part of the
plaintiff other than as stated in the preceding findings."
"Fifth. The defendants did not deliver the iron or any part of
it to the plaintiff on or about the time specified in their offer,
nor did they deliver it as soon as they had manufactured the
required amount. They postponed the execution of the contract from
time to time, and finally insisted, as a condition of the delivery
of the iron that the plaintiff should pay certain
Page 124 U. S. 69
outstanding indebtedness on other dealings, which the defendants
claimed to be due to them from the plaintiff, and, also, as a
further condition, that payment for the iron should be made upon
delivery; that shipment should be by rail instead of by boat, and
in installments of one hundred tons per month, instead of one cargo
of the full amount, and that the plaintiff should pay, in addition
to the contract price, one dollar per ton for extra freight. The
plaintiff did not comply with these conditions, and the iron has
never been delivered."
"Sixth. At the time when the letter containing these conditions
was sent by the defendants to the plaintiff, November 7, 1879, the
market value of number one foundry iron of the kind manufactured by
the defendants was thirty-four dollars per ton, afloat in
Milwaukee."
"Seventh. From May, 1878, to November, 1878, the defendants
delivered to the plaintiff four hundred and thirty-five tons of
iron, of the value of seventeen dollars per ton, to be accounted
for by the plaintiff to the defendants at that price. The plaintiff
has accounted and paid for all of this iron except 6 1979/2240
tons, for which amount payment has not been made, nor has the iron
been returned to the defendants. A statement of this account was
submitted by the defendants to the plaintiff, showing that there
was due and unpaid thereon $117.02, on the eighteenth day of June,
1879."
"Eighth. Between April 20, 1876, and October 5, 1878, the
defendants sold and delivered to the plaintiff a quantity of coal,
a statement of the weights and prices of which was rendered by the
defendants to the plaintiff. Upon receipt of the cargoes at
Milwaukee, the coal was weighed at the dock by the plaintiff, and
thereafter he submitted to the defendants a statement of the
weights and demanded a deduction on account of shortage in weight,
which he claimed to exist. The defendants assented to and allowed
the claim for shortage, and the plaintiff paid the balance of the
account in full. The claim for shortage was made by the plaintiff
in good faith, upon the basis of weights taken at his dock, and the
defendants did not in any manner object to the plaintiff's claim
until after he had insisted upon the performance of the contract
upon which this action was brought. "
Page 124 U. S. 70
"Ninth. In the months of October and November, 1878, the
defendants sold and delivered to the plaintiff coal at certain
prices, which, with the interest added to the day of the adjustment
of the account, April 16, 1879, amounted to the sum of twenty
thousand three hundred and four dollars and seventy-one cents. Of
this amount, the plaintiff paid to the defendant sums of money from
time to time, which, with interest to the said sixteenth day of
April, 1879, amounted to nineteen thousand six hundred and
seventy-eight dollars and ninety-four cents. A statement of said
account was made by the defendants to the plaintiff, showing a
balance due from the latter to the former on said day, amounting to
six hundred and twenty-five dollars and seventy-seven cents. This
balance has not, nor has any part of it, been paid by the plaintiff
to the defendants."
"Upon these facts I do respectfully report as my conclusions of
law:"
"First. The plaintiff is entitled to recover from the defendants
the difference between the contract price of the four hundred tons
of iron which were to be delivered about the first of September,
1879, and the market value of the said iron afloat in Milwaukee, on
the seventh day of November, 1879, when the contract was finally
broken by the said defendants, amounting to the sum of five
thousand eight hundred dollars, with interest from November 7,
1879, to the date of this report."
"Second. The plaintiff is indebted to the defendants in the sum
of one hundred and seventeen dollars and two cents, with interest
from June 18, 1879, for the 6 1979/2240 tons of iron, as stated in
the seventh finding of fact, amounting at the date of this report,
to the sum of one hundred and forty-eighth dollars and twenty cents
($148.20), and they are entitled to have the said amount offset
against the amount otherwise due from them to the plaintiff, as
stated in the first conclusion of law."
"Third. The plaintiff is indebted to the defendants in the sum
of six hundred and twenty-five dollars and seventy-seven cents,
with interest from April 16, 1879, for the balance of the account
for coal sold to the plaintiff, as stated in the ninth
Page 124 U. S. 71
finding of facts, amounting at the date of this report to the
sum of seven hundred and ninety-nine dollars, and they are entitled
to have the said amount offset against the amount otherwise due
from them to the plaintiff, as stated in the first conclusion of
law."
"Fourth. The defendants have not established their right to
reopen the account between them and the plaintiff for coal
delivered from April 20, 1876, and October 5, 1878, as stated in
the eighth finding of facts, and they are therefore concluded by
the settlement and adjustment made in that respect, and not
entitled to the counterclaim in that behalf stated in their answer
herein."
"Fifth. The plaintiff is entitled to judgment against the
defendants for the sum of six thousand two hundred and sixty-four
dollars and twelve cents ($6,264.12), with interest thereon from
the date of this report, with the costs of this action, and
judgment for that amount is accordingly directed."
The defendants moved the court for a new trial upon a "case and
exceptions," made according to the practice in the State of New
York, in which they excepted to the first, fourth, and fifth
conclusions of law found by the referee; but the motion was denied,
and the court thereupon made an order denying it and directing
"that judgment be entered herein pursuant to the report of the
referee, with costs." Thereupon judgment was entered for the
plaintiff for the $6,264.12, and $192.08 interest from the date of
the report, and $399.70 costs, amounting in all to $6,855.90. The
defendants have brought a writ of error to review the judgment.
The item of recovery allowed to the plaintiff by the referee was
for 400 tons of iron a $14.50 per ton, being the difference between
$19.50, the contract price, and $34, the market value on November
7, 1879.
The only questions open to review here are whether there was any
error of law in the judgment rendered by the circuit court upon the
facts found by the referee. The judgment having been entered
"pursuant to the report of the referee," the facts found by him are
conclusive in this Court.
Thornton v.
Carson, 7 Cranch 596,
11 U. S. 601;
Alexandria Canal v.
Swann,
Page 124 U. S. 72
5 How. 83;
York & Cumberland Railroad
v. Myers, 18 How. 246;
Heckers v.
Fowler, 2 Wall. 123;
Bond v. Dustin,
112 U. S. 604,
112 U. S.
606-607;
Paine v. Railroad, 118 U.
S. 152,
118 U. S.
158.
The second and third findings of fact show that there was a
complete, valid, and binding contract made between the parties,
which was not void for uncertainty or for any other reason. It is
expressly found that the term "cargo," employed in the
correspondence between the parties by which the contract was
entered into, was understood by both of them to mean a cargo of 400
tons. It is also expressly found that the contract for the delivery
of the iron had no relation to or connection with any other
dealings between the parties, and that the performance thereof by
the defendants was not conditioned upon the performance of any act
on the part of the plaintiff other than as stated in the second and
third findings of fact.
It is contended by the defendants that the referee erred in
taking the $34 per ton, the market value of the iron on November 7,
1879, as the measure of damages, instead of the market price in
September, when the iron was to be delivered, and when it is
alleged the breach of the contract occurred. But although the
defendants did not deliver any of the iron on or about September 1,
1879, nor as soon as they had manufactured the required amount, yet
it appears from the findings of fact, considered together, that the
breach of the contract did not take place until November 7, 1879.
The statement in the findings that the defendants "postponed the
execution of the contract from time to time," and finally insisted
upon certain requirements as conditions of the delivery of the iron
must be accepted as a statement that the postponement of the
execution of the contract from time to time down to November 7,
1879, was with the assent of the plaintiff. From the fact that, as
late as November 7, 1879, the defendants were naming conditions on
which they would deliver the iron, it must be inferred that the
question of delivery was still regarded by both parties as an open
one, and that the mere failure to deliver the iron by the first of
September, 1879, or
Page 124 U. S. 73
even thereafter, as soon as the required amount had been
manufactured, was not regarded by either party as a breach of the
contract. It was in the power of the defendants, instead of merely
postponing the execution of the contract from time to time, to have
absolutely refused to perform it if they found that the price of
iron was rising in the market, as is alleged in argument. But it is
not found as a fact by the referee that there was any advance in
the market value of the iron in question between September 1, 1879,
or the time the iron was manufactured, and November 7, 1879, nor is
the price of the iron in the market found as a fact at any other
date than November 7, 1879.
On the findings of fact, the rule of damages applied to this
case was in accordance with the authorities. Benjamin on Sales
§ 872; 2 Sedgwick on Damages, 7th ed., 134, note
b;
Ogle v. Earl Vane, L.R. 2 Q.B. 275, and in the Exchequer
Chamber, L.R. 3 Q.B. 272;
Hickman v. Haynes, L.R. 10 C.P.
598;
Hill v. Smith, 34 Vt. 535, 547;
Newton v.
Wales, 3 Robertson (N.Y.Sup.Ct.) 453.
It is also alleged for error that the referee erred in refusing
to open the account between the parties and to allow the
defendants' counterclaim for $1,926.73, as wrongfully charged to
them by the plaintiff for shortages on coal. The finding of the
referee is that the plaintiff, after weighing the coal, submitted
to the defendants a statement of the weights and asked a deduction
on account of shortage; that the defendants assented to and allowed
the claim; that the plaintiff paid the balance of the account in
full; that the claim for shortage was made by the plaintiff in good
faith, upon the basis of weights taken at his dock, and that the
defendants did not in any manner object to the plaintiff's claim
until after he had insisted upon the performance of the contract on
which this action was brought. On these facts, the referee found as
a conclusion of law that the defendants had not established their
right to reopen the account for the coal in question; that they
were concluded by the settlement and adjustment made in that
respect, and that they were not entitled to the counterclaim in
that behalf stated in their answer.
Page 124 U. S. 74
The answer alleged in respect to such counterclaim that the
statements of the weight of the coal made by the plaintiff to the
defendants were false, and were so known to be by the plaintiff,
and that the amount which he had received from the defendants for
shortage was obtained from them by his unlawful act. No facts in
support of this allegation of the answer are found by the referee,
and his conclusion of law was correct.
This case not having been tried by the circuit court on the
filing of a waiver in writing of a trial by jury, this Court
cannot, on this writ of error, review any of the exceptions taken
to the admission or exclusion of evidence, or any of the exceptions
to the findings of fact by the referee, or to his refusal to find
facts as requested.
Bond v. Dustin, 112 U.
S. 604,
112 U. S.
606-607;
Paine v. Central Vermont Railroad,
118 U. S. 152,
118 U. S.
158.
The judgment of the circuit court is
Affirmed.